A prefabricated shed for installing a reactive compensation device

By designing facilities such as hub boxes and power supply boxes within the prefabricated silo, analog signals are converted into digital signals for transmission, solving the problems of complex wiring and signal attenuation in intelligent power transmission and transformation stations, improving safety and controllability, and meeting the needs of intelligent systems.

CN115559578BActive Publication Date: 2026-02-27STATE GRID JIANGSU ELECTRIC POWER CO XUZHOU POWER SUPPLY CO
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202211301037.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-24
Publication Date
2026-02-27
Estimated Expiration
2042-10-24

AI Technical Summary

Technical Problem

Existing reactive power compensation devices in intelligent power transmission and transformation stations suffer from problems such as complex wiring, signal attenuation, safety hazards, lack of auxiliary facilities, and inability to monitor in real time.

Method used

Design a prefabricated compartment for installing a reactive power compensation device, which includes a hub box, power supply box, low-voltage compensation box, high-voltage compensation box, air conditioner, fire extinguisher box, camera, fire alarm and lighting, etc. It realizes the conversion of analog signals into digital signals for transmission, has human-machine interaction function, and is easy to move and fix with casters and lifting rings.

Benefits of technology

It improves the safety and controllability of reactive power compensation devices, solves the problems of complex lines and signal attenuation, provides real-time monitoring and convenient equipment management, and meets the needs of intelligent power transmission and transformation stations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115559578B_ABST
    Figure CN115559578B_ABST
Patent Text Reader

Abstract

The application discloses a prefabricated bin for installing a reactive power compensation device, which comprises a prefabricated bin body, a collection box movably installed in the prefabricated bin body, a power supply box movably installed in the prefabricated bin body, a low-voltage compensation box movably installed in the prefabricated bin body and a high-voltage compensation box movably installed in the prefabricated bin body. The collection box, the power supply box, the low-voltage compensation box and the high-voltage compensation box are movably installed in the prefabricated bin body, thereby improving the safety of the reactive power compensation device, solving the problem of complicated primary line incoming lines of existing box-type high-voltage and low-voltage reactive power compensation devices and existing safety hazards. The equipment collection box in the prefabricated bin body converts analog signals collected by the equipment in the prefabricated bin body into digital signals or optical signals, realizes information transmission through a standard interface and a station control layer, solves the problem of complicated secondary line interfaces and the problem of signal attenuation existing in long-distance transmission of analog signals.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application belongs to the technical field of power equipment, and particularly relates to a prefabricated bin for installation of a reactive power compensation device. BACKGROUND

[0002] In actual operation of the reactive power compensation device, the PCS (protection and control unit) is installed as an interval layer, and the TA (current transformer) and TV (voltage transformer) device and switch are installed as a process layer in the distribution room, and the reactive power compensation device is installed as a main primary equipment in the primary equipment site, so that the line laying is complicated, the control command issued by the PCS can be transmitted to the compensation device at a long distance, signal attenuation exists, and faults are prone to occur to cause the protection device to malfunction or refuse to act. When the reactive power compensation device is not in the substation but is used for on-site reactive power compensation of the line at the far end of the line, the device state is uncontrollable or the monitorable quantity is small.

[0003] The existing box-type reactive power compensation device is an important reactive power compensation equipment, but in actual operation, the primary line is often overhead or is branched from the distribution cabinet, the line is complicated, the appearance is affected, and safety hazards exist. The secondary line is directly led from the capacitor device to the distribution room, the interface is complicated, signal attenuation exists in long-distance transmission of the analog signal, in addition, the traditional box-type high-voltage reactive power compensation device does not have fireproofing, monitoring and other equipment, the auxiliary facilities are poor, does not have human-computer interaction function, the on-duty personnel cannot know the existing state of the device in real time and comprehensively, and cannot trace the historical state of the device, and the box is thin, the size is variable, a large amount of on-site installation and debugging work is needed, and the development needs of the intelligent power transmission and transformation station cannot be met. SUMMARY

[0004] In view of the problems in the prior art, the present application aims to provide a prefabricated bin for installation of a reactive power compensation device, which solves the problem that the development needs of the intelligent power transmission and transformation station cannot be met.

[0005] In order to achieve the above object, the application provides the following technical scheme: A prefabricated warehouse for installing a reactive compensation device, comprising a prefabricated warehouse body, a junction box movably mounted in the prefabricated warehouse body, a power supply box movably mounted in the prefabricated warehouse body, a low-voltage compensation box movably mounted in the prefabricated warehouse body, a high-voltage compensation box movably mounted in the prefabricated warehouse body, a partition plate fixedly mounted in the prefabricated warehouse body, an inner door hinged to the partition plate, a glass observation window fixedly mounted in the partition plate and the inner door, an air conditioner slidably mounted on one side of the prefabricated warehouse body, a side sliding plate fixedly mounted on one end of the air conditioner, a table fixedly mounted in the prefabricated warehouse body, an integrated computer arranged on the top of the table, an air conditioner outdoor unit fixedly mounted on the top of the prefabricated warehouse body, a sliding groove frame fixedly mounted on both sides of the front and back of the prefabricated warehouse body, a sliding groove arranged on one side of the sliding groove frame away from the prefabricated warehouse body, a sliding block slidably mounted in the sliding groove, a rotating seat rotatably mounted on one side of the sliding block away from the sliding groove, a plug column fixedly mounted on one side of the rotating seat, a connecting rod fixedly mounted on one side of the rotating seat away from the plug column, a friction rubber plate fixedly mounted on one end of the connecting rod away from the rotating seat, a camera fixedly mounted on both sides of the top of the inner cavity of the prefabricated warehouse body, a fire alarm fixedly mounted on the top of the inner cavity of the prefabricated warehouse body, a warehouse door hinged to one side of the prefabricated warehouse body, and a fixed seat fixedly mounted on the top of the prefabricated warehouse body, wherein the air conditioner outdoor unit is fixedly mounted on the inner side of the fixed seat.

[0006] Preferably, the front of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box is hinged with a box door, the inner side of the box door is fixedly mounted with a transparent window, and the front of the box door is fixedly mounted with a handle, and the back of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box is arranged with a wiring groove.

[0007] Through the above technical scheme, the advantages are that the box door is arranged to facilitate the observation of the equipment running in the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box, and the wiring groove arranged on the back facilitates wiring.

[0008] Preferably, the back of the prefabricated warehouse body is fixedly mounted with a protective frame, the inner side of the protective frame is arranged with a wire groove, one end of the protective frame is clamped with a sealing plate, and the position of the protective frame corresponds to the position of the partition plate.

[0009] Through the above technical scheme, the advantages are that the protective frame is arranged to facilitate the protection of the wiring groove, preventing rainwater from entering the inside of the prefabricated warehouse from the wiring groove.

[0010] Preferably, the bottom of the inner cavity of the prefabricated warehouse body is fixedly provided with four bottom sliding plates, the bottom of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box is provided with a groove, and the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box are slidably arranged outside the four bottom sliding plates through the groove.

[0011] Through the above technical scheme, the advantage is that when the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box are maintained, the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box can be slid outside the bottom sliding plate by pulling, so that the wire body located at the back is exposed, the maintenance is facilitated, and the positions of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box can be adjusted according to the actual wiring requirements.

[0012] Preferably, the partition plate is located between the table and the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box, and the positions of the table and the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box correspond to the positions of the glass observation window fixedly arranged in the partition plate.

[0013] Through the above technical scheme, the advantage is that the partition plate can separate the table from the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box, and the supervisor can observe the running state of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box on the other side of the partition plate through the glass observation window.

[0014] Preferably, one side of the prefabricated warehouse body is fixedly provided with a side sliding plate, the air conditioner is slidably arranged outside the side sliding plate, the bottom of the air conditioner is fixedly provided with a pull plate, the top of one side of the partition plate is provided with a rectangular groove, the size of the plug plate corresponds to the size of the rectangular groove, and the position of the plug plate corresponds to the position of the rectangular groove.

[0015] Through the above technical scheme, the advantage is that the side sliding plate can move the air conditioner in the prefabricated warehouse body, so as to adjust the position of the air conditioner. In summer, the air conditioner can blow cold air to the spaces on both sides of the partition plate at the same time to reduce the temperature in the prefabricated warehouse body. In winter, the air conditioner can be slid to make the plug plate close the rectangular groove, so that the air conditioner only blows hot air to the space on one side of the partition plate, preventing the temperature on the other side of the partition plate from being too high.

[0016] Preferably, the bottom of the prefabricated warehouse body is fixedly provided with universal wheels, the universal wheels are six, and the six universal wheels are symmetrically distributed on the bottom of the prefabricated warehouse body, the top of the prefabricated warehouse body is fixedly provided with lifting rings, the lifting rings are four, and the four lifting rings are symmetrically distributed at the four corners of the top of the prefabricated warehouse body.

[0017] The six universal wheels are arranged to facilitate the movement of the prefabricated warehouse body as a whole, the movement is simple, the prefabricated warehouse body can be moved to a suitable position, and after being moved to the suitable position, a suitable fixing head can be selected according to the terrain, when being located on a muddy surface, only the sliding block is caused to slide in the sliding groove by rotating the friction rubber plate downwardly by manually knocking the friction rubber plate, so that the column is inserted into the mud, thereby fixing the prefabricated warehouse body, and the prefabricated warehouse body is prevented from moving during use, when being located on a hard ground, only the friction rubber plate is caused to contact the ground by rotating the friction rubber plate downwardly, thereby increasing the friction, and the movement of the prefabricated warehouse body during use is reduced, and the four lifting rings are arranged to facilitate the lifting and moving of the prefabricated warehouse body, and the moving effect is improved.

[0018] Preferably, a lighting lamp is fixedly installed at the top of the inner cavity of the prefabricated warehouse body, and a fire-fighting box is fixedly installed on one side of the inner cavity of the prefabricated warehouse body.

[0019] The lighting lamp is arranged to illuminate the inside of the prefabricated warehouse body, which facilitates the night inspection of the inside equipment of the prefabricated warehouse body by the staff, and also facilitates the observation of the running state of the junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box located on the other side of the partition plate by the monitoring personnel, and the fire-fighting box can be used to timely extinguish the fire in the prefabricated warehouse body, thereby ensuring safety.

[0020] Compared with the prior art, the present application has the following advantages:

[0021] 1. The junction box, the power supply box, the low-voltage compensation box and the high-voltage compensation box are arranged in the prefabricated warehouse body, and air conditioners, fire-fighting boxes, cameras, fire alarm devices and lighting lamps are arranged in the prefabricated warehouse body as auxiliary facilities, thereby improving the safety of the reactive power compensation device, solving the problem of complicated primary line wiring of the existing box-type high-voltage and low-voltage reactive power compensation device, and eliminating the safety hazard; the equipment junction box in the prefabricated warehouse body converts the analog signal collected by the equipment in the prefabricated warehouse body into a digital signal or an optical signal, realizes information transmission through a standard interface and a station control layer, solves the problem of complicated secondary line interface, and solves the problem of signal attenuation caused by long-distance transmission of analog signals; the table has a man-machine interaction function, collects all signals in the junction box, archives data and provides analysis, provides a visual integrated computer, and comprehensively understands the existing state of the device, thereby facilitating daily control and maintenance.

[0022] 2. The side slide plate allows the air conditioner to move inside the prefabricated silo, thereby adjusting the position of the air conditioner. In hot summer, the air conditioner can simultaneously blow cold air into the spaces on both sides of the partition to cool down the temperature inside the prefabricated silo. In winter, the air conditioner can be slid to seal the rectangular groove with the blocking plate, so that the air conditioner blows hot air into the space on one side of the partition to prevent the temperature on the other side of the partition from getting too high. Attached Figure Description

[0023] Figure 1 This is a three-dimensional structural diagram of the present invention;

[0024] Figure 2 This is a top view of the internal structure of the present invention;

[0025] Figure 3 This is a bottom-view three-dimensional structural diagram of the present invention;

[0026] Figure 4 This is an enlarged structural diagram of point A in the present invention;

[0027] Figure 5 This is a frontal view of the internal structure of the present invention;

[0028] Figure 6 This is a partial side view of the structure of the present invention.

[0029] In the diagram: 1. Prefabricated compartment; 2. Lifting ring; 3. Compartment door; 4. Air conditioner outdoor unit; 5. Fixing base; 6. Friction rubber plate; 7. Connecting rod; 8. Rotary seat; 9. Slide frame; 10. Protective frame; 11. Wire channel; 12. Slide; 13. Sliding block; 14. Insert post; 15. Sealing plate; 16. Casters; 17. Side slide plate; 18. Blocking plate; 19. Air conditioner; 20. Fire box; 21. Glass observation window; 22. All-in-one computer; 23. Table; 24. Partition; 25. Inner door; 26. Junction box; 27. Power supply box; 28. Low-voltage compensation box; 29. ​​High-voltage compensation box; 30. Camera; 31. Fire alarm; 32. Lighting light; 33. Bottom slide plate; 34. Wiring channel; 35. Compartment door. Detailed Implementation

[0030] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0031] like Figures 1-6The utility model discloses a prefabricated warehouse for installing reactive compensation device, including prefabricated warehouse body 1, the inside movable mounting of prefabricated warehouse body 1 has the junction box 26, the inside movable mounting of prefabricated warehouse body 1 has the power supply box 27, the inside movable mounting of prefabricated warehouse body 1 has low voltage compensation box 28, the inside movable mounting of prefabricated warehouse body 1 has high voltage compensation box 29, the inside fixed mounting of prefabricated warehouse body 1 has the partition 24, the inside hinged mounting of partition 24 has the inside door 25, the inside fixed mounting of partition 24 and inside door 25 all has glass observation window 21, the inside of prefabricated warehouse body 1 one side slidingly installed air conditioning 19, air conditioning 19 one end fixedly installed with side slide plate 17, the inside fixed mounting of prefabricated warehouse body 1 has table 23, the top of table 23 is provided with integrated computer 22, the top of prefabricated warehouse body 1 fixedly installed with air conditioning outdoor unit 4, the both sides of prefabricated warehouse body 1 front and back are fixedly installed with sliding groove frame 9, the side away from prefabricated warehouse body 1 of sliding groove frame 9 is set up with sliding groove 12, the inside slidingly installed with sliding block 13 of sliding groove 12, the side away from sliding groove 12 of sliding block 13 rotatably installed with rotary seat 8, the one side fixed mounting of rotary seat 8 has inserted column 14, the side away from inserted column 14 of rotary seat 8 fixedly installed with connecting rod 7, the one end fixedly installed with friction rubber plate 6 of connecting rod 7 away from rotary seat 8, the both sides of prefabricated warehouse body 1 inner chamber top are fixedly installed with camera 30, the top of prefabricated warehouse body 1 inner chamber is fixedly installed with fire alarm 31, the one side of prefabricated warehouse body 1 is hinged with warehouse door 3, the top of prefabricated warehouse body 1 is fixedly installed with fixed seat 5, the inboard of fixed seat 5 is fixedly installed with air conditioning outdoor unit 4.

[0032] The working principle of the above technical solution is as follows:

[0033] The prefabricated warehouse body 1 is provided with a cable distribution box 26, a power supply box 27, a low-voltage compensation box 28 and a high-voltage compensation box 29, and is also provided with air conditioners 19, a fire-fighting box 20, a camera 30, a fire alarm 31 and lighting lamps 32, which improves the safety of the reactive power compensation device, solves the problem of complicated primary line wiring of the existing box-type high-voltage and low-voltage reactive power compensation device, and eliminates the hidden danger; the equipment cable distribution box 26 in the prefabricated warehouse body 1 converts the analog signals collected by the equipment in the prefabricated warehouse body 1 into digital signals or optical signals, and realizes information transmission through a standard interface and a station control layer, thereby solving the problem of complicated secondary line interface and signal attenuation in long-distance transmission of analog signals; the table 23 is provided with a man-machine interaction function, collects all signals in the cable distribution box 26, archives data and provides analysis, and provides a visual integrated computer 22 to comprehensively understand the existing state of the device, facilitate daily control and maintenance, and move the air conditioner 19 in the prefabricated warehouse body 1 through the side slide plate 17 to adjust the position of the air conditioner 19; in summer, the air conditioner 19 can blow cold air to the space on both sides of the partition plate 24 to reduce the temperature inside the prefabricated warehouse body 1; in winter, the air conditioner 19 is slid to make the baffle plate 18 close the rectangular groove, so that the air conditioner 19 blows hot air to the space on one side of the partition plate 24 to prevent the temperature on the other side of the partition plate 24 from being too high; the six universal wheels 16 are provided to facilitate the movement of the prefabricated warehouse body 1 as a whole, the movement is simple, the prefabricated warehouse body 1 as a whole can be moved to a suitable position, and after being moved to the suitable position, a suitable fixing head can be selected according to the terrain; when being located on a muddy surface, the insertion column 14 is inserted into the inside of the mud by rotating the rotating seat 8 outside the sliding block 13, making the sliding block 13 slide downward in the sliding groove 12 by manually hitting and rubbing the rubber plate 6, so as to fix the prefabricated warehouse body 1 and ensure that the prefabricated warehouse body 1 does not move during use; when being located on a hard surface, the friction rubber plate 6 is brought into contact with the ground by rotating the rotating seat 8 outside the sliding block 13, so as to increase the friction and reduce the movement of the prefabricated warehouse body 1 during use; in addition, the four lifting rings 2 are provided to facilitate the lifting and moving of the prefabricated warehouse body 1, thereby improving the moving effect.

[0034] In another embodiment, as Figures 1-6As shown, the front of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 is hinged with a box door 35, the inside of the box door 35 is fixedly installed with a transparent window, the front of the box door 35 is fixedly installed with a handle, the back of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 is provided with a wiring groove 34, the back of the prefabricated warehouse body 1 is fixedly installed with a protective frame 10, the inside of the protective frame 10 is provided with a wire groove 11, one end of the protective frame 10 is clamped with a sealing plate 15, the position of the protective frame 10 corresponds to the position of the partition plate 24, the bottom of the inner cavity of the prefabricated warehouse body 1 is fixedly installed with four bottom sliding plates 33, the bottom of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 is provided with a groove, and the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 are respectively slidably installed on the outside of the four bottom sliding plates 33, the partition plate 24 is located between the table 23 and the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29, and the positions of the table 23 and the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 correspond to the position of the glass observation window 21 installed in the partition plate 24.

[0035] The box door 35 is provided to facilitate observation of the equipment inside the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29, the wiring groove 34 is provided on the back to facilitate wiring, the protective frame 10 is provided to facilitate protection of the wiring groove 34, prevent rainwater from entering the inside of the prefabricated warehouse body 1 from the wiring groove 34, when the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 are maintained, the staff can slide the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 on the outside of the bottom sliding plate 33, so as to expose the wire body on the back, facilitate maintenance, in addition, the position of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 can be adjusted according to the actual wiring requirement, the partition plate 24 can separate the table 23 from the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29, the supervisor can observe the running state of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 on the other side of the partition plate 24 through the glass observation window 21.

[0036] In another embodiment, as shown in Figures 1-6 One side of the prefabricated warehouse body 1 is fixedly installed with a side sliding plate 17, an air conditioner 19 is slidably installed on the outside of the side sliding plate 17, the bottom of the air conditioner 19 is fixedly installed with a pull plate, a rectangular groove is formed in the top of one side of the partition plate 24, the size of the plug plate 18 corresponds to the size of the rectangular groove, and the position of the plug plate 18 corresponds to the position of the rectangular groove.

[0037] The side slide plate 17 can move the air conditioner 19 inside the prefabricated warehouse 1, so as to adjust the position of the air conditioner 19. In summer, the air conditioner 19 can blow cold air to the spaces on both sides of the partition 24 to reduce the temperature inside the prefabricated warehouse 1. In winter, the slidable air conditioner 19 can make the blocking plate 18 close the rectangular groove, so that the air conditioner 19 only blows hot air to the space on one side of the partition 24, preventing the temperature on the other side of the partition 24 from being too high.

[0038] In another embodiment, as shown in Figures 1-6 The bottom of the prefabricated warehouse 1 is fixedly provided with six universal wheels 16, which are symmetrically distributed on the bottom of the prefabricated warehouse 1. The top of the prefabricated warehouse 1 is fixedly provided with four lifting rings 2, which are symmetrically distributed on the four corners of the top of the prefabricated warehouse 1.

[0039] The six universal wheels 16 facilitate the movement of the prefabricated warehouse 1 as a whole. The movement is simple, and the prefabricated warehouse 1 can be moved to a suitable position as a whole. After being moved to a suitable position, a suitable fixing head can be selected according to the terrain. When located on a muddy surface, the sliding block 13 can be lowered in the sliding groove 12 by rotating the friction rubber plate 6 downward by rotating the swivel seat 8 outside the sliding block 13, so that the insertion column 14 is inserted into the mud, thereby fixing the prefabricated warehouse 1 and preventing it from moving during use. When located on a hard surface, the friction rubber plate 6 can be brought into contact with the ground by rotating the friction rubber plate 6 downward by rotating the swivel seat 8 outside the sliding block 13, thereby increasing the friction and reducing the movement of the prefabricated warehouse 1 during use. In addition, the four lifting rings 2 facilitate the lifting and moving of the prefabricated warehouse 1, improving the moving effect.

[0040] In another embodiment, as shown in Figures 1-6 The top of the inner cavity of the prefabricated warehouse 1 is fixedly provided with a lighting lamp 32, and one side of the inner cavity of the prefabricated warehouse 1 is fixedly provided with a fire-fighting box 20.

[0041] The lighting lamp 32 illuminates the inside of the prefabricated warehouse 1, facilitating the night inspection of the equipment inside the prefabricated warehouse 1 by the staff, and also facilitating the observation of the running state of the junction box 26, the power supply box 27, the low-voltage compensation box 28 and the high-voltage compensation box 29 on the other side of the partition 24 by the monitor. The fire-fighting box 20 can extinguish the fire in the prefabricated warehouse 1 in time, ensuring safety.

[0042] The working principle and use process of the present application: the prefabricated warehouse body 1 is provided with a collection box 26, a power supply box 27, a low-voltage compensation box 28 and a high-voltage compensation box 29, and is also provided with air conditioners 19, a fire-fighting box 20, a camera 30, a fire alarm 31 and a lighting lamp 32 auxiliary facilities, which improves the safety of the reactive power compensation device, solves the problem of complex primary line wiring of the existing box-type high-voltage and low-voltage reactive power compensation device, and exists hidden trouble; the equipment collection box 26 in the prefabricated warehouse body 1 converts the analog signal collected by the equipment in the prefabricated warehouse body 1 into a digital signal or an optical signal, realizes information transmission through a standard interface and a station control layer, solves the problem of complex secondary line interface, and adopts analog signal long-distance transmission to exist signal attenuation; the table 23 is provided with a man-machine interaction function, collects all signals in the collection box 26, archives data and provides analysis, provides a visual integrated computer 22, comprehensively understands the existing state of the device, and is convenient for daily control and maintenance; the side slide plate 17 is provided, so that the air conditioner 19 can move in the prefabricated warehouse body 1, so as to adjust the position of the air conditioner 19; in summer, the air conditioner 19 can blow cold wind to the space on both sides of the partition plate 24 to reduce the temperature in the prefabricated warehouse body 1; in winter, the slidable air conditioner 19 makes the blocking plate 18 close the rectangular groove, so that the air conditioner 19 only blows hot wind to the space on one side of the partition plate 24, preventing the temperature on the other side of the partition plate 24 from being too high; the six universal wheels 16 are provided to facilitate the movement of the prefabricated warehouse body 1 as a whole, the moving mode is simple, the prefabricated warehouse body 1 as a whole can be moved to a suitable position, and after being moved to a suitable position, a suitable fixing head can be selected according to the terrain; when being located on a muddy surface, the rotating seat 8 is only rotated on the outside of the sliding block 13, the end of the insertion column 14 away from the rotating seat 8 is downward, then the friction rubber plate 6 is manually hit and rubbed to make the sliding block 13 slide in the sliding groove 12, so that the insertion column 14 is inserted into the inside of the mud, thereby fixing the prefabricated warehouse body 1, and ensuring that the prefabricated warehouse body 1 will not move during use; when being located on a hard ground, the rotating seat 8 is only rotated on the outside of the sliding block 13, the end of the friction rubber plate 6 away from the rotating seat 8 is downward, then the friction rubber plate 6 is contacted with the ground, so as to increase the friction, thereby reducing the movement of the prefabricated warehouse body 1 during use; in addition, the four lifting rings 2 are provided to facilitate the lifting and moving of the prefabricated warehouse body 1, and the moving effect is improved.

[0043] Although the embodiments of the present application have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present application, and the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. A prefabricated compartment for installing a reactive power compensation device, comprising a prefabricated compartment body (1), characterized in that: A junction box (26) is movably installed inside the prefabricated silo (1). A power supply box (27) is movably installed inside the prefabricated silo (1). A low-voltage compensation box (28) is movably installed inside the prefabricated silo (1). A high-voltage compensation box (29) is movably installed inside the prefabricated silo (1). A partition (24) is fixedly installed inside the prefabricated silo (1). An inner door (25) is installed inside the partition (24) via a hinge. A glass observation window (21) is fixedly installed inside both the partition (24) and the inner door (25). An air conditioner (19) is slidably installed on one side inside the prefabricated silo (1). A side slide plate (17) is fixedly installed at one end of the air conditioner (19). A table (23) is fixedly installed inside the prefabricated silo body (1). An all-in-one computer (22) is installed on the top of the table (23). An air conditioner outdoor unit (4) is fixedly installed on the top of the prefabricated silo body (1). Slide frames (9) are fixedly installed on both sides of the front and back of the prefabricated silo body (1). A slide groove (12) is opened on the side of the slide frame (9) away from the prefabricated silo body (1). A slider (13) is slidably installed inside the slide groove (12). A rotating seat (8) is rotatably installed on the side of the slider (13) away from the slide groove (12). A plug (14) is fixedly installed on one side of the rotating seat (8). A connecting rod (7) is fixedly installed on the side of the rotating seat (8) away from the plug (14). The connecting rod (7) is away from the side of the rotating seat (8) away from the plug (14). A friction rubber plate (6) is fixedly installed at one end of the rotating seat (8). Cameras (30) are fixedly installed on both sides of the top of the prefabricated silo (1). A fire alarm (31) is fixedly installed on the top of the prefabricated silo (1). A silo door (3) is installed on one side of the prefabricated silo (1) via a hinge. A fixed seat (5) is fixedly installed on the top of the prefabricated silo (1). An air conditioner outdoor unit (4) is fixedly installed on the inner side of the fixed seat (5). A door (35) is installed on the front of the junction box (26), power supply box (27), low-voltage compensation box (28), and high-voltage compensation box (29) via a hinge. A transparent window is fixedly installed inside the door (35). Handles are fixedly installed. Wiring grooves (34) are opened on the back of the junction box (26), power supply box (27), low voltage compensation box (28) and high voltage compensation box (29) and the back of the prefabricated silo (1). A protective frame (10) is fixedly installed on the back of the prefabricated silo (1). A wire groove (11) is opened inside the protective frame (10). A sealing plate (15) is snapped onto one end of the protective frame (10). The position of the protective frame (10) corresponds to the position of the partition (24). Four bottom sliding plates (33) are fixedly installed at the bottom of the inner cavity of the prefabricated silo (1). Grooves are opened at the bottom of the junction box (26), power supply box (27), low voltage compensation box (28) and high voltage compensation box (29).Furthermore, the junction box (26), power supply box (27), low-voltage compensation box (28), and high-voltage compensation box (29) are slidably installed on the outside of the four bottom slide plates (33) through grooves. A rectangular groove is provided on the top of one side of the partition plate (24). The specifications and dimensions of the blocking plate (18) are compatible with the specifications and dimensions of the rectangular groove, and the position of the blocking plate (18) corresponds to the position of the rectangular groove. A lighting lamp (32) is fixedly installed on the top of the inner cavity of the prefabricated silo (1), and a fire box (20) is fixedly installed on one side of the inner cavity of the prefabricated silo (1).

2. The prefabricated silo for installing a reactive power compensation device according to claim 1, characterized in that: The partition (24) is located between the table (23) and the junction box (26), power supply box (27), low voltage compensation box (28) and high voltage compensation box (29). The positions of the table (23) and the junction box (26), power supply box (27), low voltage compensation box (28) and high voltage compensation box (29) correspond to the positions of the glass observation window (21) installed inside the partition (24).

3. The prefabricated silo for installing a reactive power compensation device according to claim 1, characterized in that: A side slide plate (17) is fixedly installed on one side of the prefabricated silo (1), and the air conditioner (19) is slidably installed on the outside of the side slide plate (17). A pull plate is fixedly installed on the bottom of the air conditioner (19).

4. The prefabricated silo for installing a reactive power compensation device according to claim 1, characterized in that: The bottom of the prefabricated silo (1) is fixedly equipped with casters (16). There are six casters (16), and the six casters (16) are symmetrically distributed at the bottom of the prefabricated silo (1). The top of the prefabricated silo (1) is fixedly equipped with lifting rings (2). There are four lifting rings (2), and the four lifting rings (2) are symmetrically distributed in a rectangle at the four corners of the top of the prefabricated silo (1).

Citation Information

Patent Citations

  • Device capable of moving indoor air-conditoner

    CN105004031A

  • Prefabricated cabin type reactive compensation chamber

    CN115085214A

  • Level gauge for water conservancy project measurement

    CN213274221U

  • Maintenance-free breathable substation prefabricated cabin

    CN217215612U