A floating wind turbine installation method

By combining the track crane and car crane in the coastal dock, the fan assembly is completed, and combined with the gear meshing and reel design of the spreader, the problem of high difficulty in installing wind turbines in deep waters is solved, and efficient, safe and low-cost wind turbine installation is achieved.

CN116163891BActive Publication Date: 2025-08-29POLY CHANGSHA PORT & SHIPPING ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211674146.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-26
Publication Date
2025-08-29
Estimated Expiration
2042-12-26

AI Technical Summary

Technical Problem

It is difficult to install the traditional jackup fan installation boat in deep waters, and the floating foundation is greatly affected by wind speed, waves and flow rates, which increases the difficulty of alignment and installation of wind turbines.

Method used

At the coastal wharf, the main and auxiliary crawlers and car cranes are used to complete the assembly of the fan unit and the floating platform. The angle of the wind wheel blades is adjusted through the spreader, and the wind wheel assembly is completed in advance with the advantages of the dock yard. Combined with the gear meshing and reel design of the spreader, it improves the stability and convenience of the lifting.

Benefits of technology

It effectively reduces the resource pressure of the jackup fan installation ship in deep water seas, reduces cost investment, reduces the difficulty of wind turbine alignment installation, improves safety, and shortens the construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116163891B_ABST
    Figure CN116163891B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for installing a floating wind turbine, which includes the following steps: crawler crane assembly and positioning, wind turbine component unloading, floating foundation berthing, tower installation, primary leveling adjustment, nacelle installation, secondary leveling adjustment, wind rotor assembly, wind rotor hoisting, and tertiary leveling adjustment. The present invention relates to the field of offshore wind power construction technology. The floating wind turbine installation method utilizes a main and auxiliary crawler crane and a truck crane to complete the assembly of the wind turbine unit and the floating platform at a coastal wharf, alleviating the pressure of scarce resources of self-elevating wind turbine installation vessels in deepwater areas and effectively reducing cost investment. The floating foundation is less affected by wind speed, waves, and flow speed in the harbor, greatly reducing the difficulty of aligning and installing the wind turbine unit, and providing high safety. At the same time, the advantage of the wharf yard area is fully utilized, and the wind rotor assembly work is completed in advance using a truck crane, which greatly shortens the construction period and reduces costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore wind power construction, and in particular to a floating wind turbine installation method. Background Art

[0002] Due to limited offshore space resources, the development of offshore wind power is continuously moving from shallow offshore areas to deep offshore areas. Considering safety and economic factors, wind turbine foundations are also shifting from fixed foundations in shallow waters to floating foundations in deep waters.

[0003] Currently, existing jack-up wind turbine installation vessels operate at depths of mostly 35m to 50m, making them inadequate for deepwater wind turbine installation operations. Floating foundations, affected by the mooring system, present significant challenges for offshore installation using traditional jack-up wind turbine installation vessels. Furthermore, floating foundations are significantly affected by wind speed, waves, and currents in the construction area, significantly increasing the difficulty of aligning and installing wind turbines. Therefore, to overcome these technical challenges, a floating wind turbine installation technology is urgently needed. Summary of the Invention

[0004] In response to the shortcomings of the existing technology, the present invention provides a floating wind turbine installation method, which solves the problem that traditional self-elevating wind turbine installation vessels are difficult to install at sea, and the floating foundation is greatly affected by wind speed, waves and flow speed in the construction sea area, which greatly increases the difficulty of aligning and installing wind turbines.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: A floating wind turbine installation method includes the following construction steps:

[0006] S1. Crawler crane assembly and positioning: After the crawler crane is assembled in the yard behind the wharf, the main and auxiliary crawler cranes are moved forward to the designated positions at the wharf berth;

[0007] S2. Unloading of wind turbine components: The transport vessel carrying wind turbine components is moored at the berth. The main and auxiliary crawler cranes and truck crane are used to barge the wind turbine components to the designated location on the dock. After the barge is completed, the transport vessel unties the mooring and departs.

[0008] S3. Floating foundation berthing: The floating foundation slowly berths to the pier with the cooperation of three tugboats and completes the temporary mooring at the pier;

[0009] S4. Tower installation: After the dock mooring is completed, the multi-section tower is installed on the floating foundation wind turbine column using the main and auxiliary crawler cranes;

[0010] S5. One-time adjustment of levelness: After each tower section is hoisted, the ballast water of the floating foundation is adjusted to ensure that its levelness meets the hoisting requirements of the next stage;

[0011] S6. Nacelle installation: Use the main crawler crane to install the nacelle on the top of the tower;

[0012] S7. Secondary adjustment of levelness: After the nacelle is hoisted, the ballast water of the floating foundation is adjusted to ensure that its levelness meets the requirements of the next stage of hoisting;

[0013] S8. Wind rotor assembly: After the blades are turned over, two truck cranes are used to assemble the blades and the hub;

[0014] S9. Wind rotor hoisting: After the main crawler crane and the truck crane complete the turning of the wind rotor, the main crawler crane completes the alignment and installation of the wind rotor and the main shaft;

[0015] S10. Three-time adjustment of horizontality: After the wind rotor is hoisted, the ballast water of the floating foundation is adjusted to ensure that its loading conditions meet the towing requirements of the next stage.

[0016] Preferably, a sling is used in both the nacelle installation and wind wheel assembly processes in steps S6 and S8. The sling is provided at the ends of the main crawler crane and the truck crane, and includes a hanger and a sling. The bottom of the hanger is fixedly connected to an arc-shaped cover frame, and the hanger is connected to the middle of the arc-shaped cover frame. An adjustment arc-shaped rod is provided on the inner side of the arc-shaped cover frame, and a tooth opening is provided on the upper part of the adjustment arc-shaped rod. A gear is rotatably connected to the inner side of the hanger, and the gear meshes with the tooth opening for transmission. A driving component 1 is provided on the rear side of the gear, and the driving component 1 is used to drive the adjustment arc-shaped rod to rotate.

[0017] One end of the sling is connected to one side of the adjusting arc rod through a clamping member, and the clamping member is used to connect the sling and the adjusting arc rod to form an enclosed state;

[0018] A tightening box is provided on the other side of the adjusting arc rod, and a winding shaft is rotatably connected to the inner side of the tightening box, and the other end of the sling is fixedly connected to the winding shaft. A driving component 2 is provided on the rear side of the winding shaft, and the driving component 2 is used to drive the winding shaft to rotate and wind the sling;

[0019] The bottom end of the adjusting arc rod is provided with a pressing wheel assembly, and the pressing wheel assembly is used for pressing the hoisted object.

[0020] Preferably, the driving member 1 and the driving member 2 have the same structure, and both the driving member 1 and the driving member 2 include a worm gear, a worm and a servo motor, the worm gear and the worm are meshed for transmission, and the output end of the servo motor is fixedly connected to one end of the worm gear.

[0021] Preferably, the worm wheel at the second driving member is fixedly connected to one end of the winding shaft, the worm at the second driving member is rotationally connected to the inner side of the tightening box, and the worm wheel at the second driving member is fixedly connected to the outer side of the tightening box.

[0022] Preferably, the worm wheel at one driving member is fixedly connected to one side of the gear, the worm at one driving member is rotationally connected to the inner side of the hanger, and the worm wheel at one driving member is fixedly connected to the outer side of the hanger.

[0023] Preferably, the clamping member includes a buckle seat and a square buckle head, the square buckle head is fixedly connected to one end of the sling, and the buckle seat is fixedly connected to one side of the adjusting arc rod;

[0024] A buckle groove is provided in the middle of the buckle seat, and a clamping column is slidably connected to the buckle groove. A hydraulic cylinder is fixedly connected to the outer side of the buckle seat, and the output end of the hydraulic cylinder is fixedly connected to the clamping column through a coupling.

[0025] Preferably, the pressure wheel assembly includes a bent rod and a rubber wheel rotatably connected to its end, the bent rod is hinged to the end of the adjusting arc rod away from the rubber wheel, and a telescopic rod is hinged to the middle part of the bent rod, and one end of the telescopic rod away from the telescopic rod is hinged to the end of the adjusting arc rod, and a spring is provided on the outside of the telescopic rod.

[0026] Beneficial effects

[0027] The present invention provides a method for installing a floating wind turbine. Compared with the prior art, it has the following advantages:

[0028] The present invention utilizes main and auxiliary crawler cranes and truck cranes to complete the assembly of wind turbine units and floating platforms at coastal docks, alleviating the pressure on the scarce resources of self-elevating wind turbine installation vessels in deepwater areas and effectively reducing cost investment. In addition, the floating foundation is less affected by wind speed, waves, and current speed in the harbor, greatly reducing the difficulty of aligning and installing the wind turbine units and improving safety. At the same time, the advantage of the dock yard area is fully utilized, and the wind rotor assembly work is completed in advance by using truck cranes, which greatly shortens the construction period and reduces costs.

[0029] The present invention uses a sling in conjunction with the nacelle installation and wind rotor assembly process. The gears mesh with each other, and then the arc-shaped rod is adjusted to slide on the arc-shaped cover frame, so that the angle of the wind rotor blade can be adjusted, thereby facilitating the installation of the fan blade and solving the problem of troublesome blade angle adjustment.

[0030] The sling is wound up by setting a reel to ensure the stability and firmness of the sling during lifting. At the same time, the clamping component is set to facilitate the fixing and loosening of the lifted objects, thereby improving the convenience of the equipment.

[0031] By arranging the pressing wheel assembly, a buffer is provided between the hoisted object and the adjusting arc rod, so that the hoisted object will not be deformed due to a strong contraction force when being tightened. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1This is a side view of the floating wind turbine of the present invention after hoisting is completed;

[0033] Figure 2 This is the layout diagram of the wharf after the wind turbine and tower are unloaded.

[0034] Figure 3 Schematic diagram of the wind wheel assembly of the present invention

[0035] Figure 4 It is a structural cross-sectional view of the sling of the present invention;

[0036] Figure 5 For the present invention Figure 4 A partial enlarged view of point A in the middle;

[0037] Figure 6 For the present invention Figure 4 A partial enlarged view of point B in the middle.

[0038] In the figure: 1. hanger; 11. gear; 2. lifting belt; 3. arc cover frame; 4. adjusting arc rod; 41. tooth mouth; 5. tightening box; 51. reel; 61. buckle seat; 611. buckle groove; 612. clamping column; 62. mouth buckle; 63. hydraulic cylinder; 71. worm gear; 72. worm; 73. servo motor; 81. bending rod; 82. rubber wheel; 83. telescopic rod; 84. spring; 101. truck crane; 102. auxiliary crawler crane; 103. main crawler crane; 201. floating foundation; 202. tower; 203. engine room; 204. blade; 205. wheel hub; 301. transport ship. DETAILED DESCRIPTION

[0039] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0040] See also Figure 1-Figure 3 The present invention provides a technical solution: a floating wind turbine installation method,

[0041] S1. Crawler Crane Assembly and Positioning: At the dockyard behind the wharf, the auxiliary crawler crane 102 is assembled using a truck crane 101. Subsequently, the auxiliary crawler crane 102 and truck crane 101 work together to assemble the main crawler crane 103. After the crawler cranes are assembled, the main crawler crane 103 and auxiliary crawler crane 102 are moved to a position 2 meters from the gantry crane track at the wharf's front edge, using a roadbed box, according to the wharf's production schedule and the berthing plan for the floating foundation 201.

[0042] S2. Unloading of wind turbine components: The transport vessel 301 carrying wind turbine components is moored to the crawler crane's position. The tower 202, nacelle 203, blades 204, and containers are barged to the pre-planned location on the dock using the main crawler crane 103, auxiliary crawler crane 102, and truck crane 101. The position of the transport vessel 301 is adjusted as needed during the process. After all barges are completed, the transport vessel 301 is unmoored and departs.

[0043] S3. Berthing of the floating foundation 201: After the transport vessel 301 unties and leaves the dock, the floating foundation 201 slowly berths to the dock with the cooperation of three tugboats. During this process, the center position of the wind turbine installation column must be controlled to be aligned with the center of the main crawler crane 103;

[0044] S4. Tower 202 Installation: The floating foundation 201 is docked. The main crawler crane 103 is connected to the upper flange lifting device of the tower 202, and the auxiliary crawler crane 102 is connected to the lower flange lifting device of the tower 202. The tower 202 is then turned over by lifting. After the turning is complete, the lower flange lifting device of the tower 202 is released, and the main crawler crane 103 slowly lifts the tower 202 and installs it on the wind turbine column of the floating foundation 201.

[0045] S5. Level adjustment: After the tower 202 is installed, the flange lifting device on the tower 202 is removed, and the ballast water of the floating foundation 201 is adjusted to ensure that its level meets the requirements of the next stage of lifting;

[0046] S6. Nacelle 203 Installation: After the top tower 202 is loaded, the main crawler crane 103 lifts the nacelle 203 lifting rigging to the top of the nacelle 203, connects the nacelle 203 lifting rigging shackle to the nacelle 203, and installs the guy rope. The main crawler crane 103 lifts the nacelle 203 to the top of the tower 202 to complete the installation;

[0047] S7. Leveling adjustment: After the nacelle 203 is hoisted, slowly unload the force and adjust the ballast water of the floating foundation 201 to ensure that its levelness meets the requirements for hoisting the wind rotor;

[0048] S8. Wind rotor assembly: After the blades 204 are in place, the auxiliary crawler crane 102 and three truck cranes 101 are used to assemble the blades 204 to the hub 205. The first and second blades 204 are assembled using the same method, using two truck cranes 101 to lift them. After assembly, the lifting points at the blade root are released, while the truck cranes 101 maintain the load on the blade tip. The third blade 204 is assembled using the auxiliary crawler crane 102 and the truck crane 101. After assembly, all crane lifting points are released.

[0049] S9. Wind rotor hoisting: The main crawler crane 103 and the mobile crane 101 work together to lift the rotor horizontally. When the rotor is 2 meters above the ground, the main crawler crane 103 continues to lift, while the mobile crane 101 controls the distance between the blade tip and the ground until the rotor is turned over. After the turning is completed, the auxiliary lifting points of the rotor are released, and the boom of the main crawler crane 103 is rotated to complete the alignment of the rotor and the main shaft.

[0050] S10. Leveling adjustment: After the wind rotor is hoisted, slowly unload the force and adjust the ballast water of the floating foundation 201 to ensure that its loading condition meets the towing requirements of the next stage;

[0051] The present invention utilizes a main crawler crane 103, an auxiliary crawler crane 102, and a truck crane 101 to coordinately complete the assembly of a wind turbine unit and a floating platform at a coastal wharf, thereby alleviating the pressure on the scarce resources of self-elevating wind turbine installation vessels in deepwater areas and effectively reducing cost investment. In addition, the floating foundation 201 is less affected by wind speed, waves, and current speed in the harbor, greatly reducing the difficulty of aligning and installing the wind turbine unit and providing high safety. Furthermore, the advantage of the wharf yard area is fully utilized, and the truck crane 101 is used in advance to complete the assembly of the wind rotor, thereby significantly shortening the construction period and reducing costs.

[0052] See also Figure 4-Figure 6In the cabin installation and wind wheel assembly processes in steps S6 and S8, a sling is used. The sling is arranged at the ends of the main crawler crane 103 and the automobile crane 101, and the sling includes a hanger 1 and a sling 2. The bottom of the hanger 1 is fixedly connected with an arc cover frame 3, and the hanger 1 is connected to the middle of the arc cover frame 3. An adjusting arc rod 4 is provided on the inner side of the arc cover frame 3. One end of the sling 2 is connected to one side of the adjusting arc rod 4 through a clamping component. The clamping component is used to connect the sling 2 and the adjusting arc rod 4 and form an enclosed state. The clamping component includes a buckle seat 61 and a mouth buckle head 62. The mouth buckle head 62 is fixedly connected to one end of the sling 2, and the buckle seat 61 is fixedly connected to one side of the adjusting arc rod 4. A buckle groove 611 is provided in the middle of the buckle seat 61, and the buckle groove A clamping column 612 is slidably connected at 611, and a hydraulic cylinder 63 is fixedly connected to the outer side of the buckle seat 61, and the output end of the hydraulic cylinder 63 is fixedly connected to the clamping column 612 through a coupling. A tooth opening 41 is provided on the upper part of the adjusting arc rod 4, and a gear 11 is rotatably connected to the inner side of the hanger 1, and the gear 11 is meshed with the tooth opening 41 for transmission. A driving component 1 is provided on the rear side of the gear 11, and the driving component 1 is used to drive the adjusting arc rod 4 to rotate. The present invention is used in conjunction with the nacelle installation and wind wheel assembly processes through the hanger, which uses the gear 11 to mesh with the tooth opening 41, and then adjusts the arc rod 4 to slide at the arc cover frame 3, so as to adjust the angle of the wind wheel blade 204, thereby facilitating the installation of the fan blade 204 and solving the problem of troublesome angle adjustment of the blade 204. The problem is that a tightening box 5 is provided on the other side of the adjusting arc rod 4, and the inner side of the tightening box 5 is rotatably connected to the winding shaft 51 and the other end of the sling 2 is fixedly connected to the winding shaft 51, and a driving component 2 is provided on the rear side of the winding shaft 51. The driving component 2 is used to drive the winding shaft 51 to rotate and wind the sling 2. The driving component 1 and the driving component 2 have the same structure, and the driving component 1 and the driving component 2 both include a worm gear 71, a worm 72 and a servo motor 73. The worm gear 71 and the worm 72 are engaged for transmission, and the output end of the servo motor 73 is fixedly connected to one end of the worm 72. The worm gear 71 at the driving component 2 is fixedly connected to one end of the winding shaft 51, and the worm 72 at the driving component 2 is rotatably connected to the inner side of the tightening box 5. The worm gear 71 at the driving component 2 and The outside of the tightening box 5 is fixedly connected, a worm gear 71 of the driving component is fixedly connected to one side of the gear 11, a worm 72 of the driving component is rotatably connected to the inside of the hanger 1, a worm gear 71 of the driving component is fixedly connected to the outside of the hanger 1, and a pressure wheel assembly is provided at the bottom end of the adjusting arc rod 4, and the pressure wheel assembly is used to press the hoisted object. The sling 2 is reeled in by setting a reel-up shaft 51 to ensure the stability and firmness of the sling during hoisting. At the same time, by setting a clamping component, it is convenient to fix and loosen the hoisted object, thereby improving the convenience of the equipment. The pressure wheel assembly includes a bent rod 81 and a rubber wheel 82 rotatably connected to its end. The bent rod 81 is hinged to the end of the adjusting arc rod 4 away from the rubber wheel 82, and a telescopic rod 83 is hinged to the middle of the bent rod 81.The end of the telescopic rod 83 away from the telescopic rod 83 is hinged to the end of the adjusting arc rod 4. A spring 84 is provided on the outside of the telescopic rod 83. By providing a pressure wheel assembly, a buffer is provided between the hoisted object and the adjusting arc rod 4, so that the hoisted object will not be deformed due to the strong contraction force when tightening.

[0053] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.

[0054] The use of the sling in S6 and S8 of the present invention is the same. Taking the assembly of the wind wheel as an example, the working principle of the sling is: first, the sling is installed on the lifting end of the automobile crane 101, and then the sling is moved to the wind wheel blade 204 by the automobile crane 101, and the adjusting arc rod 4 is placed on the upper part of the blade 204, and then the sling 2 is passed around the bottom side of the blade 204, and then the sling 2 and the adjusting arc rod 4 are clamped by the clamping component. When clamping, the hydraulic cylinder 63 drives the clamping column 612 to retract, and then the mouth buckle 62 is inserted into the buckle groove 611, and then the hydraulic cylinder 63 pushes the clamping column 612 through the mouth buckle 62, and then the sling 2 and the adjusting arc rod 4 are fixed, and then the servo motor 73 at the second driving component drives the worm 72 to engage with the worm gear 71, and then the worm gear 71 drives The dynamic reeling shaft 51 rotates, causing the reeling shaft 51 to reel in the sling 2, so that the sling 2 fastens the blade 204 to the adjusting arc rod 4. At the same time, the rubber wheel 82 contacts the blade 204, and the spring 84 and the telescopic rod 83 cooperate to play a buffering role, so that the blade 204 and the adjusting arc rod 4 are buffered, so that the blade 204 is fastened and will not be deformed due to the strong contraction force. Then, the blade 204 is lifted by two sets of car cranes 101 and moved to the hub 205, and then the worm gear 71 at one part of the driving component drives the worm 72 to engage with the worm gear 71, and then the worm gear 71 drives the reeling shaft 51 to rotate, so that the gear 11 engages with the tooth mouth 41, and then the adjusting arc rod 4 slides at the arc cover frame 3, so that the angle of the wind wheel blade 204 can be adjusted.

[0055] It should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus.

[0056] While embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions, and variations may be made to these embodiments without departing from the principles and spirit of the invention, and that the scope of the invention is defined by the appended claims and their equivalents.

Claims

1. A floating wind turbine installation method, characterized in that: The construction steps include: S1. Crawler crane assembly and positioning: After the crawler crane is assembled in the yard behind the wharf, the main and auxiliary crawler cranes are moved forward to the designated positions at the wharf berth; S2. Unloading of wind turbine components: The transport vessel carrying wind turbine components is moored at the berth. The main and auxiliary crawler cranes and truck crane are used to barge the wind turbine components to the designated location on the dock. After the barge is completed, the transport vessel unties the mooring and departs. S3. Floating foundation berthing: The floating foundation slowly berths to the pier with the cooperation of three tugboats and completes the temporary mooring at the pier; S4. Tower installation: After the dock mooring is completed, the multi-section tower is installed on the floating foundation wind turbine column using the main and auxiliary crawler cranes; S5. One-time adjustment of levelness: After each tower section is hoisted, the ballast water of the floating foundation is adjusted to ensure that its levelness meets the hoisting requirements of the next stage; S6. Nacelle installation: Use the main crawler crane to install the nacelle on the top of the tower; S7. Secondary adjustment of levelness: After the nacelle is hoisted, the ballast water of the floating foundation is adjusted to ensure that its levelness meets the requirements of the next stage of hoisting; S8. Wind rotor assembly: After the blades are turned over, two truck cranes are used to assemble the blades and the hub; S9. Wind rotor hoisting: After the main crawler crane and the truck crane complete the turning of the wind rotor, the main crawler crane completes the alignment and installation of the wind rotor and the main shaft; S10. Three-time adjustment of levelness: After the wind rotor is hoisted, the ballast water of the floating foundation is adjusted to ensure that its loading condition meets the towing requirements of the next stage; A sling is used in both the nacelle installation and wind wheel assembly processes in steps S6 and S8. The sling is provided at the ends of the main crawler crane and the truck crane, and includes a hanger and a sling. The bottom of the hanger is fixedly connected to an arc-shaped cover frame, and the hanger is connected to the middle of the arc-shaped cover frame. An adjustment arc-shaped rod is provided on the inner side of the arc-shaped cover frame, and a tooth opening is provided on the upper part of the adjustment arc-shaped rod. A gear is rotatably connected to the inner side of the hanger, and the gear meshes with the tooth opening for transmission. A driving component 1 is provided on the rear side of the gear, and the driving component 1 is used to drive the adjustment arc-shaped rod to rotate; One end of the sling is connected to one side of the adjusting arc rod through a clamping member, and the clamping member is used to connect the sling and the adjusting arc rod to form an enclosed state; A tightening box is provided on the other side of the adjusting arc rod, and a winding shaft is rotatably connected to the inner side of the tightening box, and the other end of the sling is fixedly connected to the winding shaft. A driving component 2 is provided on the rear side of the winding shaft, and the driving component 2 is used to drive the winding shaft to rotate and wind the sling; The bottom end of the adjusting arc rod is provided with a pressing wheel assembly, and the pressing wheel assembly is used for pressing the hoisted object.

2. A floating wind turbine installation method according to claim 1, characterized in that: The driving components 1 and 2 have the same structure, and both of them include a worm wheel, a worm and a servo motor. The worm wheel and the worm are meshed and driven, and the output end of the servo motor is fixedly connected to one end of the worm.

3. A floating wind turbine installation method according to claim 2, characterized in that: The worm wheel at the second driving member is fixedly connected to one end of the winding shaft, the worm at the second driving member is rotationally connected to the inner side of the tightening box, and the worm wheel at the second driving member is fixedly connected to the outer side of the tightening box.

4. A floating wind turbine installation method according to claim 3, characterized in that: The worm wheel at one driving component is fixedly connected to one side of the gear, the worm at one driving component is rotationally connected to the inner side of the hanger, and the worm wheel at one driving component is fixedly connected to the outer side of the hanger.

5. The method for installing a floating wind turbine according to claim 1, wherein: The clamping member includes a buckle seat and a square buckle head, the square buckle head is fixedly connected to one end of the sling, and the buckle seat is fixedly connected to one side of the adjusting arc rod; A buckle groove is provided in the middle of the buckle seat, and a clamping column is slidably connected to the buckle groove. A hydraulic cylinder is fixedly connected to the outer side of the buckle seat, and the output end of the hydraulic cylinder is fixedly connected to the clamping column through a coupling.

6. The method for installing a floating wind turbine according to claim 1, wherein: The pressure wheel assembly includes a bent rod and a rubber wheel rotatably connected to its end. The bent rod is hinged to the end of the adjusting arc rod away from the rubber wheel, and a telescopic rod is hinged to the middle of the bent rod, and one end of the telescopic rod away from the telescopic rod is hinged to the end of the adjusting arc rod, and a spring is provided on the outside of the telescopic rod.

Citation Information

Patent Citations

  • Offshore wind driven generator split installation construction method

    CN106677995A

  • Mounting method for offshore wind turbine

    CN113090470A