A device capable of real-time monitoring of soil deformation of multiple types of foundation pits
By designing a monitoring device including a shell, elastic layer, coating layer, positioner, processor, pressure plate and refrigeration components, the problem that traditional monitoring equipment cannot monitor irregular deformation of the foundation pit soil under complex geological conditions is solved, real-time monitoring and accurate simulation of the shape of the depression holes is achieved.
Patent Information
- Application Number
- CN202211594481.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-13
- Publication Date
- 2025-04-18
- Estimated Expiration
- 2042-12-13
AI Technical Summary
Under complex geological conditions, traditional monitoring equipment cannot effectively monitor irregular deformation of foundation pit soil and changes in depression holes due to loss of vision, making it difficult to achieve real-time monitoring and accurate simulation.
A monitoring device including a housing, a first and a second elastic layer, a coating layer, a positioner, a processor, a press plate and a refrigeration assembly is designed. By pouring liquid into the area between the housing and the elastic layer and deforming the first elastic layer to fill the depression with gravity, the shape of the depression hole is simulated in conjunction with data from the positioner and processor, and the third elastic layer is formed into a solid form through the refrigeration assembly to simulate the depression profile.
Real-time monitoring of foundation pit soil and accurate simulation of depression holes in the absence of field of view are achieved. The depression profile can be monitored at any time point and the continuity and accuracy of monitoring are ensured. It is suitable for soil deformation monitoring of foundation pit soil under complex geological conditions.
Smart Images

Figure CN116222407B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of geological conditions, and in particular to a device capable of real-time monitoring of deformation of soil bodies of multiple types of foundation pits. Background Art
[0002] In the process of monitoring the deformation of foundation pit soil, most of the soil deformation is uniform, so the monitoring work is relatively simple. For areas with complex geological conditions, in the process of monitoring the deformation of foundation pit soil, because the soil deformation speeds in different areas of the foundation pit are different, long-term monitoring takes too long. Moreover, in the monitoring process, if there is a local depression on the ground, the shape of the depression will further change in an irregular manner under complex geological conditions. For large-area foundation pits, most monitoring equipment is difficult to carry out corresponding monitoring work for the above situation. Therefore, in order to quickly confirm the probability of depression caused by the geological conditions in the area corresponding to the foundation pit, it is necessary to fill the foundation pit with heavy objects to simulate the state after the foundation pit is backfilled, so as to obtain the foundation pit collapse points in advance and facilitate the corresponding pre-remediation. However, the method of filling heavy objects makes it impossible for traditional monitoring equipment to carry out corresponding monitoring work due to the loss of field of view. Summary of the invention
[0003] In view of the above-mentioned existing problems, the technical problem to be solved by the present invention is to be able to effectively monitor the further changes of the sunken holes during the ground subsidence process without vision, and at the same time to be able to make real-time judgment on the changing state of the sunken holes and simulate the shape of the sunken holes, so as to provide a device with high accuracy that can monitor the deformation of multiple types of foundation pit soil in real time.
[0004] The present invention provides a device capable of real-time monitoring of the deformation of multiple types of foundation pit soil bodies, comprising a plurality of monitoring mechanisms, wherein the monitoring mechanisms comprise a shell, a first elastic layer is provided at the bottom of the shell, a second elastic layer is provided at the top of the shell, liquid is poured into the area between the shell, the first elastic layer and the second elastic layer, the top of the first elastic layer is connected to the bottom of the second elastic layer by a plurality of connecting lines, a coating layer is provided at the bottom of the first elastic layer abutting therewith, a plurality of evenly distributed locators are embedded in the coating layer, and a processor is further included, the locator is connected to the processor signal, and the top of the shell is provided with a A pressure plate abutting against it, the interior of the pressure plate is hollow, the interior of the pressure plate is connected to an external water source, the bottom of the pressure plate is provided with a third elastic layer fixedly connected to it, the pressure plate is provided with a plurality of first through holes and a plurality of second through holes, the cavity formed between the third elastic layer and the pressure plate is connected to the pressure plate through the first through holes, the third elastic layer is hollow, the top of the third elastic layer is provided with a plurality of third through holes, the pressure plate is connected to the interior of the third elastic layer through the second through holes, a refrigeration component is provided in the third elastic layer, and the positioner and the processor are both electrically connected to an external power supply.
[0005] Preferably, the refrigeration assembly includes a plurality of hoses, a plurality of partitions are provided inside the pressure plate, liquid nitrogen is introduced into the space between the pressure plate and the partitions, the space between the pressure plate and the partitions is connected to the end of the hose, and the second pipe is used for introducing liquid nitrogen.
[0006] Preferably, a first pipe and several second pipes are provided on the top of the pressure plate, the first pipe is connected to the pressure plate, the first pipe is used to introduce an external water source, the second pipe is connected to the pressure plate, and the space between the pressure plate and the partition is connected to the second pipe.
[0007] Preferably, a connecting hole is provided on the side wall of the shell, a connecting tube is provided on the edge of the pressure plate, the connecting tube is inserted into the connecting hole, the connecting tube is used to pass liquid, the connecting tube is connected with the interior of the shell through the connecting hole, and a switch valve is provided on the connecting tube.
[0008] Preferably, it also includes a plurality of 3D cameras, and the 3D cameras are located on the periphery of the monitoring mechanism.
[0009] Preferably, different third elastic layers are provided at their bottoms with marking layers of different colors.
[0010] Preferably, a plurality of electric telescopic rods are provided on the top of the pressure plate, the telescopic ends of the electric telescopic rods are fixedly connected to the top of the pressure plate, the fixed ends of the electric telescopic rods are provided with fixed rods fixedly connected thereto, the fixed rods are used to be fixed on the ground, the electric telescopic rods are electrically connected to an external power supply, and the electric telescopic rods are connected to the processor signals.
[0011] The beneficial effects of the present invention are:
[0012] The present invention provides a device capable of real-time monitoring of deformation of multiple types of foundation pit soil. When monitoring the soil of the foundation pit, the coating layer is laid flat on the soil surface of the foundation pit, and then the monitoring mechanism is placed into the foundation pit at an angle perpendicular to the coating layer according to the shape and position of the foundation pit until the foundation pit is filled with the monitoring mechanism, and then the area between the shell, the first elastic layer and the second elastic layer is filled with liquid, and the third elastic layer at the bottom of the pressing plate is pressed tightly by the first elastic layer. Under the action of the pressing plate, the liquid in the area between the shell, the first elastic layer and the second elastic layer is prevented from being pushed open. Under the pressure of the foundation pit soil by the device and the influence of the softness of the soil and geological factors, Under the influence of the impact, the foundation pit soil will deform downward to a certain extent, causing multiple depressions in the foundation pit soil. When it is necessary to confirm the depression at a certain point in time, the liquid in the area between the shell, the first elastic layer and the second elastic layer can cause the first elastic layer to deform and fill the depression of the foundation pit soil under the action of gravity, so that the coating layer and the depression are completely fitted together, and the coating layer at the depression is stretched out and the multiple locators on the coating layer at the depression detect their own positions, and the detection point data of the multiple locators are sent to the processor, so that the processor simulates the contour of the depression according to the detection data of the shape of the depression. At this time, the second elastic layer The second elastic layer is pulled downward by the action of the plurality of connecting lines aligned with the foundation pit soil, so that the depression on the surface of the second elastic layer can be close to the contour shape of the depression at the foundation pit soil, and the pressure plate, under the action of the external water source, fills the cavity formed between the third elastic layer and the pressure plate with water, so that a protrusion corresponding to the depression on the surface of the second elastic layer is formed on the surface of the third elastic layer, and then the water source in the third elastic layer can be frozen by the refrigeration component at this time, so that the third elastic layer can form an integrated solid form with the water source inside it after freezing, and then the pressure plate is lifted, so that the contour of the depression at the foundation pit soil can be simulated, and because the water source is frozen and solidified The volume becomes smaller, and through the cooperation of the third through hole on the third elastic layer, the pressure plate and the first through hole, the ice body in the third elastic layer due to the reduction in volume can be compensated by water source, so as to fill the volume reduced by solidification, and ensure that the third elastic layer can always be in close contact with the second elastic layer, so that the simulation of the contour of the depression of the foundation pit soil body is more accurate. By comparing the contour of the depression of the foundation pit soil body simulated by the detection point data of multiple locators and the contour of the depression of the foundation pit soil body simulated after the water in the third elastic layer solidifies, if the difference is not large, the contour of the depression of the foundation pit soil body simulated after the solidification of the third elastic layer and the final contour after filling the thickness of the coating layer can be used as the standard.If the gap is large, the contour of the foundation pit soil depression simulated by the detection point data of multiple locators can be used as the standard. Through the use of this device, it is possible to simultaneously monitor the contour of the foundation pit soil depression at any time point, monitor the contour of the foundation pit soil depression without field of view, and monitor the foundation pit soil depression with a high degree of irregularity. At the same time, it can also realize the non-separation monitoring of the foundation pit soil depression, ensuring the continuity and accuracy of monitoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only preferred embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0014] Figure 1 It is a cross-sectional view of the overall structure of a device capable of real-time monitoring of deformation of multiple types of foundation pit soil bodies according to the present invention;
[0015] Figure 2 The present invention is a device capable of real-time monitoring of deformation of multiple types of foundation pit soil bodies. Figure 1 A local enlarged schematic diagram;
[0016] Figure 3 The present invention is a device capable of real-time monitoring of deformation of multiple types of foundation pit soil bodies. Figure 1 A local enlarged schematic diagram of point B.
[0017] In the figure, 1 is a shell, 2 is a first elastic layer, 3 is a second elastic layer, 4 is a connecting line, 5 is a coating layer, 6 is a positioner, 7 is a processor, 8 is a pressure plate, 9 is a third elastic layer, 10 is a first through hole, 11 is a second through hole, 12 is a third through hole, 13 is a hose, 14 is a partition, 15 is a first pipeline, 16 is a second pipeline, 17 is a connecting hole, 18 is a connecting pipe, 19 is a switch valve, 20 is a 3D camera, 21 is an electric telescopic rod, and 22 is a fixed rod. DETAILED DESCRIPTION
[0018] In order to better understand the technical content of the present invention, specific embodiments are provided below, and the present invention is further described in conjunction with the accompanying drawings.
[0019] See also Figures 1 to 3The present invention provides a device capable of real-time monitoring of deformation of multiple types of foundation pit soil, including a plurality of monitoring mechanisms, wherein the monitoring mechanism comprises a shell 1, a first elastic layer 2 is provided at the bottom of the shell 1, a second elastic layer 3 is provided at the top of the shell 1, a liquid is poured into the area between the shell 1, the first elastic layer 2 and the second elastic layer 3, the top of the first elastic layer 2 is connected to the bottom of the second elastic layer 3 by a plurality of connecting lines 4, a coating layer 5 abutting the first elastic layer 2 is provided at the bottom, a plurality of evenly distributed positioners 6 are embedded in the coating layer 5, and a processor 7 is also included, the positioner 6 is connected to the processor 7 by signal, a pressing plate 8 abutting the shell 1 is provided at the top, and the pressing plate 8 abuts the shell 1. The interior of the plate 8 is hollow, and the interior of the pressing plate 8 is connected to an external water source. The bottom of the pressing plate 8 is provided with a third elastic layer 9 fixedly connected thereto, and the pressing plate 8 is provided with a plurality of first through holes 10 and a plurality of second through holes 11. The cavity formed between the third elastic layer 9 and the pressing plate 8 is connected to the pressing plate 8 through the first through holes 10. The third elastic layer 9 is hollow, and a plurality of third through holes 12 are provided on the top of the third elastic layer 9. The pressing plate 8 is connected to the interior of the third elastic layer 9 through the second through holes 11. A refrigeration component is provided in the third elastic layer 9. The positioner 6 and the processor 7 are both electrically connected to an external power supply. When the soil of the foundation pit is monitored, the coating layer 5 is leveled. The monitoring mechanism is laid on the soil surface of the foundation pit. At this time, the position of the locator 6 on the coating layer 5 can be regarded as the initial position. Then, according to the shape and position of the foundation pit, the monitoring mechanism is placed into the foundation pit at a perpendicular angle to the coating layer 5 until the foundation pit is filled with the monitoring mechanism. Then, the area between the shell 1, the first elastic layer 2 and the second elastic layer 3 is filled with liquid, and the third elastic layer 9 at the bottom of the pressing plate 8 is pressed tightly by the first elastic layer 2. Under the action of the pressing plate 8, the liquid in the area between the shell 1, the first elastic layer 2 and the second elastic layer 3 is prevented from being pushed open. Under the pressure of the device on the foundation pit soil, the softness of the soil and the influence of geological factors, the foundation pit is The pit soil will deform downward to a certain extent, causing multiple depressions in the foundation pit soil. When it is necessary to confirm the depression at a certain point in time, the liquid in the area between the shell 1, the first elastic layer 2 and the second elastic layer 3 can deform the first elastic layer 2 under the action of gravity and fill the depression of the foundation pit soil, so that the coating layer 5 is completely attached to the depression. The coating layer 5 at the depression is stretched open and the multiple locators 6 on the coating layer 5 at the depression detect their own positions, and the detection point data of the multiple locators 6 are sent to the processor 7, so that the processor 7 simulates the contour of the depression according to the detection data of the shape of the depression. At this time,The second elastic layer 3 is pulled downward by the multiple connecting lines 4 aligned with the foundation pit soil, so that the depression on the surface of the second elastic layer 3 can be close to the contour shape of the depression of the foundation pit soil, and the pressing plate 8, under the action of the external water source, fills the cavity formed between the third elastic layer 9 and the pressing plate 8 with water, so that a protrusion corresponding to the depression on the surface of the second elastic layer 3 is formed on the surface of the third elastic layer 9, and then the water source in the third elastic layer 9 can be frozen by the refrigeration component, so that the third elastic layer 9 can form an integrated solid form with the water source inside it after freezing, and then the pressing plate 8 is lifted, so that the contour of the depression of the foundation pit soil can be simulated, and because the volume of the water source decreases after freezing and solidification, the third through hole 12 on the third elastic layer 9, the pressing plate 8 and the first through hole 10 can be used to compensate for the ice body in the third elastic layer 9 due to the decrease in volume, thereby compensating the volume reduced due to solidification. Filling is performed to ensure that the third elastic layer 9 can always be in close contact with the second elastic layer 3, so that the simulation of the contour of the foundation pit soil depression is more accurate. The contour of the foundation pit soil depression simulated by the detection point data of the plurality of locators 6 and the contour of the foundation pit soil depression simulated after the water in the third elastic layer 9 solidifies are compared. If the difference is not large, the contour of the foundation pit soil depression simulated after the third elastic layer 9 solidifies and the final contour after filling the thickness of the coating layer 5 can be used as the standard. If the difference is large, The contour of the foundation pit soil depression simulated by the detection point data of the multiple locators 6 can be used as the standard. Through the use of this device, it is possible to simultaneously monitor the contour of the foundation pit soil depression at any time point, monitor the contour of the foundation pit soil depression without field of view, and monitor the foundation pit soil depression with a high degree of irregularity, such as for depressions with a cross-section changing from a semicircular shape to a gourd shape or an inverted trapezoid. At the same time, it can also realize non-separation monitoring of the foundation pit soil depression, ensuring the continuity and accuracy of monitoring, and is more suitable for monitoring larger depressions.
[0020] Specifically, the refrigeration assembly includes a plurality of hoses 13, a plurality of partitions 14 are provided inside the pressure plate 8, liquid nitrogen is introduced into the space between the pressure plate 8 and the partition 14, the space between the pressure plate 8 and the partition 14 is connected with the end of the hose 13, the liquid nitrogen in the space between the pressure plate 8 and the partition 14 is introduced into the hose 13, and the water in the third elastic layer 9 is cooled by the cooperation between the hose 13 and the liquid nitrogen, so as to shape the water in the third elastic layer 9, ensuring that the shape contour formed is highly similar to the contour of the depressed part of the foundation pit soil.
[0021] Specifically, a first pipe 15 and a plurality of second pipes 16 are provided on the top of the pressing plate 8, the first pipe 15 is connected to the pressing plate 8, the first pipe 15 is used to introduce an external water source, the second pipe 16 is connected to the pressing plate 8, the space between the pressing plate 8 and the partition 14 is connected to the second pipe 16, and the second pipe 16 is used to introduce liquid nitrogen. Through the cooperation of the first pipe 15 and the plurality of second pipes 16, the water source and the liquid nitrogen can be injected separately when the device needs to perform contour shaping work, which is beneficial to the subsequent contour shaping work, and the water source and the liquid nitrogen can also be injected separately according to actual needs.
[0022] Specifically, a connecting hole 17 is provided on the side wall of the shell 1, and a connecting pipe 18 is provided on the edge of the pressure plate 8. The connecting pipe 18 is inserted into the connecting hole 17. The connecting pipe 18 is used to pass liquid. The connecting pipe 18 is connected with the interior of the shell 1 through the connecting hole 17. A switch valve 19 is provided on the connecting pipe 18. Through the cooperation between the connecting hole 17 and the connecting pipe 18, the liquid can be easily injected into the shell 1. At the same time, through the action of the switch valve 19, the switch valve 19 can be opened when needed, thereby facilitating the injection and extraction of liquid, and further facilitating the use, disassembly and transportation of the device.
[0023] Specifically, it also includes a plurality of 3D cameras 20, which are located at the periphery of the monitoring mechanism. Through the action of the 3D cameras 20, the contour formed by the third elastic layer 9 at any time period can be monitored without affecting the continuous changes in the depression of the foundation pit soil.
[0024] Specifically, different marking layers (not shown) of different colors are provided at the bottom of the third elastic layers 9. Through the effect of the marking layers (not shown), the depression contours of the depressions in the foundation pit soil at different positions can be accurately known, and confusion is not likely to occur.
[0025] Specifically, a plurality of electric telescopic rods 21 are provided on the top of the pressing plate 8, and the telescopic ends of the electric telescopic rods 21 are fixedly connected to the top of the pressing plate 8. The fixed ends of the electric telescopic rods 21 are provided with fixed rods 22 fixedly connected thereto, and the fixed rods 22 are used to be fixed on the ground. The electric telescopic rods 21 are electrically connected to an external power supply, and the electric telescopic rods 21 are signal-connected to the processor 7. Through the action of the fixed rods 22, the electric telescopic rods 21 and the pressing plate 8 can be effectively fixed to avoid separation of the pressing plate 8 from the shell 1, thereby ensuring the reliability of the use of the device. At the same time, it is convenient to lift the pressing plate 8 through the electric telescopic rods 21 and perform corresponding contour monitoring on the third elastic layer 9.
[0026] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A device capable of real-time monitoring of soil deformation of multiple types of foundation pits, characterized in that: The invention comprises several monitoring mechanisms, wherein the monitoring mechanism comprises a shell, a first elastic layer is provided at the bottom of the shell, a second elastic layer is provided at the top of the shell, liquid is perfused in the area between the shell, the first elastic layer and the second elastic layer, the top of the first elastic layer is connected to the bottom of the second elastic layer by several connecting lines, a coating layer abutting therewith is provided at the bottom of the first elastic layer, a plurality of evenly distributed positioners are embedded in the coating layer, and a processor is also included, the positioner is connected to the processor signal, a pressing plate abutting therewith is provided at the top of the shell, the interior of the pressing plate is hollow, the interior of the pressing plate is connected to an external water source, a third elastic layer fixedly connected thereto is provided at the bottom of the pressing plate, a plurality of first through holes and a plurality of second through holes are provided on the pressing plate, a cavity formed between the third elastic layer and the pressing plate is connected to the pressing plate through the first through holes, the third elastic layer is hollow, a plurality of third through holes are provided at the top of the third elastic layer, the pressing plate is connected to the interior of the third elastic layer through the second through holes, a refrigeration component is provided in the third elastic layer, and the positioner and the processor are both electrically connected to an external power supply.
2. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 1, characterized in that: The refrigeration assembly includes a plurality of hoses, a plurality of partitions are arranged inside the pressure plate, liquid nitrogen is introduced into the space between the pressure plate and the partitions, and the space between the pressure plate and the partitions is connected to the end of the hose.
3. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 2, characterized in that: A first pipe and a plurality of second pipes are provided on the top of the pressing plate, the first pipe is connected to the pressing plate, the first pipe is used to introduce an external water source, the second pipe is connected to the pressing plate, the space between the pressing plate and the partition is connected to the second pipe, and the second pipe is used to introduce liquid nitrogen.
4. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 1, characterized in that: A connecting hole is provided on the side wall of the shell, a connecting pipe is provided on the edge of the pressure plate, the connecting pipe is inserted into the connecting hole, the connecting pipe is used to pass liquid, the connecting pipe is connected with the interior of the shell through the connecting hole, and a switch valve is provided on the connecting pipe.
5. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 1, characterized in that: It also includes a plurality of 3D cameras, which are located on the periphery of the monitoring mechanism.
6. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 1, characterized in that: The bottoms of different third elastic layers are provided with marking layers of different colors.
7. The device capable of real-time monitoring of deformation of multiple types of foundation pit soils according to claim 1, characterized in that: A plurality of electric telescopic rods are provided on the top of the pressing plate, the telescopic ends of the electric telescopic rods are fixedly connected to the top of the pressing plate, the fixed ends of the electric telescopic rods are provided with fixed rods fixedly connected thereto, the fixed rods are used to be fixed on the ground, the electric telescopic rods are electrically connected to an external power supply, and the electric telescopic rods are connected to the processor signal.
Citation Information
Patent Citations
Steel cofferdam bottom sealing method with seal casting
CN108867671A
Multifunctional device for monitoring geological environment of coal mining subsidence area
CN113091826A