Elevation line layout method for detailed drawing of steel-concrete composite beam with beam at the top of pier

CN116861517BActive Publication Date: 2026-11-17CHINA RAILWAY GUIZHOU HIGHWAY CONSTR CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310709749.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-06-15
Publication Date
2026-11-17
Estimated Expiration
2043-06-15

AI Technical Summary

Technical Problem

[0002]对于普通钢结构桥梁,采用基于AutoCAD软件的纬地道路系统软件进行立面线形放样技术已非常成熟,但对于中墩预抬高,跨中有预拱的槽型钢混组合梁,仅采用纬地道路系统软件进行放样无法完成

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116861517B_ABST
    Figure CN116861517B_ABST
Patent Text Reader

Abstract

This invention relates to the field of elevation alignment layout technology in bridge engineering, and provides a method for detailed elevation alignment layout of steel-concrete composite beams with beams falling on the top of the pier. This method generally includes: determining the Y-axis based on the longitudinal slope. pn Values, list the known points and their design pre-camber coordinates (Y). gn The value and Y are obtained using the commonly used quadratic parabola formula for steel beams. Zn Value, Y n For equal to Y pn Value, Y zn Value and Y gn The values ​​are added together, and a point is taken every 1000mm (X2, Y2), (X3, Y3)...(X...). n Y n The process involves organizing coordinates, drawing lines, and completing the layout. The layout method of this invention is fast, accurate, and has minimal error, providing a good method for the layout of the manufacturing lines of steel-concrete composite beams for mid-pier top placement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of elevation alignment layout technology in bridge engineering, and in particular to a method for detailed elevation alignment layout of steel-concrete composite beams with beams falling on the top of the pier. Background Technology

[0002] For ordinary steel structure bridges, the elevation alignment layout technology using the Weidi Road System software based on AutoCAD is very mature. However, for channel-shaped steel-concrete composite beams with pre-raised piers and pre-arched mid-span, the layout cannot be completed using only the Weidi Road System software. The alignment of the main components of the channel-shaped steel-concrete composite beam, such as the top plate, bottom plate, web plate, and diaphragms, determines the overall bridge alignment. The alignment of these main components is a key technical point in the manufacturing of channel-shaped steel-concrete composite beams, especially the web elevation alignment layout of channel-shaped steel-concrete composite beams with pre-raised piers and pre-arched mid-span, which is the most complex. Therefore, in the construction of steel-concrete composite beams with pier top placement, it is necessary to propose a method for detailed elevation alignment layout of steel-concrete composite beam drawings for such beams. Summary of the Invention

[0003] To solve the above-mentioned technical problems, the present invention provides a method for the elevation line layout of steel-concrete composite beams with beams falling on the top of the pier for detailed drawing.

[0004] The present invention provides the following technical solution to achieve the above objectives: A method for elevation alignment layout in the detailed drawing of a steel-concrete composite beam with a mid-pier top, S1: Taking the small mileage station line of the steel-concrete composite beam as the origin O (0,0), the horizontal direction as the X-axis, the direction of the plumb bob to the ground as the Y-axis, the nearest adjacent support position as the second point (X1, Y1), and taking a point every 1000mm, in the following order: (X2, Y2), (X3, Y3)... (X... n Y n ); Y n The value of Y is equal to pn Value, Y zn Value and Y gn Add the values ​​together; S2: Display the final linear coordinates (X...) of all points in an Excel spreadsheet. n Y n ) Use "X" n &","&Y n Commands are entered in the same column; S3: Create a new drawing file in AutoCAD software, copy all the coordinates entered in the same column into CAD, and use the CAD curve spline command to draw the final line shape, thus obtaining the elevation curve unfolding along the center line of the bridge; S4: Based on the elevation curves that unfold along the bridge centerline, draw the outline of the web that unfolds along the bridge centerline. The line layout is now complete.

[0005] In the aforementioned method for detailed elevation line layout of the steel-concrete composite beam at the top of the pier, in step S1, an Excel table is used to list the points corresponding to each 1000mm interval: (X1, Y... p1 (X2, Y) p2 )……(X) n Y pn (X1, Y) z1 (X2, Y) z2 )……(X) n Y zn ) and the known design precamber coordinates (X1, Y) g1 (X2, Y) g2 )……(X) n Y gn ); The Y pn The values ​​are all derived from the longitudinal slope value P% parameter in the design drawings, Y Pn =P%X n ; The Y Zn The values ​​are all calculated using the commonly used quadratic parabola formula for steel beams, Y. zn =Y zLn ×[1-(X n -L / 2)² / (L / 2)²];Y ZLn For L n The maximum pre-camber value at the mid-span of a single span is calculated empirically to be 0.0005 times the span length L of that span. Beneficial effects

[0006] Compared with the prior art, the present invention has the following beneficial effects: This invention first calculates Y based on the longitudinal slope. pn Values, list the known points and their design pre-camber coordinates (Y). gn The value and Y are obtained using the commonly used quadratic parabola formula for steel beams. Zn Value, Y n For equal to Y pn Value, Y zn Value and Y gn Add the values ​​together, and then take a point (X2, Y2), (X3, Y3) ... (X) every 1000mm. n Y nThen, the coordinates are organized, the line shape is drawn, and finally the layout is completed. This invention accurately calculates the elevation line shape Yn value of the steel beam by comprehensively considering the longitudinal slope of the bridge, the design camber of the beam at the top of the pier, and the manufacturing camber; this invention will use the elevation line shape Yn... n The values ​​are converted into AutoCAD software, and a clear, accurate, and visual steel beam elevation line drawing is created in AutoCAD, bringing convenience to construction and manufacturing personnel. The elevation line layout method of this invention has high precision, fast speed, and strong practicality, which improves the manufacturing quality of steel beams and reduces the construction difficulty of steel beam installation and beam placement on the pier top. Attached Figure Description

[0007] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below only relate to some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without any creative effort.

[0008] Figure 1 This is a schematic diagram comparing the elevation lines under different Y values ​​under various working conditions in the same coordinate system.

[0009] Figure 2 This is a schematic diagram of the elevation alignment under the influence of the longitudinal slope of the steel beam.

[0010] Figure 3 This is a schematic diagram of the facade lines under the influence of the pre-camber design.

[0011] Figure 4 This is a schematic diagram of the facade lines under the influence of the pre-camber during manufacturing.

[0012] Figure 5 It is a schematic diagram of the facade lines superimposed under various working conditions. Implementation

[0013] To enable those skilled in the art to better understand the present invention, the technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention.

[0014] It should be noted that in this invention, the terms "comprising" and "having," and any variations thereof, are intended to cover non-exclusive inclusion. For example, a process, method, system, product, or device that includes a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to these processes, methods, products, or devices. Furthermore, some terms, besides indicating orientation or positional relationships, may also have other meanings; for example, the term "above" may, in some cases, indicate a dependency or connection. Those skilled in the art can understand the specific meaning of these terms in this invention based on the specific circumstances.

[0015] Example. A method for detailed elevation line layout of a steel-concrete composite beam with a beam dropped from the pier top, comprising the following steps: S1: Taking the small mileage station line of the steel-concrete composite beam as the origin O (0,0), the horizontal direction is the X-axis, the direction of the plumb bob to the ground is the Y-axis, and the nearest adjacent support position is the second point (X1, Y1). The remaining points are taken every 1000mm, in the order of (X2, Y2), (X3, Y3)...(X... n Y n ); Where Xn is the distance from the origin O; points are taken on the horizontal X-axis to simulate the Y value at each point, which is convenient for drawing the elevation line drawing later; List the points taken every 1000mm in an Excel spreadsheet (i.e., (X1, Y1)...(X...). n Y n The one-to-one correspondence between (X1, Y) p1 (X2, Y) p2 )……(X) n Y pn ); Calculate the Y-axis at each point in an Excel spreadsheet based on the longitudinal slope value P% parameter in the design drawings. Pn Value, Y Pn =PX n All coordinates are set to mm; this step calculates the influence of the longitudinal slope on the steel beam bridge deck alignment using the length and slope ratio on the X-axis. List the corresponding points (X1, Y1, Y2) in an Excel spreadsheet. z1 (X2, Y) z2 )……(X) n Y zn ); Calculate the Y-axis for each additional 1000mm point using the commonly used quadratic parabola formula for steel beams. Zn The commonly used formula for a quadratic parabola in steel beams is: Y zn =YzLn ×[1-(X n -L / 2)² / (L / 2)²]; In the formula, Y ZLn For L n The maximum manufacturing pre-camber value at the mid-span of a single span is calculated based on experience and is 0.0005 times the span length L of that span. The manufacturing pre-camber is generated during the manufacturing process of the steel beam, and this value can be determined based on long-term technical experience.

[0016] Based on the pre-camber coordinate values ​​provided in the design drawings at intervals of 1000mm, list the pre-camber coordinates (X1, Y1, Y2) of the corresponding points in an Excel spreadsheet. g1 (X2, Y) g2 )……(X) n Y gn Because the bridge is a steel-concrete composite beam, after the steel beams are installed, concrete needs to be poured for the bridge deck. Therefore, considering the effects of dead load and 1 / 2 live load, the design drawings provide a design camber. The summation of the influence values ​​of the above working conditions on the elevation profile of the steel beam yields the final elevation profile Y of the steel beam. n Value, i.e., Y n The value of Y is equal to pn Value, Y zn Value and Y gn Adding values ​​(Excel calculation): S2: Display the final linear coordinates (X...) of all points in an Excel spreadsheet. n Y n ) Use "X" n &","&Y n "Commands are entered in the same column; this step is to organize the coordinates." S3: Create a new drawing file in AutoCAD software, copy all the coordinates entered in the same column into CAD, and use the CAD curve spline command to draw the final line shape, resulting in the elevation curve unfolding along the center line of the bridge; this arrangement is the line shape drawing, import the final coordinate data from Excel into AutoCAD, and draw a vivid and accurate elevation line shape drawing in CAD. S4: Based on the elevation curves that unfold along the bridge centerline, draw the outline of the web that unfolds along the bridge centerline. The line layout is now complete.

[0017] This facade alignment layout method can be modified and adjusted according to the actual situation of each data point. Without violating the actual theory of the layout method, the practicality of the method is ensured, which is conducive to the application of different steel beams in actual situations.

[0018] Obviously, the above description is only a part of the embodiments of the present invention, and not all of the embodiments. The above embodiments are not intended to limit the present invention, and various modifications and variations can be made to the present invention by those skilled in the art. Any combination, modification, equivalent substitution, improvement, and all other embodiments that can be made by those skilled in the art within the spirit and principles of the present invention should be within the protection scope of the present invention.

Claims

1. A method for detailed elevation line layout of a steel-concrete composite beam with a mid-pier top, characterized in that: Includes the following steps: S1: Taking the small mileage station line of the steel-concrete composite beam as the origin O (0,0), the horizontal direction is the X-axis, the direction of the plumb bob to the ground is the Y-axis, and the nearest adjacent support position is the second point (X1, Y1). The remaining points are taken every 1000mm, successively as (X2, Y2), (X3, Y3)... (X... n Y n ); Y n The value of Y is equal to pn Value, Y zn Value and Y gn Add the values ​​together; S2: Display the final linear coordinates (X) of all points in the Excel spreadsheet. n Y n ) Use "X n &","&Y n Commands are entered in the same column; S3: Create a new drawing file in AutoCAD software, copy all the coordinates entered in the same column into CAD, and use the CAD curve spline command to draw the final line shape, thus obtaining the elevation curve unfolding along the center line of the bridge; S4: Based on the elevation curves unfolded along the bridge centerline, draw the outline of the web unfolded along the bridge centerline, and the line layout is completed; In step S1, an Excel table is used to list the points corresponding to every 1000mm: (X1, Y... p1 (X2, Y) p2 ... (X) n Y pn (X1, Y) z1 (X2, Y) z2 ... (X) n Y zn ) and the known design precamber coordinates (X1, Y) g1 (X2, Y) g2 ... (X) n Y gn ); The Y pn The values ​​are all derived from the longitudinal slope value P% parameter in the design drawings, Y Pn =P%X n ; The Y Zn The values ​​are all calculated using the commonly used quadratic parabola formula for steel beams, Y. zn =Y zLn ×[1-(X n -L / 2) 2 / (L / 2) 2 ];Y ZLn For L n The maximum pre-camber value at the mid-span of a single span is calculated empirically to be 0.0005 times the span L of that span. Taking into account the bridge's longitudinal slope, the design camber of the beam at the top of the pier, and the manufacturing camber, the elevation Y-shape of the steel beam was accurately calculated. n value.

Citation Information

Patent Citations

  • Construction method for 48m sectional beam of passenger railway based on BIM technology

    CN105625188A

  • Vertical linear lofting method for manufacturing oblique crossing type steel box girder

    CN114214959A