A construction method for laying submarine small-diameter water pipelines under complex working conditions
Through the construction method of combining directional drilling and bottom drag, the problems of low construction efficiency and high cost in laying small-diameter water transfer pipelines in the seabed are solved, and safe and efficient construction under complex working conditions are achieved, and existing pipelines are avoided damage and navigational impact.
Patent Information
- Application Number
- CN202311173979.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2043-09-12
AI Technical Summary
Under complex working conditions, when laying small-diameter water supply pipelines in the seabed, the existing technology is prone to damage the existing pipelines, resulting in low construction efficiency and high cost, and affecting navigation.
Using the construction method of combining directional drilling and bottom-torch, the water supply pipeline is divided into two sections, and drilling and burying and sliding construction is carried out through directional drilling and pulley sending devices to avoid the impact on other pipelines, shorten the laying distance, and through directional drilling and Three-stage hole reaming technology ensures the rigidity and controllability of the drill rod.
Avoid the impact on other pipelines to the greatest extent, improve construction efficiency, reduce costs, and ensure the safety and navigation of pipelines.
Smart Images

Figure CN117307819B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pipeline construction, and in particular to a construction method for laying a submarine small-diameter water pipeline under complex working conditions. Background Art
[0002] When laying water pipelines across the channel to the island in the sea, it is common to encounter various submarine pipelines (optical cables, electrical cables) and other staggered arrangements. The buried depths of various pipelines are different. When the pipelines are laid in place, whether the first digging method or the later digging method is used, it is very easy to cause serious damage to the existing pipelines. Before laying, it is necessary to take various measures such as demolition, relocation, and protection for various pipelines within the influence range of pipeline laying, which greatly affects the progress of construction, increases costs, and seriously affects navigation. How to achieve safe and efficient pipeline laying of submarine water pipelines under complex working conditions is an urgent task. Summary of the invention
[0003] In view of the deficiencies existing in the prior art, the present invention provides a construction method for laying a small-diameter submarine water pipeline under complex working conditions, which solves the problems of low construction efficiency and high construction cost existing in the prior art.
[0004] According to an embodiment of the present invention, a construction method for laying a submarine small-diameter water pipeline under complex working conditions includes the following steps:
[0005] S1. Measure the total length of the water pipeline to be laid, and divide the measured total water pipeline into two sections of similar length, one section of the water pipeline is a bottom-drag pipeline, and the other section of the water pipeline is a drilled and buried pipeline;
[0006] S2. After the two pipelines are welded, one end of the drilled and buried pipeline is pulled by a tugboat on one side of the flow channel, and the movable end of the drilled and buried pipeline is pulled to the middle of the flow channel. On the other side of the flow channel, a directional drill is used to drive the drill rod to open a buried channel for the drilled and buried pipeline, and the unearthed point of the buried channel is set in the middle of the flow channel, and the drill rod is passed through the unearthed point;
[0007] S3, the drill pipe is picked up by a salvage ship and extended to a tugboat, where the drill pipe and drilling tools are disassembled and replaced with drill pipe and drilling tools for hole expansion;
[0008] S4. The directional drilling rig provides traction to pull back the drilled-buried pipeline and the bottom-drag pipeline, so that the joints of the drilled-buried pipeline and the bottom-drag pipeline enter the buried channel.
[0009] Preferably, in step S2, before dragging the drilled-buried pipeline for sliding construction, a pulley sending device for supporting the drilled-buried pipeline and the bottom-drag pipeline is installed, the pulley sending device includes a fixed pulley and a mobile pulley, the fixed pulley includes a fixed bracket installed at the sea-entering end and a pulley equidistantly installed on the top of the fixed bracket, the mobile pulley includes a mobile bracket and a pulley installed on the top of the mobile bracket, the pulleys are arranged in pairs and are installed to be tilted and rotated, and the top ends of the relative pulleys are close to each other.
[0010] Preferably, anode protection blocks are welded at equal intervals on the outer wall of the bottom-drag pipeline, and anti-corrosion treatment is performed on the welds after they are cooled.
[0011] Preferably, the welding construction of the anode protection block is carried out at the offshore end of the pulley sending device.
[0012] Preferably, the pulleys include rubber pulleys and resin pulleys, and the rubber pulleys and the resin pulleys are arranged alternately.
[0013] Preferably, the inner diameter of the buried channel is 1.2 to 1.5 times the outer diameter of the buried pipeline.
[0014] Preferably, in step S2, opening the buried channel includes: S201, when the directional drilling rig is drilling a rock layer section for the buried channel, installing a three-roller drill bit, and when drilling close to the rock layer and the silt layer, withdrawing the three-roller drill bit, replacing it with a forward-thrust rock reamer, and using the forward-thrust rock reamer to expand the junction of the rock layer and the silt layer, and withdrawing the reamer after the rock layer expansion is completed; S202, replacing it with a duckfoot plate guide head, and guiding it to the silt layer outside the rock layer through the duckfoot plate guide head, and then guiding the steel casing along the lower drill pipe, the guide steel casing is located between the rock layer and the silt layer, and finally completing the guidance of the silt layer through the duckfoot plate guide head.
[0015] Preferably, in step S201, the forward rock reamer is used to perform three-stage reaming, including successively using 12-1 / 2", φ457 reamer and φ610 reamer, and using the φ610 reamer to reame the interface between the rock layer and the silt layer.
[0016] Preferably, in step S2, when opening the buried channel, a small-diameter drill rod is used in the front section and a large-diameter drill rod is used in the rear section.
[0017] Preferably, in step S4, when pulling back the drilled and buried pipeline, a drilling tool assembly is used, the drilling tool assembly includes a drill rod, a reamer, a pull-back universal joint and a main pipeline, and the pull-back process is performed continuously.
[0018] Compared with the prior art, the present invention has the following beneficial effects:
[0019] 1. The construction technology of combining directional drilling and bottom dragging is adopted to avoid the impact on other pipelines within the pipeline laying range to the greatest extent, and the directional drilling method is adopted to shorten the laying distance of the pipeline. If the bottom dragging is adopted, the original pipeline needs to cross the obstacle before entering the water plant, while the directional drilling directly passes through the obstacle in a straight line, so that the pipe is saved to a certain extent.
[0020] 2. Both sides of the flow channel are constructed simultaneously. The bottom-drag pipeline and the drilled pipeline are welded separately. The pipeline can be fully welded directly in the existing tunnel. After that, the bottom-drag pipeline can be lowered through the pulley sending device, which improves the construction efficiency of the water supply pipeline.
[0021] 3. Use pulley sending devices, including fixed pulleys and mobile pulleys, to assist the water pipeline in sliding down. The pulleys are arranged in pairs, and the functions of the pulleys are differentiated. The rubber pulley protects and buffers the water pipeline, and the nylon pulley provides bearing capacity and reasonable support for the water pipeline, making the sliding of the water pipeline more flexible and convenient.
[0022] 4. Thickening and balancing the bottom-drag pipeline. Increasing the wall thickness of the bottom-drag pipeline not only enables the bottom-drag pipeline to sink to the bottom of the seabed, but also improves the corrosion resistance of the bottom-drag pipeline. Compared with other methods, adding balancing weight effectively controls the construction cost.
[0023] 5. Install anode protection blocks on the bottom-towed pipeline and weld and install them when the bottom-towed pipeline is about to enter the sea. This can prevent the anode protection blocks from getting stuck on the pulley during the sliding process after being welded on the bottom-towed pipeline, causing interference with the bottom-towed construction.
[0024] 6. During directional drilling construction, when passing through rock layers and silt layers, use three-stage hole expansion and increase steel casing to avoid bending of the drill rod due to uneven hardness at the junction of the rock layer and the silt layer, and ensure the rigidity and controllability of the drill rod.
[0025] 7. During directional drilling construction, if a large-diameter drill rod is used throughout the entire section, it will cause a large torque loss. If a small-diameter drill rod is used throughout the entire section, it will cause insufficient torque after the guiding distance is too long. Therefore, using a small-diameter drill rod in the front section and a large-diameter drill rod in the back section can not only save torque loss but also ensure construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a front view of the construction of salvaging drill pipe in an embodiment of the present invention.
[0027] Figure 2 This is a front view of the construction of connecting the drill rod and the water pipeline in an embodiment of the present invention.
[0028] Figure 3 This is a front view of the construction of the water supply pipeline in the embodiment of the present invention.
[0029] Figure 4 It is a top view of the construction of salvaging the drill pipe in an embodiment of the present invention.
[0030] Figure 5 The process flow chart of an embodiment of the present invention. DETAILED DESCRIPTION
[0031] The technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0032] like Figure 1-5 The present invention proposes a construction method for laying a submarine small-diameter water pipeline under complex working conditions, comprising the following steps:
[0033] S1. Measure the total length of the water pipeline to be laid, and divide the measured total water pipeline into two sections of similar length, one section of the water pipeline is a bottom-drag pipeline, and the other section of the water pipeline is a drilled and buried pipeline;
[0034] S2. After the two pipelines are welded, one end of the drilled and buried pipeline is pulled by a tugboat on one side of the flow channel, and the movable end of the drilled and buried pipeline is pulled to the middle of the flow channel. On the other side of the flow channel, a directional drill is used to drive the drill rod to open a buried channel for the drilled and buried pipeline, and the unearthed point of the buried channel is set in the middle of the flow channel, and the drill rod is passed through the unearthed point;
[0035] S3, the drill pipe is picked up by a salvage ship and extended to a tugboat, where the drill pipe and drilling tools are disassembled and replaced with drill pipe and drilling tools for hole expansion;
[0036] S4. The directional drilling rig provides traction to pull back the drilled-buried pipeline and the bottom-drag pipeline, so that the joints of the drilled-buried pipeline and the bottom-drag pipeline enter the buried channel.
[0037] Both the drilled and buried pipes and the bottom-drag pipes use thickened 12mm pipes, which is conducive to the best bottom-drag traction control.
[0038] The unearthed point of the drilled channel is set on the side of the waterway away from the entry point of the drilled channel. The drilled channel crosses the waterway, avoiding a large number of obstacles and shortening the laying length of the pipeline.
[0039] During the construction of a submarine water pipeline, the total length of the pipeline was 5.4km, the bottom-drag pipeline was set to be 2.6km long, and the drilled and buried pipeline was set to be 2.8km long. In order to speed up the construction progress, during the construction of the project, the newly built tunnel was used as a prefabrication site for steel pipe welding. The entire pipeline was divided into three sections for welding. The drilled and buried pipeline was welded in one go, and the bottom-drag pipeline was welded in two times. The weld quality of the welded pipeline was inspected. After passing the inspection, the steel pipe was promptly treated with anti-corrosion.
[0040] After the tugboat drags the bottom of the water pipeline to the unearthed point of the drilled channel, the tugboat no longer provides traction to the water pipeline. The traction of the water pipeline and the traction of the directional drilling backhaul are all provided by the directional drilling rig. The drill rod, drilling tools, transfer case and main pipeline are connected on the tugboat, and the backhaul construction of the water pipeline is carried out.
[0041] In step S2, before dragging the drilled-buried pipe for sliding construction, a pulley sending device for supporting the drilled-buried pipe and the bottom-drag pipe is installed, the pulley sending device includes a fixed pulley and a mobile pulley, the fixed pulley includes a fixed bracket installed at the sea-entering end and a pulley equidistantly installed on the top of the fixed bracket, the mobile pulley includes a mobile bracket and a pulley installed on the top of the mobile bracket, the pulleys are arranged in pairs and are installed to be tilted and rotated, and the top ends of the relative pulleys are close to each other.
[0042] The fixed bracket includes columns, beams and an operating platform. The fixed pulley is arranged at the sea-entering end of the water pipeline. The nylon pulley is used as a load-bearing wheel to support the water pipeline, and the rubber pulley is used to provide protection and buffering for the water pipeline.
[0043] The water pipeline is placed on the pulley of the pulley sending device by a tire excavator and a forklift. At the estuary, multiple tire excavators are used to assist the water pipeline to slowly slide down. When the water pipeline slides to the lower end of the fixed pulley, the optimal tide level is observed, and traction is provided by a tugboat to carry out bottom towing construction of the water pipeline.
[0044] As a preferred embodiment of the present invention, anode protection blocks are welded at equal intervals on the outer wall of the bottom-drag pipeline, and anti-corrosion treatment is performed on the weld after the weld is cooled.
[0045] An anode protection block is welded every ten meters along the bottom-drag pipeline; since the covering soil on the drilled-buried pipeline is thicker, and the wall thickness of the drilled-buried pipeline and the bottom-drag pipeline is increased from 10mm to 12mm to facilitate bottom-drag construction, the drilled-buried pipeline meets the corrosion protection requirements.
[0046] As a preferred embodiment of the present invention, the welding construction of the anode protection block is carried out at the offshore end of the pulley transmission device.
[0047] When the water pipeline is under-drag and slide construction, the directional drilling construction section can smoothly realize the slide construction without installing the anode protection block, but the pipeline with the anode protection block welded is very easy to rotate during the bottom-drag construction, causing the anode protection block to get stuck at the pulley, which will not only cause damage to the pulley, but also greatly increase the resistance during the bottom-drag, greatly reducing the bottom-drag construction efficiency. Therefore, at the sea inlet of the water pipeline, the operation platform of the slideway system is used to weld the anode protection block while under-drag, and the weld seams are treated with anti-corrosion in time after cooling.
[0048] As a preferred embodiment of the present invention, the pulleys include rubber pulleys and resin pulleys, which are arranged alternately. The rubber pulleys provide protection and buffering for the water pipeline, and the nylon pulleys provide support for the water pipeline, so that the force on the pipeline is more reasonable and the sliding is more flexible.
[0049] As a preferred embodiment of the present invention, the inner diameter of the buried channel is 1.2 to 1.5 times the outer diameter of the buried pipeline.
[0050] The hole is selected to be 1.5 times the outer diameter of the pipeline. The diameter of the tap water pipeline is D325, and the outer diameter of the hole is selected to be 325mm×1.5=485.85mm. Combined with the calculation results and the on-site address status, the hole needs to be pre-expanded to φ500. The rock layer section needs to be expanded to φ610 because of the need to lower the guide casing.
[0051] In step S2, opening the buried channel includes: S201, when the directional drilling rig is drilling a rock layer section for the buried channel, installing a three-roller drill bit, and when drilling close to the rock layer and the silt layer, withdrawing the three-roller drill bit, replacing it with a forward-thrust rock reamer, and using the forward-thrust rock reamer to expand the boundary between the rock layer and the silt layer, and withdrawing the reamer after the rock layer expansion is completed; S202, replacing the duckfoot plate guide head, and guiding it to the silt layer outside the rock layer through the duckfoot plate guide head, and then guiding the steel casing along the bottom of the drill pipe, the guide steel casing is located between the rock layer and the silt layer, and finally completing the guidance of the silt layer through the duckfoot plate guide head.
[0052] In step S201, the forward rock reamer is used to perform three-stage reaming, including successively using 12-1 / 2", φ457 reamer and φ610 reamer, and using the φ610 reamer to reame the interface between the rock layer and the silt layer.
[0053] As a preferred embodiment of the present invention, in step S2, when opening the buried channel, a φ168 drill rod is used in the front section and a φ219 drill rod is used in the rear section.
[0054] A duck-foot plate guide head is used to guide the drill to the silt layer outside the rock layer, about 200m away. The φ355*18mm guide steel casing along the drill pipe is about 400m long (300m in the rock hole + 100m in the silt layer). After the casing is lowered to the designated area, the silt layer guidance is continued. The pre-expansion hole of the φ325 tap water pipeline crossing the silt layer adopts a first-level reaming. After the guiding construction is completed, the drill pipe is picked up by the salvage ship and extended to the barge. The drill pipe and drilling tools are disassembled and replaced on the barge, and the φ500 reamer is connected to carry out the silt layer expansion construction.
[0055] As a preferred embodiment of the present invention, in step S4, when pulling back the drilled and buried pipeline, a drilling tool assembly is used, the drilling tool assembly includes a drill rod, a reamer, a pull-back universal joint and a main pipeline, and the pull-back process is performed continuously.
Claims
1. A construction method for laying a submarine small-diameter water pipeline under complex working conditions, characterized in that The steps include: S1. Measure the total length of the water pipeline to be laid, and divide the measured total water pipeline into two sections of similar length, one section of the water pipeline is a bottom-drag pipeline, and the other section of the water pipeline is a drilled and buried pipeline; S2. After the two pipelines are welded, one end of the drilled and buried pipeline is pulled by a tugboat on one side of the flow channel, and the movable end of the drilled and buried pipeline is pulled to the middle of the flow channel. On the other side of the flow channel, a directional drill is used to drive the drill rod to open a buried channel for the drilled and buried pipeline, and the unearthed point of the buried channel is set in the middle of the flow channel, and the drill rod is passed through the unearthed point; S3, the drill pipe is picked up by a salvage ship and extended to a tugboat, where the drill pipe and drilling tools are disassembled and replaced with drill pipe and drilling tools for hole expansion; S4, using the directional drilling rig to provide traction to pull back the drilled and buried pipeline and the bottom-drag pipeline, so that the joints of the drilled and buried pipeline and the bottom-drag pipeline enter the buried channel; In step S2, opening a buried channel includes: S201, when the directional drilling rig is drilling a hole in the rock layer section of the buried channel, a three-cone drill bit is installed, and when the hole is close to the rock layer and the mud layer, the three-cone drill bit is withdrawn, and a forward-thrust rock reamer is replaced, and the forward-thrust rock reamer is used to expand the boundary between the rock layer and the mud layer, and the reamer is withdrawn after the rock layer is expanded; S202, replace the duck-foot plate guide head, guide to the mud layer outside the rock layer through the duck-foot plate guide head, and then guide the steel casing under the drill pipe, the guide steel casing is located between the rock layer and the mud layer, and finally guide the mud layer through the duck-foot plate guide head; In step S201, the forward rock reamer is used to perform three-stage reaming, including successively using a 12-1 / 2", a φ457 reamer and a φ610 reamer, and using the φ610 reamer to reame the interface between the rock layer and the silt layer; Welding anode protection blocks at equal intervals on the outer wall of the bottom-drag pipeline, and performing anti-corrosion treatment on the weld after cooling; In step S2, when opening the buried channel, a small-diameter drill rod is used in the front section and a large-diameter drill rod is used in the rear section.
2. A construction method for laying a submarine small-diameter water pipeline under complex working conditions as claimed in claim 1, characterized in that: In step S2, before dragging the drilled-buried pipe for sliding construction, a pulley sending device for supporting the drilled-buried pipe and the bottom-drag pipe is installed, the pulley sending device includes a fixed pulley and a mobile pulley, the fixed pulley includes a fixed bracket installed at the sea-entering end and a pulley equidistantly installed on the top of the fixed bracket, the mobile pulley includes a mobile bracket and a pulley installed on the top of the mobile bracket, the pulleys are arranged in pairs and are installed to be tilted and rotated, and the top ends of the relative pulleys are close to each other.
3. A construction method for laying a submarine small-diameter water pipeline under complex working conditions as claimed in claim 2, characterized in that: The welding construction of the anode protection block is carried out at the offshore end of the pulley sending device.
4. A construction method for laying a submarine small-diameter water pipeline under complex working conditions as claimed in claim 2, characterized in that: The pulleys include rubber pulleys and resin pulleys, and the rubber pulleys and the resin pulleys are arranged alternately.
5. A construction method for laying a submarine small-diameter water pipeline under complex working conditions as claimed in claim 1, characterized in that: The inner diameter of the buried channel is 1.2 to 1.5 times the outer diameter of the drilled and buried pipeline.
6. A construction method for laying a submarine small-diameter water pipeline under complex working conditions as claimed in claim 1, characterized in that: In step S4, when pulling back the drilled and buried pipeline, a drilling tool assembly is used, the drilling tool assembly includes a drill rod, a reamer, a pull-back universal joint and a main pipeline, and the pull-back process is performed continuously.