PLEET installation method for coiled subsea pipelines

The installation of PLETs using the pipe rolling method solves the problem of high construction costs in deep water areas, enables efficient online installation of PLET terminal structures, reduces project costs, and improves construction efficiency.

CN117489875BActive Publication Date: 2026-11-17SHENZHEN OFFSHORE OIL ENG UNDERWATER TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311742270.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-18
Publication Date
2026-11-17
Estimated Expiration
2043-12-18

AI Technical Summary

Technical Problem

Traditional pipe-laying methods are costly in deep-water areas, especially the installation of PLET terminal structures at both ends of the subsea pipeline is complex and time-consuming, affecting construction efficiency.

Method used

The PLET installation is carried out using the pipe coiling method. Through a series of steps including hoisting, alignment, welding, lowering and retrieval, the PLET can be installed online, reducing the number of subsea pipeline lowering and retrieval procedures.

Benefits of technology

It reduced construction costs, improved construction efficiency, and simplified the installation process of the PLET terminal structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117489875B_ABST
    Figure CN117489875B_ABST
Patent Text Reader

Abstract

This invention discloses a method for installing coiled subsea pipeline PLET, which belongs to the field of marine oil engineering technology. The PLET installation is an online installation method. The PLET is welded to the end of the subsea pipeline, and the PLET is placed on the seabed after the operation is terminated, which saves the process of abandoning and recycling the subsea pipeline after the installation of the PLET on the side.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of coiled subsea pipeline installation in offshore oil engineering, and particularly to a method for installing coiled subsea pipelines using the PLET (Plug-in Tube) technique. Background Technology

[0002] Traditional pipe-laying methods (such as S-lay and J-lay) are generally expensive, especially in deep water where costs increase exponentially. Reel-lay, a newer method developed in the late 20th century, can lay both steel pipes and flexible hoses. 99.5% of the welding work can be completed in a controlled terrestrial environment. It offers advantages such as high weld quality, fast laying speed, low tension requirements, and low dependence on weather windows. According to foreign companies, reel-lay can be ten times more efficient than conventional methods, significantly reducing construction costs. In deep-water subsea pipeline construction, PLET terminal structures are often installed at both ends for underwater manifold connections. Similarly, Reel-lay pipelines also require PLET installations, unlike conventional side-mounted methods. Summary of the Invention

[0003] The coiled subsea pipeline PLET installation method disclosed in this invention can complete the installation of coiled subsea pipeline PLET.

[0004] To solve the above-mentioned technical problems, the present invention provides a method for installing a coiled subsea pipeline (PLET), which is completed through the following steps:

[0005] S1. The pipelaying vessel crane lifts the PLET onto the PHS and connects temporary fasteners. The crane is then disconnected from the rigging of the PLET, and the angle of the PHS is adjusted so that the PLET is in a vertical position.

[0006] S2. The pipelaying vessel stops laying pipe using the drum and tensioner, while maintaining the vessel's position, closes the moon pool, lowers the suspension clamp and locks the subsea pipe, and transfers the tensioner tension to the suspension clamp. The workstation on the work line cuts the subsea pipe, processes the upper and lower ends of the subsea pipe, moves the workstation out of the work line, connects the starting winch to the upper end of the subsea pipe, the starting winch provides pull-back tension, the drum rewinds the subsea pipe and retrieves the upper subsea pipe to the straightener position, and moves and retrieves the straightener.

[0007] S3. Connect the starting winch and A&R winch cable. Use the starting winch to pull the A&R winch cable to the designated position. Disconnect the starting winch and A&R winch. Move the PHS to the laying work line. Connect the A&R winch and PLET. Adjust the position of the lower subsea pipeline to align with the PLET and perform welding operations.

[0008] S4. The PLET buoy and connecting rigging are lifted by the pipelaying vessel crane and entered into the water from the side of the vessel. The traction winch wire rope is guided by pulleys and lowered through the moon pool. The ROV connects the buoy rigging to the traction wire rope underwater. The buoy rigging is retrieved to the PLET by the traction wire rope. The buoy rigging is then connected to the PLET. The traction winch is disconnected from the buoy rigging. The temporary fastening rigging of the PHS is removed. The A&R cable is used for force recovery to separate the PLET from the PHS.

[0009] S5. Open the moon pool hatch, release the A&R cable, lower the PLET, move the ship forward to lower the pipe until the buoy is straightened, disconnect the large crane from the buoy, continue to lower the PLET, and use the ROV to monitor the lowering of the PLET.

[0010] S6. Lower the PLET to the seabed. The ROV disconnects the A&R cable and the PLET underwater. Simultaneously, it moves the vessel aft and retrieves the A&R winch cable to the moon pool. It then connects the starting winch cable and the A&R winch cable. The A&R winch pulls the starting winch cable to the upper end of the subsea pipeline, connecting the starting winch cable and the subsea pipeline. The starting winch releases force while the drum retracts and rewinds, rewinding the upper subsea pipeline back to the drum. This completes the installation of the coiled subsea pipeline PLET.

[0011] Furthermore, in step S2, the workstation on the production line performs pipeline cutting work according to the cutting procedure.

[0012] Furthermore, in step S3, after adjusting the position of the lower subsea pipeline to align with the PLET, welding operations are performed according to the welding process.

[0013] Furthermore, in step S5, after opening the moon pool hatch, the A&R cable is released according to the tension calculation report and the ship movement distance.

[0014] The technical advantages of this invention are as follows: The PLET installation method disclosed in this invention is an online installation method. The PLET is welded to the end of the subsea pipeline, and the PLET is placed on the seabed by terminating the construction operation. This saves the process of abandoning and recycling the subsea pipeline after installing the PLET on the side, and reduces the cost of using the project. Attached Figure Description

[0015] Figure 1 This is a schematic diagram showing the PLET in a vertical state in the PLET installation method for coiled subsea pipelines provided in this embodiment of the invention.

[0016] Figure 2 This is a schematic diagram showing the lower subsea pipeline and the PLET in an aligned position in the PLET installation method for coiled subsea pipelines provided in this embodiment of the invention.

[0017] Figure 3 This is a schematic diagram of the PLET before it enters the water in the PLET installation method for coiled subsea pipelines provided in this embodiment of the invention.

[0018] Figure 4 This is a schematic diagram of the PLET lowering process in the PLET installation method for coiled subsea pipelines provided in this embodiment of the invention.

[0019] Figure 5 This is a schematic diagram of the PLET after it has been lowered to the seabed in the PLET installation method for coiled subsea pipelines provided in this embodiment of the invention.

[0020] 1—PLET; 2—PHS; 3—Drum; 4—Tensioner; 5—Workstation; 7—A&R winch cable; 8—A&R winch. Detailed Implementation

[0021] The present invention will be further described below with reference to the accompanying drawings and specific embodiments, so that those skilled in the art can better understand and implement the present invention. However, the embodiments described are not intended to limit the present invention.

[0022] This invention provides a method for installing a coiled subsea pipeline using a PLEET (Plug-in Tube) system, in conjunction with the attached... Figure 1-4 As shown, this can be completed through the following steps:

[0023] S1, such as Figure 1 As shown, the pipelaying vessel crane lifts PLAT1 onto PHS2 and connects temporary fasteners. The rigging connection between the crane and PLAT1 is then released, and the angle of PHS2 is adjusted to make PLAT1 vertical.

[0024] S2. The pipelaying vessel stops laying pipe using drum 3 and tensioner 4, while maintaining its position, closes the moon pool, lowers the suspension clamp and locks the subsea pipe, and transfers the tension of tensioner 4 to the suspension clamp. Workstation 5 on the work line cuts the subsea pipe and processes the upper and lower ends. Workstation 5 moves out of the work line and connects the starting winch to the upper end of the subsea pipe. The starting winch provides pull-back tension, and drum 3 rewinds the subsea pipe to retrieve the upper subsea pipe to the straightener position. The straightener is then moved and retrieved.

[0025] In step S2, the workstation 5 of the operation line performs the subsea pipeline cutting work according to the cutting procedure.

[0026] S3. Connect the starting winch and A&R winch cable 7. Use the starting winch to pull the A&R winch cable 7 to the designated position. Disconnect the starting winch and A&R winch. Move PHS2 to the laying work line. Connect the A&R winch and PLET1. Adjust the position of the lower subsea pipeline to align with PLET1 and perform welding operations.

[0027] In step S3, after adjusting the position of the lower subsea pipeline to align with PLET1, welding operations are carried out according to the welding process.

[0028] S4. The PLET1 buoy and connecting rigging are lifted by the pipelaying vessel crane and lowered into the water from the side of the vessel. The traction winch wire rope is guided by pulleys and lowered through the moon pool. The ROV connects the buoy rigging to the traction wire rope underwater. The buoy rigging is retrieved to PLET1 by recovering the traction wire rope. The buoy rigging is then connected to PLET1. The connection between the traction winch and the buoy rigging is released. The temporary fastening rigging of PHS2 is removed. The A&R cable is used for retrieval to separate PLET1 from PHS2.

[0029] S5. Open the moon pool hatch, release the A&R cable, lower PLET1, move the ship forward to lower the pipe until the buoy is straightened, disconnect the large crane from the buoy, continue to lower PLET1, and use ROV to monitor the lowering of PLET1.

[0030] In step S5, after opening the moon pool hatch, release the A&R cable according to the tension calculation report and the ship movement distance.

[0031] S6. Lower PLAT1 to the seabed. The ROV disconnects the A&R cable from PLAT1 underwater. Simultaneously, it moves the vessel aft and retrieves the A&R winch cable 7 to the moon pool. It connects the starting winch cable and the A&R winch cable 7. The A&R winch pulls the starting winch cable to the upper end of the subsea pipeline and connects the starting winch cable to the subsea pipeline. The starting winch releases force while the drum 3 retracts and rewinds the upper subsea pipeline to the drum 3, thus completing the installation of the coiled subsea pipeline PLAT1.

[0032] In deep-water subsea pipeline construction, PLET1 terminal structures are often installed at both ends of the pipeline for underwater manifold connections. Similarly, Reel-lay pipeline laying also requires the installation of PLET1. Unlike conventional side-mounted installation methods, this patent designs and discloses an online installation technology for PLET1 in Reel-lay pipeline construction, saving the pipeline lowering and recovery process. This includes steps such as PLET1 preparation, PLET1 welding to the subsea pipeline, PLET1 buoy hoisting and lowering, and PLET1 placement. The core equipment configuration of the Reel-lay pipeline laying vessel includes a drum 3, laying tower, alignment wheel, straightener, tensioner 4, workstation 5, and pipeline suspension module. Depending on the arrangement, the laying tower is located either in the middle or at the stern of the vessel. The difference lies in the position of this core equipment relative to the vessel, but the overall construction steps are consistent. Any Reel-lay pipeline laying vessel can be selected for the scheme design. Each operation step in this technology is designed using the Lewek Constellation pipeline laying vessel. Reel-lay pipeline laying vessels with the same core configuration can refer to this invention for PLET1 installation scheme design.

[0033] The above-described embodiments are merely preferred embodiments provided to fully illustrate the present invention, and the scope of protection of the present invention is not limited thereto. Equivalent substitutions or modifications made by those skilled in the art based on the present invention are all within the scope of protection of the present invention. The scope of protection of the present invention is defined by the claims.

Claims

1. A method for installing a coiled subsea pipeline PLEET, characterized by the following steps: S1. The pipelaying vessel crane lifts the PLET onto the PHS and connects temporary fasteners. The crane is then disconnected from the rigging of the PLET, and the angle of the PHS is adjusted so that the PLET is in a vertical position. S2. The pipelaying vessel stops laying pipe using the drum and tensioner, while maintaining the vessel's position, closes the moon pool, lowers the suspension clamp and locks the subsea pipe, and transfers the tensioner tension to the suspension clamp. The workstation on the work line cuts the subsea pipe, processes the upper and lower ends of the subsea pipe, moves the workstation out of the work line, connects the starting winch to the upper end of the subsea pipe, the starting winch provides pull-back tension, the drum rewinds the subsea pipe and retrieves the upper subsea pipe to the straightener position, and moves and retrieves the straightener. S3. Connect the starting winch and A&R winch cable. Use the starting winch to pull the A&R winch cable to the designated position. Disconnect the starting winch and A&R winch. Move the PHS to the laying work line. Connect the A&R winch and PLET. Adjust the position of the lower subsea pipeline to align with the PLET and perform welding operations. S4. The PLET buoy and connecting rigging are lifted by the pipelaying vessel crane and entered into the water from the side of the vessel. The traction winch wire rope is guided by pulleys and lowered through the moon pool. The ROV connects the buoy rigging to the traction wire rope underwater. The buoy rigging is retrieved to the PLET by the traction wire rope. The buoy rigging is then connected to the PLET. The traction winch is disconnected from the buoy rigging. The temporary fastening rigging of the PHS is removed. The A&R cable is used for force recovery to separate the PLET from the PHS. S5. Open the moon pool hatch, release the A&R cable, lower the PLET, move the ship forward to lower the pipe until the buoy is straightened, disconnect the large crane from the buoy, continue to lower the PLET, and use the ROV to monitor the lowering of the PLET. S6. Lower the PLET to the seabed. The ROV disconnects the A&R cable and the PLET underwater. Simultaneously, it moves the vessel aft and retrieves the A&R winch cable to the moon pool. It then connects the starting winch cable and the A&R winch cable. The A&R winch pulls the starting winch cable to the upper end of the subsea pipeline, connecting the starting winch cable and the subsea pipeline. The starting winch releases force while the drum retracts and rewinds, rewinding the upper subsea pipeline back to the drum. This completes the installation of the coiled subsea pipeline PLET.

2. The method for installing a coiled subsea pipeline PLEET according to claim 1, characterized in that: In step S2, the workstation on the production line performs pipeline cutting according to the cutting procedure.

3. The method of claim 1, wherein: In step S3, after adjusting the position of the lower subsea pipeline to align with the PLET, welding operations are carried out according to the welding process.

4. The method of claim 1, wherein: In step S5, after opening the moon pool hatch, release the A&R cable according to the tension calculation report and the ship movement distance.