Clustered prestressed anchoring system positioning method for front anchor surface

By monitoring deformation patterns using a cable strand pre-embedded pipe testing platform and positioning brackets, and combining testing and correction methods, the installation difficulties in clustered front anchor surface positioning were resolved. This enabled high-precision positioning of cable strand pre-embedded pipes and installation of the front anchor surface, improving construction efficiency and structural stability.

CN118029269BActive Publication Date: 2026-06-09THE 5TH ENG MBEC +1

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
THE 5TH ENG MBEC
Filing Date
2024-01-12
Publication Date
2026-06-09

Smart Images

  • Figure CN118029269B_ABST
    Figure CN118029269B_ABST
Patent Text Reader

Abstract

This invention discloses a positioning method for a cluster-type front anchor face prestressed anchoring system, comprising the following steps: processing a cable strand pre-embedded pipe testing platform to simulate the bending state of the cable strand pre-embedded pipe on the positioning support, while checking parameters such as the length and out-of-roundness of the cable strand pre-embedded pipe; observing and analyzing the deformation of the positioning support; positioning of the cable strand pre-embedded pipe using a center calibrator; after the second section of cable strand pre-embedded pipe is positioned, checking the straightness of the cable strand pre-embedded pipe connection using infrared method, and calculating the pipe opening deviation regression line based on the as-built data of the second section of cable strand pre-embedded pipe; correcting and positioning the front anchor face positioning design coordinates based on the pipe opening deviation linear regression equation; after positioning, checking the anchor cylinder center coordinates, and completing the front anchor face positioning after all anchor cylinder centers are correct. This method effectively solves the problems of spatial conflict and installation difficulties between the anchor cylinder and the already positioned cable strand pre-embedded pipe during cluster-type front anchor face positioning.