A construction quality supervision method and system for building construction
By dividing the construction areas and determining the area type based on process complexity and historical data, differentiated supervision strategies are adopted to solve the problem of unified construction quality supervision in large-scale construction projects, and efficient and reliable supervision of the construction areas is achieved.
Patent Information
- Application Number
- CN202410358550.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-03-27
AI Technical Summary
In large-scale construction projects, the differences in construction types and personnel in multiple construction areas make it difficult to unify construction quality supervision, and it is impossible to effectively combine the characteristics of different construction areas to conduct differentiated supervision, which increases construction risks and supervision difficulties.
By dividing the construction areas, determining the area type based on the process complexity of the construction project and personnel historical data, differentiated quality supervision is carried out using on-site or remote monitoring strategies to ensure real-time and reliable supervision of high-risk areas.
Differentiated supervision of construction areas has been achieved, supervision has been reduced, supervision has been ensured, real-time reliability of construction quality, and targeted supervision has been carried out in the types of areas that are adapted to different construction risks.
Smart Images

Figure CN118411067B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of quality management, and in particular relates to a construction quality supervision method and system for building construction. Background Art
[0002] Quality management of construction quality is the core of building construction. Once there are quality risks in the construction quality of building construction, it may not only greatly increase the construction safety risks of construction workers, but also pose a certain threat to the safety of people using the building in the future. Therefore, how to achieve unified supervision and management of the construction quality of building construction has become a technical problem that needs to be solved urgently.
[0003] In order to solve the above technical problems, in the existing technical solution, in the invention patent CN202311305168.9 "A construction quality supervision system suitable for engineering supervision", the material supervision status is judged based on the sampling test results, and the process flow monitoring and evaluation module monitors the construction process required to be supervised in the engineering construction in real time, thereby comprehensively analyzing the construction quality management status of the construction, but there are the following technical problems:
[0004] During construction, especially in large-scale construction projects, there are often multiple construction areas. The number of construction projects and construction personnel in different construction areas varies to a certain extent. Therefore, how to determine the supervision strategy for the construction quality of different construction areas based on factors such as the construction types of different construction areas to ensure the construction quality of the building has become a technical problem that needs to be solved urgently.
[0005] In view of the above technical problems, the present invention provides a construction quality supervision method and system for building construction. Summary of the invention
[0006] To achieve the purpose of the present invention, the present invention adopts the following technical solutions:
[0007] According to one aspect of the present invention, a construction quality supervision method for building construction is provided.
[0008] A construction quality supervision method for building construction, characterized by comprising:
[0009] S1 divides the target construction project into multiple construction areas according to the construction site, determines the construction process complexity of different construction projects in the construction area based on the construction process of the construction project, and determines whether the construction area is a screening construction area according to the construction process complexity of different construction projects in the construction area. If so, determines the area type of the construction area based on the preset area type, and enters step S4. If not, enters the next step;
[0010] S2: obtaining the number of construction workers for different construction projects in the construction area, and determining the process construction risks of different construction projects in combination with the historical construction data of the construction workers of the construction projects. When there is no construction project in the construction area whose process construction risk is greater than the preset risk, proceeding to the next step;
[0011] S3 determines the risky construction projects in the construction area based on the process construction risks of the construction projects, and determines the area type of the construction area according to the risky construction projects in the construction area, the construction process complexity of different construction projects, and the process construction risks;
[0012] S4 determines the quality supervision strategies for different construction areas according to the area types of different construction areas of the target construction project.
[0013] The beneficial effects of the present invention are:
[0014] 1. Determine whether a construction area is a screening construction area based on the complexity of the construction technology of different construction projects in the construction area, thereby screening construction areas with more complex construction technology based on the complexity of the construction technology of the construction projects in the construction area, and fully consider the technical problems with greater construction risks caused by more complex technology, thus realizing differentiated supervision of areas with higher risks.
[0015] 2. Determine the regional type of the construction area based on the risky construction projects in the construction area, the construction process complexity of different construction projects and the process construction risks. Not only the technical problems of higher construction risks caused by differences in historical construction quality of construction personnel in the construction projects are taken into account, but also the technical problems of higher construction risks caused by the process complexity of the construction projects are taken into account, thereby achieving accurate assessment of the regional types of different construction areas from different construction risks.
[0016] 3. Determine the quality supervision strategies for different construction areas based on the different area types of the target construction project, thereby achieving differentiated quality supervision strategy evaluation based on the construction risks of different construction areas. This not only ensures real-time and reliable supervision of construction areas with higher construction risks, but also reduces the difficulty of supervision through differentiated supervision.
[0017] A further technical solution is to divide the target construction project into multiple construction areas according to the construction site, including:
[0018] The construction sites of the target construction project within a preset area threshold are divided into construction areas.
[0019] A further technical solution is that the construction process of the construction project is determined based on a matching result between the construction project and a preset standard construction process library.
[0020] A further technical solution is that when there is a construction project in the construction area whose process construction risk is greater than a preset risk, the construction area is determined to be a screening construction area.
[0021] A further technical solution is to determine the risky construction projects in the construction area based on the process construction risks of the construction projects, specifically including:
[0022] When the process construction risk of the construction project is within a preset construction risk range, the construction project is determined to be a risky construction project.
[0023] A further technical solution is that the quality supervision strategy includes on-site supervision and remote monitoring device supervision. When the area type of the construction area is a screened construction area, the quality supervision of the construction area is carried out through the quality supervision strategy of on-site supervision; when the area type of the construction area does not belong to the screened construction area, the quality supervision of the construction area is carried out through the quality supervision strategy of remote monitoring device supervision.
[0024] On the other hand, the present invention provides a computer system comprising: a memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that: when the processor runs the computer program, it executes the above-mentioned construction quality supervision method for building construction.
[0025] Other features and advantages will be described in the following description, and partly become apparent from the description, or understood by practicing the invention. The purpose and other advantages of the invention are realized and obtained by the structures particularly pointed out in the description and the drawings.
[0026] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the attached drawings.
[0028] Figure 1 It is a flow chart of a construction quality supervision method for building construction;
[0029] Figure 2 It is a flow chart of a method for determining the complexity of the construction process of a construction project;
[0030] Figure 3 The present invention is a flowchart of a method for determining whether the construction area is a screening construction area. DETAILED DESCRIPTION
[0031] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this specification, not all of the embodiments. Based on the embodiments of this specification, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of this specification.
[0032] Example 1
[0033] To solve the above problems, according to one aspect of the present invention, Figure 1 According to one aspect of the present invention, a construction quality supervision method for building construction is provided, which is characterized by specifically comprising:
[0034] S1 divides the target construction project into multiple construction areas according to the construction site, determines the construction process complexity of different construction projects in the construction area based on the construction process of the construction project, and determines whether the construction area is a screening construction area according to the construction process complexity of different construction projects in the construction area. If so, determines the area type of the construction area based on the preset area type, and enters step S4. If not, enters the next step;
[0035] Furthermore, the target construction project is divided into multiple construction areas according to the construction site, including:
[0036] The construction sites of the target construction project within a preset area threshold are divided into construction areas.
[0037] Specifically, the construction process of the construction project is determined according to a matching result between the construction project and a preset standard construction process library.
[0038] In one possible embodiment, Figure 2 As shown, the method for determining the construction process complexity of the construction project in the above step S1 is:
[0039] Determining a construction target of the construction process of the construction project through the construction process of the construction project, and determining the process complexity of different construction targets according to the deviation requirements of different construction targets;
[0040] The construction process complexity of the construction project is determined based on the process complexity of different construction targets and the number of construction targets of the construction process of the construction project.
[0041] In one possible embodiment, determining whether the construction area is a screening construction area in the above step S1 specifically includes:
[0042] Determine the complex construction projects and general construction projects in the construction area according to the complexity of the construction process, and when the number of complex construction projects in the construction area is greater than the preset number of projects, determine that the construction area is a screening construction area;
[0043] When the number of complex construction projects in the construction area is not greater than the preset number of projects, the process complexity evaluation amount of the complex construction projects in the construction area is determined according to the number of complex construction projects in the construction area and the construction process complexity of different complex construction projects; when the process complexity evaluation amount of the complex construction projects in the construction area does not meet the requirements, the construction area is determined to be a screening construction area;
[0044] When the process complexity evaluation amount of the complex construction project in the construction area meets the requirements, it is judged whether the sum of the construction process complexities of different construction projects in the construction area is less than the preset complexity. If so, it is determined that the construction area does not belong to the screening construction area. If not, proceed to the next step.
[0045] Determine a process complexity evaluation amount of the general construction projects in the construction area according to the number of general construction projects in the construction area and the construction process complexity of different general construction projects;
[0046] The weight values of the process complexity assessment amounts of general construction projects and complex construction projects are determined by utilizing the proportion of the number of general construction projects and the proportion of the number of complex construction projects, and the regional process complexity of the construction area is determined in combination with the process complexity assessment amounts of the general construction projects and the process complexity assessment amounts of the complex construction projects, and whether the construction area is a screening construction area is determined based on the regional process complexity.
[0047] Specifically, determining whether the construction area is a screening construction area according to the process complexity of the area includes:
[0048] When the regional process complexity of the construction area is greater than a preset complexity threshold, the construction area is determined to be a screening construction area.
[0049] In another possible embodiment, Figure 3 As shown, the determination of whether the construction area is a screening construction area in the above step S1 specifically includes:
[0050] Determine the complex construction projects and general construction projects in the construction area by the construction process complexity, and determine the process complexity evaluation amount of the complex construction projects in the construction area according to the number of complex construction projects in the construction area and the construction process complexity of different complex construction projects;
[0051] Determine a process complexity evaluation amount of the general construction projects in the construction area according to the number of general construction projects in the construction area and the construction process complexity of different general construction projects;
[0052] The weight values of the process complexity assessment amounts of general construction projects and complex construction projects are determined by utilizing the proportion of the number of general construction projects and the proportion of the number of complex construction projects, and the regional process complexity of the construction area is determined in combination with the process complexity assessment amounts of the general construction projects and the process complexity assessment amounts of the complex construction projects, and whether the construction area is a screening construction area is determined based on the regional process complexity.
[0053] In another possible embodiment, determining whether the construction area is a screening construction area in the above step S1 specifically includes:
[0054] S11 determines whether there is a complex construction project in the construction area according to the complexity of the construction process, if yes, proceeds to step S13, if no, proceeds to the next step;
[0055] S12 determines whether the number of construction projects in the construction area is less than a preset project number threshold. If so, it is determined that the construction area does not belong to the screening construction area. If not, proceed to the next step.
[0056] S13 determines the complex construction projects and general construction projects in the construction area by the construction process complexity, determines the process complexity evaluation amount of the complex construction projects in the construction area according to the number of complex construction projects in the construction area and the construction process complexity of different complex construction projects, and judges whether the process complexity evaluation amount of the complex construction projects meets the requirements. If yes, proceed to the next step; if not, determine that the construction area belongs to the screening construction area;
[0057] S14: determining a process complexity evaluation amount of the general construction projects in the construction area according to the number of general construction projects in the construction area and the construction process complexity of different general construction projects;
[0058] S15 uses the proportion of the number of general construction projects and the proportion of the number of complex construction projects to determine the weight values of the process complexity assessment quantities of general construction projects and the process complexity assessment quantities of complex construction projects, and determines the regional process complexity of the construction area in combination with the process complexity assessment quantities of the general construction projects and the process complexity assessment quantities of the complex construction projects, and determines whether the construction area is a screening construction area based on the regional process complexity.
[0059] S2: obtaining the number of construction workers for different construction projects in the construction area, and determining the process construction risks of different construction projects in combination with the historical construction data of the construction workers of the construction projects. When there is no construction project in the construction area whose process construction risk is greater than the preset risk, proceeding to the next step;
[0060] Specifically, the historical construction data includes deviation data of different construction targets of construction projects performed by the construction personnel in different historical building projects.
[0061] In one possible embodiment, the method for determining the process construction risk of the construction project in step S2 is:
[0062] Determine the deviation data of different construction targets of the construction projects of the construction personnel in different historical building projects according to the historical construction data of the construction personnel of the construction project, and determine the number of construction targets and the deviation amount of the construction projects of the construction personnel in different historical building projects whose deviations meet the requirements according to the deviation data, and determine the comprehensive deviation amount of the construction of the construction personnel in different historical building projects in combination with the number of construction targets and the deviation amount of the construction targets whose deviations do not meet the requirements;
[0063] Determine the number of historical construction projects in which the deviations of the construction personnel in the construction target of the construction project do not meet the requirements and the deviation amount based on the deviation data, and determine the target construction risks of the construction personnel at different construction targets of the construction project in combination with the number of historical construction projects in which the deviations of the construction target of the construction project meet the requirements and the deviation amount;
[0064] The process construction risk of the construction project is determined by the comprehensive construction deviation of the construction personnel in different historical building projects, the target construction risks of the construction personnel at different construction targets of the construction project, and the number of construction personnel in the construction project.
[0065] Furthermore, the deviation data of the construction target is determined according to the deviation amount between the construction result of the construction personnel at the construction target and the deviation control range of the construction target.
[0066] In another possible embodiment, the method for determining the process construction risk of the construction project in the above step S2 is:
[0067] Determine the deviation data of different construction targets of the construction projects of the construction personnel in different historical building projects according to the historical construction data of the construction personnel of the construction project, and determine the number of construction targets and the deviation amount of the construction projects of the construction personnel in different historical building projects whose deviations meet the requirements according to the deviation data, and determine the comprehensive deviation amount of the construction of the construction personnel in different historical building projects in combination with the number of construction targets and the deviation amount of the construction targets whose deviations do not meet the requirements;
[0068] When the number of historical building projects whose comprehensive construction deviations do not meet the requirements is greater than the preset number of building projects, the process construction risk of the construction project is determined by the number of historical building projects whose comprehensive construction deviations do not meet the requirements;
[0069] When the number of historical construction projects whose comprehensive construction deviations do not meet the requirements is not greater than the preset number of construction projects, the number of historical construction projects whose deviations in the construction targets of the construction projects do not meet the requirements and the deviations are determined based on the deviation data, and the target construction risks of the construction personnel at different construction targets of the construction projects are determined in combination with the number of historical construction projects whose deviations in the construction targets of the construction projects meet the requirements and the deviations. When the proportion of construction targets whose target construction risks do not meet the requirements in the number of construction targets of the construction projects does not meet the requirements, the process construction risk of the construction project is determined by the proportion of construction targets whose target construction risks do not meet the requirements in the number of construction targets of the construction projects.
[0070] When the target construction risk does not meet the required construction target and the proportion of the number of construction targets of the construction project meets the requirement, the process construction risk of the construction project is determined by the comprehensive construction deviation of the construction personnel in different historical building projects, the target construction risks of the construction personnel at different construction targets of the construction project, and the number of construction personnel in the construction project.
[0071] In another possible embodiment, the method for determining the process construction risk of the construction project in the above step S2 is:
[0072] S21 determines the deviation data of different construction targets of the construction projects of the construction personnel in different historical building projects according to the historical construction data of the construction personnel of the construction project, and determines the number of construction targets and the deviation amount of the construction projects of the construction personnel in different historical building projects whose deviations meet the requirements according to the deviation data, and determines the comprehensive deviation amount of the construction of the construction personnel in different historical building projects in combination with the number of construction targets and the deviation amount of the construction targets whose deviations do not meet the requirements;
[0073] S22 determines whether there are any historical building projects whose construction comprehensive deviation does not meet the requirements. If so, proceed to the next step. If not, proceed to step S24.
[0074] S23 determines the number of historical construction projects in which the deviations of the construction personnel in the construction target of the construction project do not meet the requirements and the deviation amount based on the deviation data, and determines the target construction risks of the construction personnel at different construction targets of the construction project in combination with the number of historical construction projects in which the deviations of the construction target of the construction project meet the requirements and the deviation amount, and judges whether there is a construction target whose target construction risk does not meet the requirements, if so, proceeds to the next step, if not, determines the process construction risk of the construction project by the average value of the comprehensive construction deviations of the construction personnel in different historical construction projects;
[0075] S24 determines the process construction risk of the construction project through the comprehensive construction deviation of the construction personnel in different historical building projects, the target construction risks of the construction personnel at different construction targets of the construction project, and the number of construction personnel in the construction project.
[0076] Specifically, when there is a construction project in the construction area whose process construction risk is greater than a preset risk, the construction area is determined to be a screening construction area.
[0077] Further, based on the process construction risk of the construction project, the risk construction project in the construction area is determined, specifically including:
[0078] When the process construction risk of the construction project is within a preset construction risk range, the construction project is determined to be a risky construction project.
[0079] S3 determines the risky construction projects in the construction area based on the process construction risks of the construction projects, and determines the area type of the construction area according to the risky construction projects in the construction area, the construction process complexity of different construction projects, and the process construction risks;
[0080] In one possible embodiment, the method for determining the area type of the construction area in step S3 is:
[0081] Determine the construction risk assessment amount of the risk construction projects in the construction area according to the number of risk construction projects in the construction area, the construction process complexity of the risk construction projects, and the process construction risk;
[0082] Taking the construction projects in the construction area excluding the risky construction project as other construction projects, and determining the construction risk assessment amount of the other construction projects in the construction area based on the number of the other construction projects in the construction area, the construction process complexity of the other construction projects, and the process construction risk;
[0083] A comprehensive risk assessment amount of the construction area is determined based on the construction risk assessment amounts of the risk construction projects in the construction area and the construction risk assessment amounts of other construction projects, and the area type of the construction area is determined through the comprehensive risk assessment amount.
[0084] In another possible embodiment, the method for determining the area type of the construction area in the above step S3 is:
[0085] When the number of risky construction projects in the construction area is greater than the preset number of risky projects, determining the area type of the construction area by using the preset area type;
[0086] When the number of risky construction projects in the construction area is not greater than the preset number of risky projects, the construction risk assessment amount of the risky construction projects in the construction area is determined by the number of risky construction projects in the construction area, the construction process complexity of the risky construction projects, and the process construction risk;
[0087] When the construction risk assessment amount of the risk construction project in the construction area does not meet the requirement, determining the area type of the construction area by using the preset area type;
[0088] When the construction risk assessment amount of the risk construction projects in the construction area meets the requirements, the project risk assessment amounts of different construction projects in the construction area are determined according to the construction process complexity and process construction risks of different construction projects; when the sum of the project risk assessment amounts of the construction projects in the construction area does not meet the requirements, the area type of the construction area is determined by the preset area type;
[0089] When the sum of the project risk assessment amounts of the construction projects in the construction area meets the requirements, the comprehensive risk assessment amount of the construction area is determined based on the project risk assessment amounts of different construction projects, the construction risk assessment amounts of the risk construction projects in the construction area and the number of construction projects, and the area type of the construction area is determined through the comprehensive risk assessment amount.
[0090] S4 determines the quality supervision strategies for different construction areas according to the area types of different construction areas of the target construction project.
[0091] Furthermore, the quality supervision strategy includes on-site supervision and remote monitoring device supervision. When the area type of the construction area is a screened construction area, the quality supervision of the construction area is carried out through the quality supervision strategy of on-site supervision; when the area type of the construction area does not belong to the screened construction area, the quality supervision of the construction area is carried out through the quality supervision strategy of remote monitoring device supervision.
[0092] Example 2
[0093] On the other hand, the present invention provides a computer system comprising: a memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that: when the processor runs the computer program, it executes the above-mentioned construction quality supervision method for building construction.
[0094] Through the above embodiments, the present application achieves the following technical effects:
[0095] 1. Determine whether a construction area is a screening construction area based on the complexity of the construction technology of different construction projects in the construction area, thereby screening construction areas with more complex construction technology based on the complexity of the construction technology of the construction projects in the construction area, and fully consider the technical problems with greater construction risks caused by more complex technology, thus realizing differentiated supervision of areas with higher risks.
[0096] 2. Determine the regional type of the construction area based on the risky construction projects in the construction area, the construction process complexity of different construction projects and the process construction risks. Not only the technical problems of higher construction risks caused by differences in historical construction quality of construction personnel in the construction projects are taken into account, but also the technical problems of higher construction risks caused by the process complexity of the construction projects are taken into account, thereby achieving accurate assessment of the regional types of different construction areas from different construction risks.
[0097] 3. Determine the quality supervision strategies for different construction areas based on the different area types of the target construction project, thereby achieving differentiated quality supervision strategy evaluation based on the construction risks of different construction areas. This not only ensures real-time and reliable supervision of construction areas with higher construction risks, but also reduces the difficulty of supervision through differentiated supervision.
[0098] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device, equipment, and non-volatile computer storage medium embodiments, since they are basically similar to the method embodiments, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
[0099] The above is a description of a specific embodiment of the specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0100] The above description is only one or more embodiments of this specification and is not intended to limit this specification. For those skilled in the art, one or more embodiments of this specification may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of one or more embodiments of this specification shall be included in the scope of the claims of this specification.
Claims
1. A construction quality supervision method for building construction, characterized in that: Specifically include: S1 divides the target construction project into multiple construction areas according to the construction site, determines the construction process complexity of different construction projects in the construction area based on the construction process of the construction project, and determines whether the construction area is a screening construction area according to the construction process complexity of different construction projects in the construction area. If so, determines the area type of the construction area based on the preset area type, and enters step S4. If not, enters the next step; S2: obtaining the number of construction workers for different construction projects in the construction area, and determining the process construction risks of different construction projects in combination with the historical construction data of the construction workers of the construction projects. When there is no construction project in the construction area whose process construction risk is greater than the preset risk, proceeding to the next step; S3 determines the risky construction projects in the construction area based on the process construction risks of the construction projects, and determines the area type of the construction area according to the risky construction projects in the construction area, the construction process complexity of different construction projects, and the process construction risks; S4 determines the quality supervision strategies for different construction areas according to the area types of different construction areas of the target building project; The method for determining the construction process complexity of the construction project is: Determining a construction target of the construction process of the construction project through the construction process of the construction project, and determining the process complexity of different construction targets according to the deviation requirements of different construction targets; Determine the construction process complexity of the construction project based on the process complexity of different construction targets and the number of construction targets of the construction process of the construction project; Determining whether the construction area is a screening construction area specifically includes: Determine the complex construction projects and general construction projects in the construction area by the construction process complexity, and determine the process complexity evaluation amount of the complex construction projects in the construction area according to the number of complex construction projects in the construction area and the construction process complexity of different complex construction projects; Determine a process complexity evaluation amount of the general construction projects in the construction area according to the number of general construction projects in the construction area and the construction process complexity of different general construction projects; Determine the weight values of the process complexity assessment amounts of general construction projects and complex construction projects by using the proportion of the number of general construction projects and the proportion of the number of complex construction projects, and determine the regional process complexity of the construction area in combination with the process complexity assessment amounts of the general construction projects and the process complexity assessment amounts of the complex construction projects, and determine whether the construction area is a screening construction area based on the regional process complexity; The method for determining the process construction risk of the construction project is: Determine the deviation data of different construction targets of the construction projects of the construction personnel in different historical building projects according to the historical construction data of the construction personnel of the construction project, and determine the number of construction targets and the deviation amount of the construction projects of the construction personnel in different historical building projects whose deviations meet the requirements according to the deviation data, and determine the comprehensive deviation amount of the construction of the construction personnel in different historical building projects in combination with the number of construction targets and the deviation amount of the construction targets whose deviations do not meet the requirements; Determine the number of historical construction projects in which the deviations of the construction personnel in the construction target of the construction project do not meet the requirements and the deviation amount based on the deviation data, and determine the target construction risks of the construction personnel at different construction targets of the construction project in combination with the number of historical construction projects in which the deviations of the construction target of the construction project meet the requirements and the deviation amount; The process construction risk of the construction project is determined by the comprehensive construction deviation of the construction personnel in different historical building projects, the target construction risks of the construction personnel at different construction targets of the construction project, and the number of construction personnel in the construction project.
2. The construction quality supervision method for building construction according to claim 1, characterized in that: The target construction project is divided into multiple construction areas according to the construction location, including: The construction sites of the target construction project within a preset area threshold are divided into construction areas.
3. The construction quality supervision method for building construction according to claim 1, characterized in that: The construction process of the construction project is determined according to the matching result of the construction project with a preset standard construction process library.
4. The construction quality supervision method for building construction according to claim 1, characterized in that: Determining whether the construction area is a screening construction area according to the process complexity of the area specifically includes: When the regional process complexity of the construction area is greater than a preset complexity threshold, the construction area is determined to be a screening construction area.
5. The construction quality supervision method for building construction according to claim 1, characterized in that: The historical construction data includes deviation data of different construction targets of construction projects of the construction personnel in different historical building projects.
6. The construction quality supervision method for building construction according to claim 1, characterized in that: When there is a construction project in the construction area whose process construction risk is greater than the preset risk, the construction area is determined to be a screening construction area.
7. A computer system comprising: A memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that the processor executes a construction quality supervision method for building construction as described in any one of claims 1-6 when running the computer program.