Opportunity maintenance method for multi-component equipment series production line considering multiple correlations
By constructing a multi-layer maintenance decision-making framework and cost balance model, the maintenance strategy of the multi-component equipment series production line is optimized, structural and economic correlation problems are solved, maintenance costs are significantly reduced, and production efficiency is improved.
Patent Information
- Application Number
- CN202411214930.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing maintenance strategy of multi-component equipment series production lines fails to effectively consider the structural correlation and economic correlation between equipment, resulting in high maintenance costs and low production efficiency.
This paper proposes an opportunistic maintenance method for multi-component equipment series production lines that considers multiple correlations. By constructing a maintenance decision-making framework of component layer-equipment layer-system layer, and combining the independent healthy evolution of components, disassembly sequence and equipment process correlation, a maintenance cost balance is established. model, optimize maintenance resource utilization, and dynamically generate component maintenance plans.
It effectively reduces the maintenance cost of multi-component equipment series production lines, improves the economic benefits of the processing workshop, and achieves long-term highly economical maintenance.
Smart Images

Figure CN118735307A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a technology in the field of intelligent manufacturing, specifically a method for maintaining a multi-component equipment serial production line taking into account multiple correlations. Background Art
[0002] The multi-component equipment serial production line has multiple correlations. There is economic correlation between the serial equipment. If one equipment is shut down for maintenance, the entire production line will be shut down. There is structural correlation between the key components of the equipment. The maintenance of one component requires the disassembly of other related components. The existing production line maintenance strategy does not take this feature into account. Summary of the invention
[0003] In view of the above-mentioned deficiencies in the prior art, the present invention proposes an opportunity maintenance method for a multi-component equipment serial production line that considers multiple correlations. An opportunity maintenance cost balance algorithm that considers structural correlation and economic correlation is proposed, which integrates the independent healthy evolution of components, component disassembly sequence, and equipment process association to analyze the maintenance cost-effectiveness, constructs a maintenance decision framework and closed-loop interaction mechanism at the component level-equipment level-system level, further introduces maintenance resource constraints, and dynamically outputs component maintenance plans for complex manufacturing systems. The present invention can effectively reduce the maintenance cost of a multi-component equipment serial production line, thereby significantly improving the economic benefits of a processing workshop.
[0004] The present invention is achieved through the following technical solutions: The present invention relates to an opportunistic maintenance method for a multi-component equipment serial production line considering multiple correlations, comprising two interrelated planning cycles, a component predictive maintenance cycle and a system predictive maintenance cycle; in the component predictive maintenance cycle, based on component state decay information, a maintenance cost rate model is constructed, the component-layer predictive maintenance time points are optimized, and the results are input into the system predictive maintenance cycle; in the system predictive maintenance cycle, considering multiple correlations, equipment-layer and system-layer maintenance cost surplus models are established, and the economic feasibility of early maintenance of each component is evaluated; considering maintenance resource constraints, equipment maintenance selection is carried out, and the final component maintenance decision of the current maintenance opportunity is obtained, and the final component maintenance decision is further fed back to the next component predictive maintenance cycle, and subsequent opportunistic maintenance planning is continued.
[0005] The multi-component equipment series production line specifically refers to: a manufacturing system formed by multiple multi-component equipment connected in series, wherein each equipment contains multiple key components with structural correlation, and the status of each component needs to be restored by preventive maintenance due to degradation, or fault repair work needs to be carried out to restore it from a failed state to a working state.
[0006] The component predictive maintenance cycle and the system predictive maintenance cycle specifically refer to: the two mutually input and output decision-making processes for production line maintenance planning of the present invention, and the planning cycles of the two cycles are carried out to obtain the maintenance plan within the planning period; the component predictive maintenance cycle optimizes the maintenance interval and allocates the initial maintenance time point for each independent component by only considering the state decay process of the component; the system predictive maintenance cycle takes the planning results of the component predictive maintenance cycle as input for the entire production line, considers multiple correlations and maintenance resource constraints at maintenance opportunities, makes maintenance time adjustment decisions for each component, generates a final component maintenance execution plan, and feeds it back to the component predictive maintenance cycle for subsequent component maintenance interval optimization.
[0007] The optimized component-level predictive maintenance time point refers to: in the component predictive maintenance cycle, based on the real-time monitoring information of the status data of each component of the system, combined with the maintenance and disassembly parameters of each component, a maintenance cost rate model is established, and the model is solved to obtain the optimal maintenance cycle interval of the component corresponding to the minimum cost rate; wherein, the maintenance and disassembly parameters of each component include but are not limited to preventive maintenance time, preventive maintenance cost, fault repair operation time, fault repair operation cost, component disassembly time, component disassembly cost, component failure rate distribution function; wherein, solving to obtain the optimal maintenance cycle interval of the component corresponding to the minimum cost rate specifically refers to calculating the derivative equation of the maintenance cost rate model, making the derivative equation equal to 0, and obtaining the optimal maintenance cycle interval of the equipment corresponding to the minimum cost rate; the optimal maintenance cycle interval is used as input into the system predictive maintenance cycle.
[0008] The evaluation of the economic feasibility of advance maintenance of each component refers to: in the current system predictive maintenance cycle, the maintenance opportunity is triggered when the triggered component first reaches the optimal maintenance time point obtained by the predictive maintenance cycle plan of its component, and the predictive maintenance of other components can be advanced to this maintenance opportunity. Compared with separate maintenance operations, the simultaneous execution of preventive maintenance of multiple components can significantly save the time and economic cost of disassembly, maintenance and equipment installation and commissioning. Based on the real-time health decline status of each component and multiple maintenance correlation analysis covering component disassembly and system configuration, the impact of advance decisions on the predictive maintenance of each component on the economic feasibility of the maintenance plan is quantified.
[0009] The maintenance resource constraint mentioned above means that due to the shortage of maintenance personnel, inconvenient transportation, and lack of maintenance tools, the number of maintenance teams dispatched for a single maintenance is limited, resulting in only some components in the equipment being able to perform predictive maintenance operations. Therefore, the number of devices that can perform component maintenance at each maintenance opportunity is limited.
[0010] The equipment maintenance selection mentioned above means: based on the maintenance cost balance result output of each component, the equipment maintenance benefit is calculated, and its value is the sum of the positive maintenance cost balance values in the equipment minus the disassembly cost and the equipment installation and commissioning cost. The obtained equipment maintenance benefits are sorted in descending order. Except for the maintenance triggering equipment, the equipment composition is selected to maximize the total equipment maintenance benefit, and preventive maintenance is carried out on the components with positive total maintenance cost balance in the selected equipment.
[0011] The said feedback of the final component maintenance decision to the next component predictive maintenance cycle means: after making a decision on the system predictive maintenance cycle, updating the actual maintenance time points of each current device according to the actual decision plan; assigning values to the components performing preventive maintenance, and cyclically executing the component-level predictive maintenance cycle planning for the next cycle to achieve long-term and highly economical maintenance of the production line. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a flow chart of the present invention;
[0013] Figure 2 It is a schematic diagram of the structure of a multi-component equipment series production line in an embodiment of the present invention. DETAILED DESCRIPTION
[0014] like Figure 1 As shown, this embodiment relates to a multi-component equipment serial production line opportunity maintenance method considering multiple correlations, including the following steps:
[0015] Step 1: Use a directed node graph to represent the structure of a multi-component equipment serial production line. Each device is represented by node 0 as a whole, and other nodes represent key components installed in each device. Component nodes with structural correlation are connected by directed arrows, and the direction of the arrow represents the order of disassembly between the two connected components. The arrow starts from the parent node and points to the child node, indicating that the disassembly of the component represented by the child node requires the disassembly of the component represented by the parent node first, that is, the component represented by the parent node has a higher disassembly order; a disassembly path is from node 0 to the component node without an arrow starting point; the nodes 0 of each device are connected by line segments, indicating the economic correlation between the serial devices.
[0016] Step 2: Obtain component status degradation information during the component predictive maintenance cycle: From the first component predictive maintenance cycle Start, that is ; Based on the reliability parameters of each component in each device of the production line, the failure rate distribution function is obtained .
[0017] Step 3: Define parameters and their symbolic representation: Definition is the equipment set included in the production line, indexed by ,equipment By symbol express; For equipment The collection of disassembly paths contained in , indexed by , Disassembly path in by express; for The collection of components in , indexed by , Parts in By symbol express; for The collection of components in ; for The order of disassembly in its disassembly path; for In the ratio A collection of parts with a higher disassembly order; for In the ratio The assembly of parts with a lower disassembly order; , They are indexes of component predictive maintenance cycle and system maintenance cycle respectively; Index of debugging activities for device installation; , , They are The cost of preventive maintenance, emergency repair and component disassembly; , , They are Preventive maintenance, emergency repairs, and component disassembly are time-consuming; , They are The installation and commissioning cost and time consumption; for The cost of hiring a maintenance team once; for The production delay cost rate; for rate of depreciation; , They are Value at the beginning and end of the planning period; The maximum number of devices that can be repaired during each maintenance opportunity; is the length of the planning period.
[0018] Step 4: Define variables and their formulas: Definition for In the The optimal maintenance interval obtained by optimizing the maintenance cost rate model for the predicted maintenance cycle of each component; for In the The optimal maintenance time point is obtained by optimizing the maintenance cost rate model for the predicted maintenance cycle of each component; for In the The actual maintenance interval of each component predictive maintenance cycle after adjustment by system predictive maintenance; For the The maintenance decision-making time point of the system-predicted maintenance cycle, that is, the maintenance opportunity start time point; , Respectively A trigger component and a trigger device of a system predictive maintenance cycle, wherein the trigger device refers to the device where the trigger component is located; for No. The time for completing installation and commissioning activities, including ; , , They are exist The equipment-level maintenance cost balance, system-level maintenance cost balance, and total maintenance cost balance at any given moment; for exist Timely equipment maintenance benefits; for In the The failure rate function of each component in the predicted maintenance cycle; for exist Maintenance decisions at all times; After the decision is made by the method of the present invention Moment component maintenance combination; for Depth of disassembly; is the component index corresponding to the disassembly depth in the currently planned disassembly path; For the The total predictive maintenance, component removal and equipment installation and commissioning time of a system predictive maintenance cycle.
[0019] Step 5: Solve the component-level preventive maintenance cycle in the component predictive maintenance cycle: Based on the failure rate distribution function of each component, build a maintenance cost rate model , and the optimal maintenance interval of the corresponding component with the minimum cost rate is obtained by derivation .
[0020] Step 6: Allocation and update of component-level preventive maintenance time points in the component predictive maintenance cycle: Based on the optimal maintenance interval for each component , calculate the optimal preventive maintenance time for each component The allocation results in: , .
[0021] Step 7: Determine whether the cycle is over: Determine whether the optimal preventive maintenance time of all components is greater than the planned cycle length. If so, end the production line preventive maintenance planning; if not, go to step 8.
[0022] Step 8: Determine maintenance opportunities in the system predictive maintenance cycle: Find the components with the smallest The component with the value is defined as the maintenance trigger component and the maintenance trigger device. The value is defined as the decision-making point in time for the current system's predicted maintenance cycle: , .
[0023] Step 9: Calculate the total maintenance cost balance during the system predictive maintenance cycle: For each non-repair component, The total maintenance cost balance is calculated at all times, and the disassembly depth is updated at the same time, until the final total maintenance cost balance calculation result is output, which is specifically implemented as follows.
[0024] 9-1 Setting the initial disassembly depth: Before making a predictive maintenance adjustment decision, only the maintenance triggering components is identified as being assigned to perform maintenance activities, so That is, it becomes the first component to be disassembled in the system and has the deepest disassembly position in its disassembly path. The components in other disassembly paths have not yet been decided to be disassembled, so the deepest disassembly depth in other disassembly paths is 0.
[0025] 9-2 Considering the structural correlation between components, the component index corresponding to the disassembly depth in each disassembly path is set , establish equipment-level maintenance cost balances for each component Calculation model, specifically: Balance item of corrective maintenance work It is expressed as , indicating that the early implementation of predictive maintenance will reduce the cumulative failure rate of components in the current cycle, and correspondingly reduce the cost of corrective maintenance; the balance item of equipment production delay cost It is expressed as , indicating that compared with the separate disassembly and maintenance of each component, bringing it forward to the current maintenance opportunity can save additional predictive maintenance work and disassembly time, thereby shortening the downtime delay and corresponding penalty costs of the equipment. and , the corresponding time savings are calculated separately; predict the remaining maintenance cost items It is expressed as , which means that from the perspective of long-term planning, early predictive maintenance operations will increase the frequency of predictive maintenance operations, thereby increasing the corresponding operating costs. This balance item is also calculated separately according to different component classifications; the balance item of accelerated depreciation cost of components It is expressed as , indicating that frequent maintenance operations lead to accelerated depreciation of components; equipment-level maintenance cost balance It is equal to the sum of the above four cost surplus items, which can be expressed as .
[0026] 9-3 Consider the economic relevance between series-connected devices and establish system-level maintenance cost balances for each component The calculation model is as follows: Maintenance team dispatch cost balance It is expressed as , which means that the maintenance of each machine component requires the dispatch of a professional maintenance team, and the maintenance trigger device , except Maintaining other parts can save the additional maintenance team dispatching costs caused by separate maintenance, while for other equipment, this cost is unavoidable; equipment installation and commissioning cost surplus It is expressed as , indicating that for maintenance triggering equipment , except Maintenance of other components can save the extra installation and debugging costs and time penalty of the entire equipment. For other equipment, combined maintenance of its components still requires corresponding installation and debugging costs, but the corresponding time penalty is saved; the cost surplus item of increasing the frequency of installation and debugging It is expressed as , indicating that for Premature maintenance of other equipment will increase the frequency of installation and commissioning, and correspondingly increase the cost of long-term installation and commissioning operations. No additional cost is incurred; for each device, the overall system-level maintenance cost balance is the sum of the above three items, which can be expressed as: ; Furthermore, the system-level maintenance cost balance of each component in the equipment The total system-level maintenance cost balance of each device is divided by the number of components in the corresponding device, which can be expressed as .
[0027] 9-4 Comprehensive equipment-level maintenance cost balance and system-level maintenance cost balance, total maintenance cost balance of each component The sum of the two is obtained, which can be expressed as ,like , then the description will be of preventive maintenance to advance maintenance opportunities Carrying out the disassembly can bring cost reduction under the current disassembly depth setting, otherwise it means that the maintenance cost will increase.
[0028] Step 10: Select equipment in the system's predicted maintenance cycle for maintenance: Based on the calculation results of the total maintenance cost balance of each component, further calculate the maintenance benefits of each equipment and sort them in descending order. The maximum number of equipment that can be repaired in each maintenance opportunity Under the constraint of At most The device is selected as the current maintenance device.
[0029] Step 11: Output the maintenance decision in the system predictive maintenance cycle: Output the maintenance equipment selection results obtained in step 10 and The components with positive total maintenance cost balance are regarded as the maintenance results of the current system predicted maintenance cycle, and maintenance activities are carried out.
[0030] Step 12: Feedback the actual preventive maintenance execution results in the system predictive maintenance cycle: Obtain the actual maintenance execution results, including the actual maintenance execution time points and actual maintenance intervals of each component , expressed as ,in ; and calculate The actual maintenance execution time at the moment , expressed as ; Feedback the above results to the subsequent component predictive maintenance cycle to plan the subsequent cycle, which can be expressed as , achieving long-term and highly economical maintenance of the production line.
[0031] Apply the above method to Figure 2 The maintenance plan formulation example of a multi-component equipment series production line is shown in Table 1, where the maintenance-related parameters of each component are shown in Table 1. The failure rate function distribution of each component can be obtained based on historical data and all obey the Weibull distribution ( The maintenance and production-related parameters of each equipment in the production line are shown in Table 2. Planning period =24000h, the maximum number of devices that can be repaired in each maintenance opportunity =3.
[0032] Table 1 Maintenance related parameters of each component of the equipment
[0033] Table 2 Maintenance and production related parameters of each equipment in the production line
[0034] The maintenance decision optimization method proposed in the present invention is applied to the above example, and the obtained maintenance decision scheme is shown in Table 3, wherein the first column is the time point of each system maintenance decision, the second column is the triggering device of each maintenance opportunity, the third column is the triggering component of each maintenance opportunity, and the fourth to eighth columns are the component serial numbers of each equipment in the production line that performs maintenance at each maintenance opportunity.
[0035] Table 3 Maintenance decision solution results of the embodiment of the present invention
[0036] In order to verify the effectiveness of the opportunistic maintenance method for multi-component equipment serial production lines considering multiple correlations proposed in the present invention, five other traditional production line maintenance strategies are applied to this case, and the total costs are compared. The comparison results are shown in Table 4. The traditional strategies adopted are introduced as follows: the first strategy is the independent preventive maintenance strategy, denoted as IPM. The maintenance decision of each component in the system is made only based on the maintenance interval optimization results in the component predictive maintenance cycle, without considering the structural correlation of component disassembly and the economic correlation of series equipment; the second strategy is the triggered equipment maintenance strategy, denoted as TMM. The maintenance interval optimization of each component in the system is carried out based on the component predictive maintenance cycle, and the structural correlation of disassembly between components is considered. At each maintenance opportunity, the equipment-level maintenance cost balance of each component in the maintenance triggering equipment is calculated, and only the components with positive balance in the equipment are maintained; the third is the single-component assumed maintenance strategy, denoted as SCA. This strategy adopts the assumption that each equipment is composed of a single key component, which is widely used in current related research. Based on the component predictive maintenance cycle, the maintenance interval optimization of the component with the smallest maintenance interval of each equipment in the system is carried out, and this component is used as the representative key component of the entire equipment. Considering the economic correlation of series equipment, at each maintenance opportunity, the system-level maintenance cost balance of each equipment is calculated, and The fourth strategy is the simplified equipment selection strategy, denoted as SMS, which considers the structural relevance of component disassembly and the economic relevance of series equipment without performing the equipment selection process. It randomly selects equipment with positive maintenance cost surplus components. The fifth type is the maintenance time window strategy, denoted as MTW. This strategy optimizes the maintenance intervals of each component in the system based on the predicted maintenance cycle of the component. At each maintenance opportunity, a maintenance time window is set. Count the parts of each device within the time window at the optimal maintenance time, sort the obtained numbers in descending order, and select Before For each piece of equipment, maintain the components whose optimal maintenance time is within the time window.
[0037] Table 4 Comparison of the total maintenance cost of the method of the present invention and other traditional production line maintenance strategies
[0038] From the total cost comparison, it can be concluded that the opportunity maintenance method for a multi-component equipment series production line considering multiple correlations proposed in the present invention can achieve significant total maintenance cost optimization for a multi-component equipment series production line.
[0039] Compared with the prior art, the present invention innovatively establishes a maintenance framework for multi-component equipment serial production lines that takes into account multiple correlations. By constructing a maintenance cost surplus model, the present invention systematically analyzes the impact of component disassembly structure correlation and equipment serial economic correlation on the economic efficiency of maintenance activities, and further proposes an equipment maintenance selection method under the constraints of limited maintenance resources to obtain a highly economical production line maintenance plan. Compared with traditional methods, the multi-component equipment serial production line maintenance plan obtained by the present invention can effectively reduce the total maintenance cost.
[0040] The above-mentioned specific implementation can be partially adjusted in different ways by those skilled in the art without departing from the principle and purpose of the present invention. The protection scope of the present invention shall be based on the claims and shall not be limited by the above-mentioned specific implementation. Each implementation scheme within its scope shall be subject to the constraints of the present invention.
Claims
1. A multi-component equipment serial production line opportunity maintenance method considering multiple correlations, characterized in that: It includes two interrelated planning cycles: the component predictive maintenance cycle and the system predictive maintenance cycle. In the component predictive maintenance cycle, a maintenance cost rate model is constructed based on the component state decay information, the component-level predictive maintenance timing is optimized, and the results are input into the system predictive maintenance cycle. In the system predictive maintenance cycle, multiple correlations are considered to establish equipment-level and system-level maintenance cost surplus models to evaluate the economic feasibility of early maintenance of each component. Considering maintenance resource constraints, equipment maintenance selection is carried out to obtain the final component maintenance decision for the current maintenance opportunity, and the final component maintenance decision is further fed back to the next component predictive maintenance cycle to continue with subsequent opportunity maintenance planning.
2. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The multi-component equipment series production line specifically refers to: a manufacturing system formed by multiple multi-component equipment connected in series, wherein each equipment contains multiple key components with structural correlation, and the status of each component needs to be restored by preventive maintenance due to degradation, or fault repair work needs to be carried out to restore it from a failed state to a working state.
3. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The component predictive maintenance cycle and the system predictive maintenance cycle specifically refer to: the two mutually input and output decision-making processes for production line maintenance planning of the present invention, and the planning cycles of the two cycles are carried out to obtain the maintenance plan within the planning period; the component predictive maintenance cycle optimizes the maintenance interval and allocates the initial maintenance time point for each independent component by only considering the state decay process of the component; the system predictive maintenance cycle takes the planning results of the component predictive maintenance cycle as input for the entire production line, considers multiple correlations and maintenance resource constraints at maintenance opportunities, makes maintenance time adjustment decisions for each component, generates a final component maintenance execution plan, and feeds it back to the component predictive maintenance cycle for subsequent component maintenance interval optimization.
4. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The optimized component-level predictive maintenance time point refers to: in the component predictive maintenance cycle, based on the real-time monitoring information of the status data of each component of the system, combined with the maintenance and disassembly parameters of each component, a maintenance cost rate model is established, and the model is solved to obtain the optimal maintenance cycle interval of the component corresponding to the minimum cost rate; wherein, the maintenance and disassembly parameters of each component include but are not limited to preventive maintenance time, preventive maintenance cost, fault repair operation time, fault repair operation cost, component disassembly time, component disassembly cost, component failure rate distribution function; wherein, solving to obtain the optimal maintenance cycle interval of the component corresponding to the minimum cost rate specifically refers to calculating the derivative equation of the maintenance cost rate model, making the derivative equation equal to 0, and obtaining the optimal maintenance cycle interval of the equipment corresponding to the minimum cost rate; the optimal maintenance cycle interval is used as input into the system predictive maintenance cycle.
5. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The evaluation of the economic feasibility of advance maintenance of each component refers to: in the current system predictive maintenance cycle, the maintenance opportunity is triggered when the triggered component first reaches the optimal maintenance time point obtained by the predictive maintenance cycle plan of its component, and the predictive maintenance of other components can be advanced to this maintenance opportunity. Compared with separate maintenance operations, the simultaneous execution of preventive maintenance of multiple components can significantly save the time and economic cost of disassembly, maintenance and equipment installation and commissioning. Based on the real-time health decline status of each component and multiple maintenance correlation analysis covering component disassembly and system configuration, the impact of advance decisions on the predictive maintenance of each component on the economic feasibility of the maintenance plan is quantified.
6. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The maintenance resource constraint mentioned above means that due to the shortage of maintenance personnel, inconvenient transportation, and lack of maintenance tools, the number of maintenance teams dispatched for a single maintenance is limited, resulting in only some components in the equipment being able to perform predictive maintenance operations. Therefore, the number of devices that can perform component maintenance at each maintenance opportunity is limited.
7. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The equipment maintenance selection mentioned above means: based on the maintenance cost balance result output of each component, the equipment maintenance benefit is calculated, and its value is the sum of the positive maintenance cost balance values in the equipment minus the disassembly cost and the equipment installation and commissioning cost. The obtained equipment maintenance benefits are sorted in descending order. Except for the maintenance triggering equipment, the equipment composition is selected to maximize the total equipment maintenance benefit, and preventive maintenance is carried out on the components with positive total maintenance cost balance in the selected equipment.
8. The multi-component equipment serial production line opportunity maintenance method considering multiple correlations according to claim 1 is characterized in that: The said feedback of the final component maintenance decision to the next component predictive maintenance cycle means: after making a decision on the system predictive maintenance cycle, updating the actual maintenance time points of each current device according to the actual decision plan; assigning values to the components performing preventive maintenance, and cyclically executing the component-level predictive maintenance cycle planning for the next cycle to achieve long-term and highly economical maintenance of the production line.
Citation Information
Patent Citations
Method of dynamic interaction preventive maintenance planning of equipment level and system level of production system
CN103106543A
Preventive maintenance method for turbomachinery based on component correlation
CN112100773A
Health management system and method considering single spare part guarantee
CN117611128A
Maintenance planning providing system for assistance of decision making for maintenance of e.g. mining industry system, has model-supported system connected with module which evaluates examination, and base system for making decisions
DE102006045804A1