Method and device for predicting tunnel displacement based on foundation pit excavation
By combining finite element analysis and least squares support vector machine algorithm, real-time monitoring data is used to modify the model, which solves the problem of poor timeliness in prediction of subway tunnel displacement during foundation pit excavation, achieves more accurate and timely predictions, and optimizes the construction process. , improving project safety and efficiency.
Patent Information
- Application Number
- CN202410764718.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When excavation of foundation pits in soft soil areas, existing technology is difficult to accurately and timely predict the displacement changes of subway tunnels, resulting in construction safety and efficiency problems.
Combining finite element analysis and least squares support vector machine algorithm, the finite element model is modified through real-time monitoring data, and the mapping relationship between foundation pit and tunnel parameters and displacement is established to achieve dynamic prediction.
It improves the accuracy and real-time nature of prediction, optimizes the construction process, reduces the adverse impact on the tunnel, and ensures project safety and efficiency.
Smart Images

Figure CN118760962A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of geological exploration, and in particular to a method and device for predicting tunnel displacement based on foundation pit excavation. Background Art
[0002] With the rapid development of my country's economy, the development of urban underground space has received more and more attention in large cities with precious land resources. Therefore, the foundation pits in cities have shown a development trend of "large, tight and deep", and the excavation time of the foundation pits is short and the area occupied is small, which tends to be normalized. When the construction site is small, the hydrogeological conditions are complex, and the surrounding environment is sensitive, the excessive deformation generated during the excavation of deep and large foundation pits will inevitably have an adverse effect on the existing subway tunnels in the city. The allowable deformation requirements for subway tunnels are very strict. While the excavation and unloading of the foundation pit affects the deformation of the foundation pit, it will also cause uneven deformation of the adjacent tunnels, affecting the safety of the tunnels, especially in soft soil areas with high compressibility, high sensitivity, and high water content. This phenomenon is more prominent.
[0003] Therefore, when excavating foundation pits in soft soil areas, it is particularly important to predict the deformation of existing tunnels in advance and conduct reasonable analysis and protection. Generally, real-time monitoring of foundation pits and tunnels is carried out using the Internet of Things.
[0004] In related technologies, the methods for predicting formation deformation mainly use finite element calculation method and mechanism analysis method. When using finite element calculation method, if the scale of finite element model is large, the calculation takes a long time, so the prediction results are often not timely. However, by using mechanism analysis method, by finding the mapping relationship between input and output, establishing an algorithm model, rapid prediction can be achieved, which is a prediction method superior to finite element calculation method. Summary of the invention
[0005] The embodiment of the present application provides a method and device for predicting tunnel displacement based on foundation pit excavation, which solves the problem of poor timeliness of tunnel displacement prediction. The technical solution is as follows:
[0006] In one aspect, a method for predicting displacement of a tunnel based on foundation pit excavation is provided, the method comprising:
[0007] Obtain foundation pit excavation data;
[0008] Determine the constitutive structure of the target soil layer according to the foundation pit excavation data, and simulate the comprehensive monitoring points of the foundation pit excavation by a finite element analysis method, wherein the finite element analysis method is implemented based on a finite element analysis model and the finite element analysis model is calculated based on the constitutive structure of the target soil layer;
[0009] Implement monitoring on the comprehensive monitoring points to obtain real-time monitoring data;
[0010] Correcting constitutive model parameters of the target soil layer constitutive model in the finite element analysis model based on the real-time monitoring data;
[0011] According to the modified finite element analysis model, the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data are changed to perform secondary analysis to obtain a training data set;
[0012] The least squares support vector machine algorithm is used to establish the relationship between the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The mapping relationship between them;
[0013] The foundation pit parameters and tunnel parameters of the soft soil area to be predicted are obtained and input into the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition in the soft soil area to be predicted before excavation. SD and tunnel vertical displacement Y SD .
[0014] Optionally, the method further includes:
[0015] Obtain standard sections based on drawings and exploration data;
[0016] Collect soil layer information, foundation pit information and tunnel information according to the standard section;
[0017] And the foundation pit excavation data is established based on various types of information.
[0018] Optionally, the comprehensive monitoring points include enclosure lateral displacement monitoring points, pit bottom uplift monitoring points, tunnel horizontal displacement monitoring points and vertical displacement monitoring points.
[0019] Optionally, the constitutive model parameters of the target soil layer constitutive model include elastic modulus E, Poisson's ratio μ, test constant λ, experimental constant κ and critical state line ratio M.
[0020] Optionally, the foundation pit parameters include variable foundation pit parameters and analysis result parameters, the variable foundation pit parameters include foundation pit excavation width D and each excavation unloading ratio w, and the analysis result parameters include support side displacement X JK and pit bottom uplift Y JK , wherein the analysis result parameter is the analysis result of the finite element analysis model;
[0021] The tunnel parameters include tunnel section size d and tunnel horizontal clearance L.
[0022] Optionally, the step of changing the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data to perform secondary analysis based on the modified finite element analysis model to obtain a training data set includes:
[0023] The variable foundation pit parameters and the tunnel parameters are changed to perform the secondary analysis to obtain the training data set.
[0024] Optionally, the training data set includes the foundation pit excavation width D, the tunnel cross-sectional size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK , the pit bottom bulge Y JK , tunnel horizontal displacement X SD and tunnel vertical displacement Y SD .
[0025] Optionally, the least squares support vector machine algorithm is used to establish the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The mapping relationship between them includes:
[0026] The least squares support vector machine algorithm is used to respectively establish the foundation pit excavation width D, the tunnel section size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK and the pit bottom bulge Y JK The horizontal displacement of the tunnel is X SD and tunnel vertical displacement Y SD The mapping relationship between them.
[0027] On the other hand, a prediction device based on the displacement of a tunnel excavated in a foundation pit is also provided, the device is applicable to the prediction method based on the displacement of a tunnel excavated in a foundation pit as described above, and the device comprises:
[0028] A data acquisition module is used to acquire foundation pit excavation data;
[0029] An analysis and simulation module, used for determining the constitutive property of a target soil layer according to the foundation pit excavation data, and simulating the comprehensive monitoring points of the foundation pit excavation by a finite element analysis method, wherein the finite element analysis method is implemented based on a finite element analysis model and the finite element analysis model is calculated based on the constitutive property of the target soil layer;
[0030] A real-time monitoring module is used to monitor the comprehensive monitoring points and obtain real-time monitoring data;
[0031] A model correction module, used for correcting constitutive model parameters of the target soil layer constitutive model in the finite element analysis model based on the real-time monitoring data;
[0032] A secondary analysis module, used for changing the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data according to the modified finite element analysis model to perform secondary analysis and obtain a training data set;
[0033] The mapping establishment module is used to establish the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X respectively by using the least squares support vector machine algorithm. SD and tunnel vertical displacement Y SD The mapping relationship between them;
[0034] The prediction execution module is used to obtain the foundation pit parameters and tunnel parameters of the soft soil area to be predicted and input the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition predicted before excavation in the soft soil area to be predicted. SD and tunnel vertical displacement Y SD .
[0035] On the other hand, a computer-readable storage medium is provided, wherein the storage medium stores at least one instruction, and the at least one instruction is used to be executed by a processor to implement the prediction method for displacement of a tunnel based on foundation pit excavation as described in the above aspects.
[0036] On the other hand, a computer program product is also provided, which stores at least one instruction, and the at least one instruction is loaded and executed by the processor to implement the prediction method based on tunnel displacement during foundation pit excavation as described in the above aspect.
[0037] The present application provides a method for predicting displacement of a tunnel based on foundation pit excavation, which has at least the following technical effects:
[0038] This solution combines finite element simulation with algorithmic models, obtains qualitative analysis of soil deformation through finite element simulation, and then establishes a prediction model through the algorithmic model, realizing the effective integration of the two. The algorithmic model is reusable in different projects in the same soft soil area, and the tunnel displacement under different projects can be predicted by simply changing the corresponding parameters, which improves the universality and efficiency of the method.
[0039] Improved accuracy and real-time performance: Dynamically adjust model parameters and combine real-time monitoring data to improve the accuracy and real-time performance of finite element analysis models. This helps to more accurately predict the impact of foundation pit excavation on subway tunnels and increase the accuracy of engineering decisions.
[0040] Optimize the construction process: By timely understanding the impact of foundation pit excavation on the tunnel, the construction party can adjust the excavation strategy and progress based on real-time data to minimize the adverse impact on the tunnel. This helps to optimize the construction process and improve construction efficiency.
[0041] Scientific decision support: A scientific decision support system based on real-time monitoring and model analysis is provided to help engineers and decision makers better understand the impact of foundation pit excavation on subway tunnels and make reasonable decisions based on scientific data to ensure the sustainable development of the project.
[0042] In general, the scheme comprehensively and accurately predicts the impact of foundation pit excavation on tunnel displacement by comprehensively using measured data, finite element analysis, machine learning algorithms and other means. It has high technical effects, improves project safety, reduces potential risks, optimizes the construction process, reduces maintenance costs, and provides a scientific basis for decision-making. It can provide reliable safety prediction and control means for foundation pit excavation projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 A flow chart of a method for predicting displacement of a tunnel based on foundation pit excavation provided by an exemplary embodiment of the present application is shown;
[0044] Figure 2 Shows the corresponding Figure 1 A standard cross-sectional schematic diagram of an embodiment;
[0045] Figure 3 A structural block diagram of a prediction device for displacement of a tunnel based on foundation pit excavation provided by an exemplary embodiment of the present application is shown. DETAILED DESCRIPTION
[0046] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below with reference to the accompanying drawings.
[0047] The term "multiple" as used herein refers to two or more than two. "And / or" describes the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the related objects are in an "or" relationship.
[0048] An exemplary embodiment of the present application provides a method for predicting displacement of a tunnel based on foundation pit excavation, the method comprising the following steps:
[0049] Step 101, obtaining foundation pit excavation data.
[0050] In a possible implementation, based on the standard profile, foundation pit excavation data such as soil layer stratification information, foundation pit width, unloading ratio of each excavation, tunnel section size, horizontal clearance, and tunnel burial depth are obtained.
[0051] like Figure 2 As shown in the figure, it shows a schematic diagram of the standard section, where H refers to the excavation depth of the foundation pit, h refers to the excavated depth, and H 0Refers to the thickness of the soil covering the tunnel.
[0052] Furthermore, the following contents may be included before step 101.
[0053] Content 1. Obtain standard sections based on drawings and exploration data.
[0054] Content 2: Collect soil layer information, foundation pit information and tunnel information based on standard sections.
[0055] Content 3. Establish foundation pit excavation data based on various types of information.
[0056] Step 102, determining the constitutive structure of the target soil layer according to the foundation pit excavation data, and simulating by finite element analysis method to obtain the comprehensive monitoring points of the foundation pit excavation.
[0057] Among them, the finite element analysis method is implemented based on the finite element analysis model and the finite element analysis model is based on the constitutive calculation of the target soil layer. In a possible implementation method, based on the standard section, a two-dimensional analysis model (i.e., the finite element analysis model) is established, and the MCC constitutive model (i.e., the constitutive model of the target soil layer) is selected to simulate the soft soil. The finite element analysis method is used to qualitatively analyze and simulate the impact of foundation pit excavation on the existing tunnel, that is, to determine the comprehensive monitoring points of the foundation pit excavation.
[0058] Among them, according to the on-site conditions, the comprehensive monitoring points include enclosure lateral displacement monitoring points, pit bottom uplift monitoring points, tunnel horizontal displacement monitoring points and vertical displacement monitoring points.
[0059] Step 103, monitor the comprehensive monitoring points to obtain real-time monitoring data.
[0060] Step 104: correct the constitutive model parameters of the target soil layer in the finite element analysis model based on the real-time monitoring data.
[0061] Based on the real-time monitoring data, the soil layer parameters input into the finite element analysis model are modified, that is, the constitutive model parameters of the target soil layer.
[0062] Optionally, the constitutive model parameters of the target soil layer constitutive model include elastic modulus E, Poisson's ratio μ, test constant λ, test constant κ and critical state line ratio M.
[0063] In a possible implementation, the correction content of the constitutive parameters of the target soil layer may include the following content. Adjustment method and correction basis, the specific adjustment method can be based on the measured data and actual monitoring results of the target soil layer. For example, by comparing the prediction results of the finite element analysis model with the actual monitoring data, the inversion or optimization algorithm can be used to gradually adjust the constitutive parameters of the target soil layer so that the model prediction is more in line with the actual situation. According to the actual monitoring data, constitutive parameters such as elastic modulus and Poisson's ratio can be adjusted to improve the accuracy of the model.
[0064] Step 105 , according to the modified finite element analysis model, the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data are changed to perform secondary analysis to obtain a training data set.
[0065] Further, the finite element analysis model is modified based on the real-time monitoring data and then the finite element analysis is performed again until the analysis results are consistent with the monitoring results. Specifically, the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data are changed to perform secondary analysis to obtain a training data set.
[0066] Optionally, the foundation pit parameters include variable foundation pit parameters and analysis result parameters. The variable foundation pit parameters include the foundation pit excavation width D and the unloading ratio w of each excavation. The analysis result parameters include the support side displacement X JK and pit bottom uplift Y JK , where the analysis result parameters are the analysis results of the finite element analysis model. Tunnel parameters include tunnel section size d and tunnel horizontal clearance L.
[0067] If the analysis result parameter is a model analysis result, then step 105 can be further implemented as: changing the variable foundation pit parameters and tunnel parameters to perform secondary analysis to obtain a training data set.
[0068] Correspondingly, the training data set includes the excavation width D of the foundation pit, the cross-sectional size d of the tunnel, the horizontal clearance L of the tunnel, the unloading ratio w of each excavation, and the lateral displacement X of the support. JK , pit bottom uplift Y JK , tunnel horizontal displacement X SD and tunnel vertical displacement Y SD .
[0069] At this point, it can be considered that the soil properties of the finite element analysis model are consistent with the actual soil properties. Then, the excavation width D, the unloading ratio w of each excavation, the tunnel section size d, and the horizontal clearance L of the tunnel are changed. The influence of the excavation of the foundation pit on the tunnel displacement is simulated by finite element to obtain the training data set.
[0070] In addition, in step 104 and step 105, the use of real-time monitoring data involves dynamically adjusting the finite element analysis model to ensure the real-time and accuracy of the model. The following are the operational steps and considerations that may be included.
[0071] 1. Update soil constitutive parameters in real time.
[0072] Adjust parameters based on measured data: Compare real-time monitoring data with the prediction results of the finite element analysis model. Use feedback control algorithms, such as proportional integral derivative (PID) control, to adjust the constitutive parameters of the target soil layer in real time based on the monitoring results.
[0073] Adaptive parameter adjustment: Use adaptive algorithms, such as genetic algorithms or particle swarm optimization, to automatically adjust soil constitutive parameters based on real-time monitoring data to adapt to changing subsurface conditions.
[0074] 2. Verify the real-time performance of the model.
[0075] Real-time model validation: Develop a validation strategy that includes real-time comparison of real-time monitoring data with model predictions. By examining the differences between measured data and model predictions, the real-time performance of the model under current operating conditions can be evaluated.
[0076] Real-time error analysis: A real-time error analysis system is established to track the error between actual monitoring data and model predictions. If the error exceeds a certain threshold, the system can trigger the operation of adjusting model parameters.
[0077] 3. Real-time monitoring of data transmission and processing.
[0078] Data transmission frequency: Ensure that the transmission frequency of real-time monitoring data is high enough to update the model in a timely manner. Choose appropriate data transmission channels and technologies to ensure the real-time nature of the data.
[0079] Data processing methods: Real-time monitoring data may be affected by noise and outliers, so filtering and data processing techniques are needed to ensure that the data input into the model is reliable.
[0080] 4. Model update frequency and computational efficiency.
[0081] Real-time update frequency: Set the real-time update frequency of the finite element analysis model to ensure that it can maintain sufficient real-time performance under actual engineering conditions.
[0082] Computational efficiency: Optimize the computational algorithms and model structure based on the size and complexity of the finite element model to ensure that real-time updates do not cause excessive computational burden.
[0083] Through these operations, real-time and dynamic finite element analysis model adjustments can be achieved during foundation pit excavation to more accurately reflect changes in actual underground conditions and improve the real-time and accuracy of predictions.
[0084] Step 106, using the least squares support vector machine algorithm, respectively establish the foundation pit parameters and tunnel parameters and the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The mapping relationship between them.
[0085] Specifically, the foundation pit parameters and tunnel parameters are established with the tunnel horizontal displacement X SD and tunnel vertical displacement Y SDThe mapping relationship between them can also be understood as: the design can calculate the tunnel horizontal displacement X based on the foundation pit parameters and tunnel parameters SD and tunnel vertical displacement Y SD Mathematical formula of .
[0086] In a possible implementation, the training of the algorithm model may include the following content.
[0087] Select training data: Select representative and diverse training data sets, including foundation pit parameters, tunnel parameters, monitoring data, etc. Ensure that the training data covers a variety of possible engineering conditions and changes.
[0088] Verify the accuracy of the model: Use an independent validation dataset to evaluate the accuracy of the model. You can use methods such as cross-validation to ensure that the model has good predictive performance on unseen data.
[0089] Adjust algorithm parameters: Adjust algorithm parameters based on the model verification results. This may involve kernel function selection in support vector machines, regularization parameter adjustment, etc. Find the optimal algorithm parameter configuration through repeated training and verification.
[0090] Step 107, obtain the foundation pit parameters and tunnel parameters of the soft soil area to be predicted and input them into the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition predicted before excavation in the soft soil area to be predicted SD and tunnel vertical displacement Y SD .
[0091] It should be noted that the hidden layer or processing layer in the algorithm prediction model corresponding to the least squares support vector machine algorithm is the layer in step S106 that can calculate the tunnel horizontal displacement X based on the foundation pit parameters and tunnel parameters. SD and tunnel vertical displacement Y SD Mathematical formula of .
[0092] In a possible implementation, the least squares support vector machine algorithm is used to establish the foundation pit excavation width D, tunnel section size d, tunnel horizontal clearance L, each excavation unloading ratio w, support lateral displacement X, and the like. JK and pit bottom uplift Y JK The horizontal displacement of the tunnel is X SD and tunnel vertical displacement Y SD The mapping relationship between them. Among them, the excavation width D, the unloading ratio w of each excavation, and the support side displacement X JK and pit bottom uplift Y JK are all foundation pit parameters, tunnel section size d and tunnel horizontal clearance L are all tunnel parameters, tunnel horizontal displacement X SD and tunnel vertical displacement Y SDThe first calculation formula (i.e. the hidden layer in the algorithm prediction model corresponding to the least squares support vector machine algorithm, or the processing layer) is as follows:
[0093]
[0094] Among them, a 1 to a 12 and b 1 To b 12 are the parameters of the corresponding items in the calculation process, and the parameters are learned from historical data through the least squares support vector machine algorithm in the training process. In the above formula, and log(w+1) can effectively handle the range of parameter changes and capture the significant impact of small numerical changes. Logarithmic transformation can amplify the impact when the parameter changes are small, and compress the impact when the parameter changes are large, adapting to nonlinear characteristics. It can capture the combined effect of support lateral displacement and pit bottom uplift, reflecting the significant influence of these parameters on tunnel displacement under specific conditions. In addition, the interaction term Dw represents the joint influence of foundation pit excavation width and each excavation unloading ratio. These parameters often do not act independently in actual engineering, and their interaction terms can reflect the synergistic effect of the two. High-order terms and w 2 Reflecting the square effect of excavation width, horizontal clearance and unloading ratio, it can better fit the complex influence of these parameters in actual situations and improve the fitting accuracy of the model. Through logarithmic and exponential transformations, as well as reasonable interaction terms and high-order term designs, the formula can maintain calculation stability within a wide range of parameters and will not cause numerical instability due to extreme values. The formula contains a variety of parameter transformations and interaction terms, which can adapt to different engineering conditions and scenarios and has strong adaptability. Especially in soft soil areas, the formula can adapt to different project requirements by adjusting parameter coefficients. Through the above-mentioned improved mathematical formula design, the horizontal displacement and vertical displacement of the tunnel can be accurately calculated based on the foundation pit parameters and tunnel parameters. This design not only improves the expressive power of the model, but also captures the complex relationship between the input parameters, and ensures the accuracy and consistency of the calculation through unit conversion.
[0095] In another possible implementation, the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The second calculation formula is as follows:
[0096]
[0097] where a 1 to a 11 and b 1 To b 11are the parameters of the corresponding items in the calculation process. The parameters are learned from historical data through the least squares support vector machine algorithm in the training process. The logarithmic terms log(D+1) and log(Y JK +1) Logarithmic transformation can reduce a wide range of values to a smaller range, making the model more sensitive to changes in input parameters while avoiding the impact of extreme values on the model. At the same time, logarithmic transformation can linearize the exponential growth relationship, making it easier to capture and fit the actual nonlinear relationship. The square root transformation can smooth the changes of input variables, reduce the differences between large values, and make the model more stable. In certain ranges, the square root transformation can better approximate the linear relationship and improve the fitting effect of the model. The remaining product terms can capture the interaction between parameters and provide more detailed feature representation, thereby improving the expressiveness of the model. The fractional terms can express the proportional relationship between different parameters and are suitable for capturing the characteristics of certain proportional effects. Trigonometric functions can capture periodic changes and are suitable for describing characteristics with periodicity or volatility. Exponential transformation can capture rapidly changing relationships and is suitable for describing phenomena of rapid growth or decay. By introducing a variety of nonlinear features, the model can better capture the complex nonlinear relationship between foundation pit parameters and tunnel parameters and tunnel displacement, and improve the prediction accuracy. The introduction of complex transformations (such as product terms, trigonometric functions, and exponential transformations) can provide more detailed fitting capabilities, thereby more accurately reflecting the displacement conditions in actual projects and meeting the needs of high-precision predictions.
[0098] In another possible implementation, the tunnel horizontal displacement X is calculated using the first calculation formula and the second calculation formula respectively. SD and tunnel vertical displacement Y SD After that, the tunnel horizontal displacement X can be obtained by adding and averaging. SD and tunnel vertical displacement Y SD This operation can combine the advantages of the above two calculation methods, so that the final result takes more factors into consideration and is more universal.
[0099] It should be noted that the prediction result can be obtained by inputting various data and parameters into the algorithm established in step 107, and there is no need to repeat steps 101 to 106.
[0100] Based on the above algorithm prediction model, in a certain soft soil area, according to the standard profile, the foundation pit width D, tunnel section size d, horizontal clearance L, each excavation unloading ratio w, support lateral displacement X are input into the algorithm prediction model. JK , pit bottom uplift Y JK , the horizontal displacement X of the tunnel under the corresponding excavation condition can be predicted before excavation SD and tunnel vertical displacement Y SD .
[0101] This scheme comprehensively considers multiple factors such as foundation pit width, tunnel section size, horizontal clearance, and unloading ratio of each excavation. It combines finite element simulation with algorithm model, obtains qualitative analysis of soil deformation through finite element simulation, and then establishes a prediction model through the algorithm model, realizing the effective integration of the two. Under the premise of only monitoring the lateral displacement of the foundation pit retaining structure, this method can predict the impact of each excavation on the tunnel displacement, reducing the monitoring cost. Moreover, the algorithm model is reusable in different projects in the same soft soil area. It only needs to change the corresponding parameters to predict the tunnel displacement under different projects, which improves the universality and efficiency of the method.
[0102] To sum up, the technical effects of this solution are mainly reflected in the following aspects:
[0103] Early risk identification and mitigation: By real-time monitoring and dynamic adjustment of the finite element analysis model, the impact of foundation pit excavation on the tunnel can be discovered and responded to in a timely manner, which helps to identify potential risks in advance. By adjusting the soil constitutive parameters in real time, the adverse impact on the tunnel can be mitigated, thereby ensuring the safety of the subway tunnel.
[0104] Improved accuracy and real-time performance: Dynamically adjust model parameters and combine real-time monitoring data to improve the accuracy and real-time performance of finite element analysis models. This helps to more accurately predict the impact of foundation pit excavation on subway tunnels and increase the accuracy of engineering decisions.
[0105] Optimize the construction process: By timely understanding the impact of foundation pit excavation on the tunnel, the construction party can adjust the excavation strategy and progress based on real-time data to minimize the adverse impact on the tunnel. This helps to optimize the construction process and improve construction efficiency.
[0106] Scientific decision support: A scientific decision support system based on real-time monitoring and model analysis is provided to help engineers and decision makers better understand the impact of foundation pit excavation on subway tunnels and make reasonable decisions based on scientific data to ensure the sustainable development of the project.
[0107] In general, the scheme comprehensively and accurately predicts the impact of foundation pit excavation on tunnel displacement by comprehensively using measured data, finite element analysis, machine learning algorithms and other means. It has high technical effects, improves project safety, reduces potential risks, optimizes the construction process, reduces maintenance costs, and provides a scientific basis for decision-making. It can provide reliable safety prediction and control means for foundation pit excavation projects.
[0108] Please refer to Figure 3 , which shows a structural block diagram of a prediction device based on tunnel displacement during foundation pit excavation provided by an exemplary embodiment of the present application, the device comprising:
[0109] The data acquisition module 301 is used to acquire foundation pit excavation data;
[0110] An analysis and simulation module 302 is used to determine the constitutive structure of the target soil layer according to the foundation pit excavation data, and to obtain the comprehensive monitoring points of the foundation pit excavation by simulating the finite element analysis method, wherein the finite element analysis method is implemented based on a finite element analysis model and the finite element analysis model is calculated based on the constitutive structure of the target soil layer;
[0111] A real-time monitoring module 303 is used to monitor the comprehensive monitoring points and obtain real-time monitoring data;
[0112] A model correction module 304, used for correcting constitutive model parameters of the target soil layer constitutive model in the finite element analysis model based on the real-time monitoring data;
[0113] A secondary analysis module 305 is used to change the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data according to the modified finite element analysis model to perform secondary analysis and obtain a training data set;
[0114] The mapping establishment module 306 is used to establish the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X respectively by using the least squares support vector machine algorithm. SD and tunnel vertical displacement Y SD The mapping relationship between them;
[0115] The prediction execution module 307 is used to obtain the foundation pit parameters and tunnel parameters of the soft soil area to be predicted and input the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition predicted before excavation in the soft soil area to be predicted. SD and tunnel vertical displacement Y SD .
[0116] Optionally, the device further comprises:
[0117] The first acquisition module is used to acquire the standard section according to the drawings and exploration data;
[0118] A second acquisition module is used to collect soil layer information, foundation pit information and tunnel information according to the standard section;
[0119] The third acquisition module is used to establish the foundation pit excavation data based on various types of information.
[0120] Optionally, the comprehensive monitoring points include enclosure lateral displacement monitoring points, pit bottom uplift monitoring points, tunnel horizontal displacement monitoring points and vertical displacement monitoring points.
[0121] Optionally, the constitutive model parameters of the target soil layer constitutive model include elastic modulus E, Poisson's ratio μ, test constant λ, experimental constant κ and critical state line ratio M.
[0122] Optionally, the foundation pit parameters include variable foundation pit parameters and analysis result parameters, the variable foundation pit parameters include foundation pit excavation width D and each excavation unloading ratio w, and the analysis result parameters include support side displacement X JK and pit bottom uplift Y JK , wherein the analysis result parameter is the analysis result of the finite element analysis model;
[0123] The tunnel parameters include tunnel section size d and tunnel horizontal clearance L.
[0124] Optionally, the secondary analysis module 305 is further used to change the variable foundation pit parameters and the tunnel parameters to perform the secondary analysis to obtain the training data set.
[0125] Optionally, the training data set includes the foundation pit excavation width D, the tunnel cross-sectional size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK , pit bottom uplift Y JK , tunnel horizontal displacement X SD and tunnel vertical displacement Y SD .
[0126] Optionally, the mapping establishment module 306 is further used to use the least squares support vector machine algorithm to respectively establish the foundation pit excavation width D, the tunnel cross-sectional size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK and the pit bottom bulge Y JK The horizontal displacement of the tunnel is X SD and tunnel vertical displacement Y SD The mapping relationship between them.
[0127] An embodiment of the present application also provides a computer-readable storage medium, which stores at least one instruction, at least one program, a code set or an instruction set. The at least one instruction, the at least one program, the code set or the instruction set is loaded and executed by a processor to implement the prediction method based on tunnel displacement during foundation pit excavation as provided in the above-mentioned embodiments.
[0128] Optionally, the computer readable storage medium may include: a read-only memory (ROM), a random access memory (RAM), a solid state drive (SSD), or an optical disk, etc. Among them, the random access memory may include a resistance random access memory (ReRAM) and a dynamic random access memory (DRAM).
[0129] The serial numbers of the above-mentioned embodiments of the present application are for description only and do not represent the advantages or disadvantages of the embodiments.
[0130] A person skilled in the art will understand that all or part of the steps to implement the above embodiments may be accomplished by hardware or by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, and the above-mentioned storage medium may be a read-only memory, a disk or an optical disk, etc.
[0131] The above description is only an optional embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.
Claims
1. A method for predicting tunnel displacement based on foundation pit excavation, characterized in that: The method comprises: Obtain foundation pit excavation data; Determine the constitutive structure of the target soil layer according to the foundation pit excavation data, and simulate the comprehensive monitoring points of the foundation pit excavation by a finite element analysis method, wherein the finite element analysis method is implemented based on a finite element analysis model and the finite element analysis model is calculated based on the constitutive structure of the target soil layer; Implement monitoring on the comprehensive monitoring points to obtain real-time monitoring data; Correcting constitutive model parameters of the target soil layer constitutive model in the finite element analysis model based on the real-time monitoring data; According to the modified finite element analysis model, the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data are changed to perform secondary analysis to obtain a training data set; The least squares support vector machine algorithm is used to establish the relationship between the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The mapping relationship between them; The foundation pit parameters and tunnel parameters of the soft soil area to be predicted are obtained and input into the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition predicted before excavation in the soft soil area to be predicted. SD and tunnel vertical displacement Y SD .
2. The prediction method for displacement of tunnels based on foundation pit excavation according to claim 1, characterized in that: The method further comprises: Obtain standard sections based on drawings and exploration data; Collect soil layer information, foundation pit information and tunnel information according to the standard section; And the foundation pit excavation data is established based on various types of information.
3. The prediction method of tunnel displacement based on foundation pit excavation according to claim 1 is characterized in that: The comprehensive monitoring points include enclosure lateral displacement monitoring points, pit bottom uplift monitoring points, tunnel horizontal displacement monitoring points and vertical displacement monitoring points.
4. The method for predicting displacement of tunnels based on foundation pit excavation according to claim 1, characterized in that: The constitutive model parameters of the target soil layer constitutive model include elastic modulus E, Poisson's ratio μ, test constant λ, experimental constant κ and critical state line ratio M.
5. The method for predicting displacement of tunnels based on foundation pit excavation according to claim 1, characterized in that: The foundation pit parameters include variable foundation pit parameters and analysis result parameters. The variable foundation pit parameters include foundation pit excavation width D and each excavation unloading ratio w. The analysis result parameters include support side displacement X JK and pit bottom uplift Y JK , wherein the analysis result parameter is the analysis result of the finite element analysis model; The tunnel parameters include tunnel section size d and tunnel horizontal clearance L.
6. The method for predicting displacement of tunnels based on foundation pit excavation according to claim 5, characterized in that: According to the modified finite element analysis model, the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data are changed to perform secondary analysis to obtain a training data set, including: The variable foundation pit parameters and the tunnel parameters are changed to perform the secondary analysis to obtain the training data set.
7. The method for predicting displacement of tunnels based on foundation pit excavation according to claim 5, characterized in that: The training data set includes the foundation pit excavation width D, the tunnel cross-sectional size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK , the pit bottom bulge Y JK , tunnel horizontal displacement X SD and tunnel vertical displacement Y SD .
8. The method for predicting displacement of tunnels based on foundation pit excavation according to claim 7, characterized in that: The least squares support vector machine algorithm is used to establish the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X SD and tunnel vertical displacement Y SD The mapping relationship between them includes: The least squares support vector machine algorithm is used to respectively establish the foundation pit excavation width D, the tunnel section size d, the tunnel horizontal clearance L, the unloading ratio w of each excavation, the support lateral displacement X JK and the pit bottom bulge Y JK The horizontal displacement of the tunnel is X SD and tunnel vertical displacement Y SD The mapping relationship between them.
9. A prediction device for tunnel displacement based on foundation pit excavation, characterized in that: The device is applicable to the prediction method of tunnel displacement based on foundation pit excavation as claimed in any one of claims 1 to 8, and the device comprises: A data acquisition module is used to acquire foundation pit excavation data; An analysis and simulation module, used for determining the constitutive property of a target soil layer according to the foundation pit excavation data, and simulating the comprehensive monitoring points of the foundation pit excavation by a finite element analysis method, wherein the finite element analysis method is implemented based on a finite element analysis model and the finite element analysis model is calculated based on the constitutive property of the target soil layer; A real-time monitoring module is used to monitor the comprehensive monitoring points and obtain real-time monitoring data; A model correction module, used for correcting constitutive model parameters of the target soil layer constitutive model in the finite element analysis model based on the real-time monitoring data; A secondary analysis module, used for changing the foundation pit parameters and tunnel parameters corresponding to the foundation pit excavation data according to the modified finite element analysis model to perform secondary analysis and obtain a training data set; The mapping establishment module is used to establish the foundation pit parameters and the tunnel parameters and the tunnel horizontal displacement X respectively by using the least squares support vector machine algorithm. SD and tunnel vertical displacement Y SD The mapping relationship between them; The prediction execution module is used to obtain the foundation pit parameters and tunnel parameters of the soft soil area to be predicted and input the algorithm prediction model corresponding to the least squares support vector machine algorithm to obtain the horizontal displacement X of the tunnel under the corresponding excavation condition predicted before excavation in the soft soil area to be predicted. SD and tunnel vertical displacement Y SD .
10. A computer-readable storage medium, characterized in that: The storage medium stores at least one instruction, and the at least one instruction is used to be executed by the processor to implement the prediction method based on foundation pit excavation tunnel displacement as described in any one of claims 1 to 8.
Citation Information
Patent Citations
Quick feedback analyzing system in tunnel constructing process
CN102155231A
Multi-objective optimization method for shield underneath existing tunnel construction based on GA-LSSVM and NSGA-II
CN112417573A
Tunnel structure construction method based on mine method underpinning pile foundation
CN113027464A
Foundation pit excavation deformation real-time automatic prediction method and system considering time effect
CN116702363A
Method for predicting stratum and tunnel deformation caused by foundation pit excavation based on two-stage agent model
CN118070604A
Cited By
Ground disaster monitoring and early warning system and method based on multi-source fusion
CN119625926A
Quality evaluation and analysis method for excavation support of underground powerhouse
CN119761147A
Evaluation and analysis method of excavation support quality of underground powerhouse
CN119761147B
Machine vision displacement calibration method for foundation pit construction
CN119887925A
Foundation pit deformation prediction method and system, intelligent terminal and storage medium
CN120124136A