Photovoltaic power generation project construction procedure management system and method

Through the photovoltaic power generation project construction procedure management system, intelligent algorithms and modular management are used to solve the problems of complex compliance procedures and insufficient risk management, achieve precise management and efficient handling of compliance procedures, and ensure project compliance and efficiency. .

CN118780919APending Publication Date: 2024-10-15THREE GORGES GRP YUNNAN ENERGY INVESTMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410833590.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The compliance procedures during the construction of photovoltaic power generation projects are complicated, inefficient, complicated, and risk management is insufficient, resulting in slow project progress and failure to complete procedures in a timely manner, which may lead to the risk of penalties for construction without approval.

Method used

A photovoltaic power generation project construction procedure management system is designed, including a user module, an entry module, an early warning module, a processing module, an approval module, a reporting module and an archiving module. It uses machine learning, natural language processing and intelligent classification algorithms to implement compliance procedures. Accurate management, reminder, supervision and automatic archiving.

Benefits of technology

It ensures that compliance procedures are completed on time, approval prompts are accurate and efficient, and archives are comprehensive and tidy, reducing the risk of construction before approval, improving compliance and efficiency, and enhancing the dynamics of resource allocation and the intelligence level of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780919A_ABST
    Figure CN118780919A_ABST
Patent Text Reader

Abstract

The invention discloses a photovoltaic power generation project construction procedure management system and method, a user module manages registration, login and authority distribution of a user role, an input module inputs and sorts compliance procedures needing to be handled in project development and construction and time nodes of compliance procedure handling, an early warning module carries out reminding and early warning on the user role, and an early warning module carries out early warning on the user role. The handling module receives related vouchers which are scanned and uploaded after the user role completes compliance procedure handling and eliminates reminding and early warning related to project procedures, and the approval module checks compliance procedure handling conditions for approval items and approval processes and supervises uncompleted compliance procedures. The report module regularly forms a report according to the project reminding and early warning conditions and sends the report to a user role, and the archiving module automatically classifies and archives the uploaded compliance procedures according to the projects. The project compliance procedure handling situation is managed, it is ensured that the project compliance procedure is handled on time, examination and approval prompting is accurate and efficient, and archive data is comprehensive and tidy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of project development and construction, and in particular, to a photovoltaic power generation project construction procedures management system and method. Background Art

[0002] The dual carbon strategy advocates a green, environmentally friendly, low-carbon lifestyle, accelerates the pace of reducing carbon emissions, and is conducive to guiding green technology innovation and improving the global competitiveness of industry and economy. We will continue to promote the adjustment of industrial structure and energy structure, vigorously develop renewable energy, accelerate the planning and construction of large-scale wind power and photovoltaic base projects in deserts, Gobi and wasteland areas, and strive to balance economic development and green transformation.

[0003] With the implementation of the dual carbon strategy, major energy investment companies have increased their investment in new energy power generation projects. Compared with traditional thermal power and hydropower projects, new energy power generation projects involve many compliance procedures, such as land use approval, environmental assessment, construction permits, etc.

[0004] However, the above procedures are complicated, involving multiple government departments and taking a long time, which often leads to slow project progress and even affects the overall benefits of the project. At the same time, due to the short development cycle of new energy projects, some compliance procedures are not handled in time during the project development and construction process. Due to the tight construction schedule, the risk of penalties for construction before approval is likely to arise if the procedures are not completed in time during the subsequent construction. Photovoltaic projects are particularly prone to the above risks due to their wide range of land use and complex land use conditions. Summary of the invention

[0005] The purpose of this application is to overcome the existing technical defects and provide a photovoltaic power generation project construction procedures management system and method, which manages the project compliance procedures to ensure that the project compliance procedures are handled on time, the approval prompts are accurate and efficient, and the archival materials are comprehensive and neat.

[0006] The purpose of this application is achieved through the following technical solutions:

[0007] In the first aspect, the present application proposes a photovoltaic power generation project construction procedures management system, the system comprising a user module, an input module, an early warning module, a handling module, an approval module, a report module and an archiving module;

[0008] User module, which is used to manage the registration, login and permission allocation of user roles, and provides a basis for module operations;

[0009] The input module is used to input and sort out the compliance procedures that need to be handled for project development and construction, as well as the time nodes for handling compliance procedures;

[0010] The early warning module is used to remind and warn user roles based on compliance procedures and the time nodes for handling compliance procedures;

[0011] The processing module is used to accept scanned and uploaded relevant documents after the user role completes the compliance procedures, and eliminate reminders and warnings related to project procedures;

[0012] The approval module is used to check the compliance status of approval items and approval processes, and supervise the compliance procedures that have not been completed;

[0013] The reporting module is used to regularly generate reports on project reminders and warnings and send them to user roles;

[0014] The archive module is used to automatically classify and archive the uploaded compliance procedures according to projects.

[0015] In a possible implementation, user roles are divided into project managers and project leaders.

[0016] In a possible implementation manner, the early warning module is further used to:

[0017] Remind user roles one month before the compliance formalities deadline;

[0018] Provide early warning to user roles when the prescribed compliance procedures have been completed;

[0019] Supervise compliance procedures for user role settings.

[0020] In a possible implementation, the early warning module introduces a prediction algorithm that uses a machine learning model to analyze the processing cycles and common problems of different types of procedures and provide accurate time estimates and risk warnings.

[0021] In a possible implementation, the early warning module is also used to predict the processing time of compliance procedures based on historical data and current processing status, and identify potential processing delay risks in advance.

[0022] In a possible implementation, semantic analysis and natural language processing algorithms are introduced into the early warning module to automatically parse and understand the text information and document content submitted by the user, and automatically implement updates.

[0023] In a possible implementation, the processing module introduces an adaptive reminder algorithm for dynamically adjusting the frequency and time points of reminders and warnings according to the behavior patterns and historical reaction times of the user roles.

[0024] In one possible implementation, the archiving module introduces an intelligent classification algorithm, uses machine learning and natural language processing to automatically analyze and identify file content, intelligently classifies files according to predefined classification rules, automatically generates problems that arise in the entire process, and classifies them by time to form a problem database.

[0025] In the second aspect, the present application proposes a method for managing construction procedures for a photovoltaic power generation project, the method comprising:

[0026] Step S1: The user registers and logs into the system through the user management module, and the corresponding permissions are assigned according to the user role;

[0027] Step S2: The project manager sorts out the compliance procedures required for project development and construction in the input module, specifies the time nodes, and enters them into the system;

[0028] Step S3: The system will remind, warn and supervise the process in the early warning module according to the entered compliance procedures and time nodes to ensure that the procedures are handled on time;

[0029] Step S4: The project leader completes the compliance procedures in the handling module, scans and uploads the relevant vouchers to the system, and eliminates the corresponding reminders and warnings;

[0030] Step S5: The project leader initiates an approval request in the approval module, and the project manager approves the request and checks the status of compliance procedures;

[0031] Step S6: The reporting module regularly generates reports on early warning, reminders, and supervision of the project and sends them to relevant personnel;

[0032] Step S7: The archiving module automatically archives the completed compliance formalities documents to ensure that the archive materials are comprehensive and neat, which is convenient for subsequent audit and inspection.

[0033] The above-mentioned main scheme of the present application and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection in the present application; and in the present application, (non-conflicting options) options and other options can also be freely combined. After understanding the scheme of the present application, those skilled in the art can understand that there are multiple combinations based on the prior art and common knowledge, all of which are technical schemes to be protected by the present application, and they are not exhaustively listed here.

[0034] The present application discloses a management system and method for photovoltaic power generation project construction procedures. The user module manages the registration, login and authority allocation of user roles. The input module inputs and sorts out the compliance procedures that need to be handled for project development and construction and the time nodes for handling compliance procedures. The early warning module reminds and warns the user roles. The handling module accepts the scanned and uploaded relevant vouchers after the user role completes the compliance procedures, and eliminates the reminders and warnings related to the project procedures. The approval module checks the compliance procedures for the approval matters and the approval process, and supervises the compliance procedures that have not been completed. The reporting module regularly forms reports on the project reminders and warnings and sends them to the user roles. The archiving module automatically classifies and archives the uploaded compliance procedures according to the project. By managing the compliance procedures of the project, it is ensured that the compliance procedures of the project are handled on time, the approval prompts are accurate and efficient, and the archives are comprehensive and neat. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 A schematic diagram of the structure of a photovoltaic power generation project construction procedures management system proposed in an embodiment of the present application is shown. DETAILED DESCRIPTION

[0036] The following describes the embodiments of the present application through specific examples, and those skilled in the art can easily understand other advantages and effects of the present application from the contents disclosed in this specification. The present application can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present application. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.

[0037] Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making any creative work shall fall within the scope of protection of this application.

[0038] In the existing technology, during the development and construction of photovoltaic power generation projects, the following technical problems will be faced when handling compliance procedures:

[0039] First, low processing efficiency: Compliance procedures are numerous and complicated, and traditional manual processing methods are inefficient, which can easily lead to slow project progress.

[0040] Second, the process is complicated: it involves approval and verification from multiple departments and multiple links. The process is cumbersome and prone to errors, making it difficult to ensure the smooth progress of each link.

[0041] Third, insufficient risk management: unable to effectively predict and prevent potential risks during the application process, which can easily lead to delays or illegal operations.

[0042] Fourth, unreasonable resource allocation: It is impossible to dynamically adjust resource allocation according to actual conditions, resulting in waste or shortage of resources during the processing.

[0043] In order to solve the above problems, this application proposes a photovoltaic power generation project construction procedures management system and method, which manages the project compliance procedures by setting up 7 modules including user module, entry module, early warning module, processing module, approval module, report module and archiving module, ensuring that project compliance procedures are handled on time, approval prompts are accurate and efficient, and archival materials are comprehensive and neat. It is explained in detail below.

[0044] Please refer to Figure 1 , Figure 1 A schematic structural diagram of a photovoltaic power generation project construction procedures management system proposed in an embodiment of the present application is shown. The system is applied to the field of photovoltaic power generation project development and construction, and includes a user module, an entry module, an early warning module, a processing module, an approval module, a report module and an archiving module.

[0045] The user module is used to manage the registration, login and permission allocation of user roles, providing a basis for module operations.

[0046] User roles are divided into project managers and project leaders. The user module manages user registration, login and permission allocation, providing a basis for the operation of other modules.

[0047] The input module is used to input and sort out the compliance procedures that need to be handled for project development and construction, as well as the time nodes for handling the compliance procedures.

[0048] The entry module is used by project managers in the early stages of project development to sort out the various compliance procedures that need to be handled for project development and construction, clarify the time nodes for handling various compliance procedures, and enter them into the photovoltaic power generation project construction procedures management system.

[0049] The early warning module is used to remind and warn user roles based on compliance procedures and the time nodes for handling compliance procedures;

[0050] The early warning module can remind, warn and supervise the project leader a certain time in advance according to the various compliance procedures and processing time nodes entered, and different colors can be used to distinguish the reminders.

[0051] The early warning module is also used for:

[0052] Remind the user role (project leader) one month before the compliance formalities are due;

[0053] Provide early warning to the user role (project leader) when the prescribed compliance procedures have been completed;

[0054] Supervise the compliance procedures set by user roles (project managers).

[0055] The early warning module introduces a predictive algorithm that uses a machine learning model to analyze the processing cycles and common problems of different types of procedures, and provide accurate time estimates and risk warnings.

[0056] The early warning module is also used to predict the processing time of compliance procedures based on historical data and current processing status, and to identify potential processing delay risks in advance.

[0057] Semantic analysis and natural language processing algorithms are introduced into the early warning module to automatically parse and understand the text information and document content submitted by users, and automatically update them. In addition, the early warning module links to major external policy websites, so that when relevant policies are issued, they can be downloaded and pushed in the first time.

[0058] The processing module is used to accept scanned and uploaded relevant certificates after the user role completes the compliance procedures, and eliminate reminders and warnings related to project procedures.

[0059] The processing module introduces an adaptive reminder algorithm to dynamically adjust the frequency and timing of reminders and warnings based on the user role's behavior patterns and historical response times. For example, for users who respond quickly, the system reduces the reminder frequency; for users who respond slowly, the system increases the reminder frequency and issues multiple warnings before key nodes.

[0060] The approval module is used to check the compliance status of approval items and approval processes, and to supervise the compliance procedures that have not been completed.

[0061] For example, in the approval module, the matters that need to be approved are "start of construction of photovoltaic field", "start of construction of booster station", "project grid connection", "project commissioning", "others", etc. The project leader initiates an approval request, and the project management personnel conduct the approval. During the approval process, the compliance procedures can be checked and supervision can be set for the compliance procedures that have not been completed.

[0062] The reporting module is used to regularly generate reports on project reminders and warnings and send them to user roles.

[0063] The reporting module can regularly compile reports on all warnings, reminders, and supervision of the project and send them to the project leader, project managers, and company leaders.

[0064] The archive module is used to automatically classify and archive the uploaded compliance procedures according to projects.

[0065] The archiving module can automatically classify and archive the uploaded compliance procedures according to the project in preparation for subsequent audits, inspections, etc.

[0066] An intelligent classification algorithm is introduced in the archiving module, which uses machine learning and natural language processing to automatically analyze and identify file contents, intelligently classify files according to predefined classification rules, automatically generate problems that arise in the entire process, and classify them by time to form a problem database, which can be exported by managers to form training materials.

[0067] A possible implementation of a photovoltaic power generation project construction procedures management method is given below, which is used to implement the corresponding technical effects of a photovoltaic power generation project construction procedures management system shown in the above embodiment and possible implementation. The method includes:

[0068] Step S1: The user registers and logs into the system through the user management module, and the corresponding permissions are allocated according to the user role.

[0069] The specific operations of step S1 are: user registration and login -> assignment of permissions -> operation of other modules.

[0070] Step S2: The project manager sorts out the compliance procedures required for project development and construction in the entry module, specifies the time nodes, and enters them into the system.

[0071] The specific operations of step S2 are: project managers sort out procedures -> enter procedures and time nodes -> provide basis for early warning, approval and archiving.

[0072] Step S3: The system provides reminders, warnings and supervision in the early warning module based on the entered compliance procedures and time nodes to ensure that the procedures are handled on time.

[0073] The specific operations of step S3 are: based on the input information -> generate reminders, warnings, and supervision -> remind the project leader -> provide approval and report data.

[0074] Step S4: The project leader completes the compliance procedures in the processing module, scans and uploads the relevant certificates to the system, and eliminates the corresponding reminders and warnings.

[0075] The specific operations of step S4 are: the project leader handles the procedures -> uploads the credentials -> eliminates the reminder alert -> provides approval and archives data.

[0076] Step S5: The project leader initiates an approval request in the approval module, and the project manager approves and checks the status of the compliance procedures.

[0077] The specific operations of step S5 are: project leader initiates approval -> project management personnel approves -> checks the completion status of procedures -> supervises unfinished procedures -> generates approval records.

[0078] Step S6: The reporting module regularly generates reports on the project's early warning, reminders, and supervision status and sends them to relevant personnel.

[0079] The specific operations of step S6 are: summarize warning and approval information -> generate regular reports -> send to relevant personnel -> provide archived data.

[0080] Step S7: The archiving module automatically archives the completed compliance formalities documents to ensure that the archive materials are comprehensive and neat, which is convenient for subsequent audit and inspection.

[0081] The specific operations of step S7 are: classify and archive the files of each module -> ensure that the information is comprehensive and neat -> provide a basis for audit inspection.

[0082] Compared with the prior art, the embodiments of the present application have the following beneficial effects:

[0083] First, adopt flexible compliance procedures, and project managers should conduct comprehensive sorting and setting in the early stage to solve the different compliance procedures requirements for different photovoltaic development projects.

[0084] Second, early warning methods include reminders, warnings, supervision and other methods. The supervision method can be flexibly set by project managers to meet the flexible needs of project compliance procedures management.

[0085] Third, the approval work in the development and construction process of photovoltaic power generation projects can be systematized through the approval method. During the approval process, the necessary compliance procedures can be checked in a timely manner, and supervision matters can be proposed to better realize the traceability of the approval work.

[0086] Fourth, through the processing and archiving functions, project compliance procedures can be systematically archived to ensure the legality and compliance of the project, and provide support for subsequent project completion audits and other work. Provide complete archive life cycle management, including creation, storage, use, archiving and destruction, to ensure the systematic and compliant management of archives.

[0087] Fifth, enhance the intelligence of the system. Use a variety of intelligent algorithms (such as prediction algorithms, intelligent recommendation algorithms, semantic analysis and NLP algorithms, etc.) to improve the intelligence level of the system, realize automated and intelligent compliance procedures management, and achieve all-round innovation in compliance procedures management through a variety of technologies to enhance the system's technological advancement and market competitiveness.

[0088] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A photovoltaic power generation project construction procedures management system, characterized in that: The system includes a user module, an input module, an early warning module, a processing module, an approval module, a report module and an archive module; User module, which is used to manage the registration, login and permission allocation of user roles, and provides a basis for module operations; The input module is used to input and sort out the compliance procedures that need to be handled for project development and construction, as well as the time nodes for handling compliance procedures; The early warning module is used to remind and warn user roles based on compliance procedures and the time nodes for handling compliance procedures; The processing module is used to accept scanned and uploaded relevant documents after the user role completes the compliance procedures, and eliminate reminders and warnings related to project procedures; The approval module is used to check the compliance status of approval items and approval processes, and supervise the compliance procedures that have not been completed; The reporting module is used to regularly generate reports on project reminders and warnings and send them to user roles; The archive module is used to automatically classify and archive the uploaded compliance procedures according to projects.

2. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: User roles are divided into project managers and project leaders.

3. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: The early warning module is also used for: Remind user roles one month before the compliance formalities deadline; Provide early warning to user roles when the prescribed compliance procedures have been completed; Supervise compliance procedures for user role settings.

4. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: The early warning module introduces a prediction algorithm that uses a machine learning model to analyze the processing cycles and common problems of different types of procedures, and provide accurate time estimates and risk warnings.

5. The photovoltaic power generation project construction procedures management system as claimed in claim 4, characterized in that: The early warning module is also used to predict the processing time of compliance procedures based on historical data and current processing status, and identify potential processing delay risks in advance.

6. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: The early warning module introduces semantic analysis and natural language processing algorithms to automatically parse and understand text information and document content submitted by users and automatically update them.

7. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: The processing module introduces an adaptive reminder algorithm to dynamically adjust the frequency and time points of reminders and warnings according to the behavior patterns and historical reaction times of user roles.

8. The photovoltaic power generation project construction procedures management system according to claim 1, characterized in that: The archiving module introduces an intelligent classification algorithm, uses machine learning and natural language processing to automatically analyze and identify file content, intelligently classifies files according to predefined classification rules, automatically generates problems that arise in the entire process, and classifies them by time to form a problem database.

9. A photovoltaic power generation project construction procedures management method, characterized in that: The method comprises: Step S1: The user registers and logs into the system through the user management module, and the corresponding permissions are assigned according to the user role; Step S2: The project manager sorts out the compliance procedures required for project development and construction in the input module, specifies the time nodes, and enters them into the system; Step S3: The system will remind, warn and supervise the process in the early warning module according to the entered compliance procedures and time nodes to ensure that the procedures are handled on time; Step S4: The project leader completes the compliance procedures in the handling module, scans and uploads the relevant vouchers to the system, and eliminates the corresponding reminders and warnings; Step S5: The project leader initiates an approval request in the approval module, and the project manager approves the request and checks the status of compliance procedures; Step S6: The reporting module regularly generates reports on early warning, reminders, and supervision of the project and sends them to relevant personnel; Step S7: The archiving module automatically archives the completed compliance formalities documents to ensure that the archive materials are comprehensive and neat, which is convenient for subsequent audit and inspection.