Electromechanical equipment management method and device, computer equipment and storage medium
By managing the procurement and arrival time of electromechanical equipment according to the project contract, the complex problems of equipment management in construction projects are solved, the timely arrival of equipment and report compatibility are achieved, and the safety and accuracy of procurement are improved.
Patent Information
- Application Number
- CN202410846171.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-27
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The management of electromechanical equipment in construction projects is complex, and existing technology makes it difficult to effectively manage the procurement, maintenance, and report compatibility of electromechanical equipment, resulting in slow equipment procurement and low safety and accuracy.
Provide a mechanical and electrical equipment management method that determines the sub-project start time, mechanical and electrical equipment requirements, arrival time, order contract signing time, payment time and arrival time according to the project contract. If there is an overdue situation, a warning is issued to ensure that the equipment is started before the project starts. Time is in place and the method is executed via computer equipment and storage media, establishing schedules and monitoring contract changes.
It improves the purchase and issuance speed of electromechanical equipment, solves the problem of report compatibility in receiving and issuance, and improves the safety and accuracy of equipment procurement.
Smart Images

Figure CN118798807A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of engineering management, and in particular to a method, device, computer equipment and storage medium for managing electromechanical equipment. Background Art
[0002] The procurement of electromechanical equipment in construction projects is complex and the cost accounts for the majority of the total project cost. However, due to the long construction period, the procurement and maintenance of the required electromechanical equipment takes a long time and the management is complex. It is difficult to complete the task by relying solely on manual management using EXCEL office software. Summary of the invention
[0003] In view of this, the present invention provides a method, device, computer equipment and storage medium for managing electromechanical equipment to solve the problem of complex management of electromechanical equipment in construction projects.
[0004] In a first aspect, the present invention provides a method for managing electromechanical equipment, comprising: determining the start time of each sub-project according to the engineering contract; determining the electromechanical equipment required for each sub-project according to the electromechanical equipment catalog in the engineering contract; determining the arrival time of each electromechanical equipment according to the electromechanical equipment required for each sub-project and the start time of each sub-project; determining the final signing time of the order contract for each electromechanical equipment according to the arrival time of each electromechanical equipment; determining the payment time and arrival time of each electromechanical equipment according to the final signing time of the order contract for each electromechanical equipment; if the corresponding amount is not received at the payment time of the electromechanical equipment, or, the arrival notice of the corresponding electromechanical equipment is not received at the arrival time of the electromechanical equipment, or, the arrival notice of the corresponding electromechanical equipment is not received at the arrival time of the electromechanical equipment, an overdue warning is issued.
[0005] The method provided in the embodiment of the present invention determines the time for each electromechanical equipment to be in place after obtaining the project contract, based on the start time of each sub-project and the electromechanical equipment required for each sub-project. Because the signing time of the ordering contract, the payment time, and the arrival time of the electromechanical equipment will all affect the time for the electromechanical equipment to be in place, in the embodiment of the present invention, after determining the time for each electromechanical equipment to be in place, the signing time of the ordering contract, the payment time, and the arrival time of the electromechanical equipment are determined in sequence. When one of the time nodes is overdue, an overdue warning will be issued, thereby ensuring that the electromechanical equipment can be in place when the project starts.
[0006] In an optional implementation, the method provided by the embodiment of the present invention also includes: establishing a schedule for each electromechanical equipment according to the arrival time of each electromechanical equipment, the final signing time of the order contract, the payment time, and the arrival time, and sending the schedule to the first target object.
[0007] In an optional implementation, the method provided by the embodiment of the present invention further includes: monitoring whether the project contract has changed, and if so, returning to the step of determining the start sequence of each sub-project according to the project contract.
[0008] In an optional implementation, the method provided by an embodiment of the present invention also includes: receiving documents for electromechanical equipment; determining the electromechanical equipment to be stored that has currently arrived based on the documents, and generating an arrival notification for the electromechanical equipment to be stored; determining the verification requirements for the electromechanical equipment to be stored based on the engineering contract; receiving verification data for the electromechanical equipment to be stored; if the verification data meets the verification requirements, generating an arrival notification for the electromechanical equipment to be stored.
[0009] In an optional implementation, the method provided by an embodiment of the present invention also includes: if the verification data meets the verification requirements, sending a notification of the arrival of the electromechanical equipment to be stored to the second target object; if the verification data does not meet the verification requirements, sending a return notification of the electromechanical equipment to be stored to the third target object.
[0010] In an optional implementation, the method provided by an embodiment of the present invention also includes: determining the scheduled inspection time and the outbound time of the electromechanical equipment to be stored in the engineering contract; regularly sending scheduled inspection notifications to the fourth target object according to the scheduled inspection time, and receiving a scheduled inspection result notification, wherein the scheduled inspection notification is used to prompt the fourth target object to inspect the electromechanical equipment to be stored according to the scheduled inspection time; receiving an outbound notification, and sending an outbound document and a scheduled inspection result notification to the fifth target object.
[0011] In a second aspect, the present invention provides an electromechanical equipment management device, comprising: a sub-project start time determination module, used to determine the start time of each sub-project according to the project contract; an electromechanical equipment demand analysis module, used to determine the electromechanical equipment required for each sub-project according to the electromechanical equipment catalog in the project contract; an arrival time determination module, used to determine the arrival time of each electromechanical equipment according to the electromechanical equipment required for each sub-project and the start time of each sub-project; a signing time determination module, used to determine the final signing time of the order contract for each electromechanical equipment according to the arrival time of each electromechanical equipment; an ordering process determination module, used to determine the payment time and arrival time of each electromechanical equipment according to the final signing time of the order contract for each electromechanical equipment; a warning module, if the corresponding amount is not received at the payment time of the electromechanical equipment, or, the arrival notification of the corresponding electromechanical equipment is not received at the arrival time of the electromechanical equipment, or, the arrival notification of the corresponding electromechanical equipment is not received at the arrival time of the electromechanical equipment, the warning module is used to issue an overdue warning.
[0012] In a third aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the electromechanical equipment management method of the first aspect or any corresponding embodiment thereof by executing the computer instructions.
[0013] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the electromechanical equipment management method of the first aspect or any corresponding embodiment thereof.
[0014] In a fifth aspect, the present invention provides a computer program product, comprising computer instructions for causing a computer to execute the electromechanical equipment management method of the first aspect or any corresponding embodiment thereof.
[0015] The method of the present invention is beneficial to the speed of purchasing and issuing electromechanical equipment, solves the report compatibility problem in receiving and issuing electromechanical equipment, and improves the safety and accuracy of equipment procurement. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 is a flow chart of a method for managing electromechanical equipment according to an embodiment of the present invention;
[0018] Figure 2 is a structural block diagram of a mechanical and electrical equipment management device according to an embodiment of the present invention;
[0019] Figure 3 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0021] According to an embodiment of the present invention, an embodiment of a method for managing electromechanical equipment is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0022] In this embodiment, a method for managing electromechanical equipment is provided, which can be used in mobile terminals, such as mobile phones, tablet computers, etc. Figure 1 is a flow chart of a method for managing electromechanical equipment according to an embodiment of the present invention. Figure 1 As shown, the process includes the following steps:
[0023] Step S101, determining the start time of each sub-project according to the project contract.
[0024] Step S102, determining the electromechanical equipment required for each sub-project according to the electromechanical equipment catalog in the project contract.
[0025] In an optional embodiment, each sub-project has its own required electromechanical equipment, and there may be overlaps between the electromechanical equipment required by different sub-projects.
[0026] Step S103, determining the arrival time of each electromechanical equipment according to the electromechanical equipment required by each sub-project and the start time of each sub-project.
[0027] In an optional embodiment, the arrival time of the electromechanical equipment should be earlier than the start time of the sub-project that needs to use the electromechanical equipment. If the same electromechanical equipment is needed in multiple sub-projects, the arrival time of the electromechanical equipment should be earlier than the start time of the first sub-project that needs to use the electromechanical equipment.
[0028] Step S104, determining the final signing time of the ordering contract for each electromechanical device according to the arrival time of each electromechanical device. In the embodiment of the present invention, the determined final signing time of the ordering contract refers to the lower limit of the time for signing the ordering contract.
[0029] In an optional embodiment, when purchasing electromechanical equipment, it is necessary to first sign an order contract with the seller, and then after paying the seller, the seller will provide the electromechanical equipment. After the seller provides the electromechanical equipment, it may also be necessary to transport the electromechanical equipment remotely. Therefore, in order to ensure that the electromechanical equipment can be received before the start of work, it is necessary to reasonably determine the final signing time of the order contract for the electromechanical equipment, and reserve time for the seller to prepare and transport the equipment, and time for the user to inspect the equipment.
[0030] In an optional embodiment, the production process of the electromechanical equipment is cyclical, and the production cycles of different electromechanical equipment are different. For example, the production cycle of the electromechanical equipment can be one year, half a year, etc. Under normal circumstances, it is necessary to sign an order contract before the electromechanical equipment manufacturer will arrange the order for the buyer. Therefore, when determining the final signing time of the order contract for each electromechanical equipment, it is also necessary to first determine the production cycle of each electromechanical equipment and the last production time. Combined with the production cycle of each electromechanical equipment, the last production time, and the arrival time, the final signing time of the order contract for each electromechanical equipment is determined to ensure that the electromechanical equipment can be inspected and accepted at the arrival time.
[0031] Step S105, determining the payment time and arrival time of each electromechanical equipment according to the last signing time of the order contract of each electromechanical equipment.
[0032] In an optional embodiment, when purchasing electromechanical equipment, the payment stages include advance payment, balance upon delivery, overdue penalty, etc. Therefore, the payment time for each electromechanical equipment includes the advance payment time, balance upon delivery, overdue penalty payment time, etc. of each electromechanical equipment.
[0033] In an optional embodiment, the prepayment time for each electromechanical equipment can be obtained by adding a preset time to the last signing time of the subscription contract. For example, the prepayment time for each electromechanical equipment can be one month after the last signing time of the subscription contract.
[0034] In an optional embodiment, the time for payment of the balance upon delivery can be determined based on the production cycle of the electromechanical equipment, the last production time, the transportation equipment time, and the acceptance time. The time when the buyer completes the acceptance of the electromechanical equipment can be determined based on the production cycle, the last production time, the transportation equipment time, and the acceptance time. After the acceptance is completed, the payment of the balance upon delivery can be made.
[0035] In an optional embodiment, the overdue penalty payment time includes the overdue penalty payment time for the advance payment and the overdue penalty payment time for the balance of delivery. The overdue penalty payment time for the advance payment can be obtained by adding the preset time to the advance payment time, and the overdue penalty payment time for the balance of delivery can be obtained by adding the preset time to the time for the balance of delivery.
[0036] In an optional embodiment, when the corresponding amount is not received by the time of advance payment, the time of advance payment overdue penalty payment is sent to the target object; when the corresponding amount is not received by the time of delivery balance payment, the time of delivery balance overdue penalty payment is sent to the target object.
[0037] In an optional embodiment, the payment time affects the delivery time of the electromechanical equipment seller, and also indirectly affects the arrival time of the electromechanical equipment, thereby affecting the arrival time of the electromechanical equipment.
[0038] In an optional embodiment, the arrival time refers to the time when the electromechanical equipment is received, and the arrival time refers to the time to ensure that the electromechanical equipment can be used normally, that is, after receiving the electromechanical equipment, the electromechanical equipment needs to be verified. Only if the verification result meets the conditions can it be determined that the electromechanical equipment is in place.
[0039] Execute step S106, if the corresponding payment is not received at the time of payment of the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, an overdue warning is issued.
[0040] In an optional embodiment, an overdue warning may be sent to a relevant person in charge to remind the relevant person in charge to follow up on the status of the electromechanical equipment.
[0041] For example, if the corresponding payment is not received by the time the electromechanical equipment is disbursed, an overdue warning is sent to the financial personnel; if the corresponding arrival notice of the electromechanical equipment is not received by the time the electromechanical equipment arrives, an overdue warning is sent to the purchasing personnel; or, if the corresponding arrival notice of the electromechanical equipment is not received by the time the electromechanical equipment arrives, an overdue warning is sent to the verification personnel.
[0042] The method provided in the embodiment of the present invention determines the time when each electromechanical equipment is in place after obtaining the project contract, based on the start time of each sub-project and the electromechanical equipment required for each sub-project, because the signing time of the ordering contract, the payment time, and the arrival time of the electromechanical equipment will all affect the time when the electromechanical equipment is in place. Therefore, in the embodiment of the present invention, after determining the time when each electromechanical equipment is in place, the signing time of the ordering contract, the payment time, and the arrival time of the electromechanical equipment are determined in sequence. When one of the time nodes is overdue, an overdue warning will be issued, ensuring that the electromechanical equipment can be in place when the project starts. In addition, the method of the present invention is conducive to the speed of procurement and issuance of electromechanical equipment, solves the compatibility problem of reports in the receipt and issuance of electromechanical equipment, and improves the safety and accuracy of equipment procurement.
[0043] In an optional embodiment, the electromechanical equipment management provided by the present invention also includes: establishing a schedule for each electromechanical equipment according to the arrival time of each electromechanical equipment, the final signing time of the order contract, the payment time, and the arrival time, and sending the schedule to the first target object.
[0044] In an optional embodiment, different electromechanical equipment corresponds to different timetables. The timetable of the electromechanical equipment includes the arrival time of the electromechanical equipment, the final signing time of the order contract, the payment time, and the arrival time, so that the first target object can intuitively understand the status of the electromechanical equipment at different time nodes, which is convenient for the first target object to coordinate and dispatch the project as a whole.
[0045] In an optional embodiment, the electromechanical equipment management provided by the present invention further includes: monitoring whether the engineering contract has changed, and if so, repeating the above steps S101 to S106.
[0046] In an optional embodiment, if the corresponding payment is not received at the time of payment for the electromechanical equipment, or the arrival notice of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, or the arrival notice of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, after the overdue warning is issued, it is also necessary to monitor whether the project contract has changed, because if an overdue occurs, the progress of the project may be delayed and the project contract may be modified. Therefore, it is necessary to monitor whether the project contract has changed. If it changes, it is necessary to re-determine one or more of the final signing time of the electromechanical equipment ordering contract, payment time, arrival time, and arrival time.
[0047] In an optional embodiment, the electromechanical equipment management method provided by the embodiment of the present invention further includes:
[0048] Step a1, receiving the document of electromechanical equipment.
[0049] Step a2: determining the electromechanical equipment to be stored that has currently arrived based on the documents, and generating an arrival notice for the electromechanical equipment to be stored.
[0050] In an optional embodiment, the document is a document generated when the electromechanical equipment is transported, and the information of the transported goods can be extracted from the document. Therefore, the type of the electromechanical equipment currently arriving can be determined based on the document.
[0051] Step a3: Determine the verification requirements for the electromechanical equipment to be put into storage according to the project contract.
[0052] In an optional embodiment, the verification requirements for electromechanical equipment include appearance verification requirements, function verification requirements, performance verification requirements, etc.
[0053] Step a4, receiving verification data of the electromechanical equipment to be stored.
[0054] In an optional embodiment, the verification of the electromechanical equipment to be stored can be manual verification or verification through a verification system. After manual verification or system verification, the verification system is input into the device that executes the method provided by the embodiment of the present invention, and this method is used to further determine whether the verification result meets the requirements.
[0055] Step a5: if the verification data meets the verification requirements, a notification of the arrival of the electromechanical equipment to be stored is generated and a notification of the arrival of the electromechanical equipment to be stored is sent to the second target object.
[0056] In an optional embodiment, if the verification data meets the verification requirements, after sending a notification of the arrival of the electromechanical equipment to be stored to the second target object, the electromechanical equipment to be stored will also be arranged to be stored for subsequent use.
[0057] Step a6: If the verification data does not meet the verification requirements, a return notice of the electromechanical equipment to be stored is sent to the third target object.
[0058] Step a7, determine the engineering contract to determine the scheduled inspection time and delivery time of the electromechanical equipment to be stored.
[0059] In an optional embodiment, after the electromechanical equipment is put into storage, it is also necessary to conduct regular inspections to ensure the normal use of the electromechanical equipment. The regular inspection time for different equipment is different, and the time interval between two inspections is also different.
[0060] Step a8, regularly sending a scheduled inspection notice to the fourth target object according to the scheduled inspection time, and receiving a scheduled inspection result notification sheet, wherein the scheduled inspection notice is used to prompt the fourth target object to inspect the electromechanical equipment to be stored according to the scheduled inspection time.
[0061] Step a9, receiving the outbound notification, and sending the outbound document and the scheduled inspection result notification to the fifth target object.
[0062] In an optional embodiment, the delivery document includes the delivery time of the electromechanical equipment.
[0063] In an optional embodiment, when a certain electromechanical equipment is needed in a project, a delivery notification will be sent to the equipment executing the method provided in the embodiment of the present invention, and relevant personnel will take out the electromechanical equipment from the warehouse. At this time, the equipment executing the method provided in the embodiment of the present invention sends an delivery document and a regular inspection result notification to the fifth target object. The regular inspection result notification contains the regular inspection results of the electromechanical equipment during one or more regular inspections after entering the warehouse, and the user can determine the performance of the electromechanical equipment based on the regular inspection result notification.
[0064] In an optional embodiment, the documents for the electromechanical equipment include: a waybill and a packing list.
[0065] Waybill: After the electromechanical equipment has passed the factory acceptance, the manufacturer will sort out the information such as the carrier of the packed equipment, the date of shipment, the number of the transport vehicle, the box number of the equipment, etc. to form a shipping list, referred to as the waybill. Each waybill must be numbered for easy identification. This number is called the waybill number. The waybill number is generally generated by the manufacturer when shipping. One waybill generally corresponds to one or more transport vehicle numbers.
[0066] Packing list: When the equipment on each waybill is shipped, it may be transported by one or more transport vehicles due to physical size or weight. The number of equipment boxes stacked on each transport vehicle may be different, and the corresponding box numbers will also be different. Based on this, the list of boxes transported on each transport vehicle forms a packing list. The packing list is generally numbered by the manufacturer or the carrier (transshipment) unit for easy identification. One packing list corresponds to one or more box numbers.
[0067] Box: During transportation, the equipment will be packed in containers, corrugated boxes, crates, pallets or bare pieces as needed. Each box / pallet may correspond to one or more types of equipment, while bare pieces are generally transported separately for each equipment. Whether it is boxed (pallet packaging is considered a special form of box packaging) or bare pieces, they should be numbered to facilitate differentiation during transportation and arrival. This number is uniformly called the box number. The box number is generally compiled by the manufacturer.
[0068] Equipment: According to the design documents of the design institute, the manufacturer inspects and delivers the parts / components with relatively independent functions in the generator, turbine, and public equipment. Such parts / components are generally called equipment. Each equipment needs to be independently coded for easy identification. The engineering management system generally forms the equipment code by connecting the contract code, procurement item, and procurement item of the procurement contract with a short dash.
[0069] In this embodiment, a mechanical and electrical equipment management device is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and the descriptions that have been made will not be repeated. As used below, the term "module" can implement a combination of software and / or hardware of a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0070] This embodiment provides a mechanical and electrical equipment management device, such as Figure 2 As shown, including:
[0071] The sub-project start time determination module 201 is used to determine the start time of each sub-project according to the project contract.
[0072] The electromechanical equipment demand analysis module 202 is used to determine the electromechanical equipment required for each sub-project according to the electromechanical equipment catalog in the project contract.
[0073] The arrival time determination module 203 is used to determine the arrival time of each electromechanical equipment according to the electromechanical equipment required by each sub-project and the start time of each sub-project.
[0074] The signing time determination module 204 is used to determine the final signing time of the ordering contract of each electromechanical device according to the arrival time of each electromechanical device.
[0075] The order process determination module 205 is used to determine the payment time and arrival time of each electromechanical equipment according to the last signing time of the order contract of each electromechanical equipment;
[0076] Warning module 206 is used to issue an overdue warning if the corresponding payment is not received at the time of payment for the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment.
[0077] The further functional description of each of the above modules is the same as that of the above corresponding embodiments and will not be repeated here.
[0078] The electromechanical equipment management device in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC (Application Specific Integrated Circuit) circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.
[0079] The embodiment of the present invention also provides a computer device having the above Figure 2 The electromechanical equipment management device shown.
[0080] See also Figure 3 , Figure 3 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 3 As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 3 A processor 10 is taken as an example.
[0081] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.
[0082] The memory 20 stores instructions executable by at least one processor 10, so that at least one processor 10 executes the method shown in the above embodiment.
[0083] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0084] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.
[0085] The computer device also includes an input device 30 and an output device 40. The processor 10, the memory 20, the input device 30 and the output device 40 may be connected via a bus or other means. Figure 3 The example of connecting through bus is taken in the following.
[0086] The input device 30 can receive input digital or character information, and generate key signal input related to the user settings and function control of the computer device, such as a touch screen, a keypad, a mouse, a track pad, a touch pad, an indicator bar, one or more mouse buttons, a trackball, a joystick, etc. The output device 40 may include a display device, an auxiliary lighting device (e.g., an LED) and a tactile feedback device (e.g., a vibration motor), etc. The above-mentioned display device includes but is not limited to a liquid crystal display, a light emitting diode, a display and a plasma display. In some optional embodiments, the display device can be a touch screen.
[0087] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.
[0088] A part of the present invention may be applied as a computer program product, such as a computer program instruction, which, when executed by a computer, can call or provide the method and / or technical solution according to the present invention through the operation of the computer. Those skilled in the art should understand that the existence of the computer program instruction in a computer-readable medium includes, but is not limited to, a source file, an executable file, an installation package file, etc., and accordingly, the way in which the computer program instruction is executed by the computer includes, but is not limited to: the computer directly executes the instruction, or the computer compiles the instruction and then executes the corresponding compiled program, or the computer reads and executes the instruction, or the computer reads and installs the instruction and then executes the corresponding installed program. Here, the computer-readable medium may be any available computer-readable storage medium or communication medium accessible to the computer.
[0089] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A method for managing electromechanical equipment, characterized in that: The method comprises: Determine the start time of each sub-project according to the project contract; Determine the electromechanical equipment required for each sub-project based on the electromechanical equipment catalog in the project contract; Determine the time for each electromechanical equipment to be in place based on the electromechanical equipment required for each sub-project and the start time of each sub-project; Determine the final signing time of the ordering contract for each electromechanical equipment based on the arrival time of each electromechanical equipment; Determine the payment time and arrival time of each electromechanical equipment according to the final signing time of the ordering contract of each electromechanical equipment; If the corresponding payment is not received by the time the electromechanical equipment is disbursed, or the corresponding arrival notice of the electromechanical equipment is not received by the time the electromechanical equipment arrives, or the corresponding arrival notice of the electromechanical equipment is not received by the time the electromechanical equipment arrives, an overdue warning will be issued.
2. The method according to claim 1, characterized in that Also includes: According to the arrival time of each electromechanical equipment, the final signing time of the ordering contract, the payment time, and the arrival time, a schedule for each electromechanical equipment is established, and the schedule is sent to the first target object.
3. The method according to claim 1, characterized in that Also includes: Monitor whether the project contract has changed. If so, return to the step of determining the start order of each sub-project according to the project contract.
4. The method according to claim 1, characterized in that: Also includes: Documents for receiving electromechanical equipment; Determine the electromechanical equipment to be stored that has arrived according to the document, and generate an arrival notice for the electromechanical equipment to be stored; Determine the verification requirements for the electromechanical equipment to be put into storage according to the engineering contract; Receiving verification data of the electromechanical equipment to be stored; If the verification data meets the verification requirements, a notification of the arrival of the electromechanical equipment to be stored is generated.
5. The method according to claim 4, characterized in that Also includes: If the verification data meets the verification requirements, sending a notification of the arrival of the electromechanical equipment to be stored to the second target object; If the verification data does not meet the verification requirements, a return notice of the electromechanical equipment to be stored is sent to the third target object.
6. The method according to claim 4, characterized in that Also includes: Determine the scheduled inspection time and the delivery time of the electromechanical equipment to be stored in the project contract; Regularly sending a scheduled inspection notice to the fourth target object according to the scheduled inspection time, and receiving a scheduled inspection result notification sheet, wherein the scheduled inspection notice is used to prompt the fourth target object to inspect the electromechanical equipment to be stored according to the scheduled inspection time; Receive the outbound notification and send the outbound document and the inspection result notification to the fifth target object.
7. A mechanical and electrical equipment management device, characterized in that: The device comprises: The sub-project start time determination module is used to determine the start time of each sub-project according to the project contract; The electromechanical equipment demand analysis module is used to determine the electromechanical equipment required for each sub-project based on the electromechanical equipment catalog in the project contract; The arrival time determination module is used to determine the arrival time of each electromechanical equipment according to the electromechanical equipment required by each sub-project and the start time of each sub-project; The signing time determination module is used to determine the final signing time of the ordering contract of each electromechanical equipment according to the arrival time of each electromechanical equipment; The ordering process determination module is used to determine the payment time and arrival time of each electromechanical equipment according to the last signing time of the ordering contract of each electromechanical equipment; The warning module is used to issue an overdue warning if the corresponding payment is not received at the time of payment of the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment, or the arrival notification of the corresponding electromechanical equipment is not received at the time of arrival of the electromechanical equipment.
8. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the electromechanical equipment management method according to any one of claims 1 to 6 by executing the computer instructions.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the electromechanical equipment management method according to any one of claims 1 to 6.
10. A computer program product, characterized in that The method comprises computer instructions, wherein the computer instructions are used to cause a computer to execute the electromechanical equipment management method according to any one of claims 1 to 6.
Citation Information
Patent Citations
Equipment management method and application thereof
CN114240176A
Contract buying management control system and method
CN1567314A
System and method for controlling purchase
TW200428252A
Purchase management system and method
US20040254854A1
Device management apparatus, device management system, and computer program product
US20130185461A1