MDEL1000 rubber-tyred transporter and manufacturing method
Through the double-layer structure design and systematic assembly and welding process, the technical challenges of traditional beam lifters in camber, interchangeability and welding deformation are solved, the manufacturing efficiency and quality of the MDEL1000 tire-type transporter are improved, and high interchangeability is achieved properties and porosity, saving materials and costs.
Patent Information
- Application Number
- CN202410977116.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-22
AI Technical Summary
During the manufacturing and installation process, traditional beam lifting machines face difficulties in accurately realizing the camber value of the main beam, controlling segment interchangeability and 100% through hole rate, as well as welding deformation.
It adopts a double-layer structure design and welds the cover plate and the pasting plate, and the web and the pasting plate into components. The CNC machining center equipment performs drilling and assembly into a three-shaped beam structure. The inner and outer sides are welded and corrected, and the theodolite is used to detect and Bolt tightening ensures the accuracy and stability of the main beam segments.
It effectively solves the problems of camber control, welding deformation and structural fit, improves manufacturing efficiency and quality reliability, optimizes the connection plate processing process, shortens the production cycle, and saves materials and costs.
Smart Images

Figure CN118809093A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mechanical manufacturing, and specifically relates to an MDEL1000 tire transporter and a manufacturing method thereof. Background Art
[0002] With the continuous development of modern engineering construction, the demand for the manufacture and installation of large structural parts is increasing. Especially in the field of bridge construction, heavy-duty handling equipment such as beam lifting machines and tire-type handling machines have become indispensable and important tools. Beam lifting machines and handling machines not only need to have sufficient load-bearing capacity, but also need to meet strict size, camber and welding quality requirements to ensure the safety and reliability of the structure.
[0003] Traditional beam lifting machines, such as the 550-ton beam lifting machine of China Railway, adopt a single-layer structure with an overall size of 46.19mx 6.15mx 3.7m, the heaviest section is 21.56 tons, and each section contains 366 holes. Its web and cover structure are part-level, with a 60mm camber, and there is no special requirement for the middle part of the web of the main beam. Although this structural form meets certain usage requirements, there are certain technical challenges in the manufacturing and installation process.
[0004] In contrast, the MDEL1000 tire-type transporter adopts a double-layer structure with an overall size of 43.28mx 6.8m x4.09m. The heaviest segment is 39.46 tons, and each segment has 1,080 holes. Its web and cover structure is component-level, with a camber of 80mm, and the connecting plates in the middle of the web of the main beam need to fit tightly, with a fit requirement of 0mm to 1mm. These characteristics put forward higher requirements on the manufacturing process, including how to ensure the overall camber value, interchangeability and 100% through-hole rate of the main beam, and how to control welding deformation, which are the key points of technical research. Summary of the invention
[0005] 1. Technical issues to be resolved
[0006] The present invention mainly aims at the above problems and proposes an MDEL1000 tire transporter and a manufacturing method, the purpose of which is to solve how to ensure the accurate realization of each camber value of the main beam, the interchangeability of the main beam segments and 100% through-hole rate, and control the welding deformation of the main beam during the production process.
[0007] (II) Technical solution
[0008] To achieve the above object, the first aspect of the present invention provides a method for manufacturing an MDEL1000 tire transporter, comprising the following steps:
[0009] The cover plate and the pasting plate are welded together to form a first component, and the web plate and the pasting plate are welded together to form a second component, and then holes are drilled using a CNC machining center device to divide the first component into an upper first component and a lower first component, and the second component into an upper second component and a lower second component;
[0010] The entire main beam is given a shrinkage camber margin and a lower main beam consisting of a lower tooling frame and a lower partition kit is manufactured. After the lower main beam is completed, the lower first component and the lower second component are respectively fitted to the camber surface of the frame of the lower main beam to assemble into a three-beam structure, wherein the lower first component serves as the bottom surface of the three-beam structure and the lower second component serves as the side surface of the three-beam;
[0011] After the three-type beam is formed, the connecting plate is fitted with the camber of the lower second component of the three-type beam structure, and the main beam upper partition kit, the upper tooling frame, the upper second component and the longitudinal reinforcement are assembled with the connecting plate. After the assembly is completed, the camber of the upper first component is fitted with the upper second component and positioned to obtain an unwelded main beam segment composed of an upper main beam segment and a lower main beam segment;
[0012] After the main beam segments are assembled, the internal welding of the upper main beam segments and the lower main beam segments is completed respectively, and the upper main beam segments are moved from the upper end of the lower main beam segments to the lower position, and the outer side welding of the upper main beam segments and the lower main beam segments is performed respectively. After the welding is qualified, the upper main beam segments and the lower main beam segments are corrected;
[0013] Use the theodolite to check the arch of the lower main beam segment. After the arch is qualified, the upper main beam segment is hoisted on the upper end of the lower main beam stage, and the upper main beam segment connection plate is connected to the lower main beam segment with bolts;
[0014] After the main beam segment is assembled as a whole, multiple main beam segments are manufactured, and the multiple main beam segments are fixed to the corresponding webs and cover plates by welding using web connecting plates and cover connecting plates, and corresponding holes are drilled.
[0015] Furthermore, the web blanking process also includes placing a process camber shrinkage allowance and groove processing.
[0016] Furthermore, the manufacturing process of the connecting plate also includes cutting, spot welding, overall processing and assembly to form a frame.
[0017] Furthermore, before drilling with a CNC machining center, the method also includes calibrating the welded first component and the second component.
[0018] Furthermore, the calibration method includes calibrating the first component and the second component by combining fire attack and cold calibration.
[0019] Furthermore, a 20mm shrinkage camber margin is provided for the entire main beam, and a lower main beam is manufactured which is composed of a lower tooling frame and a lower partition kit.
[0020] Furthermore, a plurality of main beam segments are fixed by welding with corresponding webs and cover plates using web connecting plates and cover connecting plates, and corresponding holes are drilled, wherein a magnetic drill and a radial drill are used to align the webs and cover plates and perform corresponding drilling.
[0021] To achieve the above-mentioned object, the second aspect of the present invention provides an MDEL1000 tire transporter manufactured by the above-mentioned manufacturing method.
[0022] (III) Beneficial effects
[0023] Compared with the prior art, the MDEL1000 tire-type transporter and manufacturing method provided by the present invention are intended to solve the technical challenges faced by traditional beam lifting machines during the manufacturing and installation process. By adopting a double-layer structural design, accurately controlling the camber, and achieving high interchangeability and through-hole rate, the present invention proposes a systematic assembly and welding process, including welding the cover plate and the pasting plate, the web plate and the pasting plate into components, and then performing CNC drilling processing; then assembling the lower and upper main beam segments in a predetermined order, and performing internal and external welding and correction, and finally ensuring the overall accuracy and stability of the main beam segment through the steps of theodolite detection and bolt tightening. This method effectively solves key problems such as camber control, welding deformation, and structural fit, and improves manufacturing efficiency and quality reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a schematic structural diagram of an MDEL1000 tire transporter disclosed in this application.
[0025] Figure 2 This is a structural schematic diagram of a main beam segment disclosed in this application.
[0026] Figure 3 This is a schematic diagram of the structure of a connecting plate disclosed in this application.
[0027] Figure 4 This is a schematic structural diagram of a first component disclosed in this application.
[0028] Figure 5 This is a schematic structural diagram of a second component disclosed in this application.
[0029] Figure 6 This is a schematic diagram of the structure of a lower main beam disclosed in this application.
[0030] Figure 7 This is a schematic diagram of a structure in which a connecting plate is arranged on a lower main beam disclosed in the present application.
[0031] Figure 8 This is a schematic structural diagram of a main beam segment disclosed in the present application before assembly.
[0032] The reference numerals shown in the figure are: 1. cover plate; 2. pasting plate; 3. web plate; 4. first component; 5. second component; 6. lower tooling frame; 7. lower partition kit; 8. lower main beam; 9. connecting plate; 10. main beam segment; 11. upper main beam segment; 12. lower main beam segment; 13. web plate connecting plate; 14. cover plate connecting plate. DETAILED DESCRIPTION
[0033] The present invention will be described in detail below in conjunction with the accompanying drawings, and the technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0035] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0036] See also Figure 1 As shown, the first aspect of the present invention provides a method for manufacturing an MDEL1000 tire transporter, and the specific steps are as follows:
[0037] First, the cover plate 1 and the plate 2 are welded together to form a first component 4 (see Figure 4 ), and at the same time, the web 3 and the plate 2 are welded together to form a second component 5 (see Figure 5 ). Subsequently, a CNC machining center device is used to perform a drilling operation, and then the first component 4 and the second component 5 are respectively divided into an upper layer and a lower layer, namely, an upper layer first component and a lower layer first component, and an upper layer second component and a lower layer second component.
[0038] Next, in order to ensure the accurate camber of the main beam, the preset camber adjustment is performed on the entire main beam, and an integral lower main beam 8 consisting of a lower tooling frame 6 and a lower partition kit 7 is manufactured. After the lower main beam 8 is completed, the lower first component and the lower second component are closely fitted to the camber surface of the frame of the lower main beam 8 to assemble into a three-beam structure, in which the lower first component is used as the bottom surface and the lower second component is used as the side surface (see Figure 6 ).
[0039] Then, after the three-beam structure is formed, the connecting plate 9 is attached to the lower second component (see Figure 3 and Figure 7 ), and then assemble the upper partition kit, the upper tooling tire frame, the upper second component and the longitudinal reinforcement with the connecting plate 9 (see Figure 8 ). After the assembly is completed, the upper first component and the upper second component are fitted and positioned according to a predetermined camber, thereby obtaining a complete unwelded main beam segment.
[0040] After the main beam segments are assembled, the internal welding of the upper main beam segment 11 and the lower main beam segment 12 is performed respectively. After the internal welding is completed, the upper main beam segment 11 is moved to a lower position, and then the outer sides of the upper main beam segment 11 and the lower main beam segment 12 are welded respectively. After the welding is completed and inspected to be qualified, the upper main beam segment 11 and the lower main beam segment 12 are corrected.
[0041] Use the theodolite to detect the camber of the lower main beam segment 12. After confirming that it is qualified, hoist the upper main beam segment 11 onto the lower main beam segment 12, and firmly connect the connecting plates of the upper and lower main beam segments by bolting (see Figure 2 ).
[0042] Finally, the plurality of main beam segments 10 are assembled as a whole, the webs and cover plates of each segment are welded and fixed using the web connecting plates 13 and the cover connecting plates 14, and the corresponding drilling operations are performed to finally form a complete main beam structure (see FIG. Figure 1 ).
[0043] Through this systematic manufacturing method, the present invention not only effectively solves technical problems such as controlling camber, welding deformation and structural fit, but also greatly improves manufacturing efficiency and reliability of product quality.
[0044] The web cutting process also includes reserving process camber shrinkage allowance and performing groove processing to ensure the accuracy and welding quality of the final structure.
[0045] In addition, the manufacturing process of the connecting plate 9 is also very critical, including the steps of material cutting, spot welding fixation, overall processing and assembly into a frame to ensure the stability and reliability of the connecting parts.
[0046] Before drilling with the CNC machining center, the welded first component 4 and the second component 5 need to be corrected. The correction method uses a combination of fire attack and cold correction to ensure that the flatness and fit of the components meet the requirements.
[0047] In order to control the arch of the main beam, a 20mm shrinkage arch margin is reserved for the entire main beam, and an integrated lower main beam structure consisting of a lower tooling frame 6 and a lower partition kit 7 is made to ensure dimensional accuracy during the manufacturing process.
[0048] Finally, the plurality of main beam segments 10 are welded and fixed through the web connecting plates 13 and the cover connecting plates 14, and the corresponding drilling operation is performed. In this process, the web and the cover are aligned using equipment such as a magnetic drill and a radial drill to ensure the accuracy and consistency of the drilling positions.
[0049] Through the process research project of MDEL1000 tire transporter, remarkable results and economic benefits have been achieved. In terms of economic benefits, the optimization of the connection plate machining process shortened the production cycle by 15 days, saved 627 kg of materials, and avoided the use of 10 tons of drilling mold materials, saving 75,000 yuan in drilling mold production costs. In addition, the main beam crane cost also saved 70,000 yuan. In terms of benefits, through this manufacturing process research, it provides a reference basis for the company to undertake similar projects, and explores the production experience such as the shrinkage margin parameters and assembly welding sequence of large closed box structures, laying the foundation for the subsequent preparation of processes. The successful promotion of the project not only improves production efficiency, but also reserves a complete and effective set of technical documents for similar products in the future, and lays a solid foundation for extensive cooperation. Finally, the successful completion of this process research further solidified the process at the summary meeting, providing a valuable reference for the process preparation of subsequent products.
[0050] Therefore, no matter from which point of view, the embodiments should be regarded as illustrative and non-restrictive, and the scope of the present application is limited by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present application. Any figure mark in the claims should not be regarded as limiting the claims involved. In addition, it is obvious that the word "comprising" does not exclude other units or steps, and the singular does not exclude the plural. Multiple units or devices stated in the device claim can also be implemented by the same unit or device through software or hardware. The words first, second, etc. are used to indicate names, and do not indicate any particular order.
[0051] The above embodiments are only used to illustrate the technical solution of the present application and are not intended to limit it. Although the present application has been described in detail with reference to the preferred embodiments, a person skilled in the art should understand that the technical solution of the present application may be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present application.
Claims
1. A method for manufacturing a MDEL1000 tire transporter, characterized in that: The steps include: The cover plate and the pasting plate are welded together to form a first component, and the web plate and the pasting plate are welded together to form a second component, and then holes are drilled using a CNC machining center device to divide the first component into an upper first component and a lower first component, and the second component into an upper second component and a lower second component; The entire main beam is given a shrinkage camber margin and a lower main beam consisting of a lower tooling frame and a lower partition kit is manufactured. After the lower main beam is completed, the lower first component and the lower second component are respectively fitted to the camber surface of the frame of the lower main beam to assemble into a three-beam structure, wherein the lower first component serves as the bottom surface of the three-beam structure and the lower second component serves as the side surface of the three-beam; After the three-type beam is formed, the connecting plate is fitted with the camber of the lower second component of the three-type beam structure, and the main beam upper partition kit, the upper tooling frame, the upper second component and the longitudinal reinforcement are assembled with the connecting plate. After the assembly is completed, the camber of the upper first component is fitted with the upper second component and positioned to obtain an unwelded main beam segment composed of an upper main beam segment and a lower main beam segment; After the main beam segments are assembled, the internal welding of the upper main beam segments and the lower main beam segments is completed respectively, and the upper main beam segments are moved from the upper end of the lower main beam segments to the lower position, and the outer side welding of the upper main beam segments and the lower main beam segments is performed respectively. After the welding is qualified, the upper main beam segments and the lower main beam segments are corrected; Use the theodolite to check the arch of the lower main beam segment. After the arch is qualified, the upper main beam segment is hoisted on the upper end of the lower main beam stage, and the upper main beam segment connection plate is connected to the lower main beam segment with bolts; After the main beam segment is assembled as a whole, multiple main beam segments are manufactured, and the multiple main beam segments are fixed to the corresponding webs and cover plates by welding using web connecting plates and cover connecting plates, and corresponding holes are drilled.
2. The method for manufacturing a MDEL1000 tire transporter according to claim 1, characterized in that: The web cutting process also includes the processing of the shrinkage allowance of the camber and the groove.
3. The method for manufacturing a MDEL1000 tire transporter according to claim 1, characterized in that: The manufacturing process of the connecting plate also includes cutting, spot welding, overall processing and assembly to form a frame.
4. The method for manufacturing the MDEL1000 tire transporter according to claim 1, characterized in that: Before drilling with a CNC machining center device, the method also includes calibrating the welded first component and the second component.
5. The method for manufacturing the MDEL1000 tire transporter according to claim 4, characterized in that: The calibration method includes calibrating the first component and the second component by combining fire attack and cold calibration.
6. The method for manufacturing the MDEL1000 tire transporter according to claim 1, characterized in that: A 20mm shrinkage camber allowance is given to the entire main beam, and a lower main beam consisting of a lower tooling frame and a lower partition kit is made.
7. The method for manufacturing the MDEL1000 tire transporter according to claim 1, characterized in that: Multiple main beam segments are fixed with web connecting plates and cover connecting plates by electric welding to corresponding webs and cover plates, and corresponding holes are drilled, wherein magnetic drills and radial drills are used to align the webs and cover plates and perform corresponding drilling.
8. A MDEL1000 tire transporter, characterized in that: Made by the manufacturing method described in any one of claims 1 to 7.
Citation Information
Patent Citations
Method for manufacturing and controlling camber of crane main girder
CN104607815A
Lifting device
CN109956394A
Tire type transporter and folding method thereof
CN114940442A
Bridge structure
KR1020090068525A
Jig for crane girder and girder manufacture
KR1020160036990A