Electric power engineering cost project cost analysis system and method

Through the cost analysis system of power engineering cost project, the problems of lack of pricing basis and inconsistent cost calculation in the cost management of marketing projects in Tibet companies were solved, and the reasonable control and management transparency of project cost expenditures were achieved, and the level of cost management and economic benefits were improved.

CN118886607APending Publication Date: 2024-11-01STATE GRID TIBET ELECTRIC POWER CO LTD ECONOMIC & TECH RES INST
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411010760.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

In the cost management of marketing projects of Tibet, there are problems such as lack of pricing basis, inconsistent cost calculation, excessive coarse cost particle size, indetailed cost details, and insufficient understanding of the correlation between fixed quotas at the grassroots level, resulting in difficulty in controlling project investment.

Method used

A cost analysis system for power engineering cost projects was designed, including data acquisition and management, cost structure classification and analysis, budget preparation and control, risk management, real-time monitoring and reporting, decision support and optimization, standardization and training, through real-time data acquisition and analyze, identify risk factors, generate visual charts, provide decision support tools to ensure standardization and transparency in project expense management.

Benefits of technology

It effectively solved the problems of unreasonable project expenses and inconsistent management, improved the level of cost management, ensured scientific and reasonable control of marketing project costs, and improved the economic benefits of power engineering projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886607A_ABST
    Figure CN118886607A_ABST
Patent Text Reader

Abstract

The invention provides an electric power engineering cost project cost analysis system and method, and relates to the field of electric power engineering cost. The method comprises the steps of data acquisition and management, cost structure classification and analysis, budgeting and control, risk management, real-time monitoring and reporting, decision support and optimization, standardization and training. By solving the problems of unreasonable cost composition, non-uniform compilation depth and non-standard cost expenditure of project declaration caused by lack of marketing project standards and bases, the cost expenditure of the project is effectively controlled, and a scientific and reasonable cost management mode is formulated, so that the cost of the marketing project is ensured to be controlled; the electric power engineering cost information transparency is enhanced, the cost management level is improved, the healthy development of the electric power industry is promoted, project construction needs to be strictly audited and controlled, and the cost control of the marketing project has important significance for improving the economic benefit of the project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power engineering cost, and in particular to a system and method for analyzing the cost of electric power engineering cost items. Background Art

[0002] In recent years, with the deepening of the reform of transmission and distribution prices and the power system, State Grid Corporation of China has issued a new version of the "State Grid Corporation Marketing Project Management Measures" (State Grid Enterprise Management

[2023] No. 254), requiring: "Make full use of digital means to standardize project processes, control project investments, ensure project implementation, and improve project benefits." And the "Marketing Reserve Project Cost Control Reference Standard" document, which puts forward higher requirements for the precise control of costs throughout the marketing project process.

[0003] At present, there are some difficulties in the cost management of marketing projects in Tibet Company. First, some pricing bases are missing, there is a lack of marketing project quotas applicable to plateau areas, and the fee calculation standards are not unified; second, the cost granularity is too coarse, the cost details are not listed as required, and there are missing items; third, the grassroots lack understanding of the relationship between work items and quotas, and the quota is not accurate. It is also necessary to improve the technical and economic standardization management system of marketing projects to accurately control the cost of marketing projects. Summary of the invention

[0004] 1. Technical issues to be resolved

[0005] In view of the deficiencies in the prior art, the present invention provides a system and method for analyzing the cost of electric power engineering projects, which solves the problems of lack of current pricing basis and difficulty in controlling project investment.

[0006] (II) Technical solution

[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: a system and method for analyzing the cost of power engineering projects, including data collection and management, cost structure classification and analysis, budget preparation and control, risk management, real-time monitoring and reporting, decision support and optimization, standardization and training; the data collection and management is to collect and manage various data of power engineering projects in real time or regularly; the cost structure classification and analysis is to organize and analyze the costs of power engineering projects according to different classification standards; the budget preparation and control is to establish a budget module in the system to prepare and manage the budget of power engineering projects; the risk management is to identify risk factors that may affect the cost in power engineering projects by integrating risk management modules; the real-time monitoring and reporting is to provide real-time monitoring of the cost of power engineering projects and generate various reports and visual charts; the decision support and optimization is to provide decision support tools through the system, through data analysis and simulation optimization, to help the project team formulate more effective cost control and resource allocation strategies; the standardization and training is to formulate standardized operating procedures and specifications.

[0008] Preferably, the various data include data on construction progress, human resource input, material usage, and equipment operation status, which are acquired through on-site records, sensor data, or manual input, and stored in a database for management, real-time monitoring of the power engineering cost database and timely feedback to the project team and management.

[0009] Preferably, the classification standards are engineering stage, cost type and resource, and the classification is analyzed; the engineering stage is divided into design stage, procurement stage and construction stage; the cost type is divided into direct cost and indirect cost; the resources are divided into manpower, materials and equipment.

[0010] Preferably, the budget module will formulate a budget based on historical data, industry standards and actual conditions, and monitor budget execution through real-time data updates and cost control functions.

[0011] Preferably, the risk factors are evaluated through quantitative and qualitative analysis to assess the likelihood and impact of risks including market fluctuations, supply chain issues, and technological change risks, and to develop response strategies to reduce the potential impact of risks on costs.

[0012] Preferably, the generation of the visual chart is to facilitate the management and project team to understand the economic status and cost trend of the project at any time, and the report is in terms of budget execution, cost deviation analysis, and resource utilization.

[0013] Preferably, the decision support tool combines artificial intelligence and professional knowledge by setting up an intelligent system and an expert system, and provides decision suggestions by simulating the expert decision-making process to determine the best supplier selection or technical solution.

[0014] Preferably, the standardization and training is to provide the project team with training and technical support for the use of the system, ensuring that the system can be effectively applied to the actual management of power engineering projects.

[0015] Preferably, the analysis method comprises the following steps:

[0016] Step 1: Obtain various data including construction progress, human resource input, material usage, and equipment operation status through on-site records, sensor data, or manual input, and store them in the database for management. Monitor the power engineering cost database in real time and provide timely feedback to the project team and management.

[0017] Step 2: Analyze the data stored in the database. Through the established budget module, formulate the budget according to historical data, industry standards and actual conditions, and monitor the budget execution through real-time data update and cost control functions.

[0018] Step 3: Then, by integrating the risk management module, identify the risk factors that may affect the cost in the power engineering project and formulate response strategies to reduce the potential impact of risks on costs.

[0019] Step 4: Real-time monitoring and reporting is then provided by providing real-time monitoring of the cost situation of the power engineering project, and generating various reports and visual charts to facilitate management and project teams to understand the economic status and cost trends of the project at any time.

[0020] Step 5: Then, through the decision support tools provided by the system, decision suggestions are provided by simulating the expert decision-making process to determine the best supplier selection or technical solution.

[0021] Step 6: Standardization and training Provide project teams with training and technical support on the use of the system to ensure that the system can be effectively applied in the actual management of power engineering projects.

[0022] Working principle: Through data collection and management, various data of power engineering projects are collected in real time or regularly and managed, and then the cost structure is classified and analyzed to organize and analyze the costs of power engineering projects according to different classification standards. Then, budget preparation and control are carried out to establish a budget module in the system, and budget preparation and management of power engineering projects are carried out. The next step is risk management, which is to identify risk factors that may affect costs in power engineering projects through integrated risk management modules. At the same time, real-time monitoring and reporting are carried out by providing real-time monitoring of the cost situation of power engineering projects, and generating various reports and visual charts. Decision support and optimization are then carried out through the system to provide decision support tools, through data analysis and simulation optimization, to help project teams formulate more effective cost control and resource allocation strategies, and finally standardization and training operations are carried out, which is to formulate standardized operating procedures and specifications.

[0023] (III) Beneficial effects

[0024] The present invention provides a system and method for analyzing the cost of electric power engineering projects. It has the following beneficial effects:

[0025] 1. It solved the problems of unreasonable cost structure, inconsistent preparation depth and irregular cost expenditure in project applications caused by the lack of marketing project standards and basis, and effectively controlled the cost expenditure of the project.

[0026] 2. A scientific and reasonable cost management method has been formulated to ensure that the cost of marketing projects is controlled, strengthen the transparency of power project cost information, improve the level of cost management, and promote the healthy development of the power industry. Project construction needs to undergo strict review and control. Cost control of marketing projects is of great significance to improving the economic benefits of projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 The present invention provides an overall flow chart of a system and method for analyzing the cost of electric power engineering projects. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] like Figure 1As shown, an embodiment of the present invention provides a system and method for analyzing the cost of power engineering projects, including data collection and management, cost structure classification and analysis, budget preparation and control, risk management, real-time monitoring and reporting, decision support and optimization, standardization and training; data collection and management is to collect and manage various data of power engineering projects in real time or regularly; cost structure classification and analysis is to organize and analyze the costs of power engineering projects according to different classification standards; budget preparation and control is to establish a budget module in the system to prepare and manage the budget of power engineering projects; risk management is to identify risk factors that may affect costs in power engineering projects by integrating risk management modules; real-time monitoring and reporting is to provide real-time monitoring of the cost of power engineering projects and generate various reports and visual charts; decision support and optimization is to provide decision support tools through the system, through data analysis and simulation optimization, to help project teams formulate more effective cost control and resource allocation strategies; standardization and training is to formulate standardized operating procedures and specifications.

[0030] Various data including construction progress, human resource input, material usage, and equipment operation status are obtained through on-site records, sensor data, or manual input, and stored in the database for management. The power engineering cost database is monitored in real time and feedback is provided to the project team and management in a timely manner.

[0031] The classification standards are by project stage, by cost type and by resource, and they are analyzed; by project stage, it is divided into design stage, procurement stage and construction stage; by cost type, it is divided into direct cost and indirect cost; by resources, it is divided into manpower, materials and equipment.

[0032] The budget module formulates budgets based on historical data, industry standards and actual conditions, and monitors budget execution through real-time data updates and cost control functions.

[0033] Risk factors are assessed through quantitative and qualitative analysis to assess the possibility and impact of risks including market fluctuations, supply chain issues, and technological changes, and to develop response strategies to reduce the potential impact of risks on costs.

[0034] The purpose of generating visual charts is to help management and project teams understand the economic status and cost trends of the project at any time. The reports include budget execution, cost deviation analysis, and resource utilization.

[0035] Decision support tools combine artificial intelligence and expertise by setting up intelligent systems and expert systems, providing decision recommendations by simulating the expert decision-making process to determine the best supplier selection or technical solution.

[0036] Standardization and training provide project teams with training and technical support on the use of the system to ensure that the system can be effectively applied in the actual management of power engineering projects.

[0037] The analysis method comprises the following steps:

[0038] Step 1: Obtain various data including construction progress, human resource input, material usage, and equipment operation status through on-site records, sensor data, or manual input, and store them in the database for management. Monitor the power engineering cost database in real time and provide timely feedback to the project team and management.

[0039] Step 2: Analyze the data stored in the database. Through the established budget module, formulate the budget according to historical data, industry standards and actual conditions, and monitor the budget execution through real-time data update and cost control functions.

[0040] Step 3: Then, by integrating the risk management module, identify the risk factors that may affect the cost in the power engineering project and formulate response strategies to reduce the potential impact of risks on costs.

[0041] Step 4: Real-time monitoring and reporting is then provided by providing real-time monitoring of the cost situation of the power engineering project, and generating various reports and visual charts to facilitate management and project teams to understand the economic status and cost trends of the project at any time.

[0042] Step 5: Then, through the decision support tools provided by the system, decision suggestions are provided by simulating the expert decision-making process to determine the best supplier selection or technical solution.

[0043] Step 6: Standardization and training Provide project teams with training and technical support on the use of the system to ensure that the system can be effectively applied in the actual management of power engineering projects.

[0044] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A power engineering cost analysis system, characterized by: It includes data collection and management, cost structure classification and analysis, budget preparation and control, risk management, real-time monitoring and reporting, decision support and optimization, standardization and training; the data collection and management is to collect and manage various data of power engineering projects in real time or regularly; the cost structure classification and analysis is to organize and analyze the costs of power engineering projects according to different classification standards; the budget preparation and control is to set up a budget module in the system to prepare and manage the budget of power engineering projects; the risk management is to identify risk factors that may affect the cost in power engineering projects through the integration of risk management modules; the real-time monitoring and reporting is to provide real-time monitoring of the cost situation of power engineering projects and generate various reports and visual charts; the decision support and optimization is to provide decision support tools through the system, through data analysis and simulation optimization, to help project teams formulate more effective cost control and resource allocation strategies; the standardization and training is to formulate standardized operating procedures and specifications.

2. The power engineering cost analysis system according to claim 1, characterized in that: The data include construction progress, human resource input, material usage, and equipment operation status. They are obtained through on-site records, sensor data, or manual input, and stored in a database for management. The power engineering cost database is monitored in real time and feedback is provided to the project team and management in a timely manner.

3. The power engineering cost analysis system according to claim 1, characterized in that: The classification standards are based on project stage, cost type and resources, and are analyzed; the project stage is divided into design stage, procurement stage and construction stage; the cost type is divided into direct cost and indirect cost; the resources are divided into manpower, materials and equipment.

4. The power engineering cost analysis system according to claim 1, characterized in that: The budget module formulates budgets based on historical data, industry standards and actual conditions, and monitors budget execution through real-time data updates and cost control functions.

5. The power engineering cost analysis system according to claim 1, characterized in that: The risk factors are assessed through quantitative and qualitative analysis to assess the possibility and impact of market fluctuations, supply chain issues, and technological change risks, and to formulate response strategies to reduce the potential impact of risks on costs.

6. The power engineering cost analysis system according to claim 1, characterized in that: The purpose of generating the visual chart is to facilitate the management and project team to understand the economic status and cost trends of the project at any time. The report is about budget execution, cost deviation analysis, and resource utilization.

7. The power engineering cost analysis system according to claim 1, characterized in that: The decision support tool combines artificial intelligence and professional knowledge by setting up intelligent systems and expert systems, and provides decision suggestions by simulating expert decision-making processes to determine the best supplier selection or technical solution.

8. The power engineering cost analysis system according to claim 1, characterized in that: The standardization and training mentioned above is to provide the project team with training and technical support on the use of the system, ensuring that the system can be effectively applied in the actual management of power engineering projects.

9. A method for analyzing the cost of an electric power project provided by the system for analyzing the cost of an electric power project according to any one of claims 1 to 8, characterized in that: The analysis method comprises the following steps: Step 1: Obtain various data including construction progress, human resource input, material usage, and equipment operation status through on-site records, sensor data, or manual input, and store them in the database for management. Monitor the power project cost database in real time and provide timely feedback to the project team and management. Step 2: Analyze the data stored in the database. Through the established budget module, formulate the budget according to historical data, industry standards and actual conditions, and monitor the budget execution through real-time data updates and cost control functions. Step 3: Then, through the integrated risk management module, identify the risk factors that may affect the cost of the power engineering project and formulate response strategies to reduce the potential impact of risks on costs. Step 4: Real-time monitoring and reporting is then used to monitor the cost of power engineering projects in real time and generate various reports and visual charts to help management and project teams understand the economic status and cost trends of the projects at any time. Step 5: Then, through the decision support tools provided by the system, decision suggestions are provided by simulating the expert decision-making process to determine the best supplier selection or technical solution. Step 6: Standardization and training Provide the project team with training and technical support on the use of the system to ensure that the system can be effectively applied in the actual management of power engineering projects.