Oil field project risk analysis method and device, electronic equipment and storage medium

By using random sampling and Monte Carlo simulation methods for risk analysis in oil field projects, the problem of uncertainty in economic evaluation of oil field projects in the existing technology is solved, providing a more scientific basis for investment decision-making, and reducing project risks.

CN118941065APending Publication Date: 2024-11-12CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310524064.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-05-10
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

There is uncertainty in the economic evaluation methods of existing oilfield projects, and it is difficult to effectively consider the risks of technical solutions, reduce the risks of project operations and development, and propose early warning measures.

Method used

The random sampling method is used to calculate multiple results in the probability distribution of economic evaluation indicators, and a probability distribution map is drawn. The risk probability analysis is carried out based on the Monte Carlo simulation method to determine internal rate of return, financial net present value, dynamic investment recovery period and other indicators. risk factors and probability distribution provide scientific and reasonable basis for investment decision-making.

Benefits of technology

Through the combined action of multiple risk factors, economic evaluation of risk probability distribution will help oilfield construction companies make more scientific and reasonable investment decisions, reduce project risks, and provide quantitative standards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118941065A_ABST
    Figure CN118941065A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides an oil field project risk analysis method and device, electronic equipment and a storage medium. The method comprises the steps that economic evaluation indexes are determined; determining risk factors of the economic evaluation indexes; setting probability distribution for the risk factors; extracting a plurality of data from the probability distribution of the risk factors by adopting a random sampling method, and calculating a plurality of economic evaluation index results; and drawing probability distribution and a cumulative probability distribution diagram according to the plurality of economic index results. In the embodiment of the invention, risk probability analysis is carried out on the economic evaluation of the oilfield construction project based on the Monte Carlo simulation method, so that an oilfield construction enterprise makes a decision according to factors such as own financial ability, risk evaluation indexes and strategic planning, and the possibility of the occurrence of the economic evaluation indexes under different risk factors is clearly mastered; economic evaluation risk probability distribution under the combined action of multiple risk factors is presented, so that a scientific and reasonable quantitative standard basis is better provided for an oil field construction enterprise to make an investment decision.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of oil and gas exploration technology, and in particular to an oilfield project risk analysis method, device, electronic equipment, and storage medium. Background Art

[0002] The economic evaluation of oil and gas field projects involves analyzing and predicting the economic benefits of oil and gas resource exploration and future industrial production. This is done to study the feasibility of industrial production, thereby reducing the high risk of exploration investment, implementing effective planning and investment monitoring at all stages of exploration, and providing a basis for decision-making, such as formulating oilfield exploration and development plans. This process primarily includes comprehensive geological evaluation, reservoir engineering evaluation, economic parameter prediction, financial and economic evaluation, and analysis of investment returns and risk decisions.

[0003] In the existing technology, there are two main methods for economic evaluation of oil field projects:

[0004] First, a full life cycle assessment is adopted. For oilfield projects that have not yet been built, a technical predictive assessment of the entire life cycle, from exploration to discovery to development to abandonment, is conducted. This assessment encompasses multiple stages, including geological and resource evaluation, reservoir engineering evaluation, drilling / surface engineering evaluation, and economic evaluation. Risks are identified as much as possible in each technical evaluation stage, factored into the technical plan, and ultimately, a deterministic plan for risk mitigation is developed.

[0005] The second approach is to use the expected economic value method. This method considers different decision nodes and paths, including a project's resource potential, geological risks, development plan optimization, and commercial risks. It combines various scenarios, such as the benefits of successful exploration and the losses of failed exploration, to establish an evaluation decision model to calculate the expected economic value of a project under different paths.

[0006] However, the economic evaluation methods of oilfield projects in the existing technology have a certain degree of uncertainty. How to consider the technical solution risks in the solution data used in the economic evaluation of oilfield construction projects, reduce the subsequent operation and development risks of the projects, and provide early warnings and corresponding countermeasures for potential risks are difficult problems in the economic evaluation of oilfield construction projects.

[0007] It should be pointed out that the information disclosed in the background technology section of this application is only intended to deepen the understanding of the general background technology of this application, and should not be regarded as an admission or any form of implication that the information constitutes prior art already known to those skilled in the art. Summary of the Invention

[0008] In view of this, the present application provides an oilfield project risk analysis method, device, electronic device and storage medium to help solve the problem that the economic evaluation method of oilfield projects in the prior art has a certain degree of uncertainty.

[0009] In a first aspect, an embodiment of the present application provides an oilfield project risk analysis method, comprising:

[0010] Determine one or more economic evaluation indicators for oilfield projects;

[0011] determining a risk factor for each of the one or more economic evaluation indicators;

[0012] Setting a probability distribution for the risk factor of each economic evaluation indicator;

[0013] A plurality of data are extracted from the probability distribution of the risk factors of each of the economic evaluation indicators by using a random sampling method, and a plurality of economic evaluation indicator results corresponding to each of the one or more economic evaluation indicators are calculated;

[0014] According to the multiple economic indicator results corresponding to each of the economic indicators, a probability distribution and a cumulative probability distribution graph corresponding to each of the economic indicators are drawn.

[0015] In a possible implementation, determining one or more economic evaluation indicators of an oilfield project includes:

[0016] One or more economic evaluation indicators of the oilfield project are determined based on the financial status and / or risk appetite of the enterprise corresponding to the oilfield project.

[0017] In a possible implementation, the economic evaluation indicators include: internal rate of return, financial net present value, dynamic investment payback period, net present value index and / or expected value index.

[0018] In a possible implementation, the internal rate of return calculation formula is:

[0019]

[0020] Where FIRR is the internal rate of return; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

[0021] In a possible implementation, the calculation formula of the financial net present value is:

[0022]

[0023] Where FNPV is the project's net present value; i is the investor's benchmark rate of return or expected rate of return; CI is the project's cash inflow at each evaluation stage; CO is the project's cash outflow at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

[0024] In one possible implementation, the calculation formula for the dynamic investment payback period is:

[0025]

[0026] Where Pt is the dynamic investment payback period; i is the investor's benchmark rate of return or expected rate of return; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project.

[0027] In a possible implementation, the calculation formula of the net present value index is:

[0028] PI = NCF / CAPEX

[0029] Among them, PI is the net present value index; NCF is the total present value of the future net cash flow of the investment project; CAPEX is the present value of the original investment.

[0030] In a second aspect, an embodiment of the present application provides an oilfield project risk analysis device, comprising:

[0031] An economic evaluation index determination module is used to determine one or more economic evaluation indicators of an oilfield project;

[0032] a risk factor determination module, configured to determine a risk factor for each of the one or more economic evaluation indicators;

[0033] A probability distribution setting module, used to set a probability distribution for the risk factors of each economic evaluation indicator;

[0034] An economic indicator calculation module, configured to extract a plurality of data from the probability distribution of the risk factors of each of the economic evaluation indicators using a random sampling method, and calculate a plurality of economic evaluation indicator results corresponding to each of the one or more economic evaluation indicators;

[0035] The probability distribution graph drawing module is used to draw the probability distribution and cumulative probability distribution graph corresponding to each economic indicator according to the multiple economic indicator results corresponding to each economic indicator.

[0036] In a third aspect, an embodiment of the present application provides an electronic device, including:

[0037] processor;

[0038] Memory;

[0039] and a computer program, wherein the computer program is stored in the memory, and the computer program includes instructions, which, when executed by the processor, enable the electronic device to perform any one of the methods described in the first aspect.

[0040] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium includes a stored program, wherein when the program is running, the device where the computer-readable storage medium is located is controlled to execute any one of the methods described in the first aspect.

[0041] In the embodiment of the present application, a risk probability analysis is conducted on the economic evaluation of oilfield construction projects based on the Monte Carlo simulation method, so that oilfield construction companies can make decisions based on their own financial capabilities, risk evaluation indicators, strategic planning and other factors, clearly grasp the possibility of economic evaluation indicators under different risk factors, change the original economic evaluation of a single parameter and a single result, and present the economic evaluation risk probability distribution under the joint action of multiple risk factors, thereby better providing scientific and reasonable quantitative standard basis for oilfield construction companies to make investment decisions. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following is a brief introduction to the drawings required for use in the embodiments. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0043] Figure 1 A schematic diagram of a process for analyzing oilfield project risks provided in an embodiment of the present application;

[0044] Figure 2 A schematic diagram of a decision tree provided in an embodiment of the present application;

[0045] Figure 3 A probability distribution and cumulative probability distribution diagram of FNPV provided in an embodiment of the present application;

[0046] Figure 4 A probability distribution and cumulative probability distribution diagram of FIRR provided in an embodiment of the present application;

[0047] Figure 5 This application also provides a structural block diagram of an oil field project risk analysis device

[0048] Figure 6 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0049] In order to better understand the technical solution of the present application, the embodiments of the present application are described in detail below with reference to the accompanying drawings.

[0050] It should be clear that the embodiments described are only part of the embodiments of this application, not all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0051] The terms used in the embodiments of the present application are for the purpose of describing specific embodiments only and are not intended to limit the present application. The singular forms "a", "an", "the" and "the" used in the embodiments of the present application and the appended claims are also intended to include plural forms unless the context clearly indicates otherwise.

[0052] It should be understood that the term "and / or" as used herein simply describes a relationship between associated objects, indicating that three possible relationships exist. For example, "A and / or B" can represent: A alone, A and B together, or B alone. Furthermore, the character " / " in this document generally indicates an "or" relationship between the associated objects.

[0053] See also Figure 1 , is a flow chart of a method for analyzing oilfield project risks provided by an embodiment of the present application. Figure 1 As shown, it mainly includes the following steps.

[0054] Step S101: Determine one or more economic evaluation indicators of an oilfield project.

[0055] In a specific implementation, one or more economic evaluation indicators for an oilfield project can be determined based on the financial status and / or risk appetite of the enterprise associated with the oilfield project. These economic evaluation indicators include internal rate of return, net present value, dynamic payback period, net present value index, and / or expected value index.

[0056] The following is an explanation of each economic evaluation indicator.

[0057] 1) Internal Rate of Return:

[0058] The internal rate of return (IRR) is an indicator of the efficiency of project capital utilization. It is the discount rate that makes the net present value of the evaluated project equal to zero. The IRR reflects the profitability of the project itself and its inherent level of return. A project is considered economically viable only when the calculated IRR is greater than the investor's benchmark rate of return or expected rate of return. The calculation formula is:

[0059]

[0060] Where FIRR is the internal rate of return; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

[0061] 2) Financial Net Present Value:

[0062] The financial net present value (FNPV) indicator uses the investor's expected rate of return as the discount rate, discounting the net cash flow over the project's evaluation period to its present value, and uses this to judge the feasibility of an oil and gas project. The economic meaning of FNPV is the excess return on investment in the project. When the FNPV of a project is greater than 0, the project is considered economically profitable for investors. The formula for calculating FNPV is:

[0063]

[0064] Where FNPV is the project's net present value; i is the investor's benchmark rate of return or expected rate of return; CI is the project's cash inflow at each evaluation stage; CO is the project's cash outflow at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

[0065] 3) Dynamic payback period:

[0066] The dynamic payback period is the period required to recover the entire investment from the initial investment in an oil and gas project using the net income in each year following commercial production, taking into account the time value of money. The dynamic payback period reflects the speed of investment recovery, and thus the investment risk, by taking into account the time value of money. The dynamic payback period should also be compared with the standard or average dynamic payback period of comparable projects or with investor expectations. If it falls below the corresponding standard, the project is considered economically viable. Its calculation formula is:

[0067]

[0068] Where Pt is the dynamic investment payback period; i is the investor's benchmark rate of return or expected rate of return; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project.

[0069] 4) Net Present Value Index:

[0070] The net present value index, also known as the profitability index or profit index, refers to the ratio of the total present value of the future net cash flows of an investment project to the present value of the original investment. If the present value index of an investment project is greater than or equal to 1, it indicates that the investment project's rate of return is higher than or equal to the predetermined discount rate, and the project is acceptable. If the present value index of an investment plan is less than 1, it indicates that the investment project's rate of return is lower than the predetermined discount rate, and the project is unacceptable. Among multiple mutually exclusive alternative projects, the investment project with the most present value indexes greater than 1 should be accepted. Its calculation formula is:

[0071] PI = NCF / CAPEX

[0072] Among them, PI is the net present value index; NCF is the total present value of the future net cash flow of the investment project; CAPEX is the present value of the original investment.

[0073] 5) Expected Value Indicator:

[0074] The expected value indicator, also known as the risk exposure value or risk expectation, is a quantitative risk analysis technique often used in conjunction with decision trees. It multiplies the monetary consequences of a possible risk in a given situation by the probability of occurrence. This project incorporates both risk and cash considerations. Positive values ​​represent opportunity, while negative values ​​represent risk. The value of each possible outcome is multiplied by the probability of occurrence and then summed up to obtain the total.

[0075] See also Figure 2 , is a schematic diagram of a decision tree provided in an embodiment of the present application. Figure 2 As shown, this decision tree includes two branches: geological success and exploration failure. The probability of geological success is Pg; correspondingly, the probability of exploration failure is 1-Pg, with an expected value of -NPV3. Furthermore, geological success includes three branches: "Gas% ≤ 25%," "25% < Gas% ≤ 50%," and "Gas% > 50%." The probability of "Gas% ≤ 25%" is A%, with an expected value of +NPV1; the probability of "25% < Gas% ≤ 50%" is B%, with an expected value of +NPV2; and the probability of "Gas% > 50%" is C%, with an expected value of -NPV3.

[0076] The calculation formula of the expected value index corresponding to the decision tree is:

[0077] EMV=(A%NPV1+B%NPV2-C%NPV3)*Pg–NPV3*(1-Pg)

[0078] Among them, EMV is the expected value indicator.

[0079] Step S102: determining a risk factor for each of the one or more economic evaluation indicators.

[0080] Specifically, after determining the economic evaluation indicators of an oilfield project, the risk factors for each of the one or more economic evaluation indicators can be further determined. For example, the risk factors include return on investment risk, profitability risk, debt repayment risk (loan repayment period), inflation risk, and comprehensive risk.

[0081] Step S103: setting a probability distribution for the risk factors of each economic evaluation indicator.

[0082] Specifically, after determining the risk factors of each economic evaluation indicator, a probability distribution can be further set for the risk factors of each economic evaluation indicator.

[0083] Step S104: a random sampling method is used to extract a plurality of data from the probability distribution of the risk factors of each economic evaluation indicator, and a plurality of economic evaluation indicator results corresponding to each economic indicator in the one or more economic evaluation indicators are calculated.

[0084] In the specific implementation, random sampling is carried out for the risk factors of each economic evaluation indicator, and the economic evaluation indicator is calculated based on the random sampling results. After multiple random samplings, multiple economic evaluation indicator results are obtained for each economic evaluation indicator.

[0085] Step S105: based on the multiple economic indicator results corresponding to each economic indicator, draw a probability distribution and cumulative probability distribution graph corresponding to each economic indicator.

[0086] For example, the probability distribution and cumulative probability distribution of FNPV are as follows: Figure 3 As shown; the probability distribution and cumulative probability distribution of FIRR are shown in Figure 4 As shown in Figure 2, it can be understood that investment decisions can be made based on the probability distribution and cumulative probability distribution graph corresponding to each economic indicator.

[0087] In the embodiment of the present application, a risk probability analysis is conducted on the economic evaluation of oilfield construction projects based on the Monte Carlo simulation method, so that oilfield construction companies can make decisions based on their own financial capabilities, risk evaluation indicators, strategic planning and other factors, clearly grasp the possibility of economic evaluation indicators under different risk factors, change the original economic evaluation of a single parameter and a single result, and present the economic evaluation risk probability distribution under the joint action of multiple risk factors, thereby better providing scientific and reasonable quantitative standard basis for oilfield construction companies to make investment decisions.

[0088] For ease of understanding, the technical solution provided in this application is exemplarily described below with reference to a specific embodiment.

[0089] Specifically, an oilfield construction project company selected FNPV and FIRR as economic evaluation indicators based on its own financial and risk preferences. The company required that, under a scenario with a future return on investment of 12%, the FNPV be greater than 0 and the FIRR be greater than 10% (i.e., risk factors). A project was deemed feasible and investment was approved only if the probability of both financial indicators being met was greater than 50%. Financial modeling revealed that after multiple random sampling and calculation of economic evaluation indicators, the FNPV distribution ranged from -91 to 443 million US dollars, with a probability of being less than zero of approximately 38%. The FIRR distribution ranged from 0% to 30.1%, with a probability of being greater than 10% of nearly 50%. These two economic evaluation indicators were selected as primary screening factors, indicating a 31% probability of both the FNPV being greater than zero and the FIRR being greater than 10%. Based on these two financial indicators and the oilfield construction company's investment decision-making criteria, the project did not meet the feasibility threshold and was therefore not invested in.

[0090] Corresponding to the above embodiment, the present application also provides an oilfield project risk analysis device.

[0091] See also Figure 5 , which is a structural block diagram of an oilfield project risk analysis device provided in this application. Figure 5 As shown, it mainly includes the following modules.

[0092] An economic evaluation index determination module 501 is used to determine one or more economic evaluation indexes of an oilfield project;

[0093] A risk factor determination module 502 is configured to determine a risk factor for each of the one or more economic evaluation indicators;

[0094] A probability distribution setting module 503 is used to set a probability distribution for the risk factor of each economic evaluation indicator;

[0095] An economic indicator calculation module 504 is configured to extract a plurality of data from the probability distribution of the risk factors of each economic evaluation indicator using a random sampling method, and calculate a plurality of economic evaluation indicator results corresponding to each of the one or more economic evaluation indicators;

[0096] The probability distribution graph drawing module 505 is used to draw the probability distribution and cumulative probability distribution graph corresponding to each economic indicator according to the multiple economic indicator results corresponding to each economic indicator.

[0097] In the embodiment of the present application, a risk probability analysis is conducted on the economic evaluation of oilfield construction projects based on the Monte Carlo simulation method, so that oilfield construction companies can make decisions based on their own financial capabilities, risk evaluation indicators, strategic planning and other factors, clearly grasp the possibility of economic evaluation indicators under different risk factors, change the original economic evaluation of a single parameter and a single result, and present the economic evaluation risk probability distribution under the joint action of multiple risk factors, thereby better providing scientific and reasonable quantitative standard basis for oilfield construction companies to make investment decisions.

[0098] It should be pointed out that the specific contents involved in the embodiments of the present application can be found in the description of the above method embodiments. For the sake of brevity, they will not be repeated here.

[0099] Corresponding to the above embodiment, an embodiment of the present application further provides an electronic device.

[0100] See also Figure 6 , is a structural diagram of an electronic device provided in an embodiment of the present application. Figure 6 As shown, the electronic device 600 may include: a processor 601, a memory 602, and a communication unit 603. These components communicate via one or more buses. Those skilled in the art will appreciate that the electronic device structure shown in the figure does not limit the embodiments of the present application. It may be a bus structure or a star structure, and may include more or fewer components than shown, or combine certain components, or arrange the components differently.

[0101] The communication unit 603 is used to establish a communication channel so that the electronic device can communicate with other devices.

[0102] The processor 601 is the control center of the electronic device. It uses various interfaces and lines to connect various parts of the entire electronic device. It runs or executes software programs and / or modules stored in the memory 602, and calls data stored in the memory to perform various functions of the electronic device and / or process data. The processor can be composed of an integrated circuit (IC), for example, it can be composed of a single packaged IC, or it can be composed of multiple packaged ICs with the same or different functions. For example, the processor 601 can include only a central processing unit (CPU). In the embodiment of the present application, the CPU can be a single computing core or multiple computing cores.

[0103] The memory 602 is used to store the execution instructions of the processor 601. The memory 602 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic disk or optical disk.

[0104] When the execution instructions in the memory 602 are executed by the processor 601 , the electronic device 600 is enabled to execute part or all of the steps in the above method embodiment.

[0105] Corresponding to the above embodiment, an embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium may store a program, wherein, when the program is executed, the device containing the computer-readable storage medium may be controlled to perform some or all of the steps in the above method embodiment. In a specific implementation, the computer-readable storage medium may be a magnetic disk, an optical disk, a read-only memory (ROM), or a random access memory (RAM).

[0106] Corresponding to the above embodiment, an embodiment of the present application further provides a computer program product, which includes executable instructions. When the executable instructions are executed on a computer, the computer executes some or all of the steps in the above method embodiment.

[0107] In the embodiments of the present application, "at least one" refers to one or more, and "more" refers to two or more. "And / or" describes the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B can represent the existence of A alone, the existence of A and B at the same time, and the existence of B alone. Among them, A and B can be singular or plural. The character " / " generally indicates that the previous and next associated objects are in an "or" relationship. "At least one of the following" and similar expressions refer to any combination of these items, including any combination of single or plural items. For example, at least one of a, b and c can be represented by: a, b, c, ab, ac, bc, or abc, where a, b, c can be single or multiple.

[0108] Those skilled in the art will appreciate that the various units and algorithm steps described in the embodiments disclosed herein can be implemented using a combination of electronic hardware, computer software, and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.

[0109] Those skilled in the art will clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0110] In the several embodiments provided in this application, if any function is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this application is essentially or the part that contributes to the prior art or the part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the method described in each embodiment of this application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, and other media that can store program code.

[0111] The above description is merely a specific embodiment of the present application. Any person skilled in the art may easily conceive of variations or substitutions within the technical scope disclosed in this application, and such variations or substitutions shall be within the scope of protection of this application. The scope of protection of this application shall be subject to the scope of protection of the claims.

Claims

1. A method for oilfield project risk analysis, characterized in that: include: Determine one or more economic evaluation indicators for oil field projects; Determining a risk factor for each of the one or more economic evaluation indicators; Setting a probability distribution for each risk factor of the economic evaluation indicator; A plurality of data are extracted from the probability distribution of the risk factor of each of the economic evaluation indicators by using a random sampling method, and a plurality of economic evaluation indicator results corresponding to each of the one or more economic evaluation indicators are calculated; According to the multiple economic indicator results corresponding to each of the economic indicators, a probability distribution and a cumulative probability distribution diagram corresponding to each of the economic indicators are drawn.

2. The method according to claim 1, characterized in that Determining one or more economic evaluation indicators of the oil field project includes: One or more economic evaluation indicators of the oilfield project are determined according to the financial status and / or risk preference of the enterprise corresponding to the oilfield project.

3. The method according to claim 1, characterized in that The economic evaluation indicators include: internal rate of return, financial net present value, dynamic investment payback period, net present value index and / or expected value index.

4. The method according to claim 3, characterized in that The internal rate of return calculation formula is: Among them, FIRR is the internal rate of return; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

5. The method according to claim 3, characterized in that: The calculation formula of the financial net present value is: Among them, FNPV is the financial net present value of the project; i is the benchmark rate of return or expected rate of return of the investor; CI is the cash inflow of the project at each evaluation stage; CO is the cash outflow of the project at each evaluation stage; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project; n is the project evaluation cycle.

6. The method according to claim 3, characterized in that The calculation formula of the dynamic investment payback period is: Where Pt is the dynamic investment payback period; i is the investor's benchmark rate of return or expected rate of return; CI is the cash inflow at each evaluation stage of the project; CO is the cash outflow at each evaluation stage of the project; (CI-CO) t is the net cash flow in the tth evaluation year; t is the tth evaluation year of the project.

7. The method according to claim 3, characterized in that The calculation formula of the net present value index is: PI = NCF / CAPEX Among them, PI is the net present value index; NCF is the total present value of the future net cash flow of the investment project; CAPEX is the present value of the original investment.

8. An oilfield project risk analysis device, characterized in that: include: An economic evaluation index determination module is used to determine one or more economic evaluation indexes of an oilfield project; A risk factor determination module, used to determine the risk factor of each of the one or more economic evaluation indicators; A probability distribution setting module, used to set a probability distribution for each risk factor of the economic evaluation indicator; An economic indicator calculation module, used to extract multiple data from the probability distribution of the risk factor of each economic evaluation indicator by a random sampling method, and calculate multiple economic evaluation indicator results corresponding to each of the one or more economic evaluation indicators; The probability distribution diagram drawing module is used to draw the probability distribution and cumulative probability distribution diagram corresponding to each economic indicator according to the multiple economic indicator results corresponding to each economic indicator.

9. An electronic device, characterized in that: include: processor; Memory; And a computer program, wherein the computer program is stored in the memory, and the computer program includes instructions, and when the instructions are executed by the processor, the electronic device executes the method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute the method according to any one of claims 1 to 7.