Digging method for underground large-section geological drilling chamber

By replacing manual excavation with mechanical equipment and combining spray anchor net support and micro-difference blasting technology, the problems of high construction difficulty and high safety risks during excavation of large-section geological drilling chambers in underground holes are solved, and efficient and safe chamber excavation is achieved process.

CN118958998APending Publication Date: 2024-11-15GANSU JINGTIESHAN MINING CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411388820.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

There are problems such as high construction difficulty and high safety risks during the excavation process of underground large-section geological drilling chambers, especially when drilling in deep holes, the traditional manual excavation method is inefficient and has a risk of landslide.

Method used

Use mechanical equipment instead of manual excavation. First form a 5m-high bottom profile on the top of the underground chamber, and then excavate downward layer by layer. Use spray anchor net support and micro-difference blasting technology to form the chamber profile in sections to ensure construction. Safety and quality.

Benefits of technology

The construction method is simplified, the difficulty is reduced, the safety and efficiency is improved, the mechanized operation level and safety of underground chamber excavation is ensured, and risks in traditional construction are eliminated.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958998A_ABST
    Figure CN118958998A_ABST
Patent Text Reader

Abstract

The digging method for the underground large-section geological drilling chamber comprises the following steps that S1, the construction position of the geological chamber is determined, a connecting way is vertically tunneled on the side wall of the chamber to the center of the chamber, expanding brushing is conducted, and the bottom contour of the chamber is formed; s2, the chamber is upwards subjected to top blasting, a bottom chamber is formed, and the height is controlled to be 5 m; s3, a connection slope ramp is tunneled on one side of the top of the chamber and communicates with the top of the chamber; s4, after tunneling to the top of the chamber, excavating the top chamber to form a top contour of the chamber; s5, reinforcing and supporting the top of the chamber; and S6, after tunneling is completed at the bottom of the chamber according to the height of 5 m and at the top of the chamber according to the height of 5 m, punching blasting is conducted on the remaining 5 m of solid rock in the middle of the chamber to form a middle free face. The digging method has the beneficial effects that the digging method is simple and convenient, easy to operate, safe and reliable in digging, low in construction difficulty and high in safety, and guarantees are provided for environmental safety of operators.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of underground mine excavation methods, in particular to an underground large-section geological drilling chamber excavation method. Background Art

[0002] In the process of mineral resource exploration, geological drilling must be constructed. The physical and chemical information of the ore and rock and the composition of the ore and rock are collected by analyzing and testing the drill core, so as to determine the type, composition, grade and physical and chemical information of the ore in the exploration area. Drilling work is usually carried out on the surface, which is convenient, fast and simple to operate. However, when the surface does not have the conditions for drilling construction or when the old mine is mined to a deep depth and it is necessary to conduct deep supplementary exploration of the old mine, it is necessary to dig and drill a geological chamber underground. The deeper the borehole, the larger the size of the chamber is required. When the borehole depth exceeds 2000m, the height of the drill frame generally exceeds 14m. Therefore, the minimum size of the drill frame chamber must reach 10*9*15 (length*width*height). When the height of the underground chamber exceeds 15m, according to the current mining technology level, the traditional slag climbing operation is generally used, and the shallow stripping method is used to increase the height layer by layer. However, when the excavation reaches a certain height, the safety passage will be blocked by the slag, which poses a great safety risk. The second method is to use the method of artificial excavation of the skylight to construct the artificial skylight directly to a height of 15m, and then gradually expand and brush the top of the chamber until the overall chamber outline is formed, and then manually excavate and expand the chamber layer by layer. This method is also labor-intensive and inefficient, with high safety risks and great construction difficulty. Therefore, when constructing deep drilling chambers underground, due to the great construction difficulty, the use of the above two methods is not only difficult, but also poses great safety risks.

[0003] The publication number is: CN118065943A, and the title is: A method for excavating a large underground chamber. The specific steps disclosed are as follows: determine the underground coordinates of the chamber to be constructed, select the existing horizontal tunnel construction chamber connecting horizontal tunnel closest to the construction chamber, and then construct a horizontal chamber connecting tunnel perpendicular to the connecting horizontal tunnel, and construct an auxiliary tunnel at a location 10-30m away from the designed location of the chamber and with good rock stability. The auxiliary ramp is used to construct a skylight from top to bottom above the center point of the designed position of the chamber, and the equipment is transported to the top of the designed position of the chamber through the auxiliary ramp. The top of the chamber is excavated from top to bottom, and the rock slag produced by the excavation is slid and discharged through the skylight. The present invention first constructs an auxiliary ramp at the designed position of the chamber, and transports the relevant equipment to the top of the designed position of the chamber through the auxiliary ramp, and then excavates the chamber from top to bottom. Compared with the traditional method of construction from bottom to top, no landslide will occur during the construction process, which is safe and reliable.

[0004] Although the above method can solve the problem of excavating large-section geological drilling chambers underground, the construction method is still not safe enough and cannot solve the problem of high construction difficulty. Summary of the invention

[0005] The purpose of the present invention is to provide a method for excavating a large-section underground geological drilling chamber, which is simple in excavation method, easy in operation, safe and reliable in excavation, has low construction difficulty, high safety, and provides guaranteed environmental safety for operators.

[0006] The present invention discloses a method for excavating a large-section underground geological drilling chamber, the method comprising the following steps: S1. First, determine the construction position of the geological chamber at the 2640m level, vertically excavate a connecting road 8 on the side wall of the chamber to the center of the chamber, expand and brush according to the specifications of the chamber to form the bottom contour of the chamber; S2. The size of the chamber is blasted upward to form the bottom chamber, and the height is controlled to 5m; S3. A connecting ramp with a slope of 12.5° is excavated on one side of the chamber top, and is designed to connect with the chamber top at a height of 10m from the floor; S4. After the excavation reaches the top of the chamber, the top chamber is excavated according to the three-star arch technology to form the outline size of the top chamber. The height of the top of the chamber is also controlled to 5m; S5. For the 5m height of the chamber top, the sprayed anchor net is used for reinforcement support, the thickness of the sprayed anchor is 150mm, the depth of the anchor rod is 2m, and the steel mesh is 200*200mm; S6. After the excavation is completed according to the size of the bottom height of 5m and the top height of 5m in the chamber, the remaining height in the middle of the chamber is 5m. The solid rock layer in the middle of the chamber is drilled by hydraulic walking down-the-hole drill, and the middle core hole is blasted in a hexagonal core method to form a middle free surface; the auxiliary hole grid parameter is 2.0*2.0m, and the micro-difference blasting method is used to detonate each hole; the peripheral hole spacing is 1.5m, and the smooth blasting technology with more drilling and less charging is used to blast in sections to form the surrounding contour of the chamber.

[0007] S7. After the blasting of the solid body with a height of 5m in the middle of the chamber is completed, the rock wall with a height of 5m in the middle of the chamber is supported by spraying anchor nets on the slag rock, and connected with the top support of the chamber as a whole. After the support is completed, the remaining slag rock is cleaned up; S8. The chamber with a bottom height of 5m is supported by a sprayed anchor net, and is closely connected with the support net of the middle wall in the middle of the chamber to form a whole and improve the support strength; S9. Finally, clean up the residual residue at the bottom of the chamber and level the floor, use cement to harden it, and finally form a geological drilling working chamber.

[0008] In the step S1, the connecting passage is 22m long, and the chamber specifications length*width*height are: 10*9*15.

[0009] Beneficial effects of the present invention: 1) This excavation method has changed the traditional way of thinking about excavation. Mechanical equipment is used instead of manual excavation. First, the excavation is carried out to the top of the chamber, and the top 5m is expanded to form the top contour. This solves the technical difficulties existing in the traditional manual excavation method of the chamber. The construction difficulty is small, the operation is simple, and the safety is high. It has better solved the problems existing in the traditional chamber construction.

[0010] 2) Since a small-section connecting road is used to excavate to the top of the chamber, the top 5m is supported first and then the chamber is excavated downward layer by layer. Compared with traditional construction technology, the top construction is convenient, ensuring construction safety and quality, and eliminating the risks of traditional chamber construction.

[0011] 3) The 5m excavation in the middle of the chamber is formed by one-time blasting using micro-difference detonation technology. Due to the two upper and lower free surfaces, the blasting effect is guaranteed, which reduces the difficulty of chamber construction and improves the efficiency of chamber construction.

[0012] 4) This excavation method simplifies the construction operation mode, realizes mechanized replacement of personnel, improves the level of mechanized operation in underground chamber excavation, and ensures the inherent safety of underground chamber excavation.

[0013] 5) Measure, place points and construct in strict accordance with the design, and ensure construction accuracy to ensure that the upper and lower parts of the chamber are on the same vertical plane.

[0014] 6) During the operation, it must be ensured that the heights of the upper, middle and lower parts of the chamber are basically 5m to ensure that the cross-sectional dimensions of the chamber are under control.

[0015] 7) During the construction of the cavern, the surrounding holes must be blasted using smooth blasting technology with more drilling and less charging to ensure the smoothness of the cavern rock wall contour and minimize the blasting vibration damage to the surrounding rocks, creating good conditions for later construction safety.

[0016] 8) When blasting the middle 5m, the hole network parameters should be scientifically designed according to the rock properties and constructed according to the designed parameters, and the amount of explosives should be accurately calculated. Under the premise of ensuring the blasting quality, the damage to the rock wall of the chamber caused by the blasting of the surrounding holes should be reduced.

[0017] 9) Carry out support in strict accordance with the design of shotcrete mesh support, do a good job in the acceptance management of hidden projects, and ensure the quality of chamber support. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the structure of the chamber in the present invention.

[0019] In the figure: connecting ramp 1, charging blasthole 2, chamber top 3, blasthole filling part 4, chamber middle 5, solid rock in the middle of the chamber 6, chamber bottom 7, connecting road 8. DETAILED DESCRIPTION

[0020] The following will be combined with the attached Figure 1 The present invention is further described.

[0021] The present invention is explained by taking the excavation of a 2000m deep geological chamber in the Huashugou mining area as an example.

[0022] The present invention discloses a method for excavating a large-section underground geological drilling chamber, the method comprising the following steps: S1. First, determine the construction position of the geological chamber at the 2640m level, vertically excavate the connecting road 8 on the side wall of the chamber to the center of the chamber, expand and brush according to the specifications of the chamber, and form the contour of the bottom 7 of the chamber; S2. The size of the chamber is blasted upward to form the chamber bottom 7, and the height is controlled to 5m; S3. A connecting ramp 1 is excavated on one side of the chamber top 3, with a slope of 12.5°, and is designed to be connected to the chamber top 3 at a height of 10m from the floor; S4. After the excavation reaches the top 3 of the chamber, the top 3 of the chamber is excavated according to the three-star arch technology to form the outline size of the top 3 of the chamber. The height of the top 3 of the chamber is also controlled to 5m; S5. The height of the chamber top 3 is 5m. The chamber is reinforced with a sprayed anchor mesh. The thickness of the sprayed anchor is 150mm, the depth of the anchor rod is 2m, and the steel mesh is 200*200mm. S6. After the excavation of the chamber bottom 7 with a height of 5m and the chamber top 3 with a height of 5m is completed according to the dimensions, the remaining height of the middle part 5 of the chamber is 5m. The solid rock layer 6 in the middle part of the chamber is drilled with a hydraulic walking down-the-hole drill. The middle core hole is blasted in a hexagonal core method to form a middle free surface; the auxiliary hole grid parameter is 2.0*2.0m, and the micro-difference blasting method is used to detonate each hole one by one; the peripheral hole spacing is 1.5m, and the smooth blasting technology with more drilling and less charging is used to blast in sections to form the surrounding contour of the chamber.

[0023] S7. After the blasting of the solid body with a height of 5m in the middle of the chamber is completed, the rock wall with a height of 5m in the middle of the chamber is supported by spraying anchor nets on the slag rock, and connected with the support of the top 3 of the chamber as a whole. After the support is completed, the remaining slag rock is cleaned up; S8. The chamber with a height of 5m at the bottom of the chamber 7 is supported by a sprayed anchor net, and the support net is closely connected with the middle wall of the middle chamber 5 to form a whole and improve the support strength; S9. Finally, clean up the residual residue at the bottom of the chamber and level the floor, harden it with cement, and finally form a geological drilling working chamber.

[0024] In the step S1, the connecting passage is 22m long, and the chamber specifications length*width*height are: 10*9*15.

[0025] In the step S6, the model of the hydraulic down-the-hole drill is: ZGYX420-2.

[0026] Due to the small underground space in Huashugou, the construction of large-section chambers is extremely difficult. Therefore, this excavation method divides the excavation of the 2000m deep drilling chamber into three sections: upper, middle and lower. The thickness of each section is 5m. From the overall design concept, it simplifies the operation links and improves the construction efficiency.

[0027] Traditionally, underground geological chamber excavation is done by manually digging a shaft, raising it layer by layer from bottom to top. After excavation to the designed top height of the chamber, the chamber is expanded from the top to eventually form the top contour of the chamber. All operation links are completed manually.

[0028] The 2000m deep drilling geological chamber excavation in Huashugou Mining Area uses mechanical equipment instead of manual excavation. It first excavates to the top of the chamber, and then expands the top 5m to form the top contour, which solves the technical difficulties and safety risks of traditional manual excavation of chambers. The construction difficulty is small, the operation is simple, and the safety is high, which effectively solves the problems existing in traditional underground chamber construction.

[0029] Since a small-section connecting road is used to excavate to the top 3 of the cavern, the top 5m is supported first and then the cavern is excavated downward layer by layer. Compared with traditional construction technology, the top construction is convenient, the construction safety and quality are ensured, and the risks of traditional cavern construction are eliminated.

[0030] The height of the middle part 5 of the cavern is 5m and it is excavated by one-time blasting using micro-difference blasting technology. Due to the two upper and lower free surfaces, the blasting effect is guaranteed, which reduces the difficulty of cavern construction and improves the efficiency of cavern construction.

[0031] This simplifies the construction operation mode, realizes mechanized replacement of personnel, improves the level of mechanized operation in the 2000m underground chamber excavation in Huashugou Mine, and ensures the inherent safety of chamber excavation.

Claims

1. A method for excavating a large-section geological drilling chamber underground, characterized in that: The method comprises the following steps: S1. First, determine the construction position of the geological chamber at the 2640m level, vertically excavate the connecting road (8) on the side wall of the chamber to the center of the chamber, expand and brush according to the specifications of the chamber to form the contour of the bottom of the chamber (7); S2. The size of the chamber is blasted upward to form the bottom chamber, and the height is controlled to 5m; S3. A connecting ramp (1) is excavated on one side of the top (3) of the chamber, with a slope of 12.5°, and is designed to be connected to the top (3) of the chamber at a height of 10m from the floor; S4. After the excavation reaches the top of the chamber (3), the top of the chamber is excavated according to the three-star arch technology to form the top of the chamber (3) contour. The height of the top of the chamber (3) is also controlled to 5m; S5. The top of the chamber (3) is 5m high and reinforced with a sprayed anchor net with a thickness of 150mm; S6. After the excavation is completed at the bottom of the chamber (7) at a height of 5m and at the top of the chamber (3) at a height of 5m, there is 5m of solid rock (6) in the middle of the chamber (5). A hydraulic down-the-hole drill is selected, and the middle core hole is blasted in a hexagonal core method to form a middle free surface; the auxiliary hole grid parameter is 2.0*2.0m, and the micro-difference blasting method is used to detonate each hole; the peripheral hole spacing is 1.5m, and the smooth surface blasting technology with more holes and less charge is used to form the peripheral contour of the chamber by staged blasting; S7. After the blasting of the 5m high entity in the middle of the chamber (5), the rock wall in the middle of the chamber (5) with a height of 5m is supported by spraying anchor nets on the slag, and connected to the support of the top of the chamber (3) as a whole. After the support is completed, the remaining slag is cleaned up; S8. The bottom of the chamber (7) is 5m high and the chamber is supported by a sprayed anchor net, and the support net of the middle wall of the middle of the chamber (5) is closely connected to form a whole; S9. Finally, the residual slag at the bottom of the chamber (7) is cleaned and the floor is leveled, and hardened with cement to finally form a geological drilling working chamber.

2. A method for excavating a large-section underground geological drilling chamber as claimed in claim 1, characterized in that: In step S1, the connecting channel (8) is 22 m long, and the specifications of the chamber are length*width*height: 10*9*15.

Citation Information

Cited By

  • Construction method for underground ultra-deep drilling high and large chamber

    CN120007317A