Method for controlling flatness of cast-in-place concrete ground structure

The concrete floor is leveled by driving the guide rail and fixed plate system, and the problems of poor flatness control accuracy and construction continuity in the existing technology are solved, and efficient concrete floor flatness and adaptive construction are achieved, thereby reducing labor costs and quality risks.

CN118979424APending Publication Date: 2024-11-19CHINA CONSTR EIGHTH ENG BUREAU TECH CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411085203.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

It is difficult to ensure smoothness during construction of cast-in-place concrete floor structures. Traditional methods such as measuring and leveling of line tape measure and scraper ruler have poor continuity, low accuracy, and are prone to quality problems such as hollowing and cracking when the span is large.

Method used

The guide rail and fixed plate system are adopted to drive the roller on the fixed plate to move in the direction of the extension of the guide rail to achieve the leveling of the concrete floor. The light roller and sheep foot roller are used to lengthen multiple times to reduce the number of flattening times, and adjust it. The rail height and splicing unit are suitable for the floor length.

Benefits of technology

It improves the control accuracy and construction efficiency of concrete floor flatness, reduces the risks of hollowing and cracking, reduces labor costs, and adapts to the needs of different ground lengths.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979424A_ABST
    Figure CN118979424A_ABST
Patent Text Reader

Abstract

The invention relates to a cast-in-place concrete ground structure flatness control method which comprises the following steps that guide rails are provided, and the guide rails are arranged on the two opposite sides of a to-be-poured concrete ground; the concrete ground is poured; a fixing plate is provided, the fixing plate is provided with a rolling shaft corresponding to the guide rail, a runner wheel is rotatably installed at the bottom of the fixing plate, the rolling shaft is arranged on the guide rail to fix the fixing plate and drive the fixing plate, so that the runner wheel moves in the extending direction of the guide rail, and the runner wheel flattens the concrete ground; and the guide rail and the fixing plate are dismantled, the poured concrete ground is maintained, operation is convenient, and use is easy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete surface flatness, in particular to a method for controlling the flatness of a cast-in-place concrete floor structure. Background Art

[0002] The flatness of concrete refers to the flatness of the concrete surface. It is one of the important indicators of concrete surface quality. Its quality directly affects the service life and appearance of concrete.

[0003] With the increasing demand for modern industrial flooring, the requirements for controlling the flatness of cast-in-place concrete floor structures are becoming more and more stringent.

[0004] In the traditional cast-in-place concrete floor structure finishing construction, the elevation and flatness are controlled by measuring with a hanging tape measure and leveling with a scraper. However, the continuity of leveling is poor, and during the construction process, the hanging wire is easy to mix with the concrete and is difficult to distinguish. When the span is large, the hanging wire has large deflection and poor accuracy. The secondary decoration method will produce quality risks such as hollowing and later cracking. Therefore, some inventions have been made to improve it. Summary of the invention

[0005] The purpose of the present invention is to overcome the defects of the prior art and provide a method for controlling the flatness of a cast-in-place concrete floor structure, by driving a fixed plate to move along the extension direction of a guide rail so that a roller on the fixed plate can level the concrete floor.

[0006] The technical solution to achieve the above purpose is a method for controlling the flatness of a cast-in-place concrete floor structure, comprising the following steps:

[0007] Providing guide rails, which are arranged on opposite sides of the concrete floor to be poured;

[0008] pouring the concrete floor;

[0009] A fixed plate is provided, wherein the fixed plate is provided with a roller corresponding to the guide rail, and a roller is rotatably installed at the bottom of the fixed plate, and the roller is arranged on the guide rail to fix the fixed plate, and the fixed plate is driven so that the roller moves along the extension direction of the guide rail, and the roller levels the concrete floor;

[0010] The guide rails and the fixing plates are removed, and the poured concrete floor is maintained.

[0011] Furthermore, the fixing plate is formed with a shaft hole corresponding to the roller, and when the fixing plate is fixed, the roller is inserted into the shaft hole, and the roller is arranged on the guide rails on both sides.

[0012] Furthermore, a scraper is provided at the bottom of the fixed plate, and the bottom of the scraper is flush with the bottom of the rolling wheel. When the fixed plate is driven, the scraper scrapes the concrete floor flat.

[0013] Furthermore, the roller includes a smooth roller and a sheep's foot roller. When the fixed plate is driven, the smooth roller and the sheep's foot roller level the concrete floor.

[0014] Furthermore, the polishing roller wheel is formed by splicing a plurality of polishing roller units, one end of the polishing roller unit is formed with a first butt end, and the other end of the polishing roller unit is formed with a first mounting groove corresponding to the first butt end;

[0015] The first butt joint end of the polishing roller unit is arranged in the first mounting groove, and the first butt joint end and the first mounting groove are threadedly connected by bolts to fix the two polishing roller units.

[0016] Furthermore, the sheep foot roller is formed by splicing a plurality of sheep foot roller units, one end of the sheep foot roller unit forms a second docking end, and the other end of the sheep foot roller unit forms a second mounting groove corresponding to the second docking end;

[0017] The two sheep foot roller units are fixedly connected by arranging the second butt joint end of the sheep foot roller unit in the second mounting groove and threadedly connecting the second butt joint end and the second mounting groove by means of bolts.

[0018] Furthermore, a push-pull rod is provided on the top of the fixing plate. When the fixing plate is driven, the push-pull rod is pulled to drive the fixing plate to move along the extension direction of the slide rail.

[0019] Furthermore, a mounting hole is formed at the bottom of the guide rail. When setting the guide rail, a support rod is provided, and an adjusting nut is threaded on the support rod. The support rod is inserted into the mounting hole, and the adjusting nut is fitted to the bottom of the guide rail. The adjusting nut is screwed to make the height of the guide rail adjustable.

[0020] Furthermore, the bottom of the support rod is threadedly connected with an anti-pullout nut, and when the concrete floor is poured, the anti-pullout nut is buried in the concrete floor.

[0021] Furthermore, the guide rail is formed by splicing a plurality of guide rail units, one end of the guide rail unit forms a third docking end, and the other end of the guide rail unit forms a third installation groove corresponding to the third docking section;

[0022] The two guide rail units are fixedly connected by arranging the third butt joint end of the guide rail unit in the third mounting groove and threadedly connecting the third butt joint end and the third mounting groove by means of a bolt.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] By driving the fixed plate to move along the extension direction of the guide rail, the roller on the fixed plate can level the concrete floor. By extending the guide rail, the guide rail can be adapted to the length of the concrete floor. By extending the smooth roller and the sheep's foot roller, the number of times the roller levels the road surface can be reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 This is a rendering of the effect of using a method for controlling the flatness of a cast-in-place concrete floor structure.

[0026] Figure 2 This is a diagram showing the effect of using a smooth roller wheel in a method for controlling the flatness of a cast-in-place concrete floor structure.

[0027] Figure 3 This is a diagram showing the effect of using a sheep-foot roller in a method for controlling the flatness of a cast-in-place concrete floor structure.

[0028] Figure 4 This is a diagram showing the effect of using a scraper in a method for controlling the flatness of a cast-in-place concrete floor structure.

[0029] Figure 5 The overall structural diagram of a guide rail for a method for controlling the flatness of a cast-in-place concrete floor structure.

[0030] Figure 6 The overall structural diagram of the guide rail extension of a cast-in-place concrete floor structure flatness control method

[0031] Figure 7 The overall structural diagram of a fixed plate of a cast-in-place concrete floor structure flatness control method.

[0032] Figure 8 This is a diagram showing the effect of extending the smooth roller wheel of a method for controlling the flatness of a cast-in-place concrete floor structure.

[0033] Fig. 9 This is a diagram showing the effect of extending the sheep-foot roller for a method of controlling the flatness of a cast-in-place concrete floor structure.

[0034] Legend: 1. Fixed plate; 11. Roller; 12. Push-pull rod; 13. Connecting shaft; 2. Guide rail; 21. Third mounting slot; 22. Third docking end; 3. Support rod; 31. Adjusting nut; 4. Concrete floor; 5. Sheep-foot roller; 51. Second mounting slot; 52. Second docking end; 6. Smooth roller; 61. First mounting slot; 62. First docking end; 7. Scraper; 71. Fixed shaft. DETAILED DESCRIPTION

[0035] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0036] See also Figure 1 and Figure 2 A method for controlling the flatness of a cast-in-place concrete floor structure comprises the following steps: providing a guide rail 2, and setting the guide rail 2 on opposite sides of a concrete floor 4 to be cast; casting the concrete floor 4; providing a fixed plate 1, and the fixed plate 1 is provided with a roller 11 corresponding to the guide rail 2, and a roller is rotatably installed at the bottom of the fixed plate 1, and the roller 11 is set on the guide rail 2 to fix the fixed plate 1, and the fixed plate 1 is driven to make the roller move along the extension direction of the guide rail 2, and the roller levels the concrete floor 4; removing the guide rail 2 and the guide rail 2 assembly, and maintaining the cast concrete floor 4.

[0037] In the present invention, a preferred embodiment is as follows: guide rails 2 are arranged on both sides of the concrete floor 4 to be poured, the guide rails 2 are arranged above the concrete floor 4, concrete is poured, a fixing plate 1 is provided, and a roller 11 of the fixing plate 1 is placed on the top of the guide rails 2. Preferably, the guide rails 2 are made of rectangular square tubes, the rollers 11 are slidably arranged on the top of the guide rails 2, and the fixing plate 1 is arranged on the two guide rails 2 by the rollers 11. The fixing plate 1 is supported by the guide rails 2 to prevent the fixing plate 1 from sinking due to the unsolidified concrete of the concrete floor 4. The roller cannot level the concrete pavement well, and the fixed plate 1 is driven to level the concrete pavement. Preferably, the fixed plate 1 can be pulled or pushed so that the fixed plate 1 can move along the extension direction of the guide rail 2, and the fixed plate 1 is driven by manpower so that the roller fixed at the bottom of the fixed plate 1 scrapes and rolls the concrete pavement 2 to 3 times. After the scraping and rolling is completed, the guide rail 2 and the fixed plate 1 are removed, and the installation position of the guide rail 2 is filled and leveled by using tools such as a scraper. After the overall completion, the concrete pavement is maintained.

[0038] Furthermore, two fixing nuts are threadedly connected to the roller 11, and the two fixing nuts are located on both sides of the guide rail 2. By screwing the fixing nuts, the fixing nuts are fitted against the sides of the guide rail 2, thereby preventing the fixing plate 1 from shifting when moving along the extension direction of the guide rail 2, causing defects in the leveling work such as unevenness of part of the road surface.

[0039] Furthermore, an external thread is formed on the roller 11 corresponding to the fixing nut, and the fixing nut is threadedly connected to the external thread.

[0040] Furthermore, a mounting hole is formed on the fixing plate 1, a bearing is arranged in the mounting hole, a connecting shaft 13 is arranged on the side of the grinding wheel, and the connecting shaft 13 is inserted in the bearing so that the connecting shaft 13 can rotate freely, so that the grinding wheel can rotate freely.

[0041] Further, the fixing plate 1 is formed with a shaft hole corresponding to the roller 11. When the fixing plate 1 is fixed, the roller 11 is inserted into the shaft hole, and the roller 11 is arranged on the guide rails 2 on both sides. Preferably, a bearing is arranged in the shaft hole, and the roller 11 is inserted in the bearing, so that the roller 11 can be freely rotatably arranged in the shaft hole.

[0042] Furthermore, a scraper 7 is provided at the bottom of the fixed plate 1, and the bottom of the scraper 7 is flush with the bottom of the roller. When the fixed plate 1 is driven, the scraper 7 scrapes the concrete floor 4. Preferably, the fixed plate 1 is formed with a setting hole, and a fixed shaft 71 is formed on the side of the scraper 7, and the fixed shaft 71 is fixed in the setting hole.

[0043] Furthermore, the rollers include a smooth roller 6 and a sheep's foot roller 5. When driving the fixed plate 1, the smooth roller 6 and the sheep's foot roller 5 level the concrete floor 4. The sheep's foot roller 5 and the smooth roller 6 can better level the surface of the concrete; the sheep's foot roller 5 can level the stones or aggregates in the concrete, and the smooth roller 6 can level the surface of the concrete.

[0044] Furthermore, the bottom of the fixed plate 1 is provided with the smooth rolling wheel 6, the sheep's foot rolling wheel 5 and the scraper 7 at intervals. The smooth rolling wheel 6, the sheep's foot rolling wheel 5 and the scraper 7 are arranged in the order of: hoop plate, smooth rolling wheel 6 and sheep's foot rolling wheel 5 from one side of the fixed plate 1 to the other side. When in use, the sheep's foot rolling wheel 5 is located in front of the travel path of the fixed plate 1. The sheep's foot rolling wheel 5 is used to level the aggregate or stone solids in the concrete pavement first, and the smooth rolling wheel 6 at the rear levels the concrete pavement. The scraper 7 at the rear scrapes the excess concrete and fills the potholes existing in the concrete pavement.

[0045] Furthermore, the polishing roller 6 is formed by splicing a plurality of polishing roller units, one end of the polishing roller unit is formed with a first butt end 62, and the other end of the polishing roller unit is formed with a first mounting groove 61 corresponding to the first butt end 62;

[0046] The first butt end 62 of the polishing roller unit is arranged in the first installation groove 61, and the first butt end 62 and the first installation groove 61 are threadedly connected by bolts to fix the two polishing roller units. By increasing the polishing roller unit, the length of the polishing roller wheel 6 after the increase is adapted to the width of the concrete pavement, so as to reduce the number of users pulling the roller device back and forth, thereby reducing labor costs.

[0047] Furthermore, the sheep foot roller 5 is formed by splicing a plurality of sheep foot roller units, one end of the sheep foot roller unit forms a second docking end 52, and the other end of the sheep foot roller unit forms a second mounting groove 51 corresponding to the second docking end 52;

[0048] The second butt end 52 of the sheep-foot roller unit is arranged in the second mounting groove 51, and the second butt end 52 and the second mounting groove 51 are threadedly connected by bolts to fix the two sheep-foot roller units. By increasing the sheep-foot roller unit, the length of the increased sheep-foot roller wheel 5 is adapted to the width of the concrete pavement, so as to reduce the number of users pulling the roller device back and forth, thereby reducing labor costs.

[0049] Furthermore, a push-pull rod 12 is provided on the top of the fixing plate 1. When the fixing plate 1 is driven, the push-pull rod 12 is pulled to drive the fixing plate 1 to move along the extension direction of the slide rail.

[0050] Furthermore, an ear plate is provided on the top of the fixing plate 1, and a connecting hole is formed on the ear plate. A docking hole is formed at the end of the push-pull rod 12 corresponding to the connecting hole. The docking hole and the connecting hole are threadedly connected by bolts to fix the push-pull rod 12 and the fixing plate 1; preferably, the push-pull rod 12 is rotatably arranged on the top of the fixing plate 1 by bolts, so that construction workers of different heights can conveniently adjust the foot bone between the push-pull rod 12 and the fixing plate 1 to push / pull the push-pull rod 12.

[0051] Furthermore, a mounting hole is formed at the bottom of the guide rail 2. When the guide rail 2 is set, a support rod 3 is provided. The support rod 3 is threaded with an adjusting nut 31. The support rod 3 is inserted into the mounting hole. The adjusting nut 31 is attached to the bottom of the guide rail 2. The adjusting nut 31 is screwed to adjust the height of the guide rail 2. By screwing the adjusting nut 31 upward or downward, the adjusting nut 31 can drive the guide rail 2 to adjust upward or downward, so that the height of the guide rail 2 is adjustable. The roller 11 is set at the top of the guide rail 2. By adjusting the height of the guide rail 2, the roller can be adjusted according to the construction conditions on site, so that the roller fits the surface of the concrete pavement.

[0052] Furthermore, the bottom of the support rod 3 is threadedly connected with an anti-pullout nut, and when the concrete floor 4 is poured, the anti-pullout nut is buried in the concrete floor 4.

[0053] Furthermore, the guide rail 2 is formed by splicing a plurality of guide rail units, one end of the guide rail unit forms a third docking end 22, and the other end of the guide rail unit forms a third mounting groove 21 corresponding to the third docking section;

[0054] The two guide rail units are fixedly connected by arranging the third butt end 22 of the guide rail unit in the third mounting groove 21 and threading the third butt end 22 and the third mounting groove 21 with a bolt. The length of the guide rail unit is extended so that the length of the guide rail 2 matches the length of the concrete floor 4.

[0055] The following is an explanation of the use of a method for controlling the flatness of a cast-in-place concrete floor structure according to the present invention.

[0056] By measuring the placement points, multiple support rods 3 are arranged on both sides of the steel bar area of ​​the concrete floor 4 to be poured. Preferably, a sleeve can be welded at the position corresponding to the support rod 3 in the steel bar area, and the sleeve is formed with an internal thread corresponding to the support rod 3, and the support rod 3 is threadedly connected in the sleeve;

[0057] An adjusting nut 31 is threadedly connected to the support rod 3, and a guide rail unit is arranged on the support rod 3. The guide rail unit is arranged at a suitable height by adjusting the adjusting nut 31;

[0058] pouring concrete in the concrete floor 4 to be poured;

[0059] Each guide rail unit is spliced ​​to the required length to form a guide rail 2, and the elevation and level of the guide rail 2 are adjusted by a level, a spirit level and an adjusting bolt, so as to improve the leveling accuracy during construction;

[0060] The roller 11 of the fixed plate 1 is placed on the guide rail 2, and the roller and scraper 7 arranged on the fixed plate 1 are in contact with the concrete floor 4. The scraping and rolling device is driven by manpower to move along the guide rail 2, and the scraping and rolling is performed 2 to 3 times to form a leveling structure layer of the cast-in-place concrete floor 4;

[0061] After the above process is completed, the fixing plate 1, the guide rail 2 and the support rod 3 are recovered;

[0062] Fill the rod eye left by support rod 3;

[0063] Cast-in-place concrete floor 4 leveling and structural layer maintenance.

[0064] The present invention is described in detail above in conjunction with the embodiments of the accompanying drawings. A person skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the present invention, and the scope of protection of the present invention shall be defined by the scope of the attached claims.

Claims

1. A method for controlling the flatness of a cast-in-place concrete floor structure, characterized in that: The steps include: Providing guide rails, which are arranged on opposite sides of the concrete floor to be poured; pouring the concrete floor; A fixed plate is provided, wherein the fixed plate is provided with a roller corresponding to the guide rail, and a roller is rotatably installed at the bottom of the fixed plate, and the roller is arranged on the guide rail to fix the fixed plate, and the fixed plate is driven so that the roller moves along the extension direction of the guide rail, and the roller levels the concrete floor; The guide rails and the fixing plates are removed, and the poured concrete floor is maintained.

2. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: The fixing plate is formed with a shaft hole corresponding to the roller. When the fixing plate is fixed, the roller is inserted into the shaft hole and the roller is arranged on the guide rails on both sides.

3. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: A scraper is arranged at the bottom of the fixed plate, and the bottom of the scraper is flush with the bottom of the rolling wheel. When the fixed plate is driven, the scraper scrapes the concrete floor flat.

4. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: The rollers include a smooth roller and a sheep-foot roller. When the fixed plate is driven, the smooth roller and the sheep-foot roller level the concrete floor.

5. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 4, characterized in that: The polishing roller wheel is formed by splicing a plurality of polishing roller units, one end of the polishing roller unit is formed with a first butt end, and the other end of the polishing roller unit is formed with a first mounting groove corresponding to the first butt end; The first butt joint end of the polishing roller unit is arranged in the first mounting groove, and the first butt joint end and the first mounting groove are threadedly connected by bolts to fix the two polishing roller units.

6. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 4, characterized in that: The sheep foot roller wheel is formed by splicing a plurality of sheep foot roller units, one end of the sheep foot roller unit forms a second butt joint end, and the other end of the sheep foot roller unit forms a second mounting groove corresponding to the second butt joint end; The two sheep foot roller units are fixedly connected by arranging the second butt joint end of the sheep foot roller unit in the second mounting groove and threadedly connecting the second butt joint end and the second mounting groove by means of bolts.

7. The method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: A push-pull rod is arranged on the top of the fixing plate. When the fixing plate is driven, the push-pull rod is pulled to drive the fixing plate to move along the extending direction of the slide rail.

8. The method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: A mounting hole is formed at the bottom of the guide rail. When setting the guide rail, a support rod is provided, and an adjusting nut is threaded on the support rod. The support rod is inserted into the mounting hole, and the adjusting nut is fitted to the bottom of the guide rail. The adjusting nut is screwed to make the height of the guide rail adjustable.

9. A method for controlling the flatness of a cast-in-place concrete floor structure according to claim 8, characterized in that: The bottom of the support rod is threadedly connected with an anti-pullout nut, and when the concrete floor is poured, the anti-pullout nut is buried in the concrete floor.

10. The method for controlling the flatness of a cast-in-place concrete floor structure according to claim 1, characterized in that: The guide rail is formed by splicing a plurality of guide rail units, one end of the guide rail unit forms a third docking end, and the other end of the guide rail unit forms a third installation groove corresponding to the third docking section; The two guide rail units are fixedly connected by arranging the third butt joint end of the guide rail unit in the third mounting groove and threadedly connecting the third butt joint end and the third mounting groove by means of a bolt.