Underground water stratum advanced detection method based on transient electromagnetic method

Through the application of transient electromagnetic method, the high cost of drilling and environmental damage is solved by using sector scanning and pulsed magnetic field technology, and efficient and low-impact detection of groundwater formations is achieved.

CN119065025AInactive Publication Date: 2024-12-03CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +2
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411012892.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Drilling method is costly and environmentally damaging in groundwater formation detection, and requires a new method for advanced detection.

Method used

Transient electromagnetic method is used to arrange horizontal and plumb fan-shaped scanning lines, send pulsed magnetic fields and receive attenuated secondary magnetic fields, and signal processing is performed to identify the apparent resistivity distribution of underground geological bodies and judge the water content.

Benefits of technology

Advance detection of groundwater formations is achieved, predicting water content distribution, reducing costs and reducing environmental damage impact.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119065025A_ABST
    Figure CN119065025A_ABST
Patent Text Reader

Abstract

The invention discloses a transient electromagnetic method-based underground water stratum advanced detection method, which specifically comprises the following steps: S1, arranging horizontal and plumb fan-shaped scanning measuring lines according to the size of a tunnel face and geological conditions, S2, sending a primary pulsed magnetic field to the underground by using an ungrounded loop, and after the primary field disappears, carrying out transient electromagnetic method-based advanced detection on the underground water stratum. S3, performing filtering, time correction, apparent resistivity calculation and apparent depth calculation on the received signal to obtain an apparent resistivity distribution result map, and calculating the apparent resistivity distribution result map according to the calculated apparent resistivity distribution result map and the calculated apparent resistivity distribution result map. According to the distribution result map of the apparent resistivity, unfavorable geologic bodies in front of the tunnel face and the water content condition are recognized and judged; according to the advanced detection method for the underground water stratum based on the transient electromagnetic method, the problems that a drilling method is high in cost, destructive operation can be carried out, and the stratum and the surrounding environment are damaged are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel engineering, and in particular to a method for advanced detection of groundwater strata based on transient electromagnetic method. Background Art

[0002] Groundwater refers to water stored in the gaps in rocks below the ground. In a narrow sense, it refers to water in saturated aquifers below the groundwater surface. Groundwater is an important component of water resources. Due to its stable water volume and good water quality, it is one of the important water sources for agricultural irrigation, industrial conditions and cities.

[0003] Usually, the drilling method is used for detection under general geological conditions. Generally, impact drilling and core drilling are carried out. A drilling rig is used to drill holes in the stratum to identify and divide the subsurface strata, and samples can be taken along the depth of the hole. However, the drilling method is expensive, requires a large amount of capital investment, and will perform destructive operations, which will have a destructive impact on the strata and the surrounding environment. Therefore, a new method is needed to conduct advanced detection of strata rich in groundwater. Summary of the invention

[0004] The purpose of the present invention is to provide a method for advanced detection of groundwater strata based on transient electromagnetic method, so as to solve the problem that the drilling method is high in cost and easily causes damage to the environment.

[0005] To achieve the above object, the present invention provides the following technical solution: a method for advanced detection of groundwater strata based on transient electromagnetic method, the specific steps comprising:

[0006] S1: Arrange horizontal and plumb sector scanning lines according to the tunnel face size and geological conditions;

[0007] S2: Use an ungrounded return line to send a pulse magnetic field underground. After the primary field disappears, there is a transition process to generate an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface, and the characteristics of the secondary field attenuating with time are measured in the receiver according to different delay times.

[0008] S3: Filter the received signal, perform time correction, calculate the apparent resistivity and apparent depth, and obtain an apparent resistivity distribution result map. According to the apparent resistivity distribution result map, identify and judge the unfavorable geological body and its water content in front of the tunnel face.

[0009] Preferably, in step S1, one or more groups of horizontal and plumb sector scanning lines are arranged with the tunnel face as the center.

[0010] Preferably, the horizontal sector scanning survey line arrangement process in step S1 includes: the horizontal survey line preferably starts at 45° from the normal direction of the wireframe to the left wall of the tunnel, and a measuring point is arranged every 15° in the clockwise direction. When the normal direction of the wireframe is consistent with the axis direction of the tunnel, a measuring point is arranged every 0.5-1.0m, and sector scanning is performed in sequence until the normal direction of the wireframe is 45° from the right wall of the tunnel.

[0011] Preferably, the plumb sector scanning survey line arrangement process in step S1 includes: the plumb line preferably starts with the normal direction of the wireframe being 45° obliquely upward to the tunnel axis direction, and a measuring point is arranged every 15° until the normal direction of the wireframe is 45° obliquely downward to the tunnel axis direction.

[0012] Preferably, the specific steps of S2 include:

[0013] A pulse magnetic field is sent underground using an ungrounded loop line, that is, a current pulse square wave is supplied on the transmitting loop line. At the moment when the trailing edge of the square wave falls, a transient magnetic field propagating underground will be generated, and eddy currents will be generated in the geological body under the excitation of the magnetic field.

[0014] After the primary field disappears, the eddy current cannot disappear immediately. It will have a transition process, which will produce an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface. The change of the secondary magnetic field will reflect the electrical properties of the underground medium. The secondary induced electromotive force is measured in the receiver according to different delay times to obtain the characteristic of the secondary field attenuating with time.

[0015] Preferably, the primary transient magnetic field excitation generates eddy currents in the geological body, the magnitude of which depends on the electrical conductivity of the geological body. The stronger the electrical conductivity, the stronger the induced eddy currents.

[0016] It can be seen from the above technical solution that the present invention has the following beneficial effects:

[0017] The method for advanced detection of groundwater strata based on transient electromagnetic method arranges horizontal and plumb fan-shaped scanning lines according to the size of the face and geological conditions, uses an ungrounded return line to send a pulse magnetic field underground, and after the primary field disappears, there is a transition process to generate an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface, and the characteristics of the secondary field attenuation with time are measured in the receiver according to different delay times. Then, data processing is performed to judge and analyze the unfavorable geological body and its water content, so as to detect the geological conditions within a certain range and the surrounding adjacent areas, predict the distribution of water content in the surrounding rock in front of the face, and predict the nature, scale, spatial distribution of unfavorable geological bodies such as low-resistance water-bearing faults, mud-filled water-rich caves, mud-containing water-bearing broken zones, etc. that may exist in front of the face, as well as the integrity and water content of the surrounding rock, thereby solving the problems of high cost and large investment of drilling method, destructive operation, and destructive impact on the formation and the surrounding environment. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the route of the present invention;

[0019] Figure 2 This is a schematic diagram of the detection principle of the present invention;

[0020] Figure 3 This is a schematic diagram of the first detection section of the present invention;

[0021] Figure 4 This is a schematic diagram of the first horizontal survey line layout of the present invention;

[0022] Figure 5 This is a schematic diagram of plumb line layout of the present invention;

[0023] Figure 6 This is a schematic diagram of the detection section of the improved solution of the present invention;

[0024] Figure 7 This is a schematic diagram of the horizontal survey line layout of the improved solution of the present invention. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0026] like Figure 1-Figure 7 As shown, a method for advanced detection of groundwater formations based on transient electromagnetic method, the specific steps include:

[0027] S1: Arrange horizontal and plumb sector scanning lines according to the tunnel face size and geological conditions;

[0028] S2: Use an ungrounded return line to send a pulse magnetic field underground. After the primary field disappears, there is a transition process to generate an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface, and the characteristics of the secondary field attenuating with time are measured in the receiver according to different delay times.

[0029] S3: Filter the received signal, perform time correction, calculate the apparent resistivity and apparent depth, and obtain an apparent resistivity distribution result map. According to the apparent resistivity distribution result map, identify and judge the unfavorable geological body and its water content in front of the tunnel face.

[0030] This method detects the geological conditions within 0-80m in front of the tunnel and the surrounding adjacent areas, predicts the water content distribution of the surrounding rock in front of the tunnel face, and predicts the nature, scale, spatial distribution of unfavorable geological bodies such as low-resistance water-containing faults, mud-filled water-rich caves, mud-containing and water-containing broken zones, as well as the integrity and water content of the surrounding rock.

[0031] This method mainly utilizes step waveform electromagnetic pulse excitation, uses an ungrounded return line to transmit a primary field underground, and after the primary field is powered off, measures the change of the induced secondary field generated by the underground medium over time.

[0032] The core specific process of this method is to use an ungrounded loop (or electric source) to send a pulse magnetic field (or electric field) underground, that is, to supply a current pulse square wave on the transmitting loop. At the moment when the trailing edge of the square wave falls, a transient magnetic field that propagates underground will be generated. Under the excitation of this magnetic field, eddy currents will be generated in the geological body. The size of the eddy current depends on the conductivity of the geological body. The stronger the conductivity, the stronger the induced eddy current. After the primary field disappears, the eddy current cannot disappear immediately. It will have a transition process (attenuation process). This transition process will generate an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface. The change of the secondary magnetic field will reflect the electrical properties of the underground medium. The secondary induced electromotive force is measured in the receiver according to different delay times to obtain the characteristics of the secondary field attenuating with time.

[0033] The working arrangement frequency of this method is generally 50-80m each time the forecast distance, and when continuous forecasting is performed, the two cycles should overlap by 10-20m.

[0034] According to the size of the tunnel face and geological conditions, one or more sets of horizontal and plumb sector scanning lines should be arranged with the tunnel face as the center. The horizontal survey line should start from the normal direction of the wireframe and the left wall of the tunnel at 45° outward, and a measuring point should be arranged every 15° in the clockwise direction. When the normal direction of the wireframe is consistent with the axis direction of the tunnel (90°), a measuring point should be arranged every 0.5-1.0m, and sector scanning should be carried out in sequence until the normal direction of the wireframe is 45° outward with the right wall of the tunnel. The plumb line should start from the normal direction of the wireframe and the axis direction of the tunnel at an angle of 45° upward, and a measuring point should be arranged every 15° until the normal direction of the wireframe and the axis direction of the tunnel are 45° downward, and the field collection work is completed.

[0035] like Figure 6-Figure 7 As shown in the figure, the implementation of the detection plan depends on the actual situation on site. If the on-site conditions permit, the measurement point and measurement line layout plan of the improved plan can be selected. According to the on-site construction and observation conditions, the specific parameters of the above observation system can be adjusted appropriately according to the requirements of relevant specifications and the actual situation on site. In the adjustment plan, according to the size of the tunnel face and the geological conditions, one or more groups of horizontal measurement lines are arranged with the tunnel face as the center. The normal direction of the coil is consistent with the tunnel excavation direction. The left wall is used as the starting point and the right wall is used as the end point. A measurement point is arranged every 0.5-1.0m from left to right, and observations are carried out in sequence.

[0036] In the requirements of on-site observation, the tunnel face needs to be cleared in advance to ensure the safety of the advance forecast work and to ensure that the tunnel face is basically flat. During on-site testing, mechanical equipment, metal objects, wires, etc. near the survey line should be removed or avoided as much as possible. The forecast work transmission frequency is generally selected from 2.5-225Hz. Other frequencies can be selected for supplementary detection according to actual needs. The transmission current is generally not less than 1A, and the minimum shutdown time should not be greater than 0.5μs. The equipment supporting the antenna should be made of insulating materials. Antenna operators should wear as few metal objects as possible to ensure safety.

[0037] Finally, special transient electromagnetic processing software is used to filter the received signal, time correct, calculate the apparent resistivity and apparent depth, and obtain the apparent resistivity distribution result map. Based on the apparent resistivity distribution result map, the unfavorable geological body and its water content in front of the tunnel face are identified and judged. Combined with geological data and detection results of other methods, the nature of the target geological body and the occurrence of groundwater are judged.

[0038] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for advanced detection of groundwater strata based on transient electromagnetic method, characterized in that: The specific steps include: S1: Arrange horizontal and plumb sector scanning lines according to the tunnel face size and geological conditions; S2: Use an ungrounded return line to send a pulse magnetic field underground. After the primary field disappears, there is a transition process to generate an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface, and the characteristics of the secondary field attenuating with time are measured in the receiver according to different delay times. S3: Filter the received signal, perform time correction, calculate the apparent resistivity and apparent depth, and obtain an apparent resistivity distribution result map. According to the apparent resistivity distribution result map, identify and judge the unfavorable geological body and its water content in front of the tunnel face.

2. The method for advanced detection of groundwater strata based on transient electromagnetic method according to claim 1 is characterized in that: In step S1, one or more sets of horizontal and plumb sector scanning lines are arranged with the tunnel face as the center.

3. The method for advanced detection of groundwater strata based on transient electromagnetic method according to claim 1 is characterized in that: The horizontal sector scanning survey line arrangement process in step S1 includes: the horizontal survey line preferably starts at an angle of 45° between the normal direction of the wireframe and the left wall of the tunnel, and a measuring point is arranged every 15° in the clockwise direction. When the normal direction of the wireframe is consistent with the tunnel axis direction, a measuring point is arranged every 0.5-1.0m, and sector scanning is performed in sequence until the normal direction of the wireframe is 45° outwards from the right wall of the tunnel.

4. The method for advanced detection of groundwater strata based on transient electromagnetic method according to claim 1 is characterized in that: The plumb bob sector scanning survey line arrangement process in step S1 includes: the plumb line preferably starts from a direction where the normal line of the wireframe is 45° upwards to the tunnel axis, and a survey point is arranged every 15° until the direction where the normal line of the wireframe is 45° downwards to the tunnel axis.

5. The method for advanced detection of groundwater strata based on transient electromagnetic method according to claim 1 is characterized in that: The specific steps of S2 include: A pulse magnetic field is sent underground using an ungrounded loop line, that is, a current pulse square wave is supplied on the transmitting loop line. At the moment when the trailing edge of the square wave falls, a transient magnetic field propagating underground will be generated, and eddy currents will be generated in the geological body under the excitation of the magnetic field. After the primary field disappears, the eddy current cannot disappear immediately. It will have a transition process, which will produce an attenuated secondary field that propagates underground. The secondary magnetic field is received by a receiving coil on the surface. The change of the secondary magnetic field will reflect the electrical properties of the underground medium. The secondary induced electromotive force is measured in the receiver according to different delay times to obtain the characteristic of the secondary field attenuating with time.

6. The method for advanced detection of groundwater strata based on transient electromagnetic method according to claim 5 is characterized in that: The primary transient magnetic field excitation generates eddy currents in the geological body, the magnitude of which depends on the electrical conductivity of the geological body. The stronger the electrical conductivity, the stronger the induced eddy currents.

Citation Information

Cited By

  • Dam hidden danger electromagnetic data interpretation method and system based on anchoring effect

    CN120143280A

  • Advanced geological prediction method for tunnel heading, and device, medium and terminal

    WO2026153402A1