Method, device and equipment for determining remetered electric quantity of electric energy meter and storage medium
By collecting multi-phase data of the power meter, determining the wiring type and abnormality level, and calculating the power supply, the problem of timely discovery and handling of traditional power meters in the case of abnormal voltages is solved, and the measurement accuracy and safety of the power meter are improved.
Patent Information
- Application Number
- CN202411641262.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-18
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2044-11-18
AI Technical Summary
Traditional electricity meters are difficult to detect and deal with in time under abnormal voltage conditions, resulting in a long metering failure, affecting the interests of both power supply and safe power supply.
By collecting three-phase voltage, current, power and power data of the power meter at every preset time, determining the wiring type, and determining the voltage abnormality level in the fault period based on the voltage abnormality conditions in the continuous data, the first and second With the third to recover the power, and finally determine the target recovery power.
It improves the accuracy of the electricity meter to recover the power, can promptly detect and deal with voltage abnormalities, reduce the duration of metering failures, and ensure the safety and fairness of power supply and use.
Smart Images

Figure CN119471551A_ABST
Abstract
Description
Technical Field
[0001] Embodiments of the present invention relate to the field of data processing technology, and in particular to a method, device, equipment and storage medium for determining the amount of additional electricity consumed by an electric energy meter. Background Art
[0002] Traditional methods of detecting metering faults of electric energy meters are mainly weekly inspection, initial inspection, meter reading by meter readers, abnormal power calculation, power consumption inspection, etc. This inspection method causes metering faults to last for a long time and cannot be discovered in time, which can easily cause losses to both the power supplier and the user, and even affect safe power supply. With the advancement of technology, metering automation systems can realize real-time collection, monitoring, analysis and processing of metering meter power information, and can quickly find metering faults.
[0003] Although the multi-function electricity meters currently in use have a voltage loss alarm function, they do not have a judgment alarm for abnormally high or low voltage on the electricity meter, nor do they separately store and count the fault time, current, voltage, power, electricity, and the amount of electricity that needs to be replenished. In addition, due to the limited storage space of the electricity meter, the electricity meter stores historical electricity data at intervals of one minute, and the time is generally one year. If the time exceeds, the previous records will be overwritten. If the voltage abnormality is not discovered and handled for a long time, and the storage time period of the electricity meter is exceeded, it is difficult to confirm the exact fault time by using a computer to read the electricity meter data on site, which affects the accurate replenishment of electricity. Summary of the invention
[0004] The embodiments of the present invention provide a method, device, equipment and storage medium for determining the amount of supplementary electricity of an electric energy meter, which can improve the accuracy of determining the amount of supplementary electricity.
[0005] In a first aspect, an embodiment of the present invention provides a method for determining the amount of electric energy to be supplemented by an electric energy meter, characterized by comprising:
[0006] Collecting first electric energy data of the electric energy meter at first preset intervals; wherein the first electric energy data includes voltage, current, power and electric quantity of three phases;
[0007] When it is determined that the electric energy meter is in working state according to the three-phase current, the connection type of the electric energy meter is obtained; wherein the connection type includes the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter;
[0008] If the voltage in the first electric energy data of the continuous set number meets the abnormal condition corresponding to the wiring type, it is determined that the voltage of the electric energy meter is abnormal during the fault period; wherein the fault period is the period during which the first electric energy data of the continuous set number are collected;
[0009] Determine the abnormality level according to the voltage and current in each first electric energy data within the fault period;
[0010] Determine a first supplementary power, a second supplementary power and a third supplementary power of the electric energy meter during the fault period; wherein the first supplementary power is determined based on preset fault data, the second supplementary power is determined based on the first electric energy data of the continuous set number; the third supplementary power is determined based on the power of the electric energy meter in a historical normal period corresponding to the fault period;
[0011] A target supplementary power of the electric energy meter is determined according to the connection type, the first supplementary power, the second supplementary power, and the third supplementary power.
[0012] In a second aspect, an embodiment of the present invention further provides a device for determining the amount of electric energy meter to compensate for the amount of electric energy meter, including:
[0013] A first electric energy data acquisition module, used for acquiring first electric energy data of the electric energy meter at a first preset time interval; wherein the first electric energy data includes voltage, current, power and electric quantity of three phases;
[0014] A wiring type acquisition module, used for acquiring the wiring type of the electric energy meter when it is determined that the electric energy meter is in a working state according to the three-phase current; wherein the wiring types include the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter;
[0015] A voltage anomaly determination module, configured to determine that the voltage of the electric energy meter is abnormal during a fault period if the voltage in a set number of consecutive first electric energy data meets the abnormal condition corresponding to the wiring type; wherein the fault period is a period during which the set number of consecutive first electric energy data is collected;
[0016] An abnormality level determination module, used to determine the abnormality level according to the voltage and current in each first electric energy data within the fault period;
[0017] a candidate supplementary power determination module, configured to determine a first supplementary power, a second supplementary power, and a third supplementary power of the electric energy meter during the fault period; wherein the first supplementary power is determined based on preset fault data, the second supplementary power is determined based on the first electric energy data of the continuous set number; and the third supplementary power is determined based on the power of the electric energy meter during a historical normal period corresponding to the fault period;
[0018] The target supplementary power determination module is used to determine the target supplementary power of the electric energy meter according to the connection type, the first supplementary power, the second supplementary power and the third supplementary power.
[0019] In a third aspect, an embodiment of the present invention further provides an electronic device, the electronic device comprising:
[0020] at least one processor; and
[0021] a memory communicatively connected to the at least one processor; wherein,
[0022] The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining the amount of supplementary electricity of the electric energy meter described in the embodiment of the present invention.
[0023] In a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining the amount of supplementary electricity consumed by an electric energy meter as described in an embodiment of the present invention when executing the computer instructions.
[0024] The embodiment of the present invention discloses a method, device, equipment and storage medium for determining the amount of electricity to be supplemented by an electric energy meter. The method comprises: collecting first electric energy data of the electric energy meter at first preset intervals; wherein the first electric energy data comprises voltage, current, power and electricity of three phases; when the electric energy meter is determined to be in a working state according to the current of three phases, obtaining the wiring type of the electric energy meter; wherein the wiring types comprise the following three types: three-phase three-wire, three-phase four-wire high supply and high metering, three-phase four-wire high supply and low metering; if the voltage in a continuous set number of first electric energy data meets the abnormal condition corresponding to the wiring type, then determining that the voltage of the electric energy meter is abnormal during the fault period; wherein the fault period is the period during which the voltage in a continuous set number of first electric energy data meets the abnormal condition corresponding to the wiring type. The time period in which the first electric energy data is located; determining the abnormality level according to the voltage and current in each first electric energy data in the fault period; determining the first supplementary power, the second supplementary power and the third supplementary power of the electric energy meter in the fault period; wherein the first supplementary power is determined based on the preset fault data, and the second supplementary power is determined based on a continuously set number of first electric energy data; the third supplementary power is determined based on the power of the electric energy meter in the historical normal period corresponding to the fault period; determining the target supplementary power of the electric energy meter according to the wiring type, the first supplementary power, the second supplementary power and the third supplementary power. The method for determining the supplementary power of the electric energy meter provided by the embodiment of the present invention, when the voltage of the electric energy meter is abnormal in the fault period, determines the target supplementary power based on the abnormality level and the first supplementary power, the second supplementary power and the third supplementary power in the fault period, which can improve the accuracy of determining the supplementary power. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a flow chart of a method for determining the amount of electricity to be supplemented by an electric energy meter in the first embodiment of the present invention;
[0026] Figure 2This is an example diagram of generating sub-fault data in Embodiment 1 of the present invention;
[0027] Figure 3 This is a flow chart for determining a target amount of replenishment electricity in Embodiment 1 of the present invention;
[0028] Figure 4 It is a structural schematic diagram of a device for determining the amount of supplementary electricity of an electric energy meter in the second embodiment of the present invention;
[0029] Figure 5 It is a structural schematic diagram of an electronic device in Embodiment 3 of the present invention. DETAILED DESCRIPTION
[0030] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0031] The metering automation system has the function of analyzing the collected data to determine whether there are any metering anomalies. Since the data is stored in the database, there is no time limit. However, due to the huge number of electricity meters, the current automation system collects electricity meter data at intervals of 15 minutes. If a voltage anomaly occurs within the 15-minute interval and needs to be compensated, the compensation time cannot be accurately determined. If the voltage fluctuates abnormally, only the average value of the voltage data for 15 minutes during the fault period is used to compensate for the electricity, which will also cause errors in the compensated electricity. Moreover, the larger the transformation ratio of the user's transformer, the greater the error. In extreme cases, it will seriously affect the accuracy and fairness of the compensated electricity.
[0032] Embodiment 1
[0033] Figure 1 This is a flow chart of a method for determining the amount of electricity to be replenished by an electric energy meter provided in the first embodiment of the present invention. This embodiment is applicable to the case of determining the amount of electricity to be replenished during a fault period. The method can be executed by a device for determining the amount of electricity to be replenished by an electric energy meter. The device can be implemented in the form of software and / or hardware. Optionally, it can be implemented by an electronic device, which can be a mobile terminal, a PC, or a server. Specifically, it includes the following steps:
[0034] S110, collecting first electric energy data of the electric energy meter at first preset time intervals.
[0035] The first electric energy data includes the voltage, current, power and power of the three phases. The first preset time may be a pre-set time period, such as 15 minutes, 30 minutes, etc., and the first preset time is not limited here. The three phases may include phase A, phase B and phase C, and the power may be the power generated within the first preset time.
[0036] S120, when it is determined according to the three-phase current that the electric energy meter is in a working state, obtaining the connection type of the electric energy meter.
[0037] Among them, the wiring types include the following three types: three-phase three-wire, three-phase four-wire high supply and high metering, and three-phase four-wire high supply and low metering. The method of determining whether the electric energy meter is in a working state based on the current of the three phases can be: compare the current of each phase with the rated current of a set ratio, and determine whether the electric energy meter is in a working state based on the comparison result. Among them, the set ratio can be 0.5%. Specifically, if the current of each phase is greater than 0.5% of the rated current, it indicates that the electric energy meter is in a working state. If the current of one phase is less than or equal to 0.5% of the rated current, it indicates that the electric energy meter is in a non-working state.
[0038] S130: If the voltage in a set number of consecutive first electric energy data meets the abnormal condition corresponding to the wiring type, it is determined that the voltage of the electric energy meter is abnormal during the fault period.
[0039] Among them, the fault period is the period in which the first electric energy data of a continuous set number is collected. The set number is preset, for example, it can be 8. In this embodiment, if the wiring type is three-phase three-wire, the abnormal condition is: the absolute value of the difference between the A phase voltage and the C phase voltage is greater than or equal to the first set value; if the wiring type is three-phase four-wire high supply and high metering, the abnormal condition is: the maximum value of the A phase voltage, the B phase voltage and the C phase voltage is greater than the second set value, and the absolute value of the difference between the smaller two phase voltages is greater than the third set value; if the wiring type is three-phase four-wire high supply and low metering, the abnormal condition is: the maximum value of the A phase voltage, the B phase voltage and the C phase voltage is greater than the fourth set value, and the absolute value of the difference between the smaller two phase voltages is greater than the fifth set value.
[0040] Among them, the first set value can be set to 2V, the second set value can be set to 55V, the third set value can be set to 5V, the fourth set value can be set to 210V, and the fifth set value can be set to 20V.
[0041] Specifically, when the connection type of the electric energy meter is three-phase three-wire, if the voltages in the eight first electric energy data collected continuously all meet the following conditions: the absolute value of the difference between the A-phase voltage and the C-phase voltage is greater than or equal to 2V, then the electric energy meter is determined to have abnormal voltage during the fault period, otherwise, the electric energy meter has no voltage abnormality. When the connection type of the electric energy meter is three-phase four-wire high supply and high timing, if the voltages in the eight first electric energy data collected continuously all meet the following conditions: the maximum value of the A-phase voltage, the B-phase voltage and the C-phase voltage is greater than 55V, and the absolute value of the difference between the two smaller phase voltages is greater than 5V, then the electric energy meter is determined to have abnormal voltage during the fault period, otherwise, the electric energy meter has no voltage abnormality. When the connection type of the electric energy meter is three-phase four-wire high supply and low timing, if the voltages in the eight continuously collected first electric energy data all meet the following conditions: the maximum value of the A phase voltage, the B phase voltage and the C phase voltage is greater than 210V, and the absolute value of the difference between the two smaller phase voltages is greater than 20V, then it is determined that the voltage of the electric energy meter is abnormal during the fault period; otherwise, the electric energy meter has no voltage abnormality.
[0042] S140, determining an abnormality level according to the voltage and current in each first electric energy data within the fault period.
[0043] The abnormal level may include a red level and a yellow level, and the red level is higher than the yellow level. Specifically, the abnormal level may be determined according to the voltage and current in each first electric energy data during the fault period: judging whether the voltage of each phase and the current of each phase during the fault period meet the second abnormal condition corresponding to the wiring type; if the second abnormal condition corresponding to the wiring type is met, the abnormal level is a red level; if the second abnormal condition corresponding to the wiring type is not met, the abnormal level is a yellow level.
[0044] In this embodiment, if the wiring type of the electric energy meter is three-phase three-wire, the second abnormal condition is: the A-phase electric energy data in 8 consecutive first electric energy data all meet the following conditions: the voltage is less than a certain proportion (such as 78%) of the rated voltage and the current is not equal to 0; or, the C-phase electric energy data in 8 consecutive first electric energy data all meet the following conditions: the voltage is less than a certain proportion (such as 78%) of the rated voltage and the current is not equal to 0, then it is determined that the C-phase voltage is undervoltage. If the wiring type of the electric energy meter is three-phase four-wire (high supply and high metering or high supply and low metering), the second abnormal condition is: the A-phase electric energy data in 8 consecutive first electric energy data all meet the following conditions: the voltage is less than a certain proportion (such as 78%) of the rated voltage and the current is not equal to 0; or, the B-phase electric energy data in 8 consecutive first electric energy data all meet the following conditions: the voltage is less than a certain proportion (such as 78%) of the rated voltage and the current is not equal to 0; or, the C-phase electric energy data in 8 consecutive first electric energy data all meet the following conditions: the voltage is less than a certain proportion (such as 78%) of the rated voltage and the current is not equal to 0.
[0045] In this embodiment, when a phase meets the second abnormal condition during the fault period, it is determined that the phase has voltage loss, and a red level alarm message is generated, which includes: the phase where the voltage loss occurs, the specific time of occurrence, and the average voltage of the phase. If any phase does not meet the second abnormal condition, a yellow level alarm message is generated, and the alarm message includes: the unstable voltage of the electric energy meter, the time of occurrence, and the average voltage of each phase.
[0046] S150, determining a first compensatory electric quantity, a second compensatory electric quantity and a third compensatory electric quantity of the electric energy meter during a fault period.
[0047] The first replenishment power is determined based on preset fault data, the second replenishment power is determined based on a set number of consecutive first electric energy data, and the third replenishment power is determined based on the power of the electric energy meter in a historical normal period corresponding to the fault period.
[0048] The preset fault data is obtained by statistically analyzing the sub-fault data acquired every second preset time.
[0049] Specifically, the preset fault data is obtained in the following manner: collecting the second electric energy data of the electric energy meter at every second preset time; when the electric energy meter is determined to be in a working state based on the three-phase current, judging whether a voltage abnormality occurs in the electric energy meter based on the three-phase voltage and the rated voltage; if a voltage abnormality occurs in the electric energy meter, determining the amount of compensatory power within the current second preset time based on the second electric energy data, and storing the second electric energy data and the compensatory power as sub-fault data in the first data table; processing the sub-fault data in the first data table at every first preset time to obtain preset fault data, and storing the preset fault data in the second data table; wherein the preset fault data includes average voltage, average current, average power and accumulated compensatory power.
[0050] Among them, the second electric energy data includes the voltage, current, power and electricity of the three phases, and the second preset time is less than the first preset time. Exemplarily, assuming that the first preset time is set to 15 minutes, the first preset time can be set to 1 minute. Specifically, the method of determining whether the electric energy meter is in a working state according to the current of the three phases can be: comparing the current of each phase with the rated current of a set ratio, and determining whether the electric energy meter is in a working state according to the comparison result. Among them, the set ratio can be 0.5%. Specifically, if the current of each phase is greater than 0.5% of the rated current, it indicates that the electric energy meter is in a working state. If the current of one phase is less than or equal to 0.5% of the rated current, it indicates that the electric energy meter is in a non-working state.
[0051] In this embodiment, the method for judging whether the electric energy meter is faulty based on the three-phase voltage and the rated voltage can be: if the three-phase voltages are all greater than or equal to a first proportion of the rated voltage (which can be set to 95%), then the electric energy meter has no voltage abnormality; if at least one of the three-phase voltages is less than the first proportion of the rated voltage, then the electric energy meter has a voltage abnormality.
[0052] In this embodiment, if a voltage abnormality occurs in the electric energy meter, the method for determining the amount of compensatory electricity within the current second preset time based on the second electric energy data can be: if the voltage of the current phase is less than the first voltage threshold and greater than or equal to the second voltage threshold, the main compensatory electricity amount is determined based on the voltage of the current phase, the rated voltage, the power of the current phase and the second preset time; if the voltage of the current phase is less than the second voltage threshold, the correction coefficient is determined based on the rated power and the power of the current phase; the compensatory electricity amount is determined based on the correction coefficient and the electricity of the current phase.
[0053] The first voltage threshold and the second voltage threshold are determined by the rated voltage. For example, the first voltage threshold may be a first proportion (95%) of the rated voltage, and the second voltage threshold may be a second proportion (60%) of the rated voltage. When the voltage of each phase in the three phases is less than the first voltage threshold and greater than or equal to the second voltage threshold, the formula for determining the main compensation amount based on the voltage of the phase, the rated voltage, the power of the phase and the second preset time can be expressed as: W 追补 =P 本相 *(Un-U 本相 ) / U 本相 *t, where W 追补 To make up for the power, P 本相 is the current phase power, Un is the rated power, U 本相 is the phase voltage, and t is the second preset time. If the phase voltage is less than the second voltage threshold, the calculation formula for determining the correction coefficient based on the rated power and the phase power can be expressed as: K = Pu / P 本相 , where Pu is the rated power, P 本相 The calculation formula for determining the supplementary power based on the correction coefficient and the power of the current phase can be expressed as: W 追补 =(K-1)×electricity.
[0054] In this embodiment, after the replenishment power of each phase is determined, the voltage, current, power, power and replenishment power of each item in the second electric energy data are stored as a sub-fault data in the first data table.
[0055] In this embodiment, after obtaining the first data table, statistics are collected on the sub-fault data in the first data table at intervals of the first preset time, and the average voltage, average current, average power and accumulated replenishment power of each phase within the first preset time are obtained. The number of sub-fault data included in the first preset time is counted, thereby obtaining preset fault data, and the preset fault data is stored in the second data table.
[0056] Optionally, in order to accurately warn of faults, when an abnormal voltage occurs in the electric energy meter, the fault can be graded according to the voltage value. Figure 2 is an example diagram of generating sub-fault data in this embodiment, such as Figure 2 As shown, the process includes the following steps:
[0057] S201, collecting second electric energy data of the electric energy meter at second preset time intervals.
[0058] S202, determine whether the current of each phase is greater than 0.5% of the rated current. If so, the electric energy meter is in working state, and then execute S203; if not, the electric energy meter is in non-working state.
[0059] S203, determine whether the voltage of each phase is less than 95% of the rated voltage. If not, the electric energy meter has no voltage abnormality. If yes, the electric energy meter has a voltage abnormality, and execute S204.
[0060] S204, determine whether the voltage of each phase is less than 90% of the rated voltage, if not, execute S205; if yes, execute S206.
[0061] S205, generating a yellow voltage abnormality warning, and determining the current compensatory power within the second preset time in a first manner, and storing the second electric energy data and the compensatory power as sub-fault data in a first data table.
[0062] S206, determine whether the voltage of each phase is less than 78% of the rated voltage, if not, execute S207, if yes, execute S208.
[0063] S207, generating an orange voltage abnormality warning, and determining the current compensatory power within the second preset time in a first manner, and storing the second electric energy data and the compensatory power as sub-fault data in a first data table.
[0064] S208, determine whether the voltage of each phase is less than 60% of the rated voltage, if not, execute S209; if yes, execute S210.
[0065] S209, generating a red voltage abnormality warning, and determining the current compensatory power within the second preset time in a first manner, and storing the second electric energy data and the compensatory power as sub-fault data in a first data table.
[0066] S210, generating a red voltage abnormality warning, and determining the amount of replenishment power within the current second preset time in a second manner, and storing the second electric energy data and the amount of replenishment power as sub-fault data in a first data table.
[0067] The first method is to determine the main compensation amount based on the current phase voltage, the rated voltage, the current phase power and the second preset time. The second method is to determine the correction coefficient based on the rated power and the current phase power; and determine the compensation amount based on the correction coefficient and the current phase power.
[0068] Specifically, after obtaining the preset fault data, the accumulated replenishment power in the preset fault data in the second data table that falls within the fault period is accumulated to obtain the first replenishment power. The second replenishment power is calculated by accumulating the replenishment power corresponding to the first power data of a set number of consecutive times within the fault period. The calculation formula of the replenishment power corresponding to the first power data can be expressed as: W 追补 =P 本相 *(Un-U 本相 ) / U 本相 *T, where W 追补 To make up for the power, P 本相 is the current phase power, Un is the rated power, U 本相 is the phase voltage, and T is the first preset time. The third replenishment power may be determined by subtracting the power of the electric energy meter in the historical normal period corresponding to the fault period from the power in the fault period to obtain the third replenishment power.
[0069] S150, determining a target supplementary power of the electric energy meter according to the abnormality level, the first supplementary power, the second supplementary power and the third supplementary power.
[0070] In this embodiment, the method of determining the target replenishment power is different according to the abnormality level.
[0071] Optionally, the method of determining the target compensatory power of the electric energy meter according to the abnormal level, the first compensatory power, the second compensatory power and the third compensatory power may be: if the abnormal level is the yellow level, then determining the ratio of the difference between the first compensatory power and the second compensatory power to the second compensatory power; if the absolute value of the ratio is less than the set ratio, then determining the first compensatory power as the target compensatory power; if the absolute value of the ratio is greater than or equal to the set ratio, then determining the ratio of the difference between the first compensatory power and the third compensatory power to the third compensatory power; if the ratio is less than the set ratio, then determining the first compensatory power as the target compensatory power; if the ratio is greater than or equal to the set ratio, then determining the third compensatory power as the target compensatory power.
[0072] The set ratio can be set to 10%, and the difference between the first and second supplementary power and the ratio of the second supplementary power can be expressed as: (W1-W2) / W2. The difference between the first and third supplementary power and the ratio of the third supplementary power can be expressed as: (W1-W3) / W3.
[0073] Optionally, the method of determining the target catch-up power of the electric energy meter based on the connection type, the first catch-up power, the second catch-up power and the third catch-up power can be: if the abnormality level is a red level, then determining the ratio of the difference between the first catch-up power and the third catch-up power and the third catch-up power; if the ratio is less than a set ratio, then determining the first catch-up power as the target catch-up power; if the ratio is greater than or equal to the set ratio, then determining the third catch-up power as the target catch-up power.
[0074] Among them, the setting ratio can be set to 10%.
[0075] For example, Figure 3 is a flow chart for determining the target replenishment power in this embodiment, such as Figure 3 As shown, the process includes the following steps:
[0076] S301, determine the abnormal level according to the voltage and current in each first electric energy data within the fault period, if it is a yellow level, execute S302, if it is a red level, execute S304.
[0077] S302: Determine a ratio of a difference between the first supplementary power and the second supplementary power to the second supplementary power.
[0078] S303, determine whether the absolute value of the ratio is less than 10%, if not, execute S304, if yes, execute S306.
[0079] S304: Determine a ratio of a difference between the first supplementary power and the third supplementary power to the third supplementary power.
[0080] S305, determine whether the absolute value of the ratio is less than 10%, if so, execute S306, if not, execute S307.
[0081] S306: Determine the first supplementary electric power as the target supplementary electric power.
[0082] S307: The third supplementary electric power is determined as the target supplementary electric power.
[0083] The technical solution of this embodiment is to collect the first electric energy data of the electric energy meter at a first preset time interval; wherein the first electric energy data includes the voltage, current, power and electricity of the three phases; when the electric energy meter is determined to be in a working state according to the current of the three phases, the wiring type of the electric energy meter is obtained; wherein the wiring types include the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter; if the voltage in the first electric energy data of a continuous set number meets the abnormal condition corresponding to the wiring type, it is determined that the voltage of the electric energy meter is abnormal during the fault period; wherein the fault period is the period during which the voltage of the first electric energy data of a continuous set number is collected. The time period in which the first electric energy data of the amount is located; the abnormality level is determined according to the voltage and current in each first electric energy data in the fault period; the first compensatory power, the second compensatory power and the third compensatory power of the electric energy meter in the fault period are determined; wherein the first compensatory power is determined based on the preset fault data, the second compensatory power is determined based on the first electric energy data of a set number of consecutive times; the third compensatory power is determined based on the power of the electric energy meter in the historical normal period corresponding to the fault period; the target compensatory power of the electric energy meter is determined according to the wiring type, the first compensatory power, the second compensatory power and the third compensatory power. The method for determining the compensatory power of the electric energy meter provided by the embodiment of the present invention, when the voltage of the electric energy meter is abnormal in the fault period, the target compensatory power is determined based on the abnormality level and the first compensatory power, the second compensatory power and the third compensatory power in the fault period, which can improve the accuracy of determining the compensatory power.
[0084] Embodiment 2
[0085] Figure 4 is a schematic diagram of the structure of a device for determining the amount of electric energy meter supplementary electricity provided by the second embodiment of the present invention, such as Figure 4 As shown, the device comprises:
[0086] The first electric energy data acquisition module 410 is used to collect first electric energy data of the electric energy meter at a first preset time interval; wherein the first electric energy data includes voltage, current, power and electric quantity of three phases;
[0087] The wiring type acquisition module 420 is used to acquire the wiring type of the electric energy meter when it is determined that the electric energy meter is in a working state according to the three-phase current; wherein the wiring types include the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter;
[0088] The voltage anomaly determination module 430 is used to determine that the voltage of the electric energy meter is abnormal during a fault period if the voltage in the first electric energy data of a continuous set number meets the abnormal condition corresponding to the wiring type; wherein the fault period is the period during which the first electric energy data of a continuous set number are collected;
[0089] The abnormality level determination module 440 is used to determine the abnormality level according to the voltage and current in each first electric energy data within the fault period;
[0090] The candidate supplementary power determination module 450 is used to determine the first supplementary power, the second supplementary power and the third supplementary power of the electric energy meter in the fault period; wherein the first supplementary power is determined based on the preset fault data, the second supplementary power is determined based on the first electric energy data of a set number of consecutive times; the third supplementary power is determined based on the power of the electric energy meter in the historical normal period corresponding to the fault period;
[0091] The target supplementary power determination module 460 is used to determine the target supplementary power of the electric energy meter according to the connection type, the first supplementary power, the second supplementary power and the third supplementary power.
[0092] Optionally, if the wiring type is three-phase three-wire, the abnormal condition is: the absolute value of the difference between the phase A voltage and the phase C voltage is greater than or equal to the first set value; if the wiring type is three-phase four-wire high supply and high measurement, the abnormal condition is: the maximum value of the phase A voltage, the phase B voltage and the phase C voltage is greater than the second set value, and the absolute value of the difference between the two smaller phase voltages is greater than the third set value; if the wiring type is three-phase four-wire high supply and low measurement, the abnormal condition is: the maximum value of the phase A voltage, the phase B voltage and the phase C voltage is greater than the fourth set value, and the absolute value of the difference between the two smaller phase voltages is greater than the fifth set value.
[0093] Optionally, the abnormality level determination module 440 is further configured to:
[0094] Determine whether the voltage of each phase and the current of each phase during the fault period meet the second abnormal condition corresponding to the wiring type;
[0095] If the second abnormal condition corresponding to the wiring type is met, the abnormal level is a red level; if the second abnormal condition corresponding to the wiring type is not met, the abnormal level is a yellow level.
[0096] Optionally, it also includes: a preset fault data acquisition module, used to:
[0097] Collecting second electric energy data of the electric energy meter at every second preset time; wherein the second electric energy data includes voltage, current, power and electric quantity of three phases, and the second preset time is less than the first preset time;
[0098] When the electric energy meter is determined to be in working state according to the three-phase current, whether the electric energy meter has voltage abnormality is determined based on the three-phase voltage and the rated voltage;
[0099] If the voltage of the electric energy meter is abnormal, the amount of replenishment power within the current second preset time is determined according to the second electric energy data, and the second electric energy data and the amount of replenishment power are stored as sub-fault data in the first data table;
[0100] Sub-fault data in the first data table at intervals of a first preset time are processed to obtain preset fault data, and the preset fault data is stored in the second data table; wherein the preset fault data includes average voltage, average current, average power and accumulated replenishment power.
[0101] Optionally, the preset fault data acquisition module is also used for:
[0102] If the current phase voltage is less than the first voltage threshold and greater than or equal to the second voltage threshold, the main compensation amount is determined based on the current phase voltage, the rated voltage, the current phase power and the second preset time; wherein the first voltage threshold and the second voltage threshold are determined by the rated voltage;
[0103] If the current phase voltage is less than the second voltage threshold, a correction factor is determined according to the rated power and the current phase power;
[0104] The supplementary power is determined based on the correction coefficient and the power of the current phase.
[0105] Optionally, the target replenishment power determination module 460 is further configured to:
[0106] If the abnormal level is yellow level, determining the ratio of the difference between the first supplementary power and the second supplementary power to the second supplementary power;
[0107] If the absolute value of the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power;
[0108] If the absolute value of the ratio is greater than or equal to the set ratio, then determining the ratio of the difference between the first supplementary power and the third supplementary power to the third supplementary power;
[0109] If the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power;
[0110] If the ratio is greater than or equal to the set ratio, the third replenishment power is determined as the target replenishment power.
[0111] Optionally, the target replenishment power determination module 460 is further configured to:
[0112] If the abnormal level is red, determining the ratio of the difference between the first supplementary power and the third supplementary power to the third supplementary power;
[0113] If the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power;
[0114] If the ratio is greater than or equal to the set ratio, the third replenishment power is determined as the target replenishment power.
[0115] The above device can execute the methods provided by all the above embodiments of the present invention, and has the corresponding functional modules and beneficial effects of executing the above methods. For technical details not described in detail in this embodiment, please refer to the methods provided by all the above embodiments of the present invention.
[0116] Embodiment 3
[0117] Figure 5 A schematic diagram of an electronic device 10 that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, the connections and relationships between the components, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0118] like Figure 5 As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.
[0119] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0120] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as a method for determining the amount of electricity to be supplemented by an electric energy meter.
[0121] In some embodiments, the method for determining the amount of electricity to be recharged by the electric energy meter may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the method for determining the amount of electricity to be recharged by the electric energy meter described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to execute the method for determining the amount of electricity to be recharged by the electric energy meter in any other appropriate manner (e.g., by means of firmware).
[0122] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0123] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0124] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0125] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0126] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.
[0127] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.
[0128] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0129] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for determining the amount of electricity to be supplemented by an electric energy meter, characterized in that: include: Collecting first electric energy data of the electric energy meter at first preset intervals; wherein the first electric energy data includes voltage, current, power and electric quantity of three phases; When it is determined that the electric energy meter is in working state according to the three-phase current, the connection type of the electric energy meter is obtained; wherein the connection type includes the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter; If the voltage in the first electric energy data of the continuous set number meets the first abnormal condition corresponding to the wiring type, it is determined that the voltage of the electric energy meter is abnormal during the fault period; wherein the fault period is the period during which the first electric energy data of the continuous set number is collected; Determine the abnormality level according to the voltage and current in each first electric energy data within the fault period; Determine a first supplementary power, a second supplementary power and a third supplementary power of the electric energy meter during the fault period; wherein the first supplementary power is determined based on preset fault data, the second supplementary power is determined based on the first electric energy data of the continuous set number; the third supplementary power is determined based on the power of the electric energy meter in a historical normal period corresponding to the fault period; A target supplementary power of the electric energy meter is determined according to the abnormality level, the first supplementary power, the second supplementary power, and the third supplementary power.
2. The method according to claim 1, characterized in that If the wiring type is three-phase three-wire, the abnormal condition is: the absolute value of the difference between the phase A voltage and the phase C voltage is greater than or equal to the first set value; if the wiring type is three-phase four-wire high supply and high measurement, the abnormal condition is: the maximum value of the phase A voltage, the phase B voltage and the phase C voltage is greater than the second set value, and the absolute value of the difference between the two smaller phase voltages is greater than the third set value; if the wiring type is three-phase four-wire high supply and low measurement, the abnormal condition is: the maximum value of the phase A voltage, the phase B voltage and the phase C voltage is greater than the fourth set value, and the absolute value of the difference between the two smaller phase voltages is greater than the fifth set value.
3. The method according to claim 1 or 2, characterized in that: Determining the abnormality level according to the voltage and current in each first electric energy data within the fault period includes: Determine whether the voltage of each phase and the current of each phase during the fault period meet the second abnormal condition corresponding to the wiring type; If the second abnormal condition corresponding to the wiring type is met, the abnormal level is a red level; if the second abnormal condition corresponding to the wiring type is not met, the abnormal level is a yellow level.
4. The method according to claim 1, characterized in that: The method for obtaining the preset fault data is: Collecting second electric energy data of the electric energy meter at every second preset time; wherein the second electric energy data includes voltage, current, power and electric quantity of three phases, and the second preset time is less than the first preset time; When it is determined that the electric energy meter is in a working state according to the three-phase current, judging whether a voltage abnormality occurs in the electric energy meter based on the three-phase voltage and the rated voltage; If the voltage of the electric energy meter is abnormal, the amount of replenishment power within the current second preset time is determined according to the second electric energy data, and the second electric energy data and the amount of replenishment power are stored as sub-fault data in the first data table; The sub-fault data in the first data table at intervals of a first preset time are processed to obtain preset fault data, and the preset fault data is stored in the second data table; wherein the preset fault data includes average voltage, average current, average power and accumulated replenishment power.
5. The method according to claim 4, characterized in that Then determining the amount of replenishment power within the current second preset time according to the second power data includes: If the current phase voltage is less than the first voltage threshold and greater than or equal to the second voltage threshold, the main compensation amount is determined based on the current phase voltage, the rated voltage, the current phase power and the second preset time; wherein the first voltage threshold and the second voltage threshold are determined by the rated voltage; If the current phase voltage is less than the second voltage threshold, a correction factor is determined according to the rated power and the current phase power; The supplementary power is determined based on the correction coefficient and the current phase power.
6. The method according to claim 3, characterized in that: Determining a target supplementary power of the electric energy meter according to the abnormal level, the first supplementary power, the second supplementary power, and the third supplementary power includes: If the abnormal level is yellow level, determining a ratio of a difference between the first supplementary power and the second supplementary power to the second supplementary power; If the absolute value of the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power; If the absolute value of the ratio is greater than or equal to the set ratio, determining the ratio of the difference between the first supplementary power and the third supplementary power to the third supplementary power; If the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power; If the ratio is greater than or equal to the set ratio, the third supplementary electric power is determined as the target supplementary electric power.
7. The method according to claim 3, characterized in that Determining a target supplementary power of the electric energy meter according to the connection type, the first supplementary power, the second supplementary power, and the third supplementary power includes: If the abnormal level is red, determining a ratio of a difference between the first supplementary power and the third supplementary power to the third supplementary power; If the ratio is less than the set ratio, the first replenishment power is determined as the target replenishment power; If the ratio is greater than or equal to the set ratio, the third supplementary electric power is determined as the target supplementary electric power.
8. A device for determining the amount of supplementary electricity of an electric energy meter, characterized in that: include: A first electric energy data acquisition module, used for acquiring first electric energy data of the electric energy meter at a first preset time interval; wherein the first electric energy data includes voltage, current, power and electric quantity of three phases; A wiring type acquisition module, used for acquiring the wiring type of the electric energy meter when it is determined that the electric energy meter is in a working state according to the three-phase current; wherein the wiring types include the following three types: three-phase three-wire, three-phase four-wire high supply and high meter, and three-phase four-wire high supply and low meter; A voltage anomaly determination module, configured to determine that the voltage of the electric energy meter is abnormal during a fault period if the voltage in a set number of consecutive first electric energy data meets the abnormal condition corresponding to the wiring type; wherein the fault period is a period during which the set number of consecutive first electric energy data is collected; An abnormality level determination module, used to determine the abnormality level according to the voltage and current in each first electric energy data within the fault period; a candidate supplementary power determination module, configured to determine a first supplementary power, a second supplementary power, and a third supplementary power of the electric energy meter during the fault period; wherein the first supplementary power is determined based on preset fault data, the second supplementary power is determined based on the first electric energy data of the continuous set number; and the third supplementary power is determined based on the power of the electric energy meter during a historical normal period corresponding to the fault period; The target supplementary power determination module is used to determine the target supplementary power of the electric energy meter according to the connection type, the first supplementary power, the second supplementary power and the third supplementary power.
9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining the supplementary electricity quantity of the electric energy meter according to any one of claims 1-7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining the supplementary electricity quantity of an electric energy meter according to any one of claims 1 to 7 when executing the computer instructions.
Citation Information
Patent Citations
Method for compensating electric charge during in case of abnormal voltage
CN111242701A
Electric quantity compensation intelligent accounting terminal
CN111766465A
Intelligent electric energy meter compensation electric quantity calculation method, system, device and storage medium
CN112485752A
Method and system for monitoring false wiring mode of three-phase intelligent electric meter in real time
CN114518549A