Gate and gate management method

By integrating WIFI modules and NFC tag boards on the gate, the WIFI and NFC functions of the mobile terminal are used to achieve rapid connection with the gate, which solves the problem of low gate management efficiency in the existing technology and simplifies the configuration and operation and maintenance process of the gate.

CN119763234APending Publication Date: 2025-04-04HANGZHOU HIKVISION DIGITAL TECHNOLOGY CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411835881.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-12
Publication Date
2025-04-04

AI Technical Summary

Technical Problem

The existing gate management system requires the management of laptops and network cables, and the rapid connection between gates and laptops cannot be achieved, resulting in low management efficiency and high burden on management personnel.

Method used

A gate is designed, equipped with a first authority board and an NFC tag board. The first authority board is equipped with a WIFI module. The NFC tag board is arranged in the first box of the gate. The rapid connection and management of the mobile terminal and the gate are realized through WIFI and NFC technologies.

Benefits of technology

It realizes that the gate can be managed without carrying a laptop and network cable, which reduces the burden on managers and improves the efficiency of gate management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119763234A_ABST
    Figure CN119763234A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a gate and a gate management method, and relates to the technical field of gates. The gate machine comprises a first authority board and an NFC label board, the first authority board is provided with a WIFI module, and the NFC label board is arranged in a first box body of the gate machine; after the WIFI module is started by the first permission board, the WIFI module is set to be in an AP mode, so that any mobile terminal is in WIFI connection with the first permission board under the condition that the mobile terminal enters a signal coverage range corresponding to the AP mode and a WIFI function is started; the NFC tag board is in NFC connection with the mobile terminal under the condition that the mobile terminal starts an NFC function and is close to the NFC tag board, so that the mobile terminal reads jump path information of the gate management interface and jumps to the gate management interface based on the jump path information; and the first permission board responds to a gate management instruction received based on the WIFI connection. Based on this, by applying the scheme provided by the embodiment of the invention, the burden of management personnel can be reduced, and the management efficiency of the gate machine can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of gate machines, and in particular to a gate machine and a gate machine management method. Background Art

[0002] The gate is a channel management device used to manage the flow of people and regulate the entry and exit of pedestrians. It is also called a personnel channel, including swing gates, wing gates, roller gates, etc. The basic components of the gate include a box and a blocking device, also called a blocking body. People can obtain the gate pass authority by scanning their faces, scanning codes, swiping cards, etc., so that the blocking body of the gate can open the channel and release people by rotating, swinging, shrinking, and retracting the box.

[0003] Usually, depending on the installation location of the gate and the application requirements, it is necessary to configure the relevant channel information of the gate, such as the indicator light effect, the passage time, etc. Once the gate fails, for example, the barrier cannot be retracted, the card swiping sensing area fails, etc., it is necessary to troubleshoot and repair the gate. In addition, in order to ensure the normal operation of the gate, daily maintenance may also be required.

[0004] Currently, gate machines are usually managed using wired networks. Therefore, when performing information configuration, troubleshooting and other operations on the gate machine, it is necessary to connect the gate machine and a laptop computer via a network cable to achieve communication between the gate machine and the laptop computer, so that the gate machine can be managed by operating the laptop computer.

[0005] However, in the above-mentioned related technologies, every time the gate is managed, it is necessary to carry a laptop and an Internet cable to the location of the gate. Moreover, for different gates, when connecting the gate and the laptop through the Internet cable, it is necessary to distinguish the IP (Internet Protocol) address of the gate, and it is impossible to achieve a fast connection between the gate and the laptop. Therefore, it not only brings a great burden to the management personnel, but also makes the gate management efficiency low. Summary of the invention

[0006] The purpose of the embodiments of the present application is to provide a gate management system, a management method and a gate, so as to reduce the burden on management personnel and improve the management efficiency of the gate. The specific technical solution is as follows:

[0007] In a first aspect, an embodiment of the present application provides a gate, a first authority board and an NFC tag board, wherein the first authority board is provided with a WIFI module, and the NFC tag board is provided in a first box of the gate;

[0008] The first authority board is used to set the WIFI module to AP mode after starting the WIFI module, so that any mobile terminal can establish a WIFI connection with the first authority board when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function;

[0009] The NFC tag board is used to establish an NFC connection with the mobile terminal when the mobile terminal turns on the NFC function and is close to the NFC tag board, so that the mobile terminal reads the jump path information of the gate management interface recorded by the NFC tag board, and jumps to the gate management interface based on the jump path information;

[0010] The first authority panel is also used to respond to gate management instructions received based on the WIFI connection; wherein the gate management instructions are instructions generated based on management operations performed by the user in the gate management interface.

[0011] Optionally, in a specific implementation, the first authority board is further used to send the jump path information to the NFC tag board through a specified transmission protocol after power-on;

[0012] The NFC tag board is also used to record the received jump path information.

[0013] Optionally, in a specific implementation, the first authority board responds to the gate management instruction received based on the WIFI connection, including:

[0014] Receiving a gate information update instruction based on the WIFI connection, and updating the recorded gate information of the gate to the information indicated by the gate information update instruction;

[0015] and / or,

[0016] A gate information reading instruction is received based on the WIFI connection, and the gate information indicated by the gate information reading instruction is pushed to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

[0017] Optionally, in a specific implementation, a protrusion is provided on the upper surface of the first box body, and the protrusion protrudes in a direction away from the upper surface of the first box body, a lens assembly is provided in the protrusion, and the lens of the lens assembly is exposed to an opening on the shell of the protrusion.

[0018] Optionally, in a specific implementation, at least a partial area of ​​the lower surface of the protrusion is connected to the upper surface of the first box body.

[0019] Optionally, in a specific implementation, the NFC label plate is disposed in the raised portion, and the NFC label plate is disposed on the top or side of the lens assembly.

[0020] Optionally, in a specific implementation, the first authority plate is disposed inside the first box and connected to the NFC tag plate via a cable, or the first authority plate is disposed inside the raised portion.

[0021] Optionally, in a specific implementation, the NFC label plate is disposed at an upper end of the front surface of the first box body.

[0022] Optionally, in a specific implementation, the first authority board responds to the gate management instruction received based on the WIFI connection, including:

[0023] Respond to a first gate management instruction for a designated passage direction of the gate received based on the WIFI connection.

[0024] Optionally, in a specific implementation, the gate machine further includes: a second authority board, the second authority board is arranged inside the second box of the gate machine, and the second authority board is communicatively connected with the first authority board;

[0025] The first authority board is further used to receive a second gate management instruction for the opposite traffic direction of the designated traffic direction based on the WIFI connection, and send the second gate management instruction to the second authority board;

[0026] The second authority board is used to respond to the received second gate management instruction.

[0027] In a second aspect, an embodiment of the present application provides a gate management method, which is applied to a gate, wherein the gate includes: a first control board and a communication board, wherein the communication board is disposed in a box on one side of the gate; the method includes:

[0028] The first control panel is communicatively connected with the mobile terminal;

[0029] The communication board is connected to the mobile terminal for communication, so that the mobile terminal obtains the jump path information of the gate management interface, and jumps to the gate management interface based on the jump path information; wherein the communication board is arranged in a box on one side of the gate;

[0030] The first control panel responds to a gate management instruction received based on a communication connection with the mobile terminal; wherein the gate management instruction is an instruction generated based on a management operation performed by a user on the gate management interface.

[0031] Optionally, in a specific implementation, the first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including:

[0032] Receiving a gate information update instruction based on a communication connection with the mobile terminal, and updating the recorded gate information of the gate to the information indicated by the gate information update instruction;

[0033] and / or,

[0034] A gate information reading instruction is received based on the communication connection with the mobile terminal, and the gate information indicated by the gate information reading instruction is pushed to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

[0035] Optionally, in a specific implementation, the first control board is communicatively connected with the mobile terminal, including:

[0036] The first control panel of the gate is communicatively connected to the mobile terminal via a communication connection line.

[0037] Optionally, in a specific implementation, the first control board is provided with a wireless communication module;

[0038] The first control panel establishes a communication connection with the mobile terminal, including:

[0039] The first control board establishes a wireless communication connection with the mobile terminal through the wireless communication module;

[0040] The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including:

[0041] The first control board responds to gate management instructions received based on the wireless communication connection.

[0042] Optionally, in a specific implementation, the first control board is provided with a WIFI module as the wireless communication module;

[0043] The first control panel establishes a communication connection with the mobile terminal, including:

[0044] After starting the WIFI module, the first control board sets the WIFI module to AP mode, so that the mobile terminal can establish a WIFI connection with the first control board when entering a signal coverage range corresponding to the AP mode and turning on the WIFI function;

[0045] The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including:

[0046] The first control panel responds to gate management instructions received based on the WIFI connection.

[0047] Optionally, in a specific implementation, the communication board is provided with a mobile communication module; wherein the mobile communication module at least includes: a 4G communication module, or a 5G communication module; the communication board is communicatively connected with the mobile terminal, including:

[0048] The communication board establishes a mobile communication connection with the mobile terminal through the mobile communication module.

[0049] Optionally, in a specific implementation, the communication board is provided with an NFC tag board; the communication board of the gate is communicatively connected with the mobile terminal so that the mobile terminal obtains the jump path information of the preset gate management interface, including:

[0050] When the mobile terminal turns on the NFC function and is close to the communication board, the communication board establishes an NFC connection with the mobile terminal, so that the mobile terminal reads the jump path information of the gate management interface recorded by the communication board.

[0051] Optionally, in a specific implementation, the method further includes:

[0052] After being powered on, the first control board sends the jump path information to the communication board through a specified transmission protocol;

[0053] The communication board records the received jump path information.

[0054] Optionally, in a specific implementation, a protrusion is provided on the upper surface of the first box body, and the protrusion protrudes in a direction away from the upper surface of the first box body, a lens assembly is provided in the protrusion, and the lens of the lens assembly is exposed to an opening on the shell of the protrusion.

[0055] Optionally, in a specific implementation, at least a partial area of ​​the lower surface of the protrusion is connected to the upper surface of the first box body.

[0056] Optionally, in a specific implementation, the NFC tag plate is disposed in the raised portion, and the first NFC plate is disposed on the top or side of the lens assembly.

[0057] Optionally, in a specific implementation, the first control board is disposed inside the first box and connected to the first NFC board via a cable; or, the first control board is disposed in the raised portion.

[0058] Optionally, in a specific implementation, the NFC label plate is disposed at an upper end of the front surface of the first box body.

[0059] Optionally, in a specific implementation, the first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including:

[0060] The method responds to a first gate management instruction for a designated passage direction of the gate received based on a communication connection with the mobile terminal.

[0061] Optionally, in a specific implementation, the gate further includes: a second box and a second control board disposed inside the second box, the second control board being communicatively connected to the first control board; the method further includes:

[0062] The first control board receives a second gate management instruction for a traffic direction opposite to the designated traffic direction based on a communication connection with the mobile terminal, and sends the second gate management instruction to the second control board;

[0063] The second control panel responds to the received second gate management instruction.

[0064] Beneficial effects of the embodiments of the present application:

[0065] As can be seen from the above, by applying the solution provided by the embodiment of the present application, when managing the gate, the mobile terminal with the WIFI function and NFC function turned on can be directly brought close to the NFC tag board set on the first box of the gate to achieve WIFI connection between the mobile terminal and the first authority board, and by reading the jump path information of the gate management interface recorded by the NFC tag board, jump to the gate management interface based on the above jump path information. Furthermore, a gate management instruction can be generated based on the management operation of the user in the gate management interface displayed by the mobile terminal, and the first authority board receives the above gate management instruction based on the WIFI connection with the mobile terminal, and responds to the above gate management instruction to achieve management of the gate.

[0066] In this way, by applying the solution provided by the embodiment of the present application, when managing the gate, the gate can be managed by using a mobile terminal with WIFI and NFC functions turned on to approach the NFC tag board set on the first box of the gate, without having to carry a laptop and an Internet cable to the location of the gate, and without having to find the IP address of the gate separately, which can reduce the management burden of the management personnel and improve the efficiency of gate management. Therefore, the solution provided by the embodiment of the present application is a solution for fast connection pairing and fast configuration during gate installation and operation, which greatly simplifies the gate configuration and operation process and can realize convenient management of the gate. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application, and for ordinary technicians in this field, other embodiments can also be obtained based on these drawings.

[0068] Figure 1 A schematic diagram of the structure of a gate provided in an embodiment of the present application;

[0069] FIG. 2 (a) to FIG. 2 (c) are schematic diagrams of the structure of a gate provided in an embodiment of the present application;

[0070] FIG3 (a) is a schematic diagram of the structure of a first authority board provided in an embodiment of the present application;

[0071] FIG3 (b) is a schematic diagram of the structure of an NFC tag board provided in an embodiment of the present application;

[0072] Figure 4 A login interface of a gate management interface provided in an embodiment of the present application;

[0073] FIG5 (a) is a signaling interaction diagram of a first authority board, an NFC tag board, and a mobile terminal provided in an embodiment of the present application;

[0074] FIG5( b ) is another signaling interaction diagram of a first authority board, an NFC tag board, and a mobile terminal provided in an embodiment of the present application;

[0075] FIG6 (a) is a schematic diagram of the structure of a protrusion provided on the upper surface of a first box body provided in an embodiment of the present application;

[0076] FIG6 (b) is a schematic diagram of a specific example of a gate provided in an embodiment of the present application;

[0077] Figure 7 A flow chart of a gate management method provided in an embodiment of the present application. DETAILED DESCRIPTION

[0078] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field based on the present application belong to the scope of protection of the present application.

[0079] Currently, in the relevant technology, every time a gate is managed, it is necessary to carry a laptop and an Internet cable to the location of the gate. Moreover, for different gates, when connecting the gate and the laptop via an Internet cable, it is necessary to distinguish the IP address of the gate, and it is impossible to achieve a quick connection between the gate and the laptop. Therefore, it not only brings a great burden to the management personnel, but also makes the efficiency of gate management low.

[0080] In order to solve the above technical problems, the embodiments of the present application provide a gate and a gate management method.

[0081] Among them, the gate can be applied to various application scenarios for managing the entry and exit of personnel, such as gates set at station entrances and exits, gates set at factory entrances and exits, gates set at residential entrances and exits, etc.; and the gate can be applied to various gate management scenarios, such as configuring relevant channel information for newly installed gates, performing daily maintenance on installed gates, troubleshooting and repairing faulty gates, etc. In addition, the gate can be various types of gates, such as swing gates, wing gates, roller gates, etc. Above, the application scenarios, management scenarios and types of the gates provided in the embodiments of the present application are not specifically limited.

[0082] Before specifically describing a gate machine and a gate machine management method provided in the above-mentioned embodiment of the present application, the relevant technical terms involved in the embodiment of the present application are first described.

[0083] 1. Gate. The gate is a channel management device used to manage the flow of people and regulate the entry and exit of pedestrians. Generally, the basic components of the gate include a box and a blocking device, also known as a blocking body. In some scenarios, the gate may include two boxes, and the passage between the two boxes is a passage for people to walk through the gate, while in other scenarios, the gate may also include only one box, which forms a passage for people to walk through the gate with the wall of the building. Among them, the gate can also be called a personnel passage, and the box included in the gate can be called a side channel. Therefore, two side channels can constitute a personnel passage, and the passage between the two side channels is the passage channel. According to the installation position of the two side channels, the two side channels can be called the main channel and the slave channel respectively. Generally, the side channel on the right side of the passage direction of the gate can be defaulted as the main channel, and the side channel on the left side of the passage direction of the gate can be defaulted as the slave channel.

[0084] 2. AP mode. AP mode is the access point mode, also known as the infrastructure mode, where AP is the abbreviation of Access Point Wireless, also known as wireless AP, or wireless access point.

[0085] 3. NFC. NFC stands for Near Field Communication, a short-range high-frequency wireless communication technology. Devices using NFC technology can exchange data when they are close to each other. Usually, NFC includes an NFC module and an NFC antenna, and an NFC module is usually composed of a high-speed microcontroller, a radio frequency chip and a matching circuit.

[0086] Among them, a gate provided by an embodiment of the present application includes: a first authority board and an NFC tag board, wherein the first authority board is provided with a WIFI module, and the NFC tag board is provided in a first box of the gate;

[0087] The first authority board is used to set the WIFI module to AP mode after starting the WIFI module, so that any mobile terminal can establish a WIFI connection with the first authority board when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function;

[0088] The NFC tag board is used to establish an NFC connection with the mobile terminal when the mobile terminal turns on the NFC function and is close to the NFC tag board, so that the mobile terminal reads the jump path information of the gate management interface recorded by the NFC tag board, and jumps to the gate management interface based on the jump path information;

[0089] The first authority panel is also used to respond to gate management instructions received based on the WIFI connection; wherein the gate management instructions are instructions generated based on management operations performed by the user in the gate management interface.

[0090] Among them, the first permission board is a hardware unit that can connect to the mobile terminal through WIFI and has some gate management functions; and the NFC tag board is a hardware unit that can connect to the mobile terminal through NFC to achieve data exchange with the mobile terminal and has a data recording function. Moreover, in the embodiment of the present application, it is not limited that the first permission board and the NFC tag board must be separate hardware units in physical form. The first permission board and the NFC tag board can exist independently or be integrated into the same physical hardware unit.

[0091] As can be seen from the above, by applying the solution provided by the embodiment of the present application, when managing the gate, the mobile terminal with the WIFI function and NFC function turned on can be directly brought close to the NFC tag board set on the first box of the gate to achieve WIFI connection between the mobile terminal and the first authority board, and by reading the jump path information of the gate management interface recorded by the NFC tag board, jump to the gate management interface based on the above jump path information. Furthermore, a gate management instruction can be generated based on the management operation of the user in the gate management interface displayed by the mobile terminal, and the first authority board receives the above gate management instruction based on the WIFI connection with the mobile terminal, and responds to the above gate management instruction to achieve management of the gate.

[0092] In this way, by applying the solution provided by the embodiment of the present application, when managing the gate, the gate can be managed by using a mobile terminal with WIFI and NFC functions turned on to approach the NFC tag board set on the first box of the gate, without having to carry a laptop and an Internet cable to the location of the gate, and without having to find the IP address of the gate separately, which can reduce the management burden of the management personnel and improve the efficiency of gate management. Therefore, the solution provided by the embodiment of the present application is a solution for fast connection pairing and fast configuration during gate installation and operation, which greatly simplifies the gate configuration and operation process and can realize convenient management of the gate.

[0093] Below, in conjunction with the accompanying drawings, a gate provided in an embodiment of the present application is described in detail.

[0094] Figure 1 This is a schematic diagram of the structure of a gate provided in an embodiment of the present application. Figure 1 As shown, the gate includes: a first authority board 101 and an NFC tag board 102, wherein the first authority board 101 is provided with a WIFI module 1011, and the NFC tag board 102 is arranged in the first box 100 of the gate.

[0095] in, Figure 1The positional relationship between the NFC tag plate 102 and the first box 100 shown is only used to indicate that the NFC tag plate 102 is set in the first box 100, but does not limit the NFC tag plate 102 to be located inside the first box 100. In addition, in the embodiment of the present application, the NFC tag plate 102 can be set at any position of the first box 100, as long as the mobile terminal with the NFC function turned on can establish an NFC connection between the NFC tag plate 102 and the mobile terminal when it is close to the first NFC tag 102. For example, the NFC tag plate can be directly set on any outer surface of the first box 1001. For example, as shown in FIG. 2 (a), the NFC tag plate 102 can be set on the upper surface of the first box 100. For another example, as shown in FIG. 2 (b), the NFC tag plate 102 can be set on the side surface of the first box 100. For another example, the NFC tag plate 102 can be set inside the first box 100. In other words, the embodiment of the present application does not limit the setting position of the NFC tag plate 102 in the first box 100.

[0096] Based on this, optionally, in a specific implementation, in the gate provided in the embodiment of the present application, the NFC tag plate 102 is disposed at the upper end of the front surface of the first box 100. For example, as shown in FIG2(c), the position pointed by the arrow is the setting position of the NFC tag plate 102 on the first box 100.

[0097] Similarly, the embodiment of the present application does not limit the location of the first authority plate 101. For example, the first authority plate 101 can be set on the outer surface of the first box 100, or can be set inside the first box 100; and, for a gate machine including two boxes, the first authority plate 100 can also be set in another box other than the first box 100, for example, set on the outer surface or inside the first box. In other words, the first authority plate 101 and the NFC tag plate 102 can be set in the same box of the gate machine, or can be set in different boxes of the gate machine.

[0098] The first authority board 101 is used to set the WIFI module 1011 to AP mode after starting the WIFI module 1011, so that any mobile terminal can establish a WIFI connection with the first authority board 101 when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function.

[0099] The NFC tag board 102 is used to establish an NCF connection with the mobile terminal when the NFC function of the mobile terminal is turned on and the mobile terminal is close to the NFC tag board 102, so that the mobile terminal reads the jump path information of the gate management interface recorded by the NFC tag board 102, and jumps to the gate management interface based on the jump path information.

[0100] The first authority panel 101 is also used to respond to gate management instructions received based on the above WIFI connection.

[0101] Among them, the above-mentioned gate management instructions are instructions generated based on the user's management operations in the gate management interface.

[0102] In the embodiment of the present application, the first authority board 101 included in the gate can start the WIFI module 1011 after power-on, and set the WIFI module 1011 to AP mode. In this way, the first authority board 101 can set up a wireless local area network by itself, and the WIFI module 1011 is an AP in the wireless local area network. Furthermore, a mobile terminal that enters the signal coverage corresponding to the AP mode and turns on the WIFI function can serve as a terminal in the above-mentioned wireless local area network, establish network communication with the above-mentioned first authority board 101, and access the above-mentioned first authority board 101 through the form of a WIFI local area network. Among them, the embodiment of the present application does not limit the specific type of the above-mentioned mobile device, and the above-mentioned mobile terminal can be various mobile devices such as mobile phones, tablet computers, smart watches, etc.

[0103] That is to say, after the first authority board 101 starts the WIFI module 1011 and sets the WIFI module 1011 to the AP mode, the mobile terminal can establish a WIFI connection with the first authority board 101 when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function. Among them, after the first authority board 101 starts the WIFI module 1011 and sets the WIFI module 1011 to the AP mode, the first authority board 101 will be used as a hotspot and as a wireless router, and the mobile terminal with the WIFI function turned on can search for wireless networks, so that when entering the signal coverage range corresponding to the above-mentioned AP mode, the wireless local area network of the above-mentioned first authority board 101 can be searched, and the mobile terminal can join the wireless local area network of the first authority board 101. At this time, the first authority board 101 can be accessed through the mobile terminal and the first authority board 101 can be operated.

[0104] For example, as shown in FIG. 3 ( a ), when the mobile device is set as a mobile phone, the first authority board 101 may include a WIFI module 1011 , a mobile phone WEB management unit 1012 , an authority board I2C (Inter-Integrated Circuit) communication module 1013 and an authority board power management unit 1014 .

[0105] Furthermore, in the embodiment of the present application, the NFC tag board 102 included in the gate can record the jump path information of the gate management interface that is pre-set, and the NFC tag board 102 can exchange data with a device using NFC technology that is close to itself. Therefore, when the above-mentioned mobile terminal turns on the NFC function and approaches the NFC tag board 102, the NFC tag board 102 can establish an NFC connection with the above-mentioned mobile terminal, so that the above-mentioned mobile terminal can read the above-mentioned jump path information recorded by the NFC tag board 102. In this way, after reading the above-mentioned jump path information, the above-mentioned mobile terminal can jump to the gate management interface based on the jump path information, and display the above-mentioned gate management interface in the display interface.

[0106] Among them, since the NFC tag board 102 supports near field communication based on NFC technology, the mobile terminal approaching the NFC tag board 102 can generally be understood as: the distance between the mobile terminal and the NFC tag board 102 is not greater than or less than the specified near field communication distance. For example, the specified near field communication distance is 3 cm. If the mobile terminal turns on the NFC function and the distance from the NFC tag board 102 is less than 3 cm, the mobile terminal can establish an NFC connection with the NFC tag board 102, or if the mobile terminal turns on the NFC function and the distance from the NFC tag board 102 is not greater than 3 cm, the mobile terminal can establish an NFC connection with the NFC tag board 102.

[0107] That is, in the embodiment of the present application, when the mobile terminal turns on the NFC function, the user can make the mobile terminal jump to the gate management interface by bringing the mobile terminal close to or touching the NFC tag board 102, so that the gate management interface is displayed in the display interface of the mobile terminal. Optionally, the gate management interface can be a WEB interface.

[0108] Optionally, the above-mentioned jump path information may include: the jump address and jump password of the above-mentioned gate management interface. Then, after reading the above-mentioned jump path information, the above-mentioned mobile terminal can directly jump to the interface indicated by the above-mentioned jump address, and log in to the interface indicated by the above-mentioned jump address through the above-mentioned jump password, thereby opening and displaying the above-mentioned gate management interface in the display interface. At this point, the above-mentioned mobile terminal completes the jump to the above-mentioned gate management interface.

[0109] For example, as shown in FIG3 (b), the NFC tag board 102 may include an NFC TAG chip 1021, an NFC antenna 1022, and a tag board power management unit 1024, wherein the NFC TAG chip 1021 is integrated with a tag board I2C communication module 1023, and the NFC TAG chip 1021 may be a programmable and rewritable chip. In the NFC tag board 102 shown in FIG3 (b), the NFC TAG chip 1021 records the jump path information of the gate management interface. The NFC antenna 1022 is an NFC induction coil, so the mobile terminal approaching the NFC tag board 102 can be understood as the mobile terminal approaching the NFC antenna 1022.

[0110] Among them, in the NFC tag board 102 shown in Figure 3 (b), the NFC TAG chip 1021 is the NFC module included in the NFC tag board 102. When a mobile terminal with an NFC function turned on approaches the NFC tag board 102, so that the distance between the above-mentioned mobile terminal and the NFC antenna 1022 is less than a preset communication distance, for example, less than 3 cm, the NFC tag board 102 and the above-mentioned mobile terminal can establish an NFC connection, and the NFC tag board 102 can exchange data with the above-mentioned mobile terminal.

[0111] As mentioned above, in the embodiment of the present application, when the first authority board 101 starts its own WIFI module and sets the WIFI module to AP mode, when the mobile terminal with both WIFI and NFC functions turned on enters the signal coverage corresponding to the AP mode and approaches the NFC tag board 102, the mobile terminal can establish a WIFI connection with the first authority board 101, and jump to the gate management interface based on the NCF connection with the NFC tag board 102. In this way, the user can perform management operations in the gate management interface displayed by the mobile terminal, so that the mobile terminal responds to the management operations to generate gate management instructions, and sends the gate management instructions to the first authority board 101 based on the WIFI connection with the first authority board 101. At this point, the first authority board 101 can respond to the gate management instructions received based on the WIFI connection to achieve management of the gate.

[0112] That is to say, in the embodiment of the present application, the gate management instruction responded to by the above-mentioned first authority panel 101 is an instruction generated based on the management operation of the user in the gate management interface displayed by the mobile device.

[0113] Among them, in order to prevent non-management personnel from managing the gate, it is usually necessary to set different management permissions for different personnel. Therefore, when the above-mentioned mobile terminal jumps to the gate management interface based on the above-mentioned jump path information, the user needs to perform management permission authentication by entering login information in the gate management interface, and when the management permission authentication is passed, that is, the user has the management permission, the user performs management operations in the gate management interface displayed by the mobile terminal, so that the mobile terminal generates a gate management instruction.

[0114] Optionally, when the mobile terminal jumps to the gate management interface based on the jump path information, the interface displayed by the mobile terminal may be a permission authentication interface, so that the user performs a verification operation in the permission authentication interface. Thus, the mobile terminal generates a verification instruction based on the verification operation, and sends the verification instruction to the first permission board 101 based on the WIFI connection with the first permission board 101, and the verification instruction may carry the user information of the user. The first permission board 101 responds to the verification instruction and determines whether the user has the management authority through the correspondence between the pre-recorded user information and the management authority. When the first permission board 101 determines that the user has the management authority, it means that the user can pass the management authority authentication, and the first permission board 101 can send the management interface to the mobile terminal based on the WIFI connection, and the mobile terminal can jump from the permission authentication interface to the management interface. In this way, the user can perform management operations on the management interface displayed by the mobile terminal, and the mobile terminal can generate a gate management instruction based on the management operation, and send the gate management instruction to the first permission board 101 based on the WIFI connection with the first permission board 101. At this point, the first permission board 101 can respond to the gate management instruction, thereby realizing the management of the gate. In this way, by using the mobile terminal to approach or touch the NFC tag board 102, the mobile terminal can be directly connected to the gate, and the management and operation of the current gate can be realized by logging into the gate management interface through permission authentication.

[0115] For example, when the mobile terminal jumps to the gate management interface based on the above jump path information, the following is displayed: Figure 4 The login interface shown, the user enters the account number and password in the above login interface, and clicks the login button. At this time, the mobile terminal sends a verification instruction to the first authority board 101 based on the WIFI connection with the first authority board 101, and the verification instruction carries the account number and password entered by the above user. The first authority board 101 responds to the above verification instruction, and determines whether the above user has management authority through the above account number and password through the correspondence between the pre-recorded user information and management authority. When the first authority board 101 determines that the above user has management authority, it means that the user can pass the management authority authentication.

[0116] Usually, for different management purposes, the user can perform different management operations on the gate management interface displayed by the mobile terminal, so that the mobile terminal will generate different gate management instructions. In this way, the first authority panel 101 can respond to the gate management instructions received based on the WIFI connection in different ways.

[0117] Based on this, optionally, in a specific implementation, the first authority board 101 responds to the gate management instruction received based on the WIFI connection, which may include the following step 1:

[0118] Step 1: The first authority board 101 receives a gate information update instruction based on a WIFI connection, and updates the gate information of the recorded gate to the information indicated by the gate information update instruction.

[0119] In this specific implementation, in some scenarios, when managing a gate, the user can reconfigure the relevant information of the gate, for example, configure the information of a newly installed gate, change the default information of the gate, etc.; for another example, repair a faulty gate, correct the fault information of the gate, etc. Therefore, the user can perform an information update operation on the gate management interface displayed by the mobile terminal, so that the mobile terminal generates a gate information update instruction as a gate management instruction. For example, modify the content of the gate information of the gate management interface displayed by the mobile terminal, and click the confirmation button of the above gate management interface after the modification, so that the mobile terminal generates a gate information update instruction as a gate management instruction in response to the modification operation of the above gate information and the click operation of the confirmation button.

[0120] In this way, the first authority board 101 can receive the gate information update instruction based on the WIFI connection with the mobile terminal, and update the gate information of the recorded gate to the information indicated by the gate information update instruction.

[0121] Optionally, in another specific implementation, the first authority board 101 responds to the gate management instruction received based on the WIFI connection, which may include the following step 2:

[0122] Step 2: The first authority panel 101 receives a gate information reading instruction based on a WIFI connection, and pushes the gate information indicated by the gate information reading instruction to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

[0123] In this specific implementation, in some scenarios, when managing the gate, the user can view the current gate information to confirm whether the gate is in normal working condition, for example, regularly view the gate information of the gate to perform regular maintenance of the gate, etc. Therefore, the user can perform an information viewing operation on the gate management interface displayed by the mobile terminal, so that the mobile terminal generates a gate information reading instruction as a gate management instruction. For example, in the gate management interface displayed by the mobile terminal, the gate information to be viewed is selected, so that the mobile terminal responds to the selection operation of the gate information and generates a gate information reading instruction for the gate information to be viewed as a gate management instruction.

[0124] In this way, the first authority board 101 can receive the gate information reading instruction based on the WIFI connection with the mobile terminal, and search for the gate information indicated by the gate information reading instruction from the gate information recorded locally, and then, based on the WIFI connection with the mobile terminal, push the gate information indicated by the gate information reading instruction found to the gate management interface displayed by the mobile terminal. Then, when receiving the gate information, the gate management interface displayed by the mobile terminal can display the received gate information.

[0125] Optionally, in a specific implementation, the first authority board 101 responds to the gate management instruction received based on the WIFI connection, which may include the following steps 1 and 2:

[0126] Step 1: The first authority board 101 receives a gate information update instruction based on a WIFI connection, and updates the gate information of the recorded gate to the information indicated by the gate information update instruction.

[0127] Step 2: The first authority panel 101 receives a gate information reading instruction based on a WIFI connection, and pushes the gate information indicated by the gate information reading instruction to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

[0128] Among them, the content of the gate management interface can be set according to the needs of gate management in actual applications, and the gate information can be set according to the needs of gates in actual applications, thereby realizing customized settings of the gate information.

[0129] In order to facilitate understanding of the interaction process between the first authority board 101, the NFC tag board 102 and the mobile terminal, an embodiment of the present application provides a signaling interaction diagram of the first authority board 101, the NFC tag board 102 and the mobile terminal, as shown in Figure 5(a). The above interaction process may include the following steps S501-S507.

[0130] S501: After starting the WIFI module, the first authority board 101 sets the WIFI module to AP mode.

[0131] S502: The mobile terminal performs a WIFI connection with the first authority board 101 and an NFC connection with the NFC tag board 102. The mobile terminal enters the signal coverage range corresponding to the AP mode, turns on the WIFI function and the NFC function, and approaches the NFC tag board.

[0132] S503: The mobile terminal reads the jump path information of the gate management interface recorded by the NFC tag board 102 based on the NFC connection with the NFC tag board 102 .

[0133] S504: The mobile terminal jumps to the gate management interface based on the jump path information.

[0134] S505: The mobile terminal generates a gate management instruction based on the management operation of the user in the displayed gate management interface.

[0135] S506: The mobile terminal sends a gate management instruction to the first authority board 101 based on the WIFI connection with the first authority board 101.

[0136] S507: The first authority board 101 responds to the gate management instruction received based on the WIFI connection with the mobile terminal.

[0137] As can be seen from the above, by applying the solution provided by the embodiment of the present application, when managing the gate, the mobile terminal with the WIFI function and NFC function turned on can be directly brought close to the NFC tag board set on the first box of the gate to achieve WIFI connection between the mobile terminal and the first authority board, and by reading the jump path information of the gate management interface recorded by the NFC tag board, jump to the gate management interface based on the above jump path information. Furthermore, a gate management instruction can be generated based on the management operation of the user in the gate management interface displayed by the mobile terminal, and the first authority board receives the above gate management instruction based on the WIFI connection with the mobile terminal, and responds to the above gate management instruction to achieve management of the gate.

[0138] In this way, by applying the solution provided by the embodiment of the present application, when managing the gate, the gate can be managed by using a mobile terminal with WIFI and NFC functions turned on to approach the NFC tag board set on the first box of the gate, without having to carry a laptop and an Internet cable to the location of the gate, and without having to find the IP address of the gate separately, which can reduce the management burden of the management personnel and improve the efficiency of gate management. Therefore, the solution provided by the embodiment of the present application is a solution for fast connection pairing and fast configuration during gate installation and operation, which greatly simplifies the gate configuration and operation process and can realize convenient management of the gate.

[0139] As mentioned above, the NFC tag board 102 may record the jump path information of the gate management interface that is preset, and when the mobile terminal turns on the NFC function and approaches the NFC tag board 102, the NFC tag board 102 may establish an NFC connection with the mobile terminal, so that the mobile terminal can read the jump path information recorded in the NFC tag board 102. In some cases, the jump path information recorded in the NFC tag board 102 is sent by the first authority board 101 to the NFC tag board after power-on.

[0140] Based on this, optionally, in a specific implementation, the first authority board 101 is further used to send the jump path information to the NFC tag board 102 through a specified transmission protocol after power-on;

[0141] Correspondingly, in this specific implementation, the NFC tag board 102 is also used to record the received jump path information.

[0142] In this specific implementation, the first authority board 101 records the jump path information of the gate management interface that is pre-set. After the first authority board 101 is powered on, it can send the jump path information to the NFC tag board 102 through a specified transmission protocol. In this way, the NFC tag board 102 can receive the jump path information and record the jump path information. After that, after the mobile terminal establishes an NFC connection with the NFC tag board 102, it can read the jump path information recorded by the NFC tag board 102.

[0143] Based on this, as shown in FIG5( b ), the interaction process between the first authority board 101 , the NFC tag board 102 and the mobile terminal may further include the following steps S508 - S509 .

[0144] S508: After being powered on, the first authority board 101 sends the jump path information to the NFC tag board 102 through a specified transmission protocol.

[0145] S509: The NFC tag board 102 records the received jump path information.

[0146] Wherein, illustratively, based on the first authority board 101 shown in FIG. 3 (a) and the NFC tag board 102 shown in FIG. 3 (b), the mobile phone WEB management unit 1012 in the first authority board 101 may record the jump path information of the pre-set gate management interface, so that after the first authority board 101 is powered on, the first authority board 101 may use the authority board I2C communication module 1013 to send the above jump path information to the NFC tag board 102. Correspondingly, the NFC TAG chip 1021 of the NFC tag board 102 is integrated with the tag board I2C communication module 1023, so that the NFC tag board 102 can receive the above jump path information through the tag board I2C communication module 1023, and write the received jump path information into the NFC TAG chip 1021, then when the NFC tag board 102 is connected to the mobile terminal by NFC, the mobile terminal can read the above jump path information recorded in the NFC TAG chip 1021 of the first NFC tag 102.

[0147] Usually, the gate can verify whether a person has the permission to pass through the gate by image recognition. Therefore, the gate can be provided with a lens assembly to collect images of people approaching the gate for the above permission verification. In order to protect the lens assembly from damage due to human factors, weather, etc., a shell can be provided to protect the lens assembly.

[0148] For example, the housing of the gate may be provided with a raised portion 103 as shown in FIG6 (a), and a lens assembly may be provided inside the raised portion 103, and the lens of the lens assembly may be exposed to the openings 1031 and 1032 on the housing of the raised portion 103. In this way, the lens of the lens assembly may capture images of the surroundings of the gate outside the raised portion 103 through the openings 1031 and 1032, and further, the lens may capture images of people approaching the gate.

[0149] Based on this, optionally, in a specific implementation, a raised portion may be provided on the upper surface of the first box body 100, and the raised portion 103 protrudes in a direction away from the upper surface of the first box body 100, a lens assembly is provided in the raised portion, and the lens of the lens assembly is exposed to an opening on the shell of the raised portion.

[0150] In this specific implementation, the protrusion 103 can protrude upward relative to the upper surface of the first box body 100. For example, as shown in FIG. 6 (b), in a specific example of a gate provided in an embodiment of the present application, a protrusion 103 is provided on the upper surface of the first box body 100, and a lens assembly is provided inside the protrusion 103, and the lens of the lens assembly is exposed to the openings 1031 and 1032 on the shell of the protrusion 103.

[0151] Furthermore, the lens of the lens assembly may be located inside the protruding portion, or may be facing outside the protruding portion and embedded in an opening on a shell of the protruding portion, so as to be exposed to the opening on the shell of the protruding portion.

[0152] Further, optionally, in a specific implementation, based on the fact that a protrusion is provided on the upper surface of the first box body 100 , at least a portion of the lower surface of the protrusion is connected to the upper surface of the first box body 100 .

[0153] For example, the entire area of ​​the lower surface of the above-mentioned raised portion is in contact with the upper surface of the first box body 100, that is, the above-mentioned raised portion is a closed whole, so that the lower surface of the above-mentioned raised portion is in contact with the upper surface of the first box body 100; for another example, the ground of the above-mentioned raised portion is hollowed out, so that the hollow portion of the lower surface of the above-mentioned raised portion is not connected to the upper surface of the first box body 100; for another example, the lower surface of the above-mentioned raised portion is provided with a connection point, and the connection point is used to connect with the upper surface of the first box body 100.

[0154] Furthermore, in the case where the protrusion can be arranged on the upper surface of the first box body 100 in a variety of ways, the protrusion 103 can also have a variety of protrusion directions. For example, as shown in FIG6 (b), the protrusion protrudes upward relative to the upper surface of the first box body 100; of course, in various connection methods, the protrusion can also protrude laterally relative to the upper surface of the first box body 100, or can protrude upward and also protrude laterally, etc.

[0155] Based on this, the embodiment of the present application does not specifically limit the connection method between the above-mentioned protrusion and the upper surface of the first box body 100. Any connection method that can enable the above-mentioned protrusion to be set on the upper surface of the first box body 100 belongs to the protection scope of the embodiment of the present application. Similarly, the embodiment of the present application does not specifically limit the protruding direction of the above-mentioned protrusion. Any protruding direction of the above-mentioned protrusion away from the upper surface of the above-mentioned first box body 100 belongs to the protection scope of the embodiment of the present application.

[0156] Furthermore, when the protrusion is provided on the upper surface of the first box body 100 , the NFC tag plate 102 may be disposed in the protrusion to protect the NFC tag plate 102 from being damaged by human factors, weather or the like.

[0157] Based on this, optionally, in a specific implementation, the NFC tag plate 102 is located in the raised portion, and the first raised housing 103 is disposed on the top or side of the lens assembly disposed in the raised portion.

[0158] Furthermore, in order to protect the first authority plate 101 from damage due to human factors, weather, etc., the first authority plate can be set inside the box of the gate machine, or, when the above-mentioned raised portion is provided on the upper surface of the above-mentioned first box 100, the first authority plate 101 can also be set in the above-mentioned raised portion.

[0159] Based on this, optionally, in a specific implementation, the first authority plate 101 is disposed inside the first box 100 and connected to the NFC tag plate 102 via a cable, or the first authority plate 101 is disposed in the above-mentioned raised portion.

[0160] In addition, optionally, in order to achieve further integration of the gate, when the upper surface of the first box 100 is provided with the protrusion, the first authority plate 101 and the NFC tag plate 102 can be both arranged in the protrusion.

[0161] As mentioned above, the gate provided in the embodiment of the present application may include the following multiple forms:

[0162] The first form: the first authority board 101 is disposed in the first box 100, and the NFC tag board 102 is disposed at the upper end of the front surface of the first box 100, and the first authority board 100 and the first NFC tag 102 are connected via a cable.

[0163] Second form: the first authority board 101 is arranged in the first box 100, and the NFC tag board 102 is arranged at the upper end of the front surface of the first box 100, and the first authority board 100 and the first NFC tag 102 are connected by a cable. In addition, a protrusion is arranged on the upper surface of the first box 100, and the protrusion 103 protrudes upward relative to the upper surface of the first box 100, and a lens assembly is arranged in the protrusion, and the lens of the lens assembly is exposed to the opening on the shell of the protrusion.

[0164] The third form: the first authority plate 101 is disposed in the first box 100, a protrusion is disposed on the upper surface of the first box 100, and the protrusion 103 protrudes upward relative to the upper surface of the first box 100, a lens assembly is disposed in the protrusion, and the lens of the lens assembly is exposed to the opening on the housing of the protrusion. In addition, the NFC tag plate 102 is disposed in the protrusion, and the NFC tag plate 102 is disposed on the top of the lens assembly.

[0165] The fourth form: a raised portion is provided on the upper surface of the first housing 100, and the raised portion 103 is raised upward relative to the upper surface of the first housing 100, a lens assembly is provided in the raised portion, and a lens of the lens assembly is exposed to an opening on the housing of the raised portion. In addition, the first authority plate 101 and the NFC tag plate 102 are both provided in the raised portion, and the NFC tag plate 102 is provided on the top of the lens assembly.

[0166] It should be emphasized that the above four forms are merely examples of the forms of the gate machine provided in the embodiments of the present application, and are not limitations. The embodiments of the present application do not specifically limit the forms of the gate machine provided. As long as a gate machine can implement any of the above-mentioned implementation methods provided in the embodiments of the present application, no matter what form it is, it belongs to the protection scope of the embodiments of the present application.

[0167] Usually, the gate has a fixed direction of travel. For example, the exit gate and the entrance gate of a subway station are separate. The exit gate and the entrance gate each have a fixed direction of travel. Pedestrians cannot exit the station through the entrance gate, and similarly, they cannot enter the station through the exit gate. Based on this, when the mobile terminal displays the gate management interface, the management operation performed by the user in the gate management interface can only be the management operation for a certain direction of travel set for the gate, and then, the gate management instruction generated based on the management operation is the gate management instruction for a certain direction of travel set for the gate.

[0168] Based on this, optionally, in a specific implementation, the first authority board 101 responds to the gate management instruction received based on the WIFI connection, which may include the following step 3:

[0169] Step 3: Respond to the first gate management instruction for the designated passage direction of the gate received based on the WIFI connection.

[0170] Generally, the gate machine may include one box or two boxes. When the gate machine includes one box, the box may be used as the first box; and when the gate machine includes two boxes, the two boxes may be used as the first box and the second box respectively.

[0171] For example, the box body serving as the main channel may be referred to as the first box body, and the box body serving as the slave channel may be referred to as the second box body. This embodiment of the present application does not make any specific limitation on this.

[0172] As mentioned above, when the gate has two directions of passage, for example, the gate at the entrance and exit of a residential area has two directions of passage, the user can enter and leave the residential area through the same gate. Based on this, when the above-mentioned mobile terminal displays the above-mentioned gate management interface, the management operation performed by the user in the above-mentioned gate management interface can be a management operation for at least one of the two directions of passage of the gate, and then, the gate management instruction generated based on the above-mentioned management operation is a gate management instruction for at least one of the two directions of passage of the gate.

[0173] Optionally, in a specific implementation, the gate may include a second authority board, which is disposed inside a second box of the gate, and the first authority board 101 is communicatively connected to the second authority board.

[0174] The second authority board is a hardware unit that can be connected to the first authority board 101 and has some gate management functions. Optionally, the second authority board and the first authority board 101 can be the same hardware unit.

[0175] In addition, optionally, for a gate machine that only includes one box, the above-mentioned first authority board 101, the NFC tag board 102 and the second authority board can all be arranged in the same box, and, in this case, it is not limited to the above-mentioned first authority board 101, the above-mentioned NFC tag board 102 and the above-mentioned second authority board must be separate hardware units in physical form. The first authority board 101, the above-mentioned NFC tag board 102 and the above-mentioned second authority board can exist independently, or can be integrated into a hardware unit of the same physical form, or any two of them can be integrated into a hardware unit of the same physical form, and the other one can exist independently.

[0176] Accordingly, in this specific implementation:

[0177] The first authority board 101 is further used to receive a second gate management instruction for the opposite passage direction of the designated passage direction based on the WIFI connection, and send the second gate management instruction to the second authority board.

[0178] The second authority board is used to respond to the received second gate management instruction.

[0179] That is to say, in this specific implementation, when the first authority board 101 receives a gate control instruction based on the WIFI connection with the mobile terminal, if the gate control instruction includes a first gate management instruction for a specified passage direction of the gate, the first authority board 101 can directly respond to the above-mentioned first gate management instruction; if the gate management instruction includes a second gate management instruction for the opposite passage direction of the specified passage direction, the first authority board 101 sends the above-mentioned second gate management instruction to the second authority board, so that the second authority board can directly respond to the above-mentioned second gate management instruction; if the gate management instruction includes the above-mentioned first gate management instruction and the above-mentioned second gate management instruction, the first authority board 101 can send the above-mentioned second gate management instruction to the second authority board while directly responding to the above-mentioned first gate management instruction, so that the second authority board can directly respond to the above-mentioned second gate management instruction.

[0180] Corresponding to the gate provided in the above-mentioned embodiment of the present application, the embodiment of the present application also provides a gate management method.

[0181] Among them, the gate management method can be applied to a gate, which includes a first control board and a communication board, and the communication board is arranged in a side box of the gate. Figure 7 A schematic diagram of a gate management method provided in an embodiment of the present application is shown in FIG. Figure 7 As shown, the method may include the following steps S701-S703.

[0182] S701: The first control board is connected to the mobile terminal for communication.

[0183] S702: The communication board is connected to the mobile terminal for communication, so that the mobile terminal obtains the jump path information of the gate management interface recorded by the communication board, and jumps to the gate management interface based on the jump path information.

[0184] S703: The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal; wherein the gate management instruction is an instruction generated based on the management operation performed by the user in the gate management interface.

[0185] In an embodiment of the present application, the gate machine may include a first control board and a communication board, and the communication board is arranged in a side box of the gate machine, and the first control board and the communication board may be arranged in the same box of the gate machine, or may be arranged in different boxes of the gate machine. Furthermore, the mobile terminal may be respectively connected to the first control board and the first communication board for communication. In this way, when the communication board and the mobile terminal are connected for communication, the mobile terminal may obtain the jump path information of the gate machine management interface recorded by the communication board, and jump to the gate machine management interface based on the jump path information. Furthermore, the user may perform management operations in the gate machine management interface displayed by the mobile terminal, and the mobile terminal may generate a gate machine management instruction based on the management operation. Furthermore, the mobile terminal may send the gate machine management instruction to the first control board based on the communication connection with the first control board. In this way, the first control board may respond to the gate machine management instruction received based on the communication connection with the mobile terminal.

[0186] Among them, the first control board is a hardware unit that can communicate with the mobile terminal and has some gate management functions; and the communication board is a hardware unit that can communicate with the mobile terminal to realize data exchange with the mobile terminal and has a data recording function. Optionally, the first control board is a hardware unit with the same function as the first permission board, for example, the first control board can be the same hardware unit as the first permission board 101. Optionally, the communication board is a hardware unit with the same function as the NFC tag board, for example, the communication board can be the same hardware unit as the NFC tag board.

[0187] In the embodiment of the present application, it is not limited that the first control board and the communication board must be separate hardware units in physical form. The first control board and the communication board may exist independently or may be integrated into the same physical hardware unit.

[0188] As can be seen from the above, by applying the solution provided by the embodiment of the present application, when managing the gate, a first control board and a communication board can be set in the gate, so that the mobile terminal can be connected to the first control board and the communication board respectively, so that the first control board executes the gate management instruction to achieve the management of the gate without having to find the IP address of the gate separately, which can reduce the management burden of the management personnel and improve the efficiency of gate management. Therefore, the solution provided by the embodiment of the present application is a solution for fast connection pairing and fast configuration of gate installation and operation, which greatly simplifies the gate configuration and operation process, and can achieve convenient management of the gate.

[0189] Optionally, in a specific implementation, the above step S703, the first control board responding to the gate management instruction received based on the communication connection with the mobile terminal, may include the following step 7031, and / or step 7032:

[0190] Step 7031: Receive a gate information update instruction based on the communication connection with the mobile terminal, and update the recorded gate information of the gate to the information indicated by the gate information update instruction.

[0191] Step 7032: Receive a gate information reading instruction based on the communication connection with the mobile terminal, and push the gate information indicated by the gate information reading instruction to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

[0192] Optionally, in a specific implementation, the above step S701, in which the first control board is connected to the mobile terminal for communication, may include the following step 7011:

[0193] Step 7011: The first control panel of the gate is communicatively connected to the mobile terminal via a communication connection line.

[0194] In this specific implementation, according to different mobile terminals, the communication connection line may be a network cable, a USB (Universal Serial Bus) data cable or other communication connection lines.

[0195] Optionally, in a specific implementation, the first control board is provided with a wireless communication module.

[0196] Accordingly, in this specific implementation, the above step S701, in which the first control board is connected to the mobile terminal for communication, may include the following step 7012:

[0197] Step 7012: The first control board establishes a wireless communication connection with the mobile terminal through the wireless communication module.

[0198] Furthermore, in this specific implementation, the above step S703, in which the first control board responds to the gate management instruction received based on the communication connection with the mobile terminal, may include the following step 7033:

[0199] Step 7033: The first control panel responds to the gate management instruction received based on the wireless communication connection.

[0200] Optionally, in a specific implementation, the first control board is provided with a WIFI module as a wireless communication module.

[0201] Accordingly, in this specific implementation, the above step 7012, in which the first control board establishes a wireless communication connection with the mobile terminal through the wireless communication module, may include the following step 4:

[0202] Step 4: After starting the WIFI module, the first control board sets the WIFI module to AP mode, so that the mobile terminal can establish a WIFI connection with the first control board when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function.

[0203] Furthermore, in this specific implementation, the above step 7033, in which the first control board responds to the gate management instruction received based on the wireless communication connection, may include the following step 5:

[0204] The first control panel responds to the gate management instruction received based on the WIFI connection.

[0205] Optionally, in a specific implementation, the communication board is provided with a mobile communication module; wherein the mobile communication module includes at least: a 4G communication module, or a 5G communication module.

[0206] Accordingly, in this specific implementation, the above step S702, in which the communication board communicates with the mobile terminal, may include the following step 7021:

[0207] Step 7021: The communication board establishes a mobile communication connection with the mobile terminal through the mobile communication module.

[0208] Optionally, in a specific implementation, the communication board is provided with an NFC tag board.

[0209] Accordingly, in this specific implementation, the above step S702, in which the communication board communicates with the mobile terminal so that the mobile terminal obtains the jump path information of the gate management interface recorded by the communication board, may include the following step 7022:

[0210] Step 7022: When the mobile terminal has the NFC function turned on and is close to the communication board, the communication board establishes an NFC connection with the mobile terminal so that the mobile terminal reads the jump path information of the gate management interface recorded by the communication board.

[0211] Optionally, in a specific implementation, when the communication board is provided with an NFC tag board, a gate management method provided in an embodiment of the present application may further include the following steps 704 and 705:

[0212] Step 704: After being powered on, the first control board sends the jump path information to the communication board through a specified transmission protocol;

[0213] Step 705: The communication board records the received jump path information.

[0214] Optionally, in a specific implementation, a protrusion is provided on the upper surface of the first box body, and the protrusion protrudes in a direction away from the upper surface of the first box body, a lens assembly is provided in the protrusion, and the lens of the lens assembly is exposed to an opening on the shell of the protrusion.

[0215] Optionally, in a specific implementation, at least a partial area of ​​the lower surface of the protrusion is connected to the upper surface of the first box body.

[0216] Optionally, in a specific implementation, the NFC tag plate is disposed in the raised portion, and the first NFC plate is disposed on the top or side of the lens assembly.

[0217] Optionally, in a specific implementation, the first control board is disposed inside the first box and connected to the first NFC board via a cable; or, the first control board is disposed inside the raised portion.

[0218] Optionally, in a specific implementation, the NFC label plate is disposed at an upper end of the front surface of the first box body.

[0219] Optionally, in a specific implementation, in the above step S703, the first control board responds to the gate management instruction received based on the communication connection with the mobile terminal, which may include the following step 7034:

[0220] Step 7034: The first control panel responds to a first gate management instruction for a designated passage direction of the gate received based on the communication connection with the mobile terminal.

[0221] Optionally, in a specific implementation, the gate machine further includes: a second control board, the second control board is arranged on the other side of the box of the gate machine, and the second control board is communicatively connected with the first control board.

[0222] Accordingly, in this specific implementation, a gate management method provided in the embodiment of the present application may further include the following steps 706 and 707:

[0223] Step 706: the first control board receives a second gate management instruction for the opposite passage direction of the designated passage direction based on the communication connection with the mobile terminal, and sends the second gate management instruction to the second control board;

[0224] Step 707: The second control board responds to the received second gate management instruction.

[0225] The second control board is a hardware unit that can be connected to the first control board for communication and has some gate management functions. Optionally, the second control board and the first control board can be the same hardware unit.

[0226] In addition, optionally, for a gate machine that only includes one box, the above-mentioned first control board, communication board and second control board can all be arranged in the same box, and, in this case, it is not limited to the above-mentioned first control board, communication board and second control board must be separate hardware units in physical form. The above-mentioned first control board, communication board and second control board can exist independently, or can be integrated into a hardware unit of the same physical form, or any two of them can be integrated into a hardware unit of the same physical form, and the other one can exist independently.

[0227] In the above embodiments, it can be implemented in whole or in part by software, hardware, firmware or any combination thereof. When implemented using software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, the process or function described in the embodiment of the present application is generated in whole or in part. The computer may be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions may be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions may be transmitted from a website site, computer, server or data center to another website site, computer, server or data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) means. The computer-readable storage medium may be any available medium that a computer can access or a data storage device such as a server or data center that includes one or more available media integrated. The available medium may be a magnetic medium (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a solid-state hard disk (SSD), etc.

[0228] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0229] Each embodiment in this specification is described in a related manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the method embodiment, since it is basically similar to the gate embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0230] The above description is only a preferred embodiment of the present application and is not intended to limit the protection scope of the present application. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application are included in the protection scope of the present application.

Claims

1. A gate machine, characterized in that: include: A first authority board and an NFC tag board, wherein the first authority board is provided with a WIFI module, and the NFC tag board is provided in a first box of the gate; The first authority board is used to set the WIFI module to AP mode after starting the WIFI module, so that any mobile terminal can establish a WIFI connection with the first authority board when it enters the signal coverage range corresponding to the AP mode and turns on the WIFI function; The NFC tag board is used to establish an NFC connection with the mobile terminal when the mobile terminal turns on the NFC function and is close to the NFC tag board, so that the mobile terminal reads the jump path information of the gate management interface recorded by the NFC tag board, and jumps to the gate management interface based on the jump path information; The first authority panel is also used to respond to gate management instructions received based on the WIFI connection; wherein the gate management instructions are instructions generated based on management operations performed by the user in the gate management interface.

2. The gate according to claim 1, characterized in that: The first authority board is further used to send the jump path information to the NFC tag board through a specified transmission protocol after power-on; The NFC tag board is also used to record the received jump path information.

3. The gate according to claim 1, characterized in that: The first authority board responds to the gate management instruction received based on the WIFI connection, including: Receiving a gate information update instruction based on the WIFI connection, and updating the recorded gate information of the gate to the information indicated by the gate information update instruction; and / or, A gate information reading instruction is received based on the WIFI connection, and the gate information indicated by the gate information reading instruction is pushed to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

4. The gate according to claim 1, characterized in that: A protrusion is disposed on the upper surface of the first housing, and the protrusion protrudes in a direction away from the upper surface of the first housing. A lens assembly is disposed in the protrusion, and a lens of the lens assembly is exposed to an opening on the housing of the protrusion.

5. The gate according to claim 4, characterized in that: At least a partial area of ​​the lower surface of the protrusion is connected to the upper surface of the first box body.

6. The gate according to claim 4, characterized in that: The NFC label plate is arranged in the raised portion, and the NFC label plate is arranged on the top or side of the lens assembly.

7. The gate according to any one of claims 4 to 6, characterized in that: The first authority plate is disposed inside the first box and connected to the NFC tag plate via a cable, or the first authority plate is disposed inside the raised portion.

8. The gate according to claim 1, characterized in that: The NFC label plate is arranged at the upper end of the front surface of the first box body.

9. The gate according to claim 1, characterized in that: The first authority board responds to the gate management instruction received based on the WIFI connection, including: Respond to a first gate management instruction for a designated passage direction of the gate received based on the WIFI connection.

10. The gate according to claim 9, characterized in that: The gate machine further comprises: a second authority board, the second authority board is arranged inside the second box of the gate machine, and the second authority board is communicatively connected with the first authority board; The first authority board is further used to receive a second gate management instruction for the opposite traffic direction of the designated traffic direction based on the WIFI connection, and send the second gate management instruction to the second authority board; The second authority board is used to respond to the received second gate management instruction.

11. A gate management method, characterized in that: Applied to a gate machine, the gate machine comprises: a first control board and a communication board, the communication board is arranged in a box on one side of the gate machine, and the method comprises: The first control panel is communicatively connected with the mobile terminal; The communication board is connected to the mobile terminal for communication, so that the mobile terminal obtains the jump path information of the gate management interface recorded by the communication board, and jumps to the gate management interface based on the jump path information; The first control panel responds to a gate management instruction received based on a communication connection with the mobile terminal; wherein the gate management instruction is an instruction generated based on a management operation performed by a user on the gate management interface.

12. The method according to claim 11, characterized in that The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including: Receiving a gate information update instruction based on a communication connection with the mobile terminal, and updating the recorded gate information of the gate to the information indicated by the gate information update instruction; and / or, A gate information reading instruction is received based on the communication connection with the mobile terminal, and the gate information indicated by the gate information reading instruction is pushed to the gate management interface based on the WIFI connection, so that the gate management interface displays the received gate information.

13. The method according to claim 11, characterized in that The first control panel is communicatively connected with the mobile terminal, including: The first control panel of the gate is communicatively connected to the mobile terminal via a communication connection line.

14. The method according to claim 11, characterized in that The first control board is provided with a wireless communication module; The first control panel establishes a communication connection with the mobile terminal, including: The first control board establishes a wireless communication connection with the mobile terminal through the wireless communication module; The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including: The first control board responds to gate management instructions received based on the wireless communication connection.

15. The method according to claim 14, characterized in that The first control board is provided with a WIFI module as the wireless communication module; The first control board establishes a wireless communication connection with the mobile terminal through the wireless communication module, including: After starting the WIFI module, the first control board sets the WIFI module to AP mode, so that the mobile terminal can establish a WIFI connection with the first control board when entering a signal coverage range corresponding to the AP mode and turning on the WIFI function; The first control board responds to the gate management instruction received based on the wireless communication connection, including: The first control panel responds to gate management instructions received based on the WIFI connection.

16. The method according to claim 11, characterized in that The communication board is provided with a mobile communication module; wherein the mobile communication module at least includes: a 4G communication module, or a 5G communication module; the communication board is connected to the mobile terminal for communication, including: The communication board establishes a mobile communication connection with the mobile terminal through the mobile communication module.

17. The method according to claim 11, characterized in that The communication board is provided with an NFC tag board; the communication board of the gate is connected to the mobile terminal for communication, so that the mobile terminal obtains the jump path information of the gate management interface recorded by the communication board, including: When the mobile terminal turns on the NFC function and is close to the communication board, the communication board establishes an NFC connection with the mobile terminal, so that the mobile terminal reads the jump path information of the gate management interface recorded by the communication board.

18. The method according to claim 17, characterized in that The method further comprises: After being powered on, the first control board sends the jump path information to the communication board through a specified transmission protocol; The communication board records the received jump path information.

19. The method according to claim 17, characterized in that A protrusion is disposed on the upper surface of the first housing, and the protrusion protrudes in a direction away from the upper surface of the first housing. A lens assembly is disposed in the protrusion, and a lens of the lens assembly is exposed to an opening on the housing of the protrusion.

20. The method according to claim 19, characterized in that At least a partial area of ​​the lower surface of the protrusion is connected to the upper surface of the first box body.

21. The method according to claim 19, characterized in that The NFC label plate is disposed in the raised portion, and the first NFC plate is disposed on the top or side of the lens assembly.

22. The method according to any one of claims 19 to 21, characterized in that: The first control board is disposed inside the first box and connected to the first NFC board via a cable; or, the first control board is disposed inside the raised portion.

23. The method according to claim 11, characterized in that The NFC label plate is arranged at the upper end of the front surface of the first box body.

24. The method according to claim 11, characterized in that The first control panel responds to the gate management instruction received based on the communication connection with the mobile terminal, including: The first control panel responds to a first gate management instruction for a designated passage direction of the gate received based on a communication connection with the mobile terminal.

25. The method according to claim 24, characterized in that The gate machine further includes: a second control panel, the second control panel is arranged on the other side of the box of the gate machine, and the second control panel is communicatively connected with the first control panel; the method further includes: The first control board receives a second gate management instruction for a traffic direction opposite to the designated traffic direction based on a communication connection with the mobile terminal, and sends the second gate management instruction to the second control board; The second control panel responds to the received second gate management instruction.

Citation Information

Patent Citations

  • Method for setting and debugging working parameters of barrier gate by using mobile phone APP

    CN109102604A

  • NFC household appliance control method

    CN114816555A

  • Way switch machine system

    CN205348039U

  • Intelligent access control equipment supporting wireless communication and NFC door opening and access control management system

    CN209149384U