Material management method, electronic equipment and computer storage medium

By extracting target materials in reserved orders and/or sales orders, determining distribution plan information, and purchasing and out-of-stocking independent of production requirements, the problem of timely and accurate adjustment of material demand under the JIT production model is solved, and inventory optimization and cost reduction are achieved.

CN119887042APending Publication Date: 2025-04-25ZHONGKE YUNGU TECH
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411941840.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-26
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

Under the JIT production model, the sales and reserved material needs are distributed through virtual returns and material collection requirements, which makes it difficult to ensure timeliness and accuracy during large adjustments, affecting the direct delivery of production materials.

Method used

By obtaining reservation orders and/or sales orders, the target type of material is extracted to determine the delivery plan information, the purchase order is determined based on the delivery plan information for purchase, and it is directly out of the warehouse after receipt, independent of production requirements.

Benefits of technology

Reduce inventory backlog, improve inventory turnover, reduce warehouse management costs and enterprise costs, and avoid the risk of impact on the distribution of production materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119887042A_ABST
    Figure CN119887042A_ABST
Patent Text Reader

Abstract

The invention discloses a material management method, electronic equipment and a computer storage medium. The method comprises the steps of obtaining a reservation order and / or a sales order; extracting materials of a target type in the reservation order and / or the sales order to determine distribution plan information; determining a purchase order according to the distribution plan information to perform purchase; and after the receiving business corresponding to the purchase order is completed, the target type of materials are delivered according to the distribution plan information. According to the technical scheme of the invention, through extracting the target type of materials in the reservation order and / or the sales order, determining the distribution plan information and purchasing, and after the receiving business corresponding to the purchasing order is completed, the target type of materials are delivered directly according to the distribution plan information, so that the stock overstock can be reduced, the stock turnover rate is improved, and the efficiency is improved. The warehouse management cost is reduced, the enterprise cost is reduced, the target material distribution mode of the reservation and sales demands is not related to the production demands, and the risk that the production material distribution is affected is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of material distribution, and in particular to a material management method, electronic equipment and computer storage medium. Background Art

[0002] With the development of enterprises, in order to reduce production costs, some factories / production lines adopt JIT (Just in time) production mode for material procurement. JIT production mode has high requirements on material supply efficiency, and has the characteristics of small batches, high delivery frequency, and fast inventory turnover. In related technologies, JIT materials can automatically trigger distribution plans after production orders are issued in the MOM (Manufacturing Operations Management) system, while JIT materials in the same factory have sales parts demand and R&D reservation and other material collection requirements. At present, the sales and reserved JIT material requirements are added to the production order by adding a virtual return material requirement and a virtual production material collection requirement, so that the materials can be distributed in a JIT manner through the production order requirements. It is difficult to ensure the timeliness and accuracy of the processing results when a large number of adjustments are made. Once the update is wrong or untimely, it will affect the JIT direct delivery of production materials, resulting in production rhythm errors. Summary of the invention

[0003] The purpose of this application is to provide a material management method, electronic equipment and computer storage medium, which can reduce inventory backlogs, improve inventory turnover, reduce warehouse management costs, reduce enterprise costs, and make the target material distribution method of reservation and sales demand not linked to production demand, avoiding the risk of production material distribution being affected.

[0004] To achieve the above purpose, the technical solution of this application is implemented as follows:

[0005] In a first aspect, the present application provides a material management method, the method comprising:

[0006] Obtain reservations and / or sales orders;

[0007] Extracting materials of the target type in the reservation order and / or the sales order to determine distribution plan information;

[0008] Determine a purchase order based on the distribution plan information to carry out the purchase;

[0009] After completing the goods receipt business corresponding to the purchase order, the target type of materials are shipped out according to the distribution plan information.

[0010] As one implementation manner, extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information includes:

[0011] Obtain demand extraction configuration information corresponding to the target type of material;

[0012] Configuration information is extracted according to the demand, and materials of the target type in the reservation order and / or the sales order are extracted to determine the distribution plan information.

[0013] As one implementation manner, extracting configuration information according to the demand, extracting materials of the target type in the reservation order and / or the sales order to determine the distribution plan information includes:

[0014] Extract configuration information according to the demand, and match whether the line items of the reservation order and / or the sales order contain materials of the target type;

[0015] If so, matching line items in the reservation order and / or the sales order are extracted and stored to determine the delivery plan information.

[0016] As one implementation mode, determining a purchase order according to the distribution plan information to carry out the purchase includes:

[0017] Matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in at least one pre-established purchase order;

[0018] If the match is successful, the matched purchase order will be used as the final purchase order for procurement.

[0019] As one implementation manner, matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order includes:

[0020] Matching is performed according to the creation time of the purchase order until the sum of the purchase quantities of the target type of materials in the matched purchase order is consistent with the demand quantity of the target type of materials in the distribution plan information, and the matching is successful.

[0021] As one implementation manner, matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order further includes:

[0022] The distribution plan information and at least one successfully matched purchase order are saved in an intermediate table to store the corresponding relationship between the distribution plan information and the at least one purchase order.

[0023] As one implementation manner, after extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the method further includes:

[0024] When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process;

[0025] If so, cancellation of the delivery plan corresponding to the delivery plan information is not allowed.

[0026] As one implementation manner, after extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the method further includes:

[0027] When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process;

[0028] If not, the delivery plan corresponding to the delivery plan information is canceled, and the purchase order corresponding to the delivery plan information is released.

[0029] In a second aspect, the present application provides an electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the material management method as described in the first aspect when executing the computer program.

[0030] In a third aspect, the present application provides a computer storage medium, in which a computer program is stored. When the computer program is executed by a processor, the steps of the material management method described in the first aspect are implemented.

[0031] The present application provides a material management method, electronic device and computer storage medium, the method comprising: obtaining a reservation order and / or a sales order; extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information; determining a purchase order according to the distribution plan information for purchasing; after completing the receiving business corresponding to the purchase order, the target type of materials are shipped out according to the distribution plan information. The technical solution of the present application, by extracting the target type of materials in the reservation order and / or the sales order, determining the distribution plan information, and then determining the purchase order according to the distribution plan information for purchasing, after completing the receiving business corresponding to the purchase order, the target type of materials are shipped out directly according to the distribution plan information, can reduce inventory backlogs, improve inventory turnover, reduce warehouse management costs, reduce enterprise costs, so that the target material distribution method for reservation and sales needs is not linked to production needs, avoiding the risk of production material distribution being affected. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0033] Figure 1 A schematic diagram of a material management method provided in an embodiment of the present application;

[0034] Figure 2 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application.

[0035] Description of reference numerals: processor 110 , memory 111 , network interface 112 , bus system 113 . DETAILED DESCRIPTION

[0036] The specific embodiments of the present application will be described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the description of the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.

[0037] It should be noted that, in this article, the terms "include", "comprises" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "includes a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element. In addition, components, features, and elements with the same name in different embodiments of the present application may have the same meaning or different meanings, and their specific meanings need to be determined by their explanation in the specific embodiment or further combined with the context of the specific embodiment.

[0038] It should be understood that, although the terms first, second, third, etc. may be used to describe various information in this article, these information should not be limited to these terms. These terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of this article, the first information may also be referred to as the second information, and similarly, the second information may also be referred to as the first information. Depending on the context, the word "if" as used herein can be interpreted as "at the time of" or "when" or "in response to determination". Furthermore, as used in this article, the singular forms "one", "one" and "the" are intended to also include plural forms, unless there is an opposite indication in the context. It should be further understood that the terms "comprising", "including" indicate the existence of features, steps, operations, elements, components, projects, kinds, and / or groups, but do not exclude the existence, occurrence or addition of one or more other features, steps, operations, elements, components, projects, kinds, and / or groups. The terms "or" and "and / or" used herein are interpreted as inclusive, or mean any one or any combination. Thus, “A, B, or C” or “A, B and / or C” means “any of the following: A; B; C; A and B; A and C; B and C; A, B, and C.” An exception to this definition will occur only when a combination of elements, functions, steps, or operations are inherently mutually exclusive in some manner.

[0039] It should be understood that, although the various steps in the flowchart in the embodiment of the present application are displayed in sequence according to the indication of the arrows, these steps are not necessarily performed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and it can be performed in other orders. Moreover, at least a portion of the steps in the figure may include a plurality of sub-steps or a plurality of stages, and these sub-steps or stages are not necessarily performed at the same time, but can be performed at different times, and their execution order is not necessarily performed in sequence, but can be performed in turn or alternately with other steps or at least a portion of the sub-steps or stages of other steps.

[0040] It should be noted that, in this article, step codes such as S101, S102, etc. are used for the purpose of expressing the corresponding content more clearly and concisely, and do not constitute a substantial limitation on the sequence. When implementing the step, those skilled in the art may execute S102 first and then S101, etc., but these should all be within the scope of protection of this application.

[0041] It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0042] See also Figure 1 , is a flow chart of a material management method provided in an embodiment of the present application. Figure 1As shown, the material management method of the present application includes the following steps:

[0043] Step S101: Obtain a reservation order and / or a sales order;

[0044] A reservation is a plan for future shipments, which includes the quantity of materials and the type of business posted when the shipment is made. Its purpose is to keep the materials that need to be shipped from the warehouse in the future in a "ready" state of the system, simplify and speed up the material in and out processing flow and material preparation tasks, and ensure that the materials can be obtained when needed. The reservation of materials can be requested by various departments through various related vouchers with account allocations, such as R&D material collection, department material collection, etc. Users can use reservations to handle production plan requirements and non-production plan requirements, and can also be used for transfers into and out of the warehouse.

[0045] Planners create reservation orders based on actual non-production material demand or unplanned production material demand. The line items of a reservation order include material name, material code, plant, movement type, effective date, etc. Non-production materials refer to materials that are not directly used in product production, including various supplies, equipment, tools, office supplies, maintenance supplies, safety protection supplies, labor protection supplies, environmental protection supplies, consumables, and other items required in the business management process of the enterprise.

[0046] Sales orders involve all aspects of sales activities conducted by enterprises through the SAP (System Applications and Products) system, including the management of sales organizations, distribution channels, product groups, and the specific division of sales areas. It allows enterprises to store and manage customer and product-related data, and is specifically designed to facilitate various business processes in the enterprise, including customer master data or material master data, sales, order delivery, pricing, billing, and credit management. Planners create sales orders based on actual sales needs. The line items of sales orders include material name, material code, factory, order type, effective date, etc.

[0047] Step S102: extracting materials of the target type in the reservation order and / or the sales order to determine the distribution plan information;

[0048] The distribution plan information includes the material name, material code, factory, movement type, order type, effective date, distribution time, and distribution location of the target type of material.

[0049] This embodiment takes the target type of material as JIT (Just in time) material as an example, but is not limited to other types of materials suitable for procurement and distribution using the method of this application. The materials of some factories and production lines are purchased using the JIT production model. The JIT production method is actually to keep the material flow and information flow in the production synchronized, so that the right amount of materials enters the right place at the right time to produce products of the right quality. This method can reduce inventory, shorten working hours, reduce costs, and improve production efficiency. It should be noted that the target type of material can also be other mobile types of materials in the reservation order and / or sales order.

[0050] Step S103: Determine a purchase order according to the distribution plan information to carry out the purchase;

[0051] Specifically, purchase orders are matched according to the distribution plan information, and the purchase orders that meet the matching requirements are sent to the SRM (Supplier Relationship Management) system for procurement. In the SRM system, the supplier generates a delivery note for the purchase order associated with the distribution plan information according to the delivery date for delivery.

[0052] Step S104: After completing the goods receipt business corresponding to the purchase order, the target type of materials are shipped out according to the distribution plan information.

[0053] Specifically, after the supplier delivers the goods according to the purchase order, the SAP system executes the receipt business for the purchase order. After the receipt is completed, the JIT materials are shipped out according to the distribution plan information corresponding to the purchase order, meeting the principle of one in and one out for physical and accounting, and achieving the goal of zero warehouse inventory.

[0054] The technical solution of the present application extracts the target type of materials in the reservation order and / or sales order, determines the distribution plan information, and then determines the purchase order according to the distribution plan information for procurement. After completing the receiving business corresponding to the purchase order, the target type of materials are directly shipped out according to the distribution plan information. This can reduce inventory backlogs, improve inventory turnover, reduce warehouse management costs, and reduce corporate costs, so that the distribution method of target materials for reservation and sales needs is not linked to production needs, avoiding the risk of affecting the distribution of production materials.

[0055] In one embodiment, extracting materials of a target type in a reservation order and / or a sales order to determine distribution plan information includes:

[0056] Obtain the demand extraction configuration information corresponding to the target type of material;

[0057] Extract configuration information based on demand and extract materials of the target type from reservation orders and / or sales orders to determine distribution plan information.

[0058] Here, the demand extraction configuration information may refer to a target demand plan extraction range configuration table, including material information of target demand that can be extracted corresponding to the reserved demand and the sales delivery order demand, such as a JIT demand plan extraction range configuration table, wherein the material information of JIT demand that can be extracted corresponding to the reserved demand includes factory, movement type, material code, effective date, etc., and the material information of JIT demand that can be extracted corresponding to the sales delivery order demand includes factory, order type, material code, effective date, etc. According to the target demand plan extraction range configuration table, the target materials in the reservation order and / or sales order can be extracted to determine the distribution plan information.

[0059] In one embodiment, extracting configuration information according to demand, extracting materials of target types in reservation orders and / or sales orders to determine distribution plan information includes:

[0060] Extract configuration information based on demand and check whether the line items in the reservation order and / or sales order contain materials of the target type;

[0061] If so, matching line items in the reservation order and / or sales order are extracted and stored to determine the delivery plan information.

[0062] Specifically, according to the target demand plan extraction range configuration table, it is possible to match whether the line items of the reservation order and / or sales order contain materials of the target type, wherein each line item includes a type of material information. By matching all the contents of the line item with the contents of the target demand plan extraction range configuration table, it is possible to determine whether the line item is a material of the target type. If so, the matching line items in the reservation order and / or sales order are stored in the distribution plan table to determine the distribution plan information.

[0063] In one embodiment, determining a purchase order according to the distribution plan information to carry out the purchase includes:

[0064] Matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in at least one pre-established purchase order;

[0065] If the match is successful, the matched purchase order will be used as the final purchase order for procurement.

[0066] In one embodiment, matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order includes:

[0067] Matching is performed according to the creation time of the purchase order until the sum of the purchase quantities of the target type of materials in the matched purchase order is consistent with the demand quantity of the target type of materials in the distribution plan information, and the match is successful.

[0068] Specifically, after the planner confirms the delivery time and delivery station information in the delivery plan in the SAP system, the delivery plan information and the purchase order are matched in the order of the creation time of the purchase order. First, the purchase quantity of the target type of material in the purchase order with the earliest creation time is matched with the demand quantity of the target type of material in the delivery plan information. If they are consistent, the match is successful. If they are inconsistent, the second purchase order is matched according to the creation time until the sum of the purchase quantities of the target type of materials in the matched purchase orders meets the demand quantity of the target type of materials in the delivery plan. At this time, a delivery plan may match one or more purchase orders. For example, if the demand quantity of material A in the current delivery plan information is 20, and the purchase quantity of material A in the first matched purchase order is 10, the next purchase order will be matched according to the purchase order creation time. If the purchase quantity of material A in the next purchase order is 10, the sum of the purchase quantities of material A in the two matched purchase orders is 20, which is consistent with the demand quantity of material A in the current delivery plan information. The match is successful, and the successfully matched purchase order is sent to the SRM system.

[0069] In one embodiment, matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order further includes:

[0070] The distribution plan information and at least one successfully matched purchase order are saved in an intermediate table to store the corresponding relationship between the distribution plan information and the at least one purchase order.

[0071] Specifically, at least one purchase order that meets the distribution plan information matching requirements is saved in an intermediate table to store the corresponding relationship between the distribution plan information and the at least one purchase order, so that the corresponding relationship between the distribution plan information and the purchase order can be queried.

[0072] In one embodiment, after extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the following steps are further included:

[0073] When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process;

[0074] If so, cancellation of the delivery plan corresponding to the delivery plan information is not allowed.

[0075] Specifically, when the user selects a line item in the distribution plan information and clicks to cancel the distribution plan, the SRM system checks whether there is a valid delivery note for the purchase order corresponding to the distribution plan. If so, it means that the supplier has prepared the materials or goods for the purchase order, and cancellation of the distribution plan is not allowed.

[0076] In one embodiment, after extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the following steps are further included:

[0077] When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process;

[0078] If not, the delivery plan corresponding to the delivery plan information is canceled, and the purchase order corresponding to the delivery plan information is released.

[0079] Specifically, when the user selects a line item in the delivery plan information and clicks to cancel the delivery plan, the SRM system checks whether there is a valid delivery note for the purchase order corresponding to the delivery plan. If not, the delivery plan corresponding to the delivery plan information selected by the user is canceled, and the purchase order corresponding to the delivery plan information is released so that the purchase order can be matched with the next delivery plan information. In this way, planners do not need to create purchase orders repeatedly, thereby improving work efficiency.

[0080] Based on the same inventive concept as the above embodiments, the present application embodiment provides an electronic device, such as Figure 2 As shown, the electronic device includes: a processor 110 and a memory 111 for storing a computer program that can be run on the processor 110; wherein, Figure 2 The processor 110 shown in the figure is not used to indicate that the number of the processor 110 is one, but is only used to indicate the positional relationship of the processor 110 relative to other devices. In actual applications, the number of the processor 110 may be one or more; similarly, Figure 2 The memory 111 shown in the figure has the same meaning, that is, it is only used to refer to the position relationship of the memory 111 relative to other devices. In actual applications, the number of memories 111 can be one or more. When the processor 110 is used to run a computer program, the above-mentioned material management method is implemented.

[0081] The electronic device may also include: at least one network interface 112. The various components in the electronic device are coupled together via a bus system 113. It is understood that the bus system 113 is used to achieve connection and communication between these components. In addition to the data bus, the bus system 113 also includes a power bus, a control bus, and a status signal bus. However, for the sake of clarity, in Figure 2 Various buses are labeled as bus system 113 .

[0082] The memory 111 may be a volatile memory or a nonvolatile memory, or may include both volatile and nonvolatile memories. The nonvolatile memory may be a read-only memory (ROM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), an electrically erasable programmable read-only memory (EEPROM), a ferromagnetic random access memory (FRAM), a flash memory, a magnetic surface memory, an optical disk, or a compact disc read-only memory (CD-ROM); the magnetic surface memory may be a disk memory or a tape memory. The volatile memory may be a random access memory (RAM), which is used as an external cache. By way of example and not limitation, many forms of RAM are available, such as static random access memory (SRAM), synchronous static random access memory (SSRAM), dynamic random access memory (DRAM), synchronous dynamic random access memory (SDRAM), double data rate synchronous dynamic random access memory (DDRSDRAM), enhanced synchronous dynamic random access memory (ESDRAM), synchronous link dynamic random access memory (SLDRAM, SyncLink Dynamic Random Access Memory), and direct RAM bus random access memory (DRRAM, Direct Rambus Random Access Memory).The memory 111 described in the embodiments of the present application is intended to include but is not limited to these and any other suitable types of memories.

[0083] The memory 111 in the embodiment of the present application is used to store various types of data to support the operation of the electronic device. Examples of these data include: any computer program used to operate on the electronic device, such as an operating system and an application; contact data; phone book data; messages; pictures; videos, etc. Among them, the operating system includes various system programs, such as a framework layer, a core library layer, a driver layer, etc., which are used to implement various basic services and handle hardware-based tasks. The application program may include various applications, such as a media player (Media Player), a browser (Browser), etc., for implementing various application services. Here, the program that implements the method of the embodiment of the present application may be included in the application program.

[0084] Based on the same inventive concept as the above-mentioned embodiment, this embodiment further provides a computer storage medium, in which a computer program is stored. The computer storage medium may be a ferromagnetic random access memory (FRAM), a read-only memory (ROM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), an electrically erasable programmable read-only memory (EEPROM), a flash memory, a magnetic surface memory, an optical disc, or a compact disc read-only memory (CD-ROM); it may also be various devices including one or any combination of the above memories, such as a mobile phone, a computer, a tablet device, a personal digital assistant, etc. When the computer program stored in the computer storage medium is executed by the processor, the above-mentioned material management method is implemented. For the specific steps implemented when the computer program is executed by the processor, please refer to Figure 1 The description of the illustrated embodiment will not be repeated here.

[0085] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0086] In this document, the terms "comprises," "comprising," or any other variations thereof, are intended to cover a non-exclusive inclusion of elements other than those listed and may also include additional elements not expressly listed.

[0087] The above are only specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A material management method, characterized in that: The method comprises: Obtain reservations and / or sales orders; Extracting materials of the target type in the reservation order and / or the sales order to determine distribution plan information; Determine a purchase order based on the distribution plan information to carry out the purchase; After completing the goods receipt business corresponding to the purchase order, the target type of materials are shipped out according to the distribution plan information.

2. The material management method according to claim 1, characterized in that: The extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information includes: Obtain demand extraction configuration information corresponding to the material of the target type; Configuration information is extracted according to the demand, and materials of the target type in the reservation order and / or the sales order are extracted to determine the distribution plan information.

3. The material management method according to claim 2, characterized in that: The extracting configuration information according to the demand, extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, includes: Extract configuration information according to the demand, and match whether the line items of the reservation order and / or the sales order contain materials of the target type; If so, matching line items in the reservation order and / or the sales order are extracted and stored to determine the delivery plan information.

4. The material management method according to claim 3, characterized in that: Determining a purchase order according to the distribution plan information to carry out the purchase includes: Matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in at least one pre-established purchase order; If the match is successful, the matched purchase order will be used as the final purchase order for procurement.

5. The material management method according to claim 4, characterized in that: The matching of the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order includes: Matching is performed according to the creation time of the purchase order until the sum of the purchase quantities of the target type of materials in the matched purchase order is consistent with the demand quantity of the target type of materials in the distribution plan information, and the matching is successful.

6. The material management method according to claim 5, characterized in that: The step of matching the required quantity of the target type of material in the distribution plan information with the purchase quantity of the target type of material in the pre-established purchase order further includes: The distribution plan information and at least one successfully matched purchase order are saved in an intermediate table to store the corresponding relationship between the distribution plan information and the at least one purchase order.

7. The material management method according to any one of claims 1 to 6, characterized in that: After extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the method further includes: When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process; If so, cancellation of the delivery plan corresponding to the delivery plan information is not allowed.

8. The material management method according to any one of claims 1 to 6, characterized in that: After extracting the target type of materials in the reservation order and / or the sales order to determine the distribution plan information, the method further includes: When the user chooses to cancel the delivery plan corresponding to the delivery plan information, verify whether the purchase order corresponding to the delivery plan information has entered the delivery process; If not, the delivery plan corresponding to the delivery plan information is canceled, and the purchase order corresponding to the delivery plan information is released.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the material management method according to any one of claims 1 to 8 are implemented.

10. A computer storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the material management method according to any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Order transaction method for Internet e-commerce

    CN112184393A

  • Logistics order cancellation confirmation method and device

    CN112418765A

  • Order processing method and device, electronic equipment and storage medium

    CN114971785A

  • Material processing method, device and system and computer readable storage medium

    CN116187900A

  • Enterprise purchase matching method and equipment

    CN117829541A