Construction site intelligent power utilization management system

By combining intelligent circuit breakers and management platforms at construction sites with big data analytics, the visualization and information management of construction power consumption is achieved, solving the problem of power safety management at construction sites, improving safety and efficiency, optimizing power configuration, and reducing accidents and costs.

CN120090344BActive Publication Date: 2026-03-17THE THIRD CONSTR CO LTD OF CHINA CONSTR THIRD ENG BUREAU
View PDF 4 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-02-19
Publication Date
2026-03-17

AI Technical Summary

Technical Problem

Temporary power safety management at construction sites is difficult to visualize, inform, and intelligently manage, leading to problems such as overloading, unauthorized wiring, short circuits due to damaged wiring, leakage, and inadequate safety management, resulting in frequent accidents.

Method used

Intelligent circuit breakers are used to collect construction power consumption data, and big data analysis is performed through a management platform to achieve visualized, information-based, and intelligent management of construction power consumption. This includes a large screen dashboard module, an electrical box monitoring module, an electrical box management module, an authorized power consumption module, an inspection management module, an alarm module, a power consumption statistics module, and a back-end settings module. Combined with a 4G IoT module, data is transmitted in real time, and the management platform calculates the load rate and makes reasonable power consumption configuration.

Benefits of technology

It has improved the level and efficiency of construction power safety management, reduced labor costs, promptly detected power failures and equipment leakage, optimized power configuration, reduced equipment investment, reduced downtime and production costs, improved energy utilization, and reduced the occurrence of accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120090344B_ABST
    Figure CN120090344B_ABST
Patent Text Reader

Abstract

The application discloses a kind of construction site intelligent power utilization management system, including management platform, user terminal, distribution box, management platform and distribution box, user terminal are communicated wirelessly, the distribution box is equipped with intelligent circuit breaker, the intelligent circuit breaker is used to collect construction power utilization data, and is transferred to management platform, the management platform is used to carry out big data analysis to construction power utilization data, realize the visual, informatization, intelligent whole process management of building site construction power utilization.The construction site intelligent power utilization management system of the application solves the problems of frequent electrical fires in temporary power utilization of building construction, difficult control of private pulling and random connection, difficult implementation of inspection management, difficult monitoring of power utilization, difficult maintenance of power utilization failure, etc.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power communication technology, and in particular to an intelligent power management system for construction sites. Background Technology

[0002] Temporary power supply at construction sites is a crucial component throughout the entire construction process, and its safe management is essential for the smooth progress of the entire project. Currently, safety issues arising from temporary power supply in construction are becoming increasingly prominent. Frequent accidents caused by overloading, haphazard wiring, damaged wiring leading to short circuits, electrical leaks, and inadequate safety management are occurring frequently, creating numerous obstacles to construction. Summary of the Invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art, and proposes an intelligent power management system for construction sites.

[0004] The technical solution of this invention is implemented as follows: This invention discloses an intelligent power management system for construction sites, including a management platform, a user terminal, and a distribution box. The management platform communicates wirelessly with the distribution box and the user terminal. The distribution box is equipped with an intelligent circuit breaker, which is used to collect construction power consumption data and transmit it to the management platform. The management platform is used to perform big data analysis on the construction power consumption data to realize the visualization, informatization, and intelligent full-process management of construction power consumption.

[0005] Furthermore, the management platform includes a large-screen dashboard module, an electrical box monitoring module, and an electrical box management module;

[0006] The large-screen dashboard modules are used to display electricity consumption data, including project overview, distribution of electrical boxes, equipment usage, alarm status, inspection status, and other data information.

[0007] The electrical box monitoring module is used to monitor, analyze and statistically process the power consumption data of each distribution box. The power consumption data includes voltage, current, temperature, leakage current, power consumption and historical data.

[0008] The electrical box management module is used to control the opening or closing of circuits in each distribution box.

[0009] Furthermore, the management platform includes an authorized power consumption module, which is used to receive power consumption requests from user terminals and perform permission comparisons. If the requesting user has power consumption permission, the power consumption is authorized and the circuit breaker is tripped after the power consumption is completed, and the power consumption is counted. If the requesting user does not have power consumption permission, an alarm is triggered and the circuit breaker is automatically tripped.

[0010] Furthermore, the management platform includes a subcontractor electricity consumption statistics module, which is used to measure the electricity consumption of each subcontractor after the subcontractor scans the code to authorize electricity use.

[0011] Furthermore, the management platform includes an inspection management module, which includes a leakage protection test module. The leakage protection test module is used to periodically control the opening and closing operation of the circuit breaker and test whether its residual current operation is normal.

[0012] The inspection management module includes a grounding test module, which is used to detect the grounding resistance of the distribution box and test whether the grounding wire inside the distribution box is securely connected based on the resistance value.

[0013] Furthermore, the management platform includes an alarm module, a power consumption statistics module, a monthly report module, and a backend settings module;

[0014] The alarm module is used for processing and statistical analysis of alarm information from the distribution box circuit.

[0015] The power statistics module is used for overall power statistics of each circuit in the distribution box;

[0016] The monthly report module is used for monthly electricity consumption analysis and optimization suggestions.

[0017] The backend settings module is used for maintaining project information, distribution box information, and personnel information.

[0018] Furthermore, the smart circuit breaker is used to transmit the collected electricity consumption data to the 4G IoT module using the MOTT protocol, and the 4G IoT module transmits the data to the management platform in real time via 4G.

[0019] Furthermore, the distribution box is used to upload electricity consumption data to the management platform at set time intervals. The distribution box is also used to upload abnormal signals to the management platform in a trigger mode. Specifically, when there is a change in the abnormal signal, the abnormal signal is immediately uploaded to the management platform so that the management platform can analyze and process the abnormal signal.

[0020] Furthermore, the management platform is used to calculate the electrical load of each distribution box and calculate the load rate of the distribution box. The load rate of the distribution box is equal to the ratio of the electrical load of the distribution box to its rated capacity. When the load rate of the distribution box is greater than a first preset value, the distribution box is prompted to operate in a first state. When the load rate of the distribution box is less than a second preset value, the distribution box is prompted to operate in a second state.

[0021] Furthermore, the distribution box includes a primary distribution box, a secondary distribution box, and a tertiary distribution box. The input terminal of the primary distribution box is electrically connected to the power distribution room, and the output terminal of the primary distribution box is electrically connected to the input terminals of multiple secondary distribution boxes. The primary distribution box supplies power to all secondary distribution boxes. The output terminal of the secondary distribution box is electrically connected to the input terminals of multiple tertiary distribution boxes. The secondary distribution box supplies power to the tertiary distribution boxes connected to it. The tertiary distribution boxes supply power to the electrical equipment. The management platform communicates with the secondary distribution boxes. The secondary distribution boxes are equipped with a communication module and an intelligent circuit breaker.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] The intelligent power management system for construction sites of this invention collects information on various circuits of construction power supply through the circuit breaker acquisition module in the temporary distribution box. After processing by the processing module, the information is exchanged with the cloud platform through the Internet of Things. At the same time, combined with the big data analysis function of the management cloud platform, it achieves the goal of visual, information-based and intelligent full-process management of temporary power supply for construction sites.

[0024] This invention employs an intelligent power management system for construction sites, which greatly improves the level and efficiency of power safety management during construction, reduces the number of management personnel, and lowers labor costs. Furthermore, this invention can rationally adjust the layout of power boxes in areas with tight or no power supply by monitoring the real-time load of the power boxes. In addition, by combining remote switching with power consumption data, it can promptly detect equipment or line leakage and long-term no-load operation of equipment, thereby improving power consumption, reducing equipment investment, and enabling reuse.

[0025] This invention can provide real-time alarms. When an alarm occurs, the circuit breaker buzzer sounds, an alarm pop-up window appears on the platform, and the equipment administrator receives a text message or phone alarm notification simultaneously. The notification informs the equipment administrator which distribution box and which circuit in which location experienced a fault alarm, accurately locating the fault point, reducing the number of faults, enabling rapid repairs, and reducing downtime and production costs caused by power failures.

[0026] The intelligent power management system for construction sites of this invention monitors the use of electricity during construction, promptly detecting situations such as over-powering of distribution boxes, idle distribution boxes, equipment leakage, and prolonged unloaded use. Through monthly reports or early warnings, it analyzes power loss points and proposes suggested optimization schemes for power configuration, thereby improving the utilization rate of electrical energy and making it more energy-efficient and environmentally friendly.

[0027] In summary, the intelligent power management system for construction sites using this invention solves problems such as frequent electrical fires during temporary power supply in construction sites, difficulty in controlling unauthorized wiring, difficulty in implementing inspection management, difficulty in monitoring power usage, and difficulty in maintaining power supply systems in case of malfunctions. Attached Figure Description

[0028] Figure 1 This is a schematic diagram of the structure of the intelligent circuit breaker provided in an embodiment of the present invention;

[0029] Figure 2 A schematic diagram of the structure of the data acquisition device for the intelligent circuit breaker provided in an embodiment of the present invention;

[0030] Figure 3 A schematic diagram of the bottom shell and cover plate of the data acquisition device for the intelligent circuit breaker provided in an embodiment of the present invention;

[0031] Figure 4 This is a schematic diagram of the bottom shell of the data acquisition device for the intelligent circuit breaker provided in an embodiment of the present invention;

[0032] Figure 5 This is an installation diagram of the phase current transformer and the zero-sequence current transformer provided in an embodiment of the present invention;

[0033] Figure 6 A circuit diagram of a data acquisition board provided in an embodiment of the present invention;

[0034] Figure 7 A circuit diagram of a rectifier board provided for an embodiment of the present invention;

[0035] Figure 8 A circuit diagram of the main control circuit section of the motherboard provided in an embodiment of the present invention;

[0036] Figure 9 A circuit diagram of the metering chip section of the motherboard provided in an embodiment of the present invention;

[0037] Figure 10 A circuit diagram of an RS485 communication circuit provided in an embodiment of the present invention;

[0038] Figure 11 A circuit diagram of a trip control circuit provided in an embodiment of the present invention;

[0039] Figure 12 A circuit diagram of the PE loop detection circuit provided in an embodiment of the present invention;

[0040] Figure 13 A circuit diagram of the PE disconnection detection circuit provided in an embodiment of the present invention;

[0041] Figure 14 A circuit diagram of a power supply circuit provided for an embodiment of the present invention;

[0042] Figure 15 A circuit diagram of a display circuit provided in an embodiment of the present invention;

[0043] Figure 16 A circuit diagram of a leakage current detection circuit provided in an embodiment of the present invention;

[0044] Figure 17 A schematic diagram of the intelligent power management system for construction sites provided in an embodiment of the present invention;

[0045] Figure 18 A schematic diagram defining the MQTT data protocol;

[0046] Figure 19 This is a schematic diagram for authorized power supply.

[0047] In the attached diagram, 1 is the electronic module, 2 is the data acquisition module, 21 is the bottom shell, 211 is the first receiving slot, 212 is the second receiving slot, 213 is the hollow cylinder, 214 is the through hole, 215 is the first connecting hole, 22 is the cover plate, 221 is the first through hole, 222 is the second through hole, 223 is the third through hole, 224 is the second connecting hole, 23 is the phase current transformer, 24 is the zero-sequence current transformer, 251 is the A terminal, 252 is the B terminal, 253 is the C terminal, 254 is the N terminal, 255 is the PE terminal, 26 is the data transmission interface, 27 is the power interface, and 3 is the circuit breaker body. Detailed Implementation

[0048] To enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0049] Unless otherwise defined, the technical or scientific terms used in this invention shall have the ordinary meaning understood by one of ordinary skill in the art to which this invention pertains. The terms "first," "second," and similar terms used in this invention do not indicate any order, quantity, or importance, but are merely used to distinguish different components. Similarly, the terms "an," "a," or "the" do not indicate a quantity limitation, but rather indicate the presence of at least one. The terms "comprising" or "including" mean that the element or object preceding the word encompasses the elements or objects listed following the word and their equivalents, without excluding other elements or objects. The terms "connected" or "linked" are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Up," "down," "left," "right," etc., are used only to indicate relative positional relationships; when the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0050] In the various figures, the same elements are represented by similar reference numerals. For clarity, not all parts in the figures are drawn to scale. Furthermore, some well-known parts may not be shown in the figures.

[0051] Many specific details of the invention, such as the structure, materials, dimensions, processing methods, and techniques of the components, are described below to provide a clearer understanding of the invention. However, as those skilled in the art will understand, the invention may be implemented without following these specific details.

[0052] This invention integrates circuit data acquisition and processing modules into a standard circuit breaker based on existing data monitoring and digitization technologies. By combining existing IoT technology with a communication module integrated into the standard circuit breaker or developing a gateway module, it enables monitoring data from all levels of temporary construction power distribution boxes and communication with the management platform. It analyzes various temporary construction power usage scenarios, establishes a targeted database on the platform, and analyzes and displays the collected and processed power usage data, transforming manual management into online, visual management. Simultaneously, it divides the platform into functional modules based on the problems to be solved, enabling standardized inspections, fault alarms, rapid fault location, big data analysis of power configuration, and power consumption statistics.

[0053] See Figure 1 This invention discloses an intelligent power management system for construction sites, including a management platform, user terminals, and distribution boxes. The management platform communicates wirelessly with the distribution boxes and user terminals. The distribution boxes are equipped with intelligent circuit breakers, which are used to collect construction power consumption data and transmit it to the management platform. The management platform is used to perform big data analysis on the construction power consumption data to achieve visualized, information-based, and intelligent full-process management of construction power consumption at construction sites.

[0054] The management platform can be a cloud platform.

[0055] The management platform includes a large screen dashboard module, an electrical box monitoring module, an electrical box management module, an authorized power consumption module, an inspection management module, an alarm module, a power consumption statistics module, a subcontractor power consumption statistics module, a monthly report module, and a backend settings module.

[0056] The large-screen dashboard modules are used to display electricity consumption data, including project overview, distribution of electrical boxes, equipment usage, alarm status, inspection status, and other data information.

[0057] The electrical box monitoring module is used to monitor, analyze and statistically process the power consumption data of each distribution box. The power consumption data includes voltage, current, temperature, leakage current, power consumption and historical data.

[0058] The electrical box management module is used to control the opening or closing of circuits in each electrical box.

[0059] Authorized power access is used to allow specific electricians or operators to use electricity by scanning a code. When unauthorized personnel use electricity, the system will send an SMS alarm and disconnect the circuit breaker, so as to achieve the purpose of accurate statistics on the electricity consumption of the work group.

[0060] The inspection management module is used for daily power consumption inspections of each distribution box;

[0061] The alarm module is used for processing and statistical analysis of alarm information from the distribution box circuit.

[0062] The power statistics module is used for overall power statistics of each circuit in the distribution box;

[0063] The subcontractor electricity consumption statistics module is used to measure the electricity consumption of each subcontractor after the subcontractor scans the code to authorize electricity use;

[0064] The monthly report module is used for monthly electricity consumption analysis and optimization suggestions.

[0065] The backend settings module is used for backend management of project information, power distribution box information, personnel information maintenance, etc.

[0066] The distribution box of this invention is equipped with an intelligent circuit breaker. The intelligent circuit breaker collects power consumption data and monitors power failures in real time. When a power failure occurs, the circuit breaker body is operated to trip, which helps to protect the life and property safety of users.

[0067] The power usage status of the power distribution box for construction power carriers can be monitored in real time through circuit breakers. In case of power failure risk, alarms will be triggered to management personnel in real time, so as to find the power failure point in time for maintenance and eliminate safety risks.

[0068] The electrical box monitoring module mainly monitors and analyzes the power consumption data (voltage, current, temperature, leakage current, power consumption, etc.) of each electrical box.

[0069] The management platform enables multi-level management, deploying enterprise back-end management, project management, and APP terminals. It displays the power consumption status of all projects and individual projects, mainly including equipment information, load usage, power consumption statistics, alarm status, and alarm handling, facilitating the overall monitoring of power consumption.

[0070] Furthermore, the authorized power consumption module receives power consumption requests from user terminals and performs permission comparisons. If the requesting user has power consumption permission, the system authorizes power consumption and disconnects the circuit breaker after power consumption is completed, and calculates the power consumption. If the requesting user does not have power consumption permission, an alarm is triggered and the circuit breaker is automatically disconnected. Project team electricians scan a code to authorize power consumption. When unauthorized personnel use power, the system sends an SMS alarm and disconnects the circuit breaker, achieving accurate power consumption statistics for the team.

[0071] Furthermore, the inspection management module is used to display and statistically analyze inspection plans and specific inspection details in real time, in conjunction with the electricity management system. By integrating the inspection management module with the electricity management system, paperless daily electricity inspections are achieved, and the real-time display and statistical analysis of inspection plans and specific inspection details effectively ensures a closed-loop inspection process.

[0072] Furthermore, the management platform includes an inspection management module, which includes a leakage protection test module. The leakage protection test module is used to periodically control the opening and closing operation of the circuit breaker (such as opening and closing) to test whether its residual current operation is normal.

[0073] The inspection management module includes a grounding test module, which is used to detect the grounding resistance of the distribution box and test whether the grounding wire inside the distribution box is securely connected based on the resistance value.

[0074] Furthermore, the alarm module is used to issue alarm notifications when electrical safety hazards occur in the circuit, informing the user of the abnormality in which electrical circuit under which distribution box. When an electrical safety hazard occurs, the alarm information is sent in real time via platform pop-ups, SMS / telephone notifications, and device-side alarms, allowing relevant personnel to be informed immediately which electrical circuit under which device is experiencing an abnormality and to promptly eliminate the hazard.

[0075] Furthermore, the alarm notification method can be one or more of the following: platform pop-up notification, SMS notification, telephone notification, and device-side alarm.

[0076] Furthermore, the smart circuit breaker is used to transmit the collected electricity consumption data to the 4G IoT module using the MQTT protocol. The 4G IoT module then transmits the data to the management platform in real time via 4G. The MQTT data protocol is defined as follows: Figure 2 As shown.

[0077] Furthermore, the distribution box is used to upload electricity consumption data to the management platform at set time intervals. The distribution box is also used to upload abnormal signals to the management platform in a trigger mode. Specifically, when there is a change in the abnormal signal, the abnormal signal is immediately uploaded to the management platform so that the management platform can analyze and process the abnormal signal.

[0078] Furthermore, the management platform is used to calculate the electrical load of each distribution box and its load factor. The load factor of a distribution box is equal to the ratio of its electrical load to its rated capacity. When the load factor of a distribution box is greater than a first preset value, it indicates that the distribution box is operating in a first state, i.e., close to full load operation. When the load factor of a distribution box is less than a second preset value, it indicates that the distribution box is operating in a second state, i.e., low energy efficiency operation. The electrical load of a distribution box refers to the total power consumed by the electrical equipment connected to the distribution box within a certain period of time.

[0079] The management platform can also process and analyze the collected data to generate charts such as load curves and load rate statistics, helping users to intuitively understand the electricity usage status. When the load of the electrical box exceeds a preset threshold, the management platform can automatically trigger a warning or alarm mechanism to promptly notify relevant personnel for handling.

[0080] The management platform can also model the construction site and the distribution boxes and electrical equipment within the construction site, display them through a large-screen dashboard module, and assign the status of the distribution boxes to different color zones. When the distribution box model is displayed in the first color on the large-screen dashboard module, it is also displayed in the first color when an alarm is present. When the distribution box is in the first state, it is displayed in the second color on the large-screen dashboard module, and then in the third color.

[0081] Furthermore, the distribution box includes a primary distribution box, a secondary distribution box, and a tertiary distribution box. The input terminal of the primary distribution box is electrically connected to the power distribution room, and the output terminal of the primary distribution box is electrically connected to the input terminals of multiple secondary distribution boxes. The primary distribution box supplies power to all secondary distribution boxes. The output terminal of the secondary distribution box is electrically connected to the input terminals of multiple tertiary distribution boxes. The secondary distribution box supplies power to the tertiary distribution boxes connected to it. The tertiary distribution boxes supply power to the electrical equipment. The management platform communicates with the secondary distribution boxes. The secondary distribution boxes are equipped with a communication module and an intelligent circuit breaker.

[0082] Furthermore, the management platform communicates wirelessly with the secondary distribution box, and also wirelessly with the primary and secondary distribution boxes. The primary and secondary distribution boxes are equipped with communication modules and intelligent circuit breakers, while the tertiary distribution box is equipped only with intelligent circuit breakers with multiple protection functions.

[0083] Primary distribution box: This box draws three-phase power, ground wire, and neutral wire from the transformer. It is specifically designed for the unique conditions of construction sites and complies with relevant construction power supply standards. The function of the primary distribution box is to serve as the starting point of the entire construction power system, providing power to the entire construction site. The primary distribution box is equipped with a tiered metering system, remote on / off function, local emergency stop button, power indicator, circuit monitoring, alarms, over / under voltage protection, leakage protection, and phase loss protection, meeting various usage needs. Its rainproof top design is suitable for outdoor work.

[0084] Secondary distribution box: This type of distribution box distributes power from the primary distribution box to the distribution points near the power consumption points, and is also designed for construction sites. The function of the secondary distribution box: As a transition between the primary and tertiary distribution boxes, the secondary distribution box is responsible for distributing power to specific power consumption areas or equipment. It is equipped with branch isolation, intelligent circuit breakers, and communication modules. While meeting platform data monitoring requirements, the intelligent circuit breakers also have over / under voltage protection, leakage protection, phase loss protection, and overload protection functions to ensure electrical safety.

[0085] A three-level distribution box is a control cabinet for electrical equipment itself, that is, a distribution box connected to the specific electrical load inside the building. The function of a three-level distribution box is to provide power to specific electrical equipment, lighting, sockets, etc., and to control and protect these devices or loads to meet their operational needs. Due to their high mobility, three-level distribution boxes are only equipped with functions such as leakage current protection, over / under voltage protection, and over-temperature protection to ensure the safety of personnel and equipment.

[0086] Furthermore, the management platform is used to analyze and process the power load of each distribution box and propose a rational power configuration scheme.

[0087] The management platform is used to divide the construction site into areas, allocate secondary distribution boxes to each area, calculate the load rate of the secondary distribution boxes in each area, assess the power consumption of each area based on the load rate, and obtain an optimized distribution box layout plan for each area based on the power consumption of each area. The power consumption status includes power shortage and idle status.

[0088] If the secondary distribution boxes in an area generally have a high load factor (e.g., over 90%), the area may face a power shortage. If the distribution boxes in an area generally have a low load factor (e.g., below 30%), the area may be considered a power slack area.

[0089] In some embodiments, the power consumption status of each area is assessed based on the load rate of the secondary distribution boxes in each area. Specifically, if more than a first preset value (which can be a proportion or a number, set as needed) of the secondary distribution boxes in a region have a high load rate (the load rate exceeds the first threshold, i.e., a high load rate), then the region is determined to be a power shortage area. If more than a second preset value (which can be a proportion or a number, set as needed, and the second preset value can be equal to the first preset value) of the secondary distribution boxes in a region have a low load rate (the load rate is lower than the second threshold, i.e., a low load rate), then the region is determined to be a power idle area.

[0090] The principle for optimizing the layout of distribution boxes in each region based on the power consumption situation is: reduce the number of secondary distribution boxes in areas with vacant power supply and increase the number of secondary distribution boxes in areas with high power demand.

[0091] The process of allocating secondary distribution boxes to each area includes: calculating the electrical load of each area based on the electrical equipment used; and selecting appropriate secondary distribution boxes for allocation based on the electrical load of each area.

[0092] The management platform is used to monitor the real-time load of electrical boxes, rationally adjust the layout of distribution boxes in areas with tight or no power supply, and, through remote switching and power consumption data, promptly detect equipment or line leakage and prolonged idle operation of equipment. It also analyzes and processes the power load of each distribution box, proposing optimized power configuration schemes. When equipment or line leakage or prolonged idle operation of equipment is detected, an alarm is triggered, and corresponding measures are taken.

[0093] Furthermore, the intelligent circuit breaker incorporates a data acquisition module, a data processing module, and a communication module. The data acquisition module uses miniature sensors to collect various information such as voltage, current, temperature, and leakage current during the circuit breaker's operation, converting the collected data into digital signals. The entire data acquisition module is assembled with the lower terminal of the circuit breaker, and the lower terminal of the data acquisition module is designed with the same outgoing terminal as the circuit breaker, achieving integration between the circuit breaker and the data acquisition module.

[0094] The data acquisition module 2 includes a bottom shell 21 and a cover plate 22. A phase current transformer 23 for detecting current is installed inside the bottom shell 21. The bottom shell 21 has a through hole 214 for the outgoing or incoming line of the circuit breaker body 3 to pass through. A data acquisition board is installed inside the bottom shell 21. The current transformer is electrically connected to the data acquisition board. The data acquisition board has terminals that correspond one-to-one with the outgoing or incoming terminals of the circuit breaker body 3. The cover plate 22 is located at the upper end of the data acquisition board and is fixedly connected to the bottom shell 21. The cover plate 22 has a first through hole 221 for the terminals and the outgoing or incoming line to pass through. The data acquisition board has a through hole for the outgoing or incoming line to pass through.

[0095] In some embodiments, the terminal block is welded and fixed to the data acquisition board.

[0096] In some embodiments, when the intelligent circuit breaker is a single-phase circuit breaker, the data acquisition board is provided with an L terminal, an N terminal 254, and a PE terminal 255. A phase current transformer 23 is installed inside the bottom shell 21, corresponding to the L-phase outgoing or incoming line, and the phase current transformer 23 surrounds the outside of the through hole 214 corresponding to the L-phase outgoing or incoming line.

[0097] In other embodiments, when the intelligent circuit breaker is a three-phase circuit breaker, the data acquisition board is provided with A terminal 251, B terminal 252, C terminal 253, N terminal 254, and PE terminal 255. Three phase current transformers 23 are installed inside the bottom housing 21, corresponding to the A, B, and C phase outgoing or incoming lines respectively. The three phase current transformers 23 are respectively surrounding the through-holes 214 corresponding to the A, B, and C phase outgoing or incoming lines.

[0098] Furthermore, the bottom wall of the bottom shell 21 is provided with a first receiving groove 211 for accommodating the phase current transformer 23.

[0099] Furthermore, when the intelligent circuit breaker is a three-phase circuit breaker, a zero-sequence current transformer 24 is also installed inside the base shell 21. The zero-sequence current transformer 24 surrounds the three phase current transformers 23 and is electrically connected to the data acquisition board. In this embodiment, the zero-sequence current transformer 24 surrounds the three-phase lines A, B, and C, as well as the neutral line N. Further, the zero-sequence current transformer surrounds the outgoing lines of the three-phase lines A, B, and C, as well as the outgoing line of the neutral line N.

[0100] The bottom wall of the bottom shell 21 is provided with a second receiving slot 212 for accommodating the zero-sequence current transformer 24.

[0101] Two wires are led out from the phase current transformer 23 and the zero-sequence current transformer 24, and are electrically connected to the data acquisition board through matching connectors. The data acquisition board is electrically connected to the main board through the data transmission interface 26, i.e., connector P4.

[0102] Furthermore, a hollow cylinder 213 is provided on the bottom wall of the bottom shell 21, corresponding one-to-one with the wire through hole 214 provided on the bottom wall of the bottom shell 21, and the hollow cylinder 213 communicates with the corresponding wire through hole 214. The diameter of the hollow cylinder 213 is the same as the diameter of the wire through hole 214.

[0103] In some embodiments, the bottom shell 21 includes a bottom wall and a first side wall extending upward from the edge of the bottom wall. The bottom wall and the first side wall are connected to form an open receiving cavity. The bottom wall of the bottom shell 21 has a second side wall extending upward. The second side wall is located outside the hollow cylinder 213 corresponding to the three-phase outgoing or incoming lines of A, B, and C or the L-phase outgoing or incoming line. A receiving slot for accommodating the phase current transformer 23 is formed between the second side wall and the corresponding hollow cylinder 213. The bottom wall of the bottom shell 21 has a third side wall and a fourth side wall extending upward. A receiving slot for accommodating the zero-sequence current transformer 24 is formed between the third side wall and the fourth side wall.

[0104] Furthermore, the first sidewall, second sidewall, third sidewall, and fourth sidewall are integrally formed with the bottom wall.

[0105] Furthermore, the bottom shell 21 is provided with a first connecting hole 215. The cover plate 22 is provided with a second connecting hole 224 corresponding to the first connecting hole 215.

[0106] Further, see Figure 6 The data acquisition board is equipped with connectors, including a data transmission interface 26 (connector P4) and a power interface 27 (connector P3). The cover plate 22 is provided with a second through hole 222 for the data transmission interface 26 to pass through and a third through hole 223 for the power interface 27 to pass through. The data acquisition board is equipped with a voltage sampling circuit. The input terminal of the voltage sampling circuit is connected to the corresponding terminal, and the output terminal of the voltage sampling circuit is connected to the data transmission interface. The current transformer is electrically connected to the data transmission interface on the data acquisition board via a connector.

[0107] Further, the voltage sampling circuit includes resistors R7, R14, and R21, as well as capacitors C1, C2, and C3. Resistor R7 is connected in parallel with capacitor C1, resistor R14 is connected in parallel with capacitor C2, and resistor R21 is connected in parallel with capacitor C3. The first end of resistor R7 is electrically connected to the A-phase terminal via a first resistor unit. The second end of resistor R7 is grounded along with the second ends of resistors R14 and R21. The first end of resistor R14 is electrically connected to the B-phase terminal via a second resistor unit. The second end of resistor R14 is grounded along with the second end of resistor R7 and R21. The second end of resistor R21 is connected, and the first end of resistor R21 is electrically connected to the C-phase terminal via the third resistor unit. The second end of resistor R21 is connected to the second end of resistor R7 and the second end of resistor R14. The first end of resistor R7 is the A-phase voltage detection point, the first end of resistor R14 is the B-phase voltage detection point, and the first end of resistor R21 is the C-phase voltage detection point. The A-phase voltage detection points, B-phase voltage detection points, and C-phase voltage detection points are respectively connected to the data transmission interface 26 set on the data acquisition board. The current transformer is connected to the data transmission interface 26 set on the data acquisition board.

[0108] Furthermore, the first resistor unit, the second resistor unit, and the third resistor unit are all composed of multiple resistors connected in series.

[0109] Furthermore, the data acquisition board is equipped with a temperature detection circuit for detecting temperature.

[0110] Furthermore, the data acquisition board is equipped with a temperature detection circuit for detecting the temperature of the terminals.

[0111] Furthermore, a thermistor is mounted on the data acquisition board and located on the back of the terminal block to detect the terminal block temperature.

[0112] The temperature detection circuit uses a thermistor. One end of the thermistor is connected to one end of resistor R23 and one end of resistor R24. The other end of resistor R23 is connected to the power supply voltage VCC. The other end of resistor R24 ​​is connected to data transmission interface 26, i.e., connector P4, and then connected to the AD sampling port of the main control chip (the main control chip is the MCU on the main board). The other end of resistor R24 ​​is connected to one end of capacitor C4. The other ends of capacitor C4 and the thermistor are grounded. The other ends of capacitor C4 and the thermistor are connected to the N terminal 254.

[0113] Further, see Figure 7 The data acquisition module also includes a rectifier board, on which a rectifier unit is provided. The input terminal of the rectifier unit is connected to the phase line, the output terminal of the rectifier unit is connected to one end of the second power resistor, and the other end of the second power resistor is connected to the power interface.

[0114] In some embodiments, the rectifier board is provided with a first rectifier unit, a second rectifier unit, and a third rectifier unit. The first end of the first rectifier unit is directly or via connector JP2 electrically connected to terminal A 251 on the data acquisition board. The first end of the second rectifier unit is directly or via connector JP4 electrically connected to terminal B 252 on the data acquisition board. The first end of the third rectifier unit is directly or via connector JP5 electrically connected to terminal C 253 on the data acquisition board. The second ends of the first rectifier unit, the second rectifier unit, and the third rectifier unit are all connected to one end of a second power resistor. The other end of the second power resistor is connected to a power interface.

[0115] The first rectifier unit, the second rectifier unit, and the third rectifier unit are each composed of at least one rectifier diode connected in series, with its positive terminal being the first terminal and its negative terminal being the second terminal.

[0116] The second end of at least one of the first rectifier unit, the second rectifier unit, and the third rectifier unit is connected to one end of the second power resistor, and the other end of the second power resistor is directly or via connector JP3 connected to the power interface 27, i.e., connector P3.

[0117] The data acquisition board and the rectifier board are electrically connected via connectors. For example, the through-hole pins on the data acquisition board can be inserted into the through-hole pins on the rectifier board, or vice versa, thus securing and electrically connecting the data acquisition board and the rectifier board.

[0118] The data acquisition board in this embodiment is equipped with through-hole pins JP1_1, JP2_1, JP3_1, JP4_1, and JP5_1. Through-hole pin JP1_1 is electrically connected to the second end of the test winding, through-hole pin JP2_1 is electrically connected to terminal A 251, through-hole pin JP3_1 is electrically connected to power interface 27, i.e., connector P3 (used to supply the voltage rectified by the rectifier board to power interface 27), through-hole pin JP4_1 is electrically connected to terminal B 252, and through-hole pin JP5_1 is electrically connected to terminal C 253.

[0119] The rectifier board is provided with through-holes JP1, JP2, JP3, JP4, and JP5. Through-hole JP1_1 is inserted into through-hole JP1, through-hole JP2_1 is inserted into through-hole JP2, through-hole JP3_1 is inserted into through-hole JP3, and through-hole JP4_1 is inserted into through-hole JP4.

[0120] The first end of the first rectifier unit is electrically connected to one end of the through-hole JP2 and one end of the first power resistor. The first end of the second rectifier unit is electrically connected to the through-hole JP4. The first end of the third rectifier unit is electrically connected to the through-hole JP5. The second ends of the first rectifier unit, the second ends of the second rectifier unit, and the second ends of the third rectifier unit are all connected to one end of the second power resistor. The other end of the first power resistor is electrically connected to the through-hole JP1. The second end of the first rectifier unit is connected to one end of the second power resistor, and the other end of the second power resistor is electrically connected to the through-hole JP3. The power supply interface 27, i.e., connector P3, is then connected via through-hole JP3 and through-hole pin JP3-1.

[0121] Of course, the circuitry on the rectifier board can also be placed on the data acquisition board.

[0122] The data acquisition module of this invention also includes a test winding. One end of the test winding is connected to one end of a first power resistor, and the other end of the first power resistor is electrically connected to a phase line (such as the A terminal corresponding to phase A in this embodiment). The other end of the test winding is grounded through a test switch device. When the test winding is energized, the zero-sequence current transformer can detect a current signal. When the test switch device is closed, the test winding is energized, and the zero-sequence current transformer can detect a current signal and transmit it to the main control circuit. The main control circuit controls the circuit breaker to trip, thus detecting whether the circuit breaker can perform a tripping operation.

[0123] Furthermore, the test winding and the zero-sequence current transformer are wound on the same magnetic ring.

[0124] Furthermore, the data acquisition module is detachably connected to the circuit breaker body 3, and the terminals of the data acquisition module are inserted into the circuit breaker body 3 and electrically connected to the outgoing or incoming terminals of the circuit breaker body 3.

[0125] Both the incoming and outgoing sides of the circuit breaker body have screw holes for fixing wires (wiring). The screw holes on the incoming side of the circuit breaker body correspond one-to-one with the incoming terminals. The screw holes on the outgoing side of the circuit breaker body correspond one-to-one with the outgoing terminals. Loosening the screws in the screw holes allows the wiring to be removed. Tightening the screws in the screw holes on the incoming side of the circuit breaker body electrically connects the incoming wire to the incoming terminal. Tightening the screws in the screw holes on the outgoing side of the circuit breaker body electrically connects the outgoing wire to the outgoing terminal.

[0126] In this embodiment, the data acquisition module is detachably connected to the outgoing terminal of the circuit breaker body 3. The terminals of the data acquisition module are inserted into the circuit breaker body 3 and electrically connected to the outgoing terminals of the circuit breaker body 3.

[0127] Furthermore, the intelligent circuit breaker of the present invention also includes an electronic module 1, which is detachably connected to the circuit breaker body 3 and the data acquisition module.

[0128] The electronic module 1 is used to upload the data collected by the data acquisition module to the external network device, and to receive and execute the instructions issued by the external network device to operate the circuit breaker body 3 to perform opening and closing operations.

[0129] Furthermore, the electronic module 1 includes an electronic housing comprising a left housing, a middle housing, and a right housing, which are detachably connected to form a mounting cavity within the electronic housing. A motherboard, a power board, and a front panel are fixed to the electronic housing. The motherboard, power board, and front panel can be installed within the mounting cavity. The motherboard is equipped with a data processing module and a communication module.

[0130] In some embodiments, the communication module is a 4G IoT module.

[0131] The data processing module mainly consists of a microprocessor and various peripherals, used to process the acquired digital signals and communicate with the communication module (such as a 4G IoT module). The data processing module and the communication module (such as the 4G IoT module) exchange commands and communicate data via a serial port, mainly including basic functions such as hardware detection, network attachment detection, and initialization settings. By integrating the IoT module and the data processing module, the digital signals acquired by the data acquisition module are processed internally and transmitted to the IoT module using the MOTT protocol. The IoT module then transmits the data to the cloud platform in real time via 4G for data interaction. For example, it can be set to upload standard digital signals such as current, voltage, and temperature to the platform every ten minutes, and to exchange information with the platform in real time for abnormal digital signals outside the standard. The platform then analyzes and processes these abnormal signals.

[0132] See Figure 8 and Figure 9 The motherboard includes a main control chip, a metering chip, and an RS485 communication circuit. One end of the RS485 communication circuit is electrically connected to the main control chip, and the other end is connected to a communication interface. The input terminal of the metering chip is electrically connected to the voltage detection points (phase A, phase B, and phase C voltage detection points) and phase current transformers 23 (phase A, phase B, and phase C current transformers) on the data acquisition board. The output terminal of the metering chip is connected to the input terminal of the main control chip.

[0133] The input terminal of the voltage sampling circuit is used to receive the phase voltage. The output terminal of the voltage sampling circuit is connected to the voltage measurement signal input terminal VAP of the metering chip, and the output terminal of the metering chip is connected to the main control circuit. The voltage measurement signal input terminal VAN of the metering chip is connected to one end of resistor R20, the other end of resistor R20 is grounded, and capacitor C29 is connected in parallel across resistor R20.

[0134] In some embodiments, taking phase A as an example, one end of the phase current transformer is connected to one end of resistor R19 and one end of resistor R23 respectively. The other end of resistor R19 is connected to the current measurement signal input terminal IAP of the metering chip and one end of capacitor C28 respectively. The other end of resistor R23 and the other end of capacitor C28 are grounded. The other end of the phase current transformer is connected to one end of resistor R25 and one end of resistor R24 ​​respectively. The other end of resistor R25 is connected to the current measurement signal input terminal IAN of the metering chip and one end of capacitor C32 respectively. The other end of resistor R24 ​​and the other end of capacitor C32 are grounded. The output terminal of the metering chip is connected to the main control circuit.

[0135] Furthermore, the intelligent circuit breaker includes a leakage current detection circuit, which includes a zero-sequence current transformer.

[0136] See Figure 16 One end of the zero-sequence current transformer is connected to one end of resistor R41, one end of capacitor C44, the input terminal of the second filter circuit, and one end of the second clamping circuit. The other end of resistor R41 and the other end of capacitor C44 are grounded, the other end of the second clamping circuit is grounded, the output terminal of the second filter circuit is connected to the input terminal of the second amplifier, and the output terminal of the second amplifier is connected to the input terminal LeakCurrent of the main control circuit.

[0137] Furthermore, one end of the zero-sequence current transformer is connected to one end of resistor R41, one end of capacitor C44, one end of resistor R37, and the first terminal of the dual-series switching diode D2. The other ends of resistor R41 and capacitor C44 are grounded. The second and third terminals of the dual-series switching diode D2 are grounded. The other end of resistor R37 is connected to one end of capacitor C45 and one end of resistor R38. The other end of capacitor C45 is grounded. The other end of resistor R38 is connected to the input terminal of the second amplifier. The output terminal of the second amplifier is connected to the input terminal LeakCurrent of the main control circuit.

[0138] Furthermore, one end of the zero-sequence current transformer is connected to one end of resistor R41, one end of capacitor C44, one end of resistor R37, and the first terminal of the dual-series switching diode D2. The other end of resistor R41 and the other end of capacitor C44 are grounded. The second and third terminals of the dual-series switching diode D2 are grounded. The other end of resistor R37 is connected to one end of capacitor C45 and one end of resistor R38. The other end of capacitor C45 is grounded. The other end of resistor R38 is connected to the negative input terminal of operational amplifier U2. The negative input terminal of operational amplifier U2 is connected to one end of resistor R34. The other end of resistor R34 is connected to the output terminal of operational amplifier U2. The positive input terminal of operational amplifier U2 is grounded. The output terminal of operational amplifier U2 is connected to one end of inductor L2. The other end of inductor L2 is connected to one end of resistor R42, one end of capacitor C46, ​​and the input terminal LeakCurrent of the main control circuit. The other ends of resistor R42 and capacitor C46 are grounded.

[0139] Furthermore, the motherboard is equipped with a storage module and a clock module, which are electrically connected to the main control chip.

[0140] Furthermore, the main control chip uses a processor.

[0141] Furthermore, the communication circuit includes a wired communication circuit, which is connected to the main control circuit. Further, the wired communication circuit is an RS485 communication circuit.

[0142] Further, see Figure 10 The RS485 communication circuit includes an isolator chip U6 and an RS485 communication chip. The isolator chip U6 is connected between the RS485 communication chip and the main control chip, and the RS485 communication chip is connected to the communication interface.

[0143] Furthermore, the motherboard is equipped with a 485 isolated power supply circuit. The 485 isolated power supply circuit includes an isolated power module MUX1, the input terminal of which is connected to a first voltage, and the output terminal of which outputs a second voltage to power the RS485 communication chip.

[0144] Furthermore, the motherboard is equipped with a wireless communication interface for connecting to a wireless communication chip (wireless communication board). The wireless communication interface is connected to the main control chip. The motherboard is also equipped with a power board interface.

[0145] Furthermore, a wireless communication board (Internet of Things module) can also be fixed on the electronic housing, at which point the circuit breaker of the present invention will have wireless communication function.

[0146] A wireless communication chip is installed on the wireless communication board.

[0147] The IoT module in this embodiment may, but is not limited to, use a 4G IoT card.

[0148] When the circuit breaker is not equipped with a wireless communication board, the circuit breaker is electrically connected to a device with wireless communication capabilities (such as a circuit breaker with wireless communication capabilities or a separate gateway device) through a communication interface.

[0149] Furthermore, the electronic module 1 also includes an electric operating module for operating the circuit breaker body 3 to open and close.

[0150] See Figure 11 The electronic module 1 of the present invention further includes a trip control circuit, which includes a driver chip U3 and a transistor MOS1. The input terminal of the driver chip U3 is connected to the output terminal of the main control circuit, and the output terminal of the driver chip U3 is connected to the control electrode of the transistor MOS1. The first electrode of the transistor MOS1 is grounded, and the second electrode of the transistor MOS1 is connected to the second pin of connector J4 and the positive electrode of diode D6. The negative electrode of diode D6 is connected to voltage HVDC and the first pin of connector J4.

[0151] Connector J4 connects to the electric operating module. The trip control circuit controls the energization or de-energization of the electric operating module, thereby controlling the tripping of the smart circuit breaker. The electric operating module can be, but is not limited to, an electromagnet.

[0152] Further, see Figure 12The circuit of the intelligent circuit breaker of the present invention further includes a PE circuit detection circuit, which includes a current transformer T2 and an operational amplifier OPA. The first input terminal of the current transformer T2 is connected to the PE outgoing line PE_OUT (the PE outgoing line PE_OUT is connected to the circuit breaker housing), and the second input terminal of the current transformer T2 is connected to the N line PE_C. The first output terminal of the current transformer T2 is connected to one end of resistor R4, one end of capacitor C2, one end of resistor R2, and the first terminal of the double series-connected switching diode D1. The other ends of resistor R4 and capacitor C2 are grounded. The second and third terminals of transistor D1 are grounded. The other end of resistor R2 is connected to one end of capacitor C3 and one end of resistor R3, respectively. The other end of capacitor C3 is grounded. The other end of resistor R3 is connected to the negative input terminal of operational amplifier U1. The negative input terminal of operational amplifier U1 is connected to one end of resistor R1. The other end of resistor R1 is connected to the output terminal of operational amplifier U1. The positive input terminal of operational amplifier U1 is grounded. The output terminal of operational amplifier U1 is connected to one end of inductor L1. The other end of inductor L1 is connected to one end of resistor R6, one end of capacitor C5, and the input terminal CheckPE of the main control circuit, respectively. The other ends of resistor R6 and capacitor C5 are grounded.

[0153] The first clamping circuit includes a dual series-connected switching diode D1. The function of the dual series-connected switching diode D1 is to clamp the voltage at a set value.

[0154] Resistors R2 and R3, along with capacitor C3, form a filter circuit.

[0155] The PE circuit detection circuit of this invention can be used for water ingress monitoring of circuit breakers. When water enters the circuit breaker, the current transformer T2 can detect a current signal. The PE circuit detection circuit of this invention can also detect leakage current.

[0156] Further, see Figure 13 The circuit of the intelligent circuit breaker of the present invention further includes a PE disconnection detection circuit, which includes an optocoupler UO1. The first input terminal of the optocoupler UO1 is connected to the first voltage HVDC via a resistor. The second input terminal of the optocoupler UO1 is connected to PE_IN. The first output terminal of the optocoupler UO1 is connected to the first input terminal of the main control circuit, one end of the resistor R11, and one end of the capacitor C8. The other end of the resistor R11 is connected to the voltage VDD. The other end of the capacitor C8 is grounded. The second output terminal of the optocoupler UO1 is grounded. PE_IN is connected to the earth.

[0157] The PE disconnection detection circuit is used to detect whether PE is connected. The principle of the PE disconnection detection circuit is as follows: HVDC is the voltage after three-phase rectification and filtering; PE_IN is connected to ground; CheckPE_Leak is the high / low level signal output by the optocoupler, which is sent to the MCU. When PE_IN is properly grounded, there is approximately 300V DC voltage between HVDC and PE_IN, the optocoupler conducts, and CheckPE_Leak is low; otherwise, it is high. The MCU determines whether PE_IN is connected to ground by detecting the high / low level of CheckPE_Leak.

[0158] The power board is equipped with a power supply circuit, which supplies power to the circuit breaker. The power supply circuit is as follows: Figure 14 As shown. The power supply circuit includes a first power supply unit, a second power supply unit, a third power supply unit, and a fourth power supply unit. The input terminal of the first power supply unit is connected to the power interface and is used to convert the voltage output from the power interface (the voltage output from the rectifier board) into a voltage HVDC. The second power supply unit is used to convert the HVDC voltage into a 12V voltage, the third power supply unit is used to convert the 12V voltage into a 5V voltage, and the fourth power supply unit is used to convert the 5V voltage into a 3.3V voltage (e.g., VDD3.3V).

[0159] A display circuit is disposed on the panel, and the panel is electrically connected to the motherboard. The display circuit includes a display screen, and the display circuit is as follows: Figure 15 As shown.

[0160] To address various temporary power supply issues in construction projects, a management platform is established. This platform includes a standardized database of temporary construction power usage, providing a visual analysis and display of the three levels of power consumption at construction sites. The cloud platform presents various power consumption information for the project in intuitive model and digital form. The standardized database regulates the daily inspection procedures for electricians, providing real-time monitoring of inspection progress to prevent inadequate implementation. The power usage status of the distribution boxes used in construction projects can also be monitored in real-time via circuit breakers. In case of potential power failures, real-time alarms are triggered for management personnel, allowing for timely identification and maintenance of the fault points to mitigate safety risks. Simultaneously, the platform can analyze and process the power load of each distribution box, proposing rational power configuration schemes.

[0161] It is understood that the above embodiments are merely exemplary embodiments used to illustrate the principles of the present invention, and the present invention is not limited thereto. For those skilled in the art, various modifications and improvements can be made without departing from the spirit and essence of the present invention, and these modifications and improvements are also considered to be within the scope of protection of the present invention.

Claims

1. A construction site intelligent power management system, characterized in that: The management platform, the user terminal and the distribution box are in wireless communication, the distribution box is internally provided with an intelligent circuit breaker, the intelligent circuit breaker is used for collecting construction power consumption data and transmitting the data to the management platform, and the management platform is used for big data analysis of the construction power consumption data to realize visualized, informatized and intelligent whole-process management of construction power consumption on a construction site; The distribution box includes a primary distribution box and secondary distribution boxes, the input end of the primary distribution box is electrically connected with a power distribution room, the output end of the primary distribution box is electrically connected with the input ends of the secondary distribution boxes, the primary distribution box supplies power to all the secondary distribution boxes, the management platform communicates with the secondary distribution boxes, and the secondary distribution boxes are internally provided with communication modules and intelligent circuit breakers; The management platform is further used for dividing the construction site into regions, allocating the secondary distribution boxes to the regions, calculating the load rates of the secondary distribution boxes in the regions, evaluating the power consumption conditions of the regions according to the load rates of the secondary distribution boxes in the regions, and obtaining an optimized distribution box arrangement scheme for each region according to the power consumption conditions of the regions. The evaluation of the power consumption conditions of the regions according to the load rates of the secondary distribution boxes in the regions specifically includes: if the load rates of more than a first preset number of the secondary distribution boxes in a region exceed a first threshold value, the region is determined as an electricity-intensive region; and if the load rates of more than a second preset number of the secondary distribution boxes in a region are lower than a second threshold value, the region is determined as an electricity-idle region. The principle of optimizing the distribution box arrangement scheme for each region according to the power consumption conditions of the regions is to reduce the number of the secondary distribution boxes in the electricity-idle regions and increase the number of the secondary distribution boxes in the electricity-intensive regions. The management platform is used for monitoring the real-time load conditions of the distribution boxes, reasonably adjusting the distribution box arrangement conditions in the electricity-intensive and electricity-idle regions, and timely discovering equipment or line leakage conditions and long-time idle operation conditions of equipment by combining remote opening and closing with power consumption data, analyzing and processing the power consumption load of each distribution box in a timely manner, and proposing an optimized power consumption configuration scheme.

2. The intelligent power management system for construction sites of claim 1, wherein: The management platform includes a large-screen board module, a distribution box monitoring module and a distribution box management module. The large-screen board module is respectively used for displaying power consumption data, including project profiles, distribution box distribution, equipment use, alarm conditions and inspection condition data information. The distribution box monitoring module is used for monitoring and analyzing and counting the power consumption data of each distribution box, and the power consumption data includes voltage, current, temperature, leakage current, power and historical data. The distribution box management module is used for open / close control of each distribution box loop.

3. The intelligent power management system for construction sites of claim 2, wherein: The management platform includes an authorized power consumption module, which is used for receiving a power consumption request of a user terminal, performing permission comparison, authorizing power consumption if the requesting user has power consumption permission, opening the circuit after the power consumption is completed, counting the power consumption, and performing alarm and automatic opening of the circuit if the requesting user does not have power consumption permission.

4. The intelligent power management system for construction sites of claim 3, wherein: The management platform includes a sub-contractor power consumption statistical module, which is used for measuring the power consumption of each sub-contractor after sub-contractor code scanning authorization power consumption.

5. The intelligent power management system for construction sites of claim 2, wherein: The management platform comprises an inspection management module, the inspection management module comprises a leakage protection test module, and the leakage protection test module is configured to control the opening and closing operation of the circuit breaker at regular time intervals and test whether the residual current action of the circuit breaker is normal. The inspection management module comprises a grounding test module, and the grounding test module is configured to detect the grounding resistance of the distribution box and test whether the grounding wire in the distribution box is firmly connected according to the resistance value of the grounding resistance.

6. The construction site intelligent power management system of claim 2, wherein: The management platform comprises an alarm module, an electric quantity statistical module, a monthly report module and a background setting module. The alarm module is configured to process and count the alarm information of the distribution box circuit. The electric quantity statistical module is configured to count the overall electric quantity of each circuit of the distribution box. The monthly report module is configured to analyze the monthly power consumption and provide optimization suggestions. The background setting module is configured to maintain project information, distribution box information and personnel information.

7. The construction site intelligent power management system of claim 1, wherein: The intelligent circuit breaker is configured to transmit the collected power consumption data to the 4G Internet of Things module by using the MOTT protocol, and the 4G Internet of Things module is configured to transmit the data to the management platform in real time by using 4G.

8. The construction site intelligent power management system of claim 7, wherein: The distribution box is configured to upload the power consumption data to the management platform at regular time intervals, and the distribution box is configured to upload the abnormal signal to the management platform in a trigger mode, specifically including: when the abnormal signal changes, the abnormal signal is immediately uploaded to the management platform for analysis and processing by the management platform.

9. The construction site intelligent power management system of claim 1, wherein: The management platform is configured to calculate the power consumption load of each distribution box and the load rate of the distribution box, and the load rate of the distribution box is equal to the ratio of the power consumption load of the distribution box to the rated capacity. When the load rate of the distribution box is greater than a first preset value, the distribution box is prompted to be in a first state of operation. When the load rate of the distribution box is less than a second preset value, the distribution box is prompted to be in a second state of operation.

10. The construction site intelligent power management system of claim 1, wherein: The distribution box further comprises a three-level distribution box, and the output end of the two-level distribution box is electrically connected to the input end of the plurality of three-level distribution boxes. The two-level distribution box supplies power to the three-level distribution boxes connected thereto, and the three-level distribution boxes supply power to the electric equipment.

Citation Information

Patent Citations

  • Alarm method for abnormal load of distribution transformer

    CN107909508A

  • Temporary power utilization supervision and safety risk management and control system for building construction site

    CN111555459A

  • Intelligent temporary distribution box for construction site and control method thereof

    CN113315224A

  • Water and electricity management system applied to construction site

    CN216449905U