Engineering cost analysis and adjustment system based on BIM technology
By designing an engineering cost analysis and adjustment system based on BIM technology, the problem of multi-stage cost refinement management in the existing technology is solved, and the refined management and control of engineering costs is achieved, and the accuracy and reliability of costs are improved.
Patent Information
- Application Number
- CN202510211614.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-25
- Publication Date
- 2025-06-13
AI Technical Summary
The existing BIM technology is difficult to achieve refined management of multi-stage costs, and it is impossible to analyze and adjust the subsequent project usage costs in a timely manner, resulting in a reduction in the accuracy and reliability of the final settlement cost.
Design an engineering cost analysis and adjustment system based on BIM technology, including engineering information classification module, data acquisition module, BIM model establishment module, stage prediction calculation module, stage cost analysis module and adjustment module. Through these modules, they collect, classify and analyze engineering data and cost data, predict multi-stage cost, conduct comparison and analysis, and adjust subsequent project usage costs based on the analysis results.
It realizes refined management and control of multi-stage engineering costs, improves cost accuracy and reliability, and ensures that costs can be maximized.
Smart Images

Figure CN120146887A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of project cost management, and specifically relates to a project cost analysis and adjustment system based on BIM technology. Background Art
[0002] BIM is an abbreviation for the content modeling method of building complex information, and it is the basic model of large-scale digital related information; BIM is to establish a virtual three-dimensional model of a building project, and use digital technology to provide a complete building project information database consistent with the actual situation for this model. This information database not only contains geometric information, professional attributes and status information describing building components, but also contains status information of non-component objects. With the help of this three-dimensional model containing building project information, the information integration degree of building projects has been greatly improved.
[0003] However, simply using BIM technology can no longer achieve refined management of multi-stage costs, and it is impossible to analyze and adjust the usage costs of subsequent projects in a timely manner in multiple stages, resulting in a decrease in the accuracy and reliability of the final settlement cost.
[0004] Therefore, those skilled in the art have proposed a project cost analysis and adjustment system based on BIM technology to solve the problems raised in the background art. Summary of the Invention
[0005] In order to solve the above technical problems, the present invention provides a project cost analysis and adjustment system based on BIM technology to solve the problems of inability to achieve refined management of multi-stage costs, inability to analyze and adjust the usage costs of subsequent projects in a timely manner in multiple stages, resulting in a decrease in the accuracy and reliability of the final settlement cost.
[0006] To achieve the above object, the present invention provides the following technical solutions:
[0007] A project cost analysis and adjustment system based on BIM technology, the system includes: an engineering information classification module, a data acquisition module, a BIM model establishment module, a stage prediction calculation module, a stage cost analysis module, and an adjustment module;
[0008] The engineering information classification module is used to collect various types of engineering information, obtain engineering data, and classify the engineering data;
[0009] The data acquisition module is used to respectively acquire cost data of different categories in the project, and store the acquired cost data separately according to categories;
[0010] The BIM model establishment module is used to construct a standardized BIM model, and integrate the obtained engineering data and cost data into the BIM model to obtain an engineering unit module;
[0011] The stage prediction calculation module is used to count various cost data of multiple stages according to the engineering unit module, predict and calculate the budget costs of various costs in multiple stages respectively, and obtain the predicted costs of multiple stages;
[0012] The stage cost analysis module is used to effectively analyze the project cost and cost, compare and analyze the predicted costs of multiple stages with the actual costs of multiple stages, and obtain the comparative analysis results of multiple stages;
[0013] The adjustment module is used to adjust the subsequent project usage cost according to the comparative analysis results of multiple stages.
[0014] Preferably, the categories into which the project information classification module divides the project data include: five project data units, namely, building engineering unit, highway engineering unit, municipal engineering unit, railway engineering unit, and water transportation engineering unit.
[0015] Preferably, the data acquisition module is used to acquire different categories of cost data of building engineering units, highway engineering units, municipal engineering units, railway engineering units, and water transportation engineering units respectively.
[0016] Preferably, the cost data includes material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data. Among them, the other relevant data is the cost data of the tax policy and environmental protection policy in the project area;
[0017] The material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data are stored independently respectively.
[0018] Preferably, after the BIM model is constructed, the BIM model establishment module integrates five project data units, namely, building engineering unit, highway engineering unit, municipal engineering unit, railway engineering unit, and water transportation engineering unit, and material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data into the BIM model to obtain five project unit modules.
[0019] Preferably, the five project unit modules include building engineering unit module, highway engineering unit module, municipal engineering unit module, railway engineering unit module, and water transportation engineering unit module.
[0020] Preferably, the stage prediction calculation module divides the construction stage into the early stage, the middle stage and the late stage, predicts and calculates the engineering material prices, labor costs, equipment costs, subcontracting process costs, project change and claim costs, project settlement costs and other related costs in the three stages of the early stage, the middle stage and the late stage, and obtains the predicted cost in the early stage, the predicted cost in the middle stage and the predicted cost in the late stage.
[0021] Preferably, the stage cost analysis module compares and analyzes the predicted cost in the early stage, the predicted cost in the middle stage and the predicted cost in the late stage with the actual cost in the early stage, the actual cost in the middle stage and the actual cost in the late stage, and obtains the comparison result in the early stage, the comparison result in the middle stage and the comparison result in the late stage.
[0022] Preferably, when analyzing the project cost and cost, the stage cost analysis module adopts the earned value method, and realizes the effective analysis of the project cost and cost through the evaluation of cost deviation, schedule deviation, cost performance index and schedule performance index. The calculation formulas are as follows:
[0023] CV = BCWP - ACWP
[0024] SV = BCWP - BCWS
[0025] CPI = BCWP / ACWS
[0026] SPI = BCWP / BCWS
[0027] Among them, CV is the cost deviation, BCWP is the budgeted cost of work performed, ACWP is the actual cost of work performed, BCWS is the budgeted cost of work scheduled (predicted and calculated cost), SV is the schedule deviation, CPI is the cost performance indicator, and SPI is the schedule performance indicator.
[0028] Preferably, the adjustment module adjusts the usage cost of the subsequent project according to the comparison results in the early stage, the comparison results in the middle stage and the comparison results in the late stage, and according to the analysis results of each stage.
[0029] Compared with the prior art, the present invention has the following beneficial effects:
[0030] 1. First, the present invention obtains project data by collecting various project information, classifies the project data, obtains different categories of cost data in the classified project data, then creates a BIM model, integrates the above-obtained classified project data and different categories of cost data in the classified project data into the BIM model to obtain an engineering unit module, uses the engineering unit module to predict and calculate the budget costs of various costs in multiple stages to obtain multi-stage predicted costs, and then compares and analyzes the multi-stage predicted costs with the multi-stage actual costs to obtain multi-stage comparison and analysis results. It is possible to adjust the subsequent cost of each stage according to the comparison and analysis results of each stage, and to perform refined management and control of the cost to ensure that the cost reaches the maximum benefit.
[0031] 2. The present invention divides the construction stage into a pre-stage, a mid-stage, and a post-stage, predicts and calculates the cost data fees of different costs in the three stages to obtain corresponding predicted costs, and uses the earned value analysis method to effectively analyze the project cost and cost, and compares and analyzes them with the actual costs in the pre-stage, mid-stage, and post-stage respectively to obtain the comparison results of the three stages. It is possible to adjust the subsequent usage cost according to the results of each stage, clarify the cost optimization space in the actual construction process of each stage, provide a reference for decision-making management, and improve the accuracy and reliability of the final settlement cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings required for use in the description of the embodiments or the prior art. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0033] Figure 1 It is a schematic flow chart of a project cost analysis and adjustment system based on BIM technology of the present invention. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0034] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts belong to the scope of protection of the present invention.
[0035] As shown in the Figure 1 accompanying drawings:
[0036] Embodiment 1:
[0037] The present invention provides a project cost analysis and adjustment system based on BIM technology. The system includes: an engineering information classification module, a data acquisition module, a BIM model establishment module, a stage prediction calculation module, a stage cost analysis module, and an adjustment module;
[0038] The engineering information classification module is used to collect various types of engineering information to obtain engineering data, and classify the engineering data;
[0039] The data acquisition module is used to respectively acquire cost data of different categories in the project, and store the acquired cost data separately according to the categories;
[0040] The BIM model establishment module is used to construct a standardized BIM model, and integrate the obtained engineering data and cost data into the BIM model to obtain an engineering unit module;
[0041] The stage prediction calculation module is used to statistically calculate various cost data in multiple stages according to the engineering unit module, respectively predict and calculate the budget costs of various costs in multiple stages, and obtain the multi-stage predicted costs;
[0042] The stage cost analysis module is used to effectively analyze the project cost and cost, compare and analyze the multi-stage predicted costs with the multi-stage actual costs, and obtain the multi-stage comparative analysis results;
[0043] The adjustment module is used to adjust the subsequent project usage costs according to the multi-stage comparative analysis results.
[0044] As can be seen from the above, first, collect various engineering information to obtain engineering data, classify the engineering data, acquire different category cost data in the classified engineering data, then create a BIM model, integrate the above-obtained classified engineering data and different category cost data in the classified engineering data into the BIM model to obtain an engineering unit module, use the engineering unit module to predict and calculate the budget costs of various costs in multiple stages to obtain the multi-stage predicted costs, and then compare and analyze the multi-stage predicted costs with the multi-stage actual costs to obtain the multi-stage comparative analysis results. The subsequent cost can be adjusted according to the comparative analysis results of each stage, and the cost can be refinedly managed and controlled to ensure that the cost reaches the maximum benefit.
[0045] Embodiment 2:
[0046] Specifically, the categories into which the engineering information classification module divides the engineering data include: five engineering data units, namely, building engineering units, highway engineering units, municipal engineering units, railway engineering units, and water transportation engineering units.
[0047] Specifically, the data acquisition module is used to acquire different categories of cost data for construction engineering units, highway engineering units, municipal engineering units, railway engineering units, and water transportation engineering units respectively.
[0048] Specifically, the cost data includes material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data. Among them, the other relevant data is the cost data of tax policies and environmental protection policies in the project area.
[0049] The material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data are stored independently respectively.
[0050] Specifically, after the BIM model is constructed, the BIM model establishment module integrates five types of engineering data units, namely construction engineering units, highway engineering units, municipal engineering units, railway engineering units, and water transportation engineering units, and material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data into the BIM model to obtain five types of engineering unit modules.
[0051] Specifically, the five types of engineering unit modules include construction engineering unit modules, highway engineering unit modules, municipal engineering unit modules, railway engineering unit modules, and water transportation engineering unit modules.
[0052] Furthermore, each of the construction engineering unit module, highway engineering unit module, municipal engineering unit module, railway engineering unit module, and water transportation engineering unit module includes material price, labor cost, equipment cost, subcontracting process cost, project change and claim, project settlement cost, and other relevant costs.
[0053] As can be seen from the above, the engineering data is divided into five types of engineering data units, namely construction engineering units, highway engineering units, municipal engineering units, railway engineering units, and water transportation engineering units. Then, different categories of cost data for the above five types of engineering data units are acquired: material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data, and other relevant data. The above data is integrated into the BIM model to achieve data integration. On this basis, construction engineering unit modules, highway engineering unit modules, municipal engineering unit modules, railway engineering unit modules, and water transportation engineering unit modules are obtained. Each of the above five unit modules contains material price, labor cost, equipment cost, subcontracting process cost, project change and claim, project settlement cost, and other relevant costs, which can improve the energy efficiency and quality of cost management and achieve cost control for the entire process of the project.
[0054] Example 3:
[0055] Specifically, the stage prediction calculation module divides the construction stage into the early stage, the middle stage, and the late stage, and predicts and calculates the engineering material prices, labor costs, equipment costs, subcontracting process costs, project change and claim costs, project settlement costs, and other related costs in these three stages to obtain the predicted cost in the early stage, the predicted cost in the middle stage, and the predicted cost in the late stage.
[0056] Specifically, the stage cost analysis module compares and analyzes the predicted cost in the early stage, the predicted cost in the middle stage, and the predicted cost in the late stage with the actual cost in the early stage, the actual cost in the middle stage, and the actual cost in the late stage to obtain the comparison result in the early stage, the comparison result in the middle stage, and the comparison result in the late stage.
[0057] Specifically, when analyzing the project cost and cost, the stage cost analysis module uses the earned value method. Through the evaluation of cost variance, schedule variance, cost performance index, and schedule performance index, the effective analysis of project cost and cost is realized. The calculation formulas are as follows:
[0058] CV = BCWP - ACWP
[0059] SV = BCWP - BCWS
[0060] CPI = BCWP / ACWS
[0061] SPI = BCWP / BCWS
[0062] Among them, CV is the cost variance, BCWP is the budgeted cost of work performed, ACWP is the actual cost of work performed, BCWS is the budgeted cost of work scheduled (predicted and calculated cost), SV is the schedule variance, CPI is the cost performance indicator, and SPI is the schedule performance indicator.
[0063] Specifically, the adjustment module adjusts the cost of subsequent projects according to the comparison results in the early stage, the comparison results in the middle stage, and the comparison results in the late stage, and according to the analysis results of each stage.
[0064] As can be seen from the above, the construction stage is divided into the preliminary stage, the intermediate stage and the late stage. The engineering material prices, labor costs, equipment costs, subcontracting process costs, project change and claim costs, project settlement costs and other related costs in the three stages are predicted and calculated to obtain the corresponding predicted costs. The earned value analysis method is used to effectively analyze the project cost and cost, and compare and analyze them with the actual costs in the preliminary stage, the intermediate stage and the late stage respectively. The comparison results in the three stages can be obtained, and the subsequent usage costs can be adjusted according to the comparison results of each stage, clarifying the cost optimization space in the actual construction process of each stage, providing a reference for decision-making management, and improving the accuracy and reliability of the final settlement cost.
[0065] The foregoing has shown and described the basic principles, main features and advantages of the present invention. For those skilled in the art, it is obvious that the present invention is limited to the details of the above-described exemplary embodiments, and without departing from the spirit or basic features of the present invention, the present invention can be implemented in other specific forms. Therefore, from any point of view, the embodiments should be regarded as exemplary and non-limiting. The scope of the present invention is defined by the appended claims rather than the above description. Therefore, it is intended to embrace all changes that fall within the meaning and scope of the equivalent elements of the claims in the present invention. Any reference signs in the claims should not be regarded as limiting the claims involved.
[0066] The embodiments of the present invention are given for the purpose of illustration and description. Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those of ordinary skill in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.
Claims
1. A construction cost analysis and adjustment system based on BIM technology, characterized in that: The system includes: an engineering information classification module, a data acquisition module, a BIM model building module, a stage prediction calculation module, a stage cost analysis module, and an adjustment module; The engineering information classification module is used to collect various types of engineering information, obtain engineering data, and classify the engineering data; The data acquisition module is used to respectively acquire cost data of different categories in the project, and store the acquired cost data according to the categories; The BIM model building module is used to build a standardized BIM model, and integrate the obtained engineering data and cost data into the BIM model to obtain an engineering unit module; The stage prediction calculation module is used to calculate the budget costs of various construction costs in multiple stages according to the engineering unit module, and obtain the multi-stage prediction costs; The stage cost analysis module is used to effectively analyze the project cost and compare the multi-stage predicted cost with the multi-stage actual cost to obtain the multi-stage comparative analysis results; The adjustment module is used to adjust the subsequent engineering use cost according to the multi-stage comparative analysis results.
2. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 1, characterized in that: The engineering information classification module classifies engineering data into five types of engineering data units: construction engineering unit, highway engineering unit, municipal engineering unit, railway engineering unit and water transport engineering unit.
3. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 2, characterized in that: The data acquisition module is used to respectively acquire different types of cost data of construction engineering units, highway engineering units, municipal engineering units, railway engineering units and water transport engineering units.
4. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 3, characterized in that: The construction cost data includes material price data, labor cost data, equipment cost data, subcontracting process cost data, engineering change and claim data, engineering settlement cost data and other relevant data, among which other relevant data are cost data of taxation policy and environmental protection policy in the area where the project is located; Material price data, labor cost data, equipment cost data, subcontracting process cost data, project change and claim data, project settlement cost data and other related data are stored independently.
5. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 4, characterized in that: After constructing the BIM model, the BIM model building module integrates five engineering data units, namely, construction engineering unit, highway engineering unit, municipal engineering unit, railway engineering unit and water transport engineering unit, as well as material price data, labor cost data, equipment cost data, subcontracting process cost data, engineering change and claim data, engineering settlement cost data and other relevant data into the BIM model to obtain five engineering unit modules.
6. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 1, characterized in that: The five engineering unit modules include a construction engineering unit module, a highway engineering unit module, a municipal engineering unit module, a railway engineering unit module and a water transport engineering unit module.
7. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 1, characterized in that: The stage prediction and calculation module divides the construction stage into the early stage, the mid-term stage and the late stage, and predicts and calculates the engineering material prices, labor costs, equipment costs, subcontracting process costs, engineering changes and claim costs, engineering settlement costs and other related costs in the three stages of the early stage, the mid-term stage and the late stage, and obtains the predicted cost of the early stage, the mid-term stage and the late stage.
8. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 1, characterized in that: The stage cost analysis module compares and analyzes the predicted cost of the early stage, the predicted cost of the mid-term stage and the predicted cost of the late stage, and the actual cost of the early stage, the actual cost of the mid-term stage and the actual cost of the late stage to obtain the comparison results of the early stage, the mid-term stage and the late stage.
9. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 8, characterized in that: The stage cost analysis module adopts the earned value method to analyze the project cost and cost. By evaluating the cost deviation, schedule deviation, cost performance index, and schedule performance index, it realizes effective analysis of the project cost and cost. The calculation formula is as follows: CV=BCWP-ACWP SV=BCWP-BCWS CPI=BCWP / ACWS SPI=BCWP / BCWS Among them, CV is the cost variance, BCWP is the budgeted cost of work performed, ACWP is the actual cost of work performed, BCWS is the budgeted cost of planned work (forecasted calculated cost), SV is the schedule variance, CPI is the cost performance index, and SPI is the schedule performance index.
10. The engineering cost analysis and adjustment system based on BIM technology as claimed in claim 1, characterized in that: The adjustment module adjusts the subsequent engineering use cost according to the comparison results of the early stage, the comparison results of the mid-stage and the comparison results of the late stage, and according to the analysis results of each stage.