Prefabricated column safety operation platform capable of being assembled

Through the assembled prefabricated column safety operation platform, the friction support components and centralized control system are used to solve the problems of slow speed, cumbersome steps and safety hazards of traditional operating platforms, and a fast, safe and cost-effective construction solution is achieved.

CN120291690APending Publication Date: 2025-07-11CSCEC TECH GRP EAST CHINA CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510318970.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-18
Publication Date
2025-07-11

AI Technical Summary

Technical Problem

The traditional large-section and large-height prefabricated column operation platform is slow to build, cumbersome steps, high cost and safety hazards, making it difficult to meet the needs of modern construction efficiency and cost control.

Method used

The assembled prefabricated column safety operation platform is adopted, including friction support components, corner connection components and centralized control system, and the platform is quickly assembled and precise pressure control through bolted connections and jack adjustments.

Benefits of technology

It has achieved rapid, safe and cost-effective operation platform construction, adapted to the needs of prefabricated components of various specifications, reduced human operation errors, and improved construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120291690A_ABST
    Figure CN120291690A_ABST
Patent Text Reader

Abstract

The invention discloses an assembly type prefabricated column safety operation platform, and belongs to the technical field of building construction facilities. The prefabricated column safety operation platform comprises a friction supporting assembly, a corner connecting assembly and a centralized control assembly. A plurality of same modules can be assembled according to the requirements of the sections of the prefabricated parts, the whole safe operation platform is formed, the construction requirements of the prefabricated parts of various specifications can be met, and the application range is wider. All the components can be machined in a factory, the assembling and disassembling process of the whole operation platform is simple and rapid, rapid assembling and disassembling can be achieved, powerful support is provided for construction safety management, and the device has the advantages of being good in protection effect and convenient to use. The operation platform can meet segmented installation of multiple sections of prefabricated columns, and high-efficiency application of the operation platform can be achieved by adjusting the telescopic length of the jack. A centralized control assembly is adopted, an intelligent adjusting mode can be achieved, the possibility of manual operation errors is reduced, and the safety controllability of the prefabricated column safety operation platform is higher.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of construction facilities, and in particular relates to a prefabricated column safety operation platform that can be assembled Background Art

[0002] In view of the office and production requirements in large-space and large-span industrial buildings, it is necessary to use precast columns with large cross-sections and large heights. However, the construction process of such precast columns requires a safe and stable operation space. The traditional method of building an operation platform is not only slow and cumbersome, but also has great safety hazards. Coupled with the high construction cost and time-consuming and laborious characteristics, it is difficult to meet the requirements of modern construction efficiency and cost control. Therefore, on the basis of ensuring construction safety, how to quickly build an operation platform for precast columns with large cross-sections and large heights and achieve cost savings has become an important issue to be solved urgently in the field of prefabricated building construction Summary of the Invention

[0003] In view of the problems existing in the above background art, the present invention proposes a prefabricated column safety operation platform that can be assembled, which solves the problems of slow construction speed, cumbersome steps, high construction cost, time-consuming and laborious, and great safety hazards of the traditional operation platform

[0004] To this end, the present invention adopts the following technical solutions: A prefabricated column safety operation platform that can be assembled, including a number of friction support components, a number of corner connection components and a centralized control system. The friction support components and the corner connection components are fixedly assembled by multiple groups of bolts to form the safety operation platform. Through the centralized control system, multiple groups of jacks are controlled to synchronously adjust to achieve precise control of the required pressure value

[0005] The friction support component includes a friction support component steel frame, a friction support component walkway board, a friction pressure component and a jacking component

[0006] The steel frame includes a friction support component horizontal bar, a friction support component vertical bar, a friction support component scissors bar, a friction support component short bar and a fixing plate. There are multiple friction support component horizontal bars, and the friction support component horizontal bars are fixedly connected to the friction support component vertical bars; the friction support component vertical bars are located at the corners of the steel frame and are connected into a whole through the friction support component horizontal bars, and are provided with multiple groups of bolt holes from top to bottom; the friction support component scissors bar is placed in the middle area, connecting the friction support component vertical bar and the friction support component horizontal bar to form a strengthened area; the short bar is located in the middle area of the middle friction support component horizontal bar far from the precast member end, and is used for the bottom fixing of the jack; the fixing plate is located in the middle area of the middle friction support component horizontal bar close to the precast member end, and is used for the top fixing of the jack

[0007] The walkway plate of the friction support assembly is placed on the top surface of the horizontal rod of the middle friction support assembly and is used as the operation support plane for workers.

[0008] The friction pressure assembly includes a friction assembly, a support frame, a pressure assembly, and a horizontal limit assembly; the friction assembly is a rigid plate, and the surface on the side close to the precast member is a rough surface to increase the friction coefficient with the surface of the precast member. The side away from the precast member is fixedly connected to the support frame, and the corners are fixedly connected to the horizontal limit assembly; the support frame is formed by welding steel pipes. The side close to the friction assembly is a square frame and is welded and fixed to the friction assembly. The side away from the friction assembly is welded and fixed to the telescopic rod of the jack; the pressure assembly is a jack device, and its support on the side close to the precast member is fixedly connected to the support frame. The side away from the precast member is welded and fixed to the short rod, which is used to push the friction assembly to move horizontally and generate a large contact pressure with the surface of the precast member; the horizontal limit assembly includes a limit rod and a telescopic spring. One end of the limit rod is welded and fixed to the friction assembly, and a circular retaining piece is provided in the middle. The telescopic spring is used to control the overall horizontal sliding of the limit rod.

[0009] The jacking assembly includes a jacking support, an adjusting nut, and a lead screw. The lead screw passes through the round hole matching the bottom of the vertical rod. The two ends of the lead screw are sleeved with the adjusting nut, and the jacking support is fixedly connected to the outer end surface of the lead screw. By adjusting the nut, the extension length of the lead screw can be controlled to ensure the overall stability of the prefabricated column safety operation platform that can be assembled.

[0010] The corner connection assembly includes a corner connection group steel frame and a corner connection group walkway plate. The corner connection group steel frame includes a corner connection group horizontal rod, a corner connection group vertical rod, and a corner connection group scissors rod. The assembly method of the corner connection group steel frame is the same as the installation form of the steel frame of the friction support assembly.

[0011] The present invention can achieve the following beneficial effects:

[0012] 1. By setting the friction support assembly, the present invention can be assembled with multiple identical modules according to the cross-section requirements of the precast member, and the entire safety operation platform can be formed by connecting the four corners, which can meet the construction requirements of precast members of various specifications and has a wider application range.

[0013] 2. Both the friction support assembly and the corner connection assembly of the present invention can be processed and assembled in the factory, and the quality and safety of the components are reliable. The assembly and disassembly process of the entire operation platform is simple and fast, and rapid installation and disassembly can be achieved, providing strong support for construction safety management. The device has the advantages of good protection effect and convenient use.

[0014] 3. The prefabricated column safety operation platform of the present invention can be integrally lifted by a hoisting device, which can meet the segmented installation of multiple prefabricated columns. In particular, it is more practical for prefabricated columns with small-range cross-section adjustment from bottom to top. The high-efficiency application of the operation platform can be achieved by adjusting the telescopic length of the jacks.

[0015] 4. The present invention adopts a centralized control system, which can realize an intelligent adjustment method, reduce the possibility of human operation errors, and has higher safety and controllability for the prefabricated column safety operation platform. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic structural diagram of the present invention.

[0017] Figure 2 It is a schematic diagram of the structural disassembly of the present invention.

[0018] Figure 3 It is a schematic structural diagram of the friction support assembly of the present invention.

[0019] Figure 4 It is a schematic structural diagram of the corner connection assembly of the present invention. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0020] The following describes in detail the specific embodiments of the present invention with reference to the accompanying drawings. The described embodiments are only illustrative and explanatory of the present invention, and do not constitute the sole limitation of the present invention.

[0021] As shown in Figure 1 , the embodiment of the present invention includes a friction support assembly 1, a corner connection assembly 2, and a centralized control system 3. The friction support assembly 1 and the corner connection assembly 2 are bolted and fixed by multiple groups of bolts. The centralized control system 3 is used to control multiple groups of jacks for synchronous adjustment and can perform precise control according to the required pressure value.

[0022] Preferably, the friction support assembly 1 includes a friction support assembly steel frame 11, a friction support assembly walkway plate 12, a friction pressure assembly 13, and a jacking assembly 14.

[0023] The steel frame 11 described above is composed of a horizontal rod 111 of the friction support assembly, a vertical rod 112 of the friction support assembly, a scissors rod 113 of the friction support assembly, a short rod 114 of the friction support assembly, and a fixing plate 115. Multiple horizontal rods 111 of the friction support assembly are provided for connecting and fixing the vertical rods 112 of the friction support assembly. The vertical rods 112 of the friction support assembly are located at the corners of the steel frame, are connected into a whole through the horizontal rods 111 of the friction support assembly, and are provided with multiple groups of bolt holes from top to bottom. The scissors rods 113 of the friction support assembly are placed in the middle area, connecting the vertical rods 112 and the horizontal rods 111 of the friction support assembly to form a strengthening area. The short rod 114 is located in the middle area of the middle horizontal rod 111 of the friction support assembly away from the end of the precast member, and is used for fixing the bottom of the jack. The fixing plate 115 is located in the middle area of the middle horizontal rod 111 of the friction support assembly close to the end of the precast member, and is used for fixing the top of the jack.

[0024] The walkway plate 12 is placed on the top surface of the middle horizontal rod 111 of the friction support assembly and is used as a support plane for workers to operate.

[0025] The friction pressure assembly 13 includes a friction assembly 131, a support frame 132, a pressure assembly 133, and a horizontal limit assembly 134. The friction assembly 131 is a rigid plate, and the surface on the side close to the precast member is a rough surface to increase the friction coefficient with the surface of the precast member. The side away from the precast member is fixedly connected to the support frame, and the corners are fixedly connected to the horizontal limit assembly 134. The support frame 132 is formed by welding steel pipes. The side close to the friction assembly 131 is a square frame and is welded and fixed to the friction assembly 131. The side away from the friction assembly 131 is welded and fixed to the telescopic rod of the jack. The pressure assembly 133 is a jack device, and its support on the side close to the precast member is fixedly connected to the support frame 132. The side away from the precast member is welded and fixed to the short rod 114, and is used to push the friction assembly 131 to move horizontally and generate a large contact pressure with the surface of the precast member. The horizontal limit assembly 134 includes a limit rod and a telescopic spring. One end of the limit rod is welded and fixed to the friction assembly, and a circular retaining piece is provided in the middle thereof. The telescopic spring is used to control the overall horizontal sliding of the limit rod.

[0026] The top support assembly 14 includes a top support 141, an adjusting nut 142, and a lead screw 143. The lead screw 143 passes through a circular hole matching the bottom of the vertical rod 112. The two ends of the lead screw 143 are sleeved with the adjusting nut 142. The top support 141 is fixedly connected to the outer end surface of the lead screw 143. The extension length of the lead screw 143 is controlled by the adjusting nut 142 to ensure the overall stability of the prefabricated column safety operation platform that can be assembled.

[0027] The corner connection assembly 2 includes a corner connection group steel frame 21, a corner connection group walkway plate 22 and a lifting lug 23. The corner connection group steel frame 21 is composed of a corner connection group horizontal rod 211, a corner connection group vertical rod 212 and a corner connection group scissor rod 213, and the assembly method of the components is consistent with the installation form of the steel frame 11 of the friction support assembly 1. The lifting lug 23 is set on the top surface of the top corner connection group horizontal rod 211 of the corner connection group steel frame 21 and is welded and fixed.

[0028] After the on-site assembly of a prefabricated column safety operation platform is completed, the operation platform can be lifted to the specified elevation position by the lifting lug 23 provided by the lifting equipment, and the adjusting nut 142 of the top support assembly 14 is adjusted first, so that the extension length of the screw rod 143 can meet the top support 141 to the surface of the prefabricated column, and then the adjusting nut 142 is tightened to limit the movement of the entire top support assembly 14, ensuring that the top support 141 of the safety operation platform can stably contact the surface of the prefabricated column to provide positive support force. Then, the centralized control system 3 is used to control the extension length of the jack, so that the friction assembly 131 is in positive contact with the surface of the prefabricated column, and then the pressure is continuously applied by the jack, so that the friction force generated by the friction surface is sufficient to support 120% of the total load required for the construction work, and then the pressure loading can be stopped, proving that the operation platform has met the conditions for workers to work.

[0029] When a prefabricated column is divided into multiple sections for installation, the prefabricated column safety operation platform can be continuously lifted and used, that is, after the installation of the prefabricated column of this section is completed, the operation platform can be slightly lifted and stabilized by using the lifting lugs 23 provided by the lifting equipment, and the adjusting nut 142 of the jacking assembly 14 is adjusted first, so that the extension length of the screw rod 143 makes the jacking 141 slightly separate from the surface of the prefabricated column, and then the centralized control system 3 is used to control the extension length of the jack, so that the friction assembly 131 is separated from the surface of the prefabricated column by a certain distance. The operation platform is lifted to the specified elevation position, and the adjusting nut 142 of the jacking assembly 14 is adjusted first, so that the extension length of the screw rod 143 can meet the requirement that the jacking 141 reaches the surface of the prefabricated column, and then the adjusting nut 142 is tightened to limit the movement of the entire jacking assembly 14, and ensure that the jacking 141 of the safety operation platform can stably contact with the surface of the prefabricated column to provide positive support force. Then, the centralized control system 3 is used to control the extension length of the jack so that the friction assembly 131 is in positive contact with the surface of the prefabricated column. Then, pressure is continuously applied through the jack so that the friction force generated by the friction surface is sufficient to support 120% of the total load required for the construction work. Only then can the pressure loading be stopped, proving that the operating platform is ready for workers to work.

[0030] The foregoing has shown and described the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments, and what is described in the above embodiments and the specification is only to illustrate the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention will have various changes and improvements, and these changes and improvements fall within the scope of the present invention claimed. The scope of the present invention claimed is defined by the appended claims and their equivalents.

Claims

1. An assembled precast column safety operation platform, characterized in that: The prefabricated column safety operation platform that can be assembled includes a number of friction support components (1), a number of corner connection components (2), and a centralized control system (3). The friction support components (1) and the corner connection components (2) are fixedly assembled by multiple groups of bolts to form the safety operation platform. The centralized control system (3) controls the synchronous adjustment of multiple groups of jacks to achieve precise regulation of the required pressure value.

2. The prefabricated column safety operation platform according to claim 1, characterized in that: The friction support component (1) includes a friction support component steel frame (11), a friction support component walkway board (12), a friction pressure component (13), and a jacking component (14).

3. The prefabricated column safety operation platform according to claim 2, wherein: The friction support component steel frame (11) includes a friction support component horizontal rod, a friction support component vertical rod, a friction support component scissors rod, a friction support component short rod, and a fixing plate. There are multiple friction support component horizontal rods, and they are fixedly connected to the friction support component vertical rods. The friction support component vertical rods are located at the corners of the steel frame, and are connected into a whole through the friction support component horizontal rods, and are provided with multiple groups of bolt holes from top to bottom. The friction support component scissors rods are placed in the middle area, connecting the friction support component vertical rods and the friction support component horizontal rods to form a strengthened area. The short rods are located in the middle area of the middle friction support component horizontal rod away from the end of the precast member, and are used for the bottom fixation of the jack. The fixing plate is located in the middle area of the middle friction support component horizontal rod close to the end of the precast member, and is used for the top fixation of the jack.

4. The prefabricated column safety operation platform according to claim 3, characterized in that: The friction support component walkway board (12) is placed on the top surface of the middle friction support component horizontal rod, and is used as the operation support plane for workers.

5. The safety operation platform for an assembled precast column according to claim 4, characterized in that: The friction pressure component includes a friction component, a support frame, a pressure component, and a horizontal limiting component. The friction component is a rigid plate, and the surface on the side close to the precast member is a rough surface, and the side away from the precast member is fixedly connected to the support frame, and the corners are fixedly connected to the horizontal limiting component. The support frame is formed by welding steel pipes. The side close to the friction component is a square frame and is welded and fixed to the friction component. The side away from the friction component is welded and fixed to the telescopic rod of the jack. The pressure component is a jack device. Its support on the side close to the precast member is fixedly connected to the support frame, and the side away from the precast member is welded and fixed to the short rod, and is used to push the friction component to move horizontally and generate a large contact pressure with the surface of the precast member. The horizontal limiting component includes a limiting rod and a telescopic spring. One end of the limiting rod is welded and fixed to the friction component, and a round stop is provided in the middle. The telescopic spring is used to control the overall horizontal sliding of the limiting rod.

6. The prefabricated column safety operation platform according to claim 5, characterized in that: The jacking component (14) includes a jacking support, an adjusting nut, and a lead screw. The lead screw passes through the round hole matching the bottom of the vertical rod. The adjusting nuts are sleeved on both ends of the lead screw, and the jacking support is fixedly connected to the outer end face of the lead screw.

7. A prefabricated column safety operation platform that can be assembled, according to claim 1 or 2 or 6, characterized in that: The corner connection component (2) includes a corner connection group steel frame and a corner connection group walkway board. The corner connection group steel frame includes a corner connection group horizontal rod, a corner connection group vertical rod, and a corner connection group scissors rod.

8. The prefabricated column safety operation platform according to claim 7, wherein: The described corner connection component (2) further includes a lifting lug, which is arranged on the top surface of the horizontal bar of the corner connection group at the top layer of the steel frame of the corner connection group and is fixed by welding.

9. Method for operating a prefabricated column safety operation platform that can be assembled, characterized by: Use a lifting device to lift the operation platform to the specified elevation position through the provided lifting lugs. First, adjust the adjusting nut of the top support component so that the extended length of the screw rod can meet the requirement that the top support abuts against the surface of the precast column. Then, tighten the adjusting nut to limit the movement of the entire top support component, ensuring that the top support of the safety operation platform can stably contact the surface of the precast column to provide a positive supporting force. Then, use the centralized control system to control the extended length of the jack so that the friction component is in positive contact with the surface of the precast column. Then, continuously apply pressure through the jack until the frictional force generated on the friction surface is sufficient to support 120% of all the loads required for the construction operation, and then stop the pressure loading, indicating that the operation platform is ready for workers to operate. When a certain precast column is installed in multiple sections, the safety operation platform for the precast column can be continuously lifted and used. After the installation of the precast column is completed, use a lifting device to slightly lift and stabilize the operation platform through the provided lifting lugs. First, adjust the adjusting nut of the top support component so that the extended length of the screw rod causes the top support to disengage from the surface of the precast column. Then, use the centralized control system to control the extended length of the jack so that the friction component is separated from the surface of the precast column by a certain distance. Lift the operation platform to the specified elevation position. First, adjust the adjusting nut of the top support component so that the extended length of the screw rod can meet the requirement that the top support abuts against the surface of the precast column. Then, tighten the adjusting nut to limit the movement of the entire top support component, ensuring that the top support of the safety operation platform can stably contact the surface of the precast column to provide a positive supporting force. Then, use the centralized control system to control the extended length of the jack so that the friction component is in positive contact with the surface of the precast column. Then, continuously apply pressure through the jack until the frictional force generated on the friction surface is sufficient to support 120% of all the loads required for the construction operation, and then stop the pressure loading, indicating that the operation platform is ready for workers to operate.