Movable working platform for heat supply pipeline ditch construction and using method
By designing a mobile work platform, rollers and friction blocks are used to facilitate the movement and positioning of materials and equipment during the construction of heating pipelines. This solves the problems of low construction efficiency and safety hazards caused by the narrow space of the pipe trench, and achieves efficient and safe welding operations.
Patent Information
- Application Number
- CN202511210337.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-27
- Publication Date
- 2025-11-18
AI Technical Summary
In the construction of heating pipelines, the narrow space in the pipe trench makes it difficult to place welding materials and equipment, resulting in low construction efficiency and potential safety hazards.
Design a mobile work platform, including a frame, a support plate, and a moving component. The platform can be flexibly moved and positioned on a pipeline using rollers and friction blocks. Materials and equipment are placed directly on the platform and positioned and pushed by the cooperation of threaded rods and friction blocks.
It solves the problem of where to put materials and equipment, improves construction efficiency and safety, reduces manpower consumption, avoids the risk of collisions and tripping, and is adaptable to various pipe specifications.
Smart Images

Figure CN120962599A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the technical field of heating pipeline construction, and in particular to a mobile work platform and its usage method for heating pipeline trench construction. Background Technology
[0002] In the construction of heating pipelines, large-diameter heating pipelines are typically 12m long each, with a distance of approximately 400mm between the supply and return water pipes. The welding operation employs an argon-electric welding process. This process requires a large amount of materials and equipment, including argon arc welding machines, welding rods, welding wires, grinding machines, and protective gear, and these materials need to be frequently retrieved during the welding process. However, due to the limited space inside the trench, the remaining space after the supply and return water pipes are installed is limited, making it difficult to place the materials and equipment required for welding nearby. Workers need to frequently move them inside and outside the trench or at different locations inside the trench, which not only consumes a lot of manpower and reduces construction efficiency, but also easily causes safety hazards such as collisions and tripping due to space congestion. Summary of the Invention
[0003] To address the problems existing in the prior art, the present invention provides a mobile working platform for heating pipeline trench construction that does not occupy the bottom space of the trench and is easy to move, as well as a method of using it.
[0004] On the one hand, the present invention provides a mobile working platform for the construction of heating pipeline trenches, which adopts the following technical solution: A mobile work platform for constructing heating pipeline trenches includes a frame and a support plate. The support plate is fixed to the inner wall of the frame. Multiple movable components capable of moving along the heating pipeline are arranged below the support plate. The heating pipeline includes a water supply pipeline and a return pipeline. Movable components are arranged on both the water supply pipeline and the return pipeline. Each movable component includes a mounting base and rollers. The mounting base is connected to the bottom of the support plate, and the rollers are installed below the mounting base. The surface of the rollers is provided with a first groove that matches the curvature of the outer wall of the heating pipeline.
[0005] Optionally, fixing blocks are provided on both sides of the mounting base. The fixing blocks are welded and fixed to the bearing plate. A connecting rod is fixed between the two fixing blocks. The connecting rod passes through the mounting base and is slidably connected to the mounting base and the connecting rod. Springs are fixed at both ends of the mounting base. The end of the spring away from the mounting base is fixed to the fixing block.
[0006] Optionally, a connecting block is fixed on the side wall of the frame, and a threaded rod is provided on the connecting block. The threaded rod passes through the connecting block and is threadedly connected to the connecting block. A friction block is rotatably connected to the bottom of the threaded rod. A second groove is provided at the bottom of the friction block, and the second groove is adapted to the outer wall of the heating pipe.
[0007] On the other hand, the present invention also discloses a method for using a mobile work platform for constructing heating pipeline trenches, comprising the following steps: S1. Erect the platform on the heating pipeline and place the welding equipment and tools on the support plate; S2. Move the platform to the vicinity of the welding point, then rotate the threaded rod to make the friction block contact the surface of the heating pipe, thereby positioning the platform.
[0008] S3. Then, the staff takes materials and operates equipment on the support plate to carry out welding operations. After the welding operation is completed, the threaded rod is rotated to make the friction block disengage from the heating pipe and push the platform to the vicinity of the next point that needs to be welded. This process is repeated to complete the welding operation of the pipe.
[0009] Compared with the prior art, the present invention has the following technical effects: 1. The working platform of this invention is directly erected on the water supply and return pipelines, without occupying space at the bottom of the pipe trench, perfectly adapting to confined working environments and solving the problem of where to place materials and equipment. 2. The roller design allows the working platform to move flexibly along the pipeline, eliminating the need for manual handling of materials and equipment and improving operational mobility. 3. Materials and equipment are placed nearby on the platform, eliminating the need for workers to travel back and forth to retrieve them, thus shortening auxiliary work time. 4. It avoids the risk of tripping and collisions caused by haphazardly piling materials and equipment in the pipe trench, improving operational safety. Attached Figure Description
[0010] Figure 1 This is a schematic diagram of the overall structure of the present invention; Figure 2 This is a schematic diagram of the structure of the moving component in this invention; Figure 3 This is a schematic diagram of the fixing block, connecting rod, and spring in this invention; Figure 4 This is a schematic diagram of the friction block and threaded rod in this invention.
[0011] Explanation of reference numerals in the attached drawings: 1. Frame; 2. Support plate; 3. Moving mechanism; 31. Moving component; 311. Mounting base; 312. Roller; 313. First groove; 314. Fixing block; 315. Connecting rod; 316. Spring; 4. Heating pipe; 5. Reinforcing rod; 6. Connecting block; 61. Threaded rod; 62. Friction block; 63. Second groove. Detailed Implementation
[0012] The following is in conjunction with the appendix Figure 1 -Appendix Figure 4 The present invention will be described in further detail below.
[0013] Reference Figures 1-4This invention discloses a mobile working platform for constructing heating pipeline trenches, comprising a frame 1, a bearing plate 2, and a moving mechanism 3. The frame 1 is rectangular and welded from channel steel. The bearing plate 2 is a steel plate, welded and fixed to the inner wall of the frame 1. The heating pipeline 4 includes a supply pipe and a return pipe. The length of the frame 1 is adapted to the working area of the 12m heating pipeline 4, and the height of the frame 1 is designed according to the diameter of the heating pipeline 4 to ensure overall center of gravity stability. Multiple reinforcing rods 5, made of angle steel, are fixed below the bearing plate 2 and welded to the bearing plate 2. The two ends of the reinforcing rods 5 are welded and fixed to the inner wall of the frame 1. The length direction of the reinforcing rods 5 is perpendicular to the length direction of the heating pipeline 4. The reinforcing rods 5 increase the overall load-bearing capacity and deformation resistance of the frame 1, preventing the middle of the frame 1 from sinking due to the placement of heavy equipment (such as an argon arc welding machine).
[0014] The support plate 2 is used to place the argon arc welding machine, welding rods, welding wire, grinding machine, and protective equipment. The moving mechanism 3 includes multiple sets of moving components 31. In this embodiment, the water supply pipe and the return water pipe each correspond to three sets of moving components 31. The moving component 31 includes a mounting base 311 and a roller 312. The roller 312 is rotatably connected to the mounting base 311. The surface of the roller 312 is provided with a first groove 313, which matches the curvature of the outer wall of the heating pipe 4. The mounting base 311 is installed below the support plate 2. Fixing blocks 314 are provided on both sides of the mounting base 311, and the fixing blocks 314 are welded and fixed to the support plate 2. A connecting rod 315 is fixed between two fixed blocks 314. The connecting rod 315 passes through the mounting base 311. The mounting base 311 is slidably connected to the connecting rod 315. The length of the connecting rod 315 is greater than the length of the mounting base 311. Springs 316 are fixed at both ends of the mounting base 311. The end of the spring 316 away from the mounting base 311 is fixed to the fixed block 314.
[0015] The surface of the roller 312 is provided with a first groove 313 that matches the curvature of the outer wall of the heating pipe 4, which ensures that the roller 312 can fit against the surface of the heating pipe 4 and thus make the roller 312 roll stably. A spring 316 is provided between the mounting base 311 and the fixing block 314, which allows the mounting base 311 to move a small distance left or right, thereby adapting to the left and right tilting of the heating pipe 4 during installation.
[0016] A connecting block 6 is fixed on the side wall of frame 1. A threaded rod 61 is provided on the connecting block 6. The threaded rod 61 passes through the connecting block 6 and is threadedly connected to the connecting block 6. A friction block 62 is rotatably connected to the bottom of the threaded rod 61. The friction block 62 is made of rubber. A second groove 63 is provided at the bottom of the friction block 62. The second groove 63 is adapted to the outer wall of the heating pipe 4. When the welding operation point is reached, the threaded rod 61 is rotated to make the friction block 62 of the extrusion block fit with the heating pipe 4, increasing the friction force, thereby positioning the mobile work platform.
[0017] This invention also discloses a method for using a mobile work platform for constructing heating pipeline trenches, comprising the following steps: S1. Erect the platform on the heating pipe 4 and place the welding equipment and tools on the support plate 2; S2. Move the platform to the vicinity of the welding operation point, and then rotate the threaded rod 61 to make the friction block 62 contact the surface of the heating pipe 4, thereby positioning the platform.
[0018] S3. Then, the staff takes materials and operates equipment on the support plate 2 to carry out welding operations. After the welding operation is completed, the threaded rod 61 is rotated to make the friction block 62 disengage from the heating pipe 4, and the platform is pushed to the vicinity of the next point that needs to be welded. This process is repeated to complete the welding operation of the pipe.
[0019] The present invention has the following technical effects: 1. Space Saving: The work platform is directly installed on the supply and return water pipes, without occupying space at the bottom of the pipe trench. It perfectly adapts to confined working environments, solving the problem of where to place materials and equipment. 2. Convenient Mobility: The 312 roller design allows the work platform to move flexibly along the pipeline, eliminating the need for manual handling of materials and equipment, reducing physical exertion, and improving operational mobility. 3. Increased Efficiency: Materials and equipment are placed nearby on the platform, eliminating the need for workers to travel back and forth to retrieve them, shortening auxiliary work time, and accelerating welding progress. 4. Enhanced Safety: It avoids the risk of tripping and collisions caused by haphazardly stacking materials and equipment in the pipe trench. The stable structure of the 312 double rollers also reduces the possibility of platform tipping over, improving operational safety. 5. Strong Adaptability: Specifically designed for various large-diameter pipes and spacing, the structure is simple and the manufacturing cost is low. The size can be adjusted according to the actual pipe specifications, exhibiting good versatility and practicality.
[0020] The above are all preferred embodiments of the present invention and are not intended to limit the scope of protection of the present invention. Therefore, all equivalent changes made in accordance with the structure, shape and principle of the present invention should be covered within the scope of protection of the present invention.
Claims
1. A mobile work platform for constructing heating pipeline trenches, characterized in that: The system includes a frame (1) and a support plate (2). The support plate (2) is fixed to the inner wall of the frame (1). Multiple movable components (31) capable of moving along the heating pipe (4) are provided below the support plate (2). The heating pipe (4) includes a water supply pipe and a return pipe. Movable components (31) are provided on both the water supply pipe and the return pipe. The movable components (31) include a mounting base (311) and a roller (312). The mounting base (311) is connected to the bottom of the support plate (2). The roller (312) is installed below the mounting base (311). The surface of the roller (312) is provided with a first groove (313) that matches the curvature of the outer wall of the heating pipe (4).
2. The mobile work platform for heating pipeline trench construction according to claim 1, characterized in that: Fixing blocks (314) are provided on both sides of the mounting base (311). The fixing blocks (314) are welded and fixed to the bearing plate (2). A connecting rod (315) is fixed between the two fixing blocks (314). The connecting rod (315) passes through the mounting base (311). The mounting base (311) and the connecting rod (315) are slidably connected. Springs (316) are fixed at both ends of the mounting base (311). The end of the spring (316) away from the mounting base (311) is fixed to the fixing block (314).
3. The mobile work platform for heating pipeline trench construction according to claim 1 or 2, characterized in that: A connecting block (6) is fixed on the side wall of the frame (1). A threaded rod (61) is provided on the connecting block (6). The threaded rod (61) passes through the connecting block (6) and is threadedly connected to the connecting block (6). A friction block (62) is rotatably connected to the bottom of the threaded rod (61). A second groove (63) is provided at the bottom of the friction block (62). The second groove (63) is adapted to the outer wall of the heating pipe (4).
4. A method of using the mobile work platform for heating pipeline trench construction as described in claim 3, characterized in that, Includes the following steps: S1. Set up the platform on the heating pipe (4) and place the welding equipment and tools on the support plate (2); S2. Move the platform to the vicinity of the welding operation point, and then rotate the threaded rod (61) to make the friction block (62) contact the surface of the heating pipe (4) to position the platform. S3. Then, the staff takes materials and operates equipment on the support plate (2) to carry out welding operations. After the welding operation is completed, the threaded rod (61) is rotated to make the friction block (62) disengage from the heating pipe (4) and push the platform to the vicinity of the next point to be welded. This process is repeated to complete the welding operation of the pipe.