Examination system and method applied to construction progress of extra-long tunnel in complex geology
By developing an assessment system and method for the construction progress of long tunnels with complex geological conditions, and utilizing Joss percentage calculation and progress index correction coefficients, the problems of real-time adjustment and incentive mechanism implementation in the existing technology for tunnel construction progress assessment have been solved, thus achieving accurate and efficient management of construction progress.
Patent Information
- Application Number
- CN202511797731.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-02
- Publication Date
- 2026-03-06
AI Technical Summary
Existing methods for assessing tunnel construction progress cannot achieve real-time dynamic adjustments or effectively assess critical nodes on the critical path, resulting in the ineffective implementation of incentive assessment mechanisms and insignificant assessment results.
A system and method for assessing the construction progress of long tunnels with complex geological conditions are adopted. By combining a data acquisition module, an indicator element analysis and calculation module, a storage module and a display module, the tunnel construction progress index is calculated using the Joss percentage (Q). Combined with factors such as the progress index correction coefficient λ, path weight Ai, and remaining path length, a monthly real-time assessment and reward/penalty mechanism is realized.
It enables real-time dynamic adjustment and intuitive assessment of the construction progress of long tunnels with complex geological conditions, ensuring the effectiveness of assessment results and the implementation of incentive mechanisms, and improving the accuracy and efficiency of construction progress management.
Smart Images

Figure CN121616150A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the technical field of construction progress assessment and management, specifically to an assessment system and method for the construction progress of long tunnels with complex geological conditions. Background Technology
[0002] Because a tunnel is a long, tubular structure, tunnel construction is a multi-stage, multi-trade underground operation characterized by narrow working faces, limited capacity for workers, numerous work cycles, large volumes of muck and material transportation, strong inter-process interference, high difficulty in construction organization, and slow progress in excavation and support. Typically, only two working faces continuously advance in a loop, and sometimes even these two faces are not fully utilized. Adding more working faces is also difficult. Therefore, tunnel engineering often becomes a key project for controlling the construction period, with a challenging timeline.
[0003] The geological conditions of some extra-long tunnels, extremely high-risk tunnels, and key control tunnels in southern Yunnan are complex, with prominent adverse geological problems such as active faults, large deformation of soft rock, karst, water-rich structures, bedding planes, and high ground temperatures, resulting in high construction risks and extreme difficulty. To ensure the steady, orderly, and accelerated construction of key control tunnel projects, and in accordance with the operational goal of ensuring the high-quality opening of a certain railway, the construction of key tunnels is being steadily and comprehensively advanced based on the specific circumstances of the project, ensuring the achievement of key schedule targets.
[0004] Currently, most methods for assessing tunnel construction progress indicators focus on the overall completion date and key milestones. A few methods use monthly excavation and support progress targets based on surrounding rock grade, drawing upon tunnel construction experience. However, most existing methods rely on single-face excavation progress assessments, failing to provide real-time adjustments to monthly progress indicators, lack a clear view of critical path milestones, and are ineffective in setting assessment points for key control points. Therefore, a better assessment system and method are needed to evaluate the completion of key control tunnel excavation and support construction progress indicators within a project section, ensuring the effectiveness of rewards and penalties based on assessment results. Summary of the Invention
[0005] To address the technical problems existing in current performance evaluation and management systems, this invention provides a performance evaluation system and method for the construction progress of long tunnels in complex geological conditions. This system and method provide a management system and method for evaluating the completion of construction progress indicators for tunnels in complex geological conditions and tunnels used in control projects.
[0006] To achieve the above objectives, this invention provides a method for assessing the construction progress of long tunnels in complex geological conditions. The method is implemented through a system for assessing the construction progress of long tunnels in complex geological conditions and includes the following steps: S1. Receive the basic information of the assessment subject at the beginning of the current period through the data acquisition module; S2. Receive the required information on the current period's assessment completion status for each path of the assessment target through the indicator element analysis and calculation module; S3. Process the path weight information and path completion percentage information of the assessed object, and output the current assessment record information of the assessed object; S4. Store the assessment results of the assessed individuals in the storage module; S5. When the storage module receives a query instruction, it reads the assessment results of the assessment object from the storage module according to the query instruction and outputs the assessment results to the display module.
[0007] In step S1, the construction unit client of the data acquisition module receives the basic information of each path of the assessment object at the beginning of the current period, including: the planned completion date, the remaining construction period, the path weight, the remaining amount of work at the beginning of the period, and other explanatory information.
[0008] In step S2, the construction unit client receives the required information on the current period's assessment completion status of each path through the indicator element analysis and calculation module, including: the current period's planned progress, the current period's actual completion progress, and the path completion percentage.
[0009] Step S3 specifically includes: adopting an assessment method based on the comprehensive percentage completion of the excavation and support plan for a single tunnel within a section, whereby the percentage is named the Joss percentage or Joss score, denoted by Q; the Joss percentage Q is calculated as a weighted average of the percentage completion of excavation and support for the remaining paths of each tunnel section in the current month; seeking an expression for the combination of elements of the construction progress indicator system that affect the assessment results for each path, thus obtaining the calculation formula for the tunnel construction progress indicator assessment: (1) In the formula: λ is the schedule indicator correction factor, with a value range of 0.95 ≤ λ ≤ 1.05; Ki represents the percentage of planned completion for each remaining path; AI is the weight coefficient or percentage for each remaining path; n is the number of remaining paths; Percentage of remaining path completed (Ki): (2) In the formula: pi represents the actual number of remaining paths completed in the current month, which is the sum of the actual completion amounts of the two working faces; if the two working faces belong to different sections, it is the completion amount of a single working face within the assessment section. Pi represents the planned quantity of the remaining path to be completed in the current month, determined by the remaining path length and the remaining construction period, and converted into monthly progress; the remaining quantity of work is the remaining path length up to the beginning of the assessment period; the remaining construction period is the time from the beginning of the assessment period to the date of completion, converted into months. The weighting coefficient Ai for the remaining paragraphs: (3) In the formula: li represents the remaining path length up to the beginning of the assessment period; L represents the total remaining path length up to the beginning of the assessment period.
[0010] The remaining paths for the section include: the routes taken to achieve breakthrough for the remaining sections of the tunnel identified as the assessment targets.
[0011] The elements of the construction progress indicator system that affect the assessment results include: planned completion date Tp, remaining construction period Ts, path weight Ai, initial remaining work volume li, current planned progress Pi, current actual completed progress pi, path completion percentage Ki, and other explanatory information, totaling 8 influencing factors.
[0012] Other explanatory circumstances include: if the remaining path involves one auxiliary tunnel entering the main tunnel and the roof is lifted, the remaining construction period will be reduced by 0.5 months; if the auxiliary tunnel enters the main tunnel and the roof is lifted twice, the remaining construction period will be reduced by 1.0 month; the completion date of each remaining section will be specified by the construction unit's assessment department according to the construction organization design.
[0013] Whether to use the progress index correction coefficient in the above formula (1), and how to determine its value, shall be determined by the assessment department of the construction unit and the construction unit being assessed.
[0014] The complex geological tunnels include: extra-long tunnels, extremely high-risk tunnels, and control tunnels with prominent geological problems such as complex geology, active faults, large deformation of soft rock, karst, water-rich structures, bedding planes, and high ground temperature, which pose high engineering construction risks and are difficult to construct.
[0015] An assessment system for evaluating the construction progress of long tunnels in complex geological conditions includes a server, a client application for assessing construction units, and a terminal application for assessing construction companies. The server comprises Server 1 and Server 2. Server 1 includes a data acquisition module and an indicator element analysis and calculation module, while Server 2 includes an assessment module and a reward / penalty evaluation module. The assessment system also includes a base station module, a data analysis module, a storage module, and a display module.
[0016] The data acquisition module is connected to the construction unit's client, the indicator element analysis and calculation module, and the assessment module via a base station module. The indicator element analysis and calculation module is connected to the construction unit's client and the assessment module via a base station module. The assessment module is connected to the construction unit's terminal, the base station module, the reward and penalty evaluation module, and the storage module. The storage module is connected to the display module.
[0017] The base station module is connected to the data acquisition module, the indicator element analysis and calculation module, the data analysis module, and the assessment module, respectively.
[0018] The data acquisition module is used to receive basic information of the initial indicator elements of the assessment object from the client of the construction unit, and to feed the collected information back to the indicator element analysis and calculation module. The indicator element analysis and calculation module is used to receive the requirement information from the construction unit's client regarding the current completion status of each path of the assessment object, and to summarize the information collected by all clients during the current assessment period. The summarized information is then used for data identification and analysis according to the assessment method. The weight coefficient Ai of the remaining section and the completion percentage Ki of the remaining path of the assessment object are obtained through the calculation formula of the tunnel construction progress indicator assessment. The current assessment result record information of the assessment object is output and the assessment result is fed back to the assessment module. The assessment module is used to receive basic information of the initial indicators of the assessed object from the data acquisition module through the base station module; to receive the assessment results calculated by the indicator element analysis and calculation module through the base station module, and to feed the assessment results back to the reward and punishment evaluation module; the assessment cycle of the assessment module is from the 21st of each month to the 20th of the following month, and on the 20th of the following month, an indicator element information table of the assessment completion status is sent to the construction unit client.
[0019] The reward and punishment assessment module is connected to the construction unit's terminal. Based on the assessment results of the assessment module, the module assesses whether the construction unit's assessment targets are rewarded or punished, feeds back the assessment results to the construction unit's terminal, and stores them through the storage module.
[0020] The storage module is used to store the current assessment results and the current reward and punishment evaluation results, and reads the target assessment results according to the query command, and outputs the assessment results to the display module.
[0021] The display module is used to display the target assessment results.
[0022] This invention provides a system and method for assessing the construction progress of long tunnels in complex geological conditions. It successfully addresses a series of problems, including limited excavation and construction at the tunnel face, the fact that tunnels are often key control projects within a construction section, tight deadlines, incomplete progress assessment indicators, unclear percentage completion rates for different remaining paths, vague weighting coefficients for remaining segments of those paths, and ambiguous relationships between remaining critical path work and remaining time. These issues lead to ineffective incentive assessment mechanisms and unclear assessment results. Through innovative research, the invention proposes using the comprehensive percentage completion of excavation and support plans for individual tunnels within a construction section. This effectively solves the above problems and more concretely and intuitively reflects the percentage completion and remaining work of the critical path during the assessment period, resulting in more effective assessment results. Attached Figure Description
[0023] Figure 1 This is a system framework diagram of an embodiment of the present invention applied to the assessment system for the construction progress of long tunnels in complex geological conditions.
[0024] Figure 2 This is a flowchart of an embodiment of the present invention applied to the assessment method for the construction progress of long tunnels in complex geological conditions.
[0025] Figure 3 This is a flowchart illustrating the indicator element determination process of an embodiment of the present invention for assessing the construction progress of long tunnels in complex geological conditions.
[0026] Figure 4 This is a schematic diagram of the construction task plan of an embodiment of the present invention applied to the assessment method for the construction progress of long tunnels with complex geological conditions.
[0027] In the diagram: 1. Construction unit terminal, 2. Construction unit client, 3. Server 1, 4. Server 2, 5. Base station module, 6. Data acquisition module, 7. Indicator element analysis and calculation module, 8. Data analysis module, 9. Assessment module, 10. Reward and punishment evaluation module, 11. Storage module, 12. Display module. Detailed Implementation
[0028] To more clearly illustrate the technical solutions of the embodiments of the present invention, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. For those skilled in the art, all other embodiments obtained without creative effort are within the scope of protection of the present invention.
[0029] To facilitate understanding of the embodiments of the present invention, further explanations and descriptions will be provided below with reference to the accompanying drawings and specific embodiments.
[0030] Example 1
[0031] A system for assessing the construction progress of long tunnels in complex geological conditions: See Figure 1 The assessment system includes a server, a client 2 for assessing construction units, and a terminal 1 for assessing construction companies. The server includes a first server 3 and a second server 4. The first server 3 is equipped with a data acquisition module 6 and an indicator element analysis and calculation module 7. The second server 4 is equipped with an assessment module 9 and a reward and penalty evaluation module 10. The assessment system also includes a base station module 5, a data analysis module 8, a storage module 11, and a display module 12.
[0032] The data acquisition module 6 is connected to the construction unit client 2, the indicator element analysis and calculation module 7, and the assessment module 9 via the base station module 5. The indicator element analysis and calculation module 7 is connected to the construction unit client 2 and the assessment module 9 via the base station module 5. The assessment module 9 is connected to the construction unit terminal 1, the base station module 5, the reward and punishment evaluation module 10, and the storage module 11. The storage module 11 is connected to the display module 12.
[0033] The base station module 5 is connected to the data acquisition module 6, the indicator element analysis and calculation module 7, the data analysis module 8, and the assessment module 9, respectively.
[0034] The data acquisition module 6 is used to receive the basic information of the initial indicator elements of the assessment object sent from the construction unit client 2, and to feed the collected information back to the indicator element analysis and calculation module 7. The indicator element analysis and calculation module 7 is used to receive the requirement information on the current completion status of each path assessment of the assessment object sent by the construction unit client 2, and to summarize the information collected by all clients during the current assessment period. The summarized information is then used for data identification and analysis according to the assessment method. The weight coefficient Ai of the remaining section and the completion percentage Ki of the remaining path are obtained through the calculation formula of the tunnel construction progress indicator assessment. The current assessment result record information of the assessment object is output and the assessment result is fed back to the assessment module 9. The assessment module 9 is used to receive basic information of the initial indicators of the assessment object from the data acquisition module 6 through the base station module 5; to receive the calculated assessment results from the indicator element analysis and calculation module 7 through the base station module 5, and to feed the assessment results back to the reward and punishment evaluation module 10; the assessment cycle of the assessment module 9 is from the 21st of each month to the 20th of the following month, and on the 20th of the following month, it sends the indicator element information table of the assessment completion status to the construction unit client 2.
[0035] The reward and punishment assessment module 10 is connected to the construction unit terminal 1. Based on the assessment results of the assessment module 9, the assessment results of the construction unit are assessed to determine whether the assessment object is rewarded or punished. The assessment results are fed back to the construction unit terminal 1 and stored through the storage module 11.
[0036] The storage module 11 is used to store the current assessment results and the current reward and punishment evaluation results, and reads the target assessment results according to the query command, and outputs the assessment results to the display module 12.
[0037] The display module 12 is used to display the target assessment results.
[0038] In this embodiment, the assessment module 9 includes a central processing unit (CPU) located in the construction unit's computer. The storage module 11 is a hard disk connected to the CPU. The display module 12 is a liquid crystal display (LCD).
[0039] The evaluation results of the reward and punishment evaluation module 10 include the following: (1) For those whose Q≥100%, a certain amount of bonus will be awarded to the project management department of the construction unit, mainly to the key management personnel of the project, of which the project manager will be awarded no less than 30% of the total bonus, and the entire line will be publicly commended; for those who have done so twice or more, the construction unit will send a letter to the construction unit group company to commend them. (2) For those whose 100% > Q ≥ 90%, a certain amount of bonus will be awarded to the project management department of the construction unit, mainly to the key management personnel of the project, of which the project manager will be awarded no less than 30% of the total bonus, and the whole line will be notified. (3) If the percentage Q of Joss increases for three consecutive months but does not exceed 100%, a one-time bonus will be awarded; if the percentage Q of Joss decreases for three consecutive months but is still greater than 90%, the bonus for that month will be cancelled. (4) If 90% > Q ≥ 75%, a warning notice will be issued across the board; if the percentage Q has not been below 90% for three consecutive months, a public reprimand will be issued across the board and 1 point will be deducted from the credit rating for that month. Those with a Q < 75% will receive a public reprimand, have 1 point deducted from their monthly credit rating, and have a copy sent to the construction company. The group company and the construction unit's leaders in charge were stationed on-site to supervise the work, and the construction unit held talks with the construction unit.
[0040] Example 2
[0041] like Figure 2 and Figure 3 The following is an application embodiment 1 illustrating a method for assessing the construction progress of a complex geological tunnel: Includes the following steps: S1. Receive the basic information of the assessment object at the beginning of the current period through data acquisition module 6; S2. Receive the required information on the current period's assessment completion status of each path for the assessment object through the indicator element analysis and calculation module 7; S3. Process the path weight information and path completion percentage information of the assessed object, and output the current assessment record information of the assessed object; S4. Store the assessment results of the assessed individuals in storage module 11; S5. When the storage module 11 receives a query instruction, it reads the assessment results of the assessment object from the storage module 11 according to the query instruction, and outputs the assessment results to the display module 12.
[0042] In step S1, the construction unit client of the data acquisition module receives the basic information of each path of the assessment object at the beginning of the current period, including: the planned completion date, the remaining construction period, the path weight, the remaining amount of work at the beginning of the period, and other explanatory information.
[0043] In step S2, the construction unit client receives the required information on the current period's assessment completion status of each path through the indicator element analysis and calculation module, including: the current period's planned progress, the current period's actual completion progress, and the path completion percentage.
[0044] Step S3 specifically includes: adopting an assessment method based on the comprehensive percentage completion of the excavation and support plan for a single tunnel within a section, whereby the percentage is named the Joss percentage or Joss score, denoted by Q; the Joss percentage Q is calculated as a weighted average of the percentage completion of excavation and support for the remaining paths of each tunnel section in the current month; seeking an expression for the combination of elements of the construction progress indicator system that affect the assessment results for each path, thus obtaining the calculation formula for the tunnel construction progress indicator assessment: (1) In the formula: λ is the schedule indicator correction factor, with a value range of 0.95 ≤ λ ≤ 1.05; Ki represents the percentage of planned completion for each remaining path; AI is the weight coefficient or percentage for each remaining path; n is the number of remaining paths; Percentage of remaining path completed (Ki): (2) In the formula: pi represents the actual number of remaining paths completed in the current month, which is the sum of the actual completion amounts of the two working faces; if the two working faces belong to different sections, it is the completion amount of a single working face within the assessment section. Pi represents the planned quantity of the remaining path to be completed in the current month, determined by the remaining path length and the remaining construction period, and converted into monthly progress; the remaining quantity of work is the remaining path length up to the beginning of the assessment period; the remaining construction period is the time from the beginning of the assessment period to the date of completion, converted into months. The weighting coefficient Ai for the remaining paragraphs: (3) In the formula: li represents the remaining path length up to the beginning of the assessment period; L represents the total remaining path length up to the beginning of the assessment period.
[0045] The remaining paths for the section include: the routes taken to achieve breakthrough for the remaining sections of the tunnel identified as the assessment targets.
[0046] The elements of the construction progress indicator system that affect the assessment results include: planned completion date Tp, remaining construction period Ts, path weight Ai, initial remaining work volume li, current planned progress Pi, current actual completed progress pi, path completion percentage Ki, and other explanatory information, totaling 8 influencing factors.
[0047] Other explanatory circumstances include: if the remaining path involves one auxiliary tunnel entering the main tunnel and the roof is lifted, the remaining construction period will be reduced by 0.5 months; if the auxiliary tunnel enters the main tunnel and the roof is lifted twice, the remaining construction period will be reduced by 1.0 month; the completion date of each remaining section will be specified by the construction unit's assessment department according to the construction organization design.
[0048] Whether to use the progress index correction coefficient in the above formula (1), and how to determine its value, shall be determined by the assessment department of the construction unit and the construction unit being assessed.
[0049] The complex geological tunnels include: extra-long tunnels, extremely high-risk tunnels, and control tunnels with prominent geological problems such as complex geology, active faults, large deformation of soft rock, karst, water-rich structures, bedding planes, and high ground temperature, which pose high engineering construction risks and are difficult to construct.
[0050] Example 3
[0051] This embodiment uses the system described in Embodiment 1 and the method described in Embodiment 2 to statistically analyze the case study of the excavation and support progress of the Manmushu Tunnel in the Yumo section of the China-Laos Railway, which has complex geological features. Through numerical calculation and analysis of the influence of different remaining paths, and combined with eight elements of the construction progress index system that affect the assessment results, including the progress index correction coefficient λ, the planned completion date Tp, the remaining construction period Ts, the path weight Ai, the initial remaining work quantity q, the current planned progress Pi, the current actual completed progress pi, the path completion percentage Ki, and other explanatory information, the path weight and the path completion percentage are determined. After linear relationship analysis, the calculation formula for the tunnel's Joss percentage Q is finally obtained.
[0052] Manmushu Tunnel is located near the Suoluo River in Yunnan Province, such as Figure 4 As shown, the tunnel entrance is at DK419+937 and the exit is at DK431+574, with a total length of 11637m. It adopts an auxiliary tunnel configuration of "entrance + 1 pilot tunnel + 3 inclined shafts + exit," with a maximum burial depth of 660m. The survey area is characterized by adverse geological conditions including landslides, debris flows, stalagmites, bedding-parallel pressure, large deformation in soft rock, and karst. Joints and folds are well-developed, and the lithology consists of sandstone, shale, and mudstone. High ground stress exists, and large deformations occur in soft rock sections. The tunnel's geological conditions are extremely complex, and the construction schedule faces immense pressure.
[0053] The method described in Example 2, when applied to the above-mentioned project, includes the following steps: S1. Data acquisition module 6 receives the basic information of each path of the assessment object at the beginning of the current period through the construction unit client 2, including: planned completion date, remaining construction period, path weight, remaining work volume at the beginning of the period and other explanatory information; S2. The indicator element analysis and calculation module 7 receives the required information on the current period's assessment completion status of each path through the construction unit's client 2, including: the current period's planned progress, the current period's actual completion progress, and the path completion percentage; S3. Process the path weight information and path completion percentage information of the assessed object, and output the current assessment record information of the assessed object; Specifically, this includes: using a comprehensive percentage assessment method based on the completion of the excavation and support plan for a single tunnel within a contract section, where the percentage is named the Joss percentage or Joss score, denoted by Q; the Joss percentage Q is calculated as a weighted average of the percentage of excavation and support completion for the remaining path in each section of the tunnel in the current month; seeking an expression for the combination of elements of the construction progress indicator system that affect the assessment results for each path, thus obtaining the calculation formula for the tunnel construction progress indicator assessment: (1) In the formula: λ is the schedule indicator correction factor, with a value range of 0.95 ≤ λ ≤ 1.05; Ki represents the percentage of planned completion for each remaining path; AI is the weight coefficient or percentage for each remaining path; n is the number of remaining paths; Percentage of remaining path completed (Ki): (2) In the formula: pi represents the actual number of remaining paths completed in the current month, which is the sum of the actual completion amounts of the two working faces; if the two working faces belong to different sections, it is the completion amount of a single working face within the assessment section. Pi represents the planned quantity of the remaining path to be completed in the current month, determined by the remaining path length and the remaining construction period, and converted into monthly progress; the remaining quantity of work is the remaining path length up to the beginning of the assessment period; the remaining construction period is the time from the beginning of the assessment period to the date of completion, converted into months. The weighting coefficient Ai for the remaining paragraphs: (3) In the formula: li represents the remaining path length up to the beginning of the assessment period; L represents the total remaining path length up to the beginning of the assessment period.
[0054] The remaining routes for the sections include: the routes taken to achieve breakthrough for the remaining sections of the tunnel identified as the assessment targets. The monthly plan is determined by the remaining workload and remaining construction period at the beginning of the assessment period; the monthly assessment period is from the 21st of the previous month to the 20th of the current month; Taking the actual excavation and support construction progress of the Manmushu Tunnel in August 2020 (July 21 - August 20) as an example, the relevant construction progress indicators for the 31-day period are detailed in Table 1: Table 1. Calculation of Tunnel Excavation and Support Construction Progress as a Percentage by Joss
[0055] The elements of the construction progress indicator system that affect the assessment results include: planned completion date Tp, remaining construction period Ts, path weight Ai, initial remaining work volume li, current planned progress Pi, current actual completed progress pi, path completion percentage Ki, and other explanatory information, totaling 8 influencing factors.
[0056] Other explanatory details include: if the remaining path involves one auxiliary tunnel entering the main tunnel and requiring roof support, the remaining construction period will be reduced by 0.5 months; if it involves two auxiliary tunnels entering the main tunnel and requiring roof support, the remaining construction period will be reduced by 1.0 month; the completion date for each remaining segment will be specified by the construction unit's assessment department based on the construction organization design. In this embodiment, the completion dates for each remaining path are: 2021 / 2 / 28, 2021 / 5 / 31, 2021 / 5 / 31, 2021 / 6 / 30, 2021 / 3 / 31.
[0057] Whether to use the progress index correction coefficient in the above formula (1), and how to determine its value, shall be determined by the assessment department of the construction unit and the construction unit being assessed.
[0058] S4. Store the assessment results of the assessment subjects in the storage module 11, and reward or punish them according to the situation in the reward and punishment assessment module 10. As shown in Table 1, in this embodiment, the percentage of Qiao Si Q=92.2%. Reward or punish them according to the situation (2) in the reward and punishment assessment module based on this result. Give the project management department of the construction unit a certain amount of bonus reward, mainly rewarding the key management personnel of the project. Among them, the project manager is rewarded with no less than 30% of the total bonus. The whole line is notified.
[0059] S5. When the storage module 11 receives a query instruction, it reads the assessment results of the assessment object from the storage module 11 according to the query instruction, and outputs the assessment results to the display module 12.
Claims
1. A method for assessing the construction progress of long tunnels in complex geological conditions, characterized in that: The evaluation method is implemented through an evaluation system for construction progress of a complex geological special tunnel, and comprises the following steps: S1. Receiving basic information of the evaluation object at the beginning of the current period through a data acquisition module; S2. Receiving demand information of the evaluation object at the current period through an index element analysis and calculation module; S3. Processing path weight information and path completion percentage information of the evaluation object, and outputting current evaluation record information of the evaluation object; S4. Storing evaluation results of the evaluation object in a storage module; S5. When the storage module receives a query instruction, reading the evaluation results of the evaluation object from the storage module according to the query instruction, and outputting the evaluation results to a display module.
2. The method for checking the construction progress of a complex geological long tunnel according to claim 1, characterized in that: In step S1, the basic information of the evaluation object at the beginning of the current period is received through a construction unit client of the data acquisition module, including: planned breakthrough date, remaining construction period, path weight, initial remaining engineering quantity, and other description conditions.
3. The method for assessing the construction progress of a complex geological long tunnel according to claim 1, characterized in that: In step S2, the demand information of the evaluation object at the current period is received through a construction unit client of the index element analysis and calculation module, including: current planned progress, current actual completion progress, and path completion percentage.
4. The method for checking the construction progress of a complex geological long tunnel according to claim 1, characterized in that: Step S3 specifically comprises: adopting an evaluation method of a single tunnel excavation and support plan completion comprehensive percentage in a bid section, the percentage is named as Q, and is a weighted average of the remaining path completion percentage of each section of the tunnel in the current month; seeking an expression of a combination of construction progress index system elements affecting the evaluation results of each path, and obtaining a calculation relationship formula of the tunnel construction progress index evaluation: (1) In the formula: λ is a progress index correction coefficient, and the value range is: 0.95≤λ≤1.05; Ki is the planned completion percentage of each remaining path; Ai is the weight coefficient or percentage of each remaining path; n is the number of remaining paths; The completion percentage Ki of the remaining path: (2) In the formula: pi is the actual completion quantity of the remaining path in the current month, which is the sum of the actual completion quantities of two working faces; if the two working faces belong to different bid sections, it is the completion quantity of a single working face in the evaluation bid section; Pi is the planned completion quantity of the remaining path in the current month, which is determined by the remaining path length and the remaining construction period, and is converted into monthly progress; the remaining engineering quantity is the remaining path length as of the beginning of the evaluation period; the remaining construction period is the time length from the beginning of the evaluation period to the breakthrough date, which is converted into months; The weight coefficient Ai of the remaining section: (3) In the formula: li is the remaining path length as of the beginning of the evaluation period; L is the total remaining path length as of the beginning of the evaluation period.
5. The method for checking the construction progress of a complex geological long tunnel according to claim 4, characterized in that: The remaining path of the section includes: a route through which each section of the tunnel remaining to be realized breakthrough of the evaluation object.
6. The method for checking the construction progress of a complex geological long tunnel according to claim 4, characterized in that: The construction progress index system elements affecting the evaluation results include: planned breakthrough date Tp, remaining construction period Ts, path weight Ai, initial remaining engineering quantity li, current planned progress Pi, current actual completion progress pi, path completion percentage Ki, and other description conditions, a total of 8 influencing factors.
7. The method for checking the construction progress of a complex geological long tunnel according to claim 6, characterized in that: The other conditions include: if the remaining path appears once auxiliary tunnel into the main tunnel roof, the remaining duration is deducted by 0.5 months; if it appears twice, the remaining duration is deducted by 1.0 month; the breakthrough date of each remaining paragraph is determined by the construction unit examination department according to the construction organization design arrangement.
8. The method according to claim 4, wherein, Whether to use the progress index correction coefficient in the formula (1) and how to determine its value are determined by the construction unit examination department and the construction unit being examined.
9. The method for evaluating the construction progress of a complex geological long tunnel according to any one of claims 1 to 8, characterized in that: The complex geological special tunnel includes: special tunnel, extremely high risk tunnel, and geological complex, active fault, soft rock large deformation, karst, water-rich structure, bedding and high ground temperature, and the construction risk is high, and the construction difficulty is large control tunnel.