Prestressed double-casing assembly type foundation pit enclosure structure and construction method thereof
By using a prestressed double-casing prefabricated foundation pit retaining structure, which utilizes precast piles, pile top casings, outer casings, and unbonded prestressed tendons, combined with composite steel support beams and end-bearing beam composite slabs, the problems of long construction cycle, poor quality stability, and high leakage risk of traditional deep foundation pit retaining structures are solved, thus achieving efficient and safe foundation pit engineering construction.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- IANGSU COLLEGE OF ENG & TECH
- Filing Date
- 2026-06-03
- Publication Date
- 2026-07-03
AI Technical Summary
Traditional deep foundation pit retaining structures suffer from long construction cycles, large amounts of wet work, poor quality stability, insufficient reliability of node connections, poor force transmission, and difficulty in controlling assembly precision. They are prone to safety hazards such as leakage and instability, making it difficult to meet the requirements of safe, efficient, and green construction for deep foundation pit projects.
The prestressed double-casing prefabricated foundation pit retaining structure is adopted, which includes precast piles, pile top casings and outer casings. Unbonded prestressed tendons are installed between the two. Combined with composite steel support beams and end-bearing beam composite plates, a closed structure is formed by high-strength bolt connection and high-pressure grouting to achieve continuous top restraint and active prestressing, thereby improving the overall stiffness and resistance to lateral displacement.
It significantly improves the overall stiffness and lateral displacement resistance of the retaining structure, controls the deformation of the top of the foundation pit retaining structure, improves construction accuracy and efficiency, enhances safety and durability, reduces leakage risk, and meets the safety and efficiency construction requirements of deep foundation pit projects.