Climbing reverse roof picking and combined excavation method for large-section tunnel fan room

By using the method of reverse overpassing and combined excavation, along with the combined support of anchor bolts, steel mesh, steel arches and shotcrete, the problem of overpassing and widening excavation in the construction of ventilation rooms in large-section tunnels was solved, achieving safe, efficient and economical construction results.

CN122407205APending Publication Date: 2026-07-17CCCC SHEC DONGMENG ENG CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CCCC SHEC DONGMENG ENG CO LTD
Filing Date
2026-05-15
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Traditional tunnel excavation methods are difficult to adapt to the needs of large-section roof lifting and widening excavation. They involve complicated procedures, large amounts of support removal, slow construction progress, high costs, and limited working space inside the tunnel. In addition, conventional excavation and support methods cannot guarantee the structural stability of intersections, affecting operational safety and structural durability.

Method used

The method of climbing and reverse top lifting and combined excavation is adopted. The excavation is organized in layers and sections, and combined with the joint support of anchor bolts, steel mesh, steel arch frame and shotcrete. The arch and arch foot are reinforced with emphasis. Excavation, backfilling and support are carried out simultaneously to form a working platform, reduce the exposure time of the surrounding rock and improve the stability of the surrounding rock.

Benefits of technology

It enables smooth connection of small-section transport channels to large-section fan rooms, reduces the risk of arch collapse, improves arch forming quality, ensures good surrounding rock stability and safety control, reduces slag discharge, improves work efficiency, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122407205A_ABST
    Figure CN122407205A_ABST
Patent Text Reader

Abstract

本发明公开了用于大断面隧道风机房的爬坡反向挑顶与组合开挖方法,包括施工准备、爬坡扩挖进洞、上部导洞支护、反向挑顶、掏渣垫开挖中台阶、下部台阶开挖及后续施工步骤;施工准备阶段完成运输通道支护、设备拼装、地质预报与放样;爬坡扩挖按设计坡度分层开挖;上部导洞施作联合支护并加强拱脚;反向挑顶开挖欠挖三角区、渣土回填并随挖随支护;中台阶掏渣垫坡、单侧开挖支护;下部台阶待强度达标后错开开挖;最后加固拱脚、做好排水与基底清理。本方法工序衔接有序,支护及时可靠,适用于大断面隧道风机房开挖。