Methods and systems for preventing collisions between multiple towers
By combining information on the static collision zone and dynamic obstacles of the tower crane, the system plans paths and executes avoidance actions in real time, solving the problem of ignoring dynamic collision risks in existing technologies and improving the safety and efficiency of multi-tower operations.
Patent Information
- Application Number
- CN202611060878.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-16
- Publication Date
- 2026-11-17
AI Technical Summary
Existing methods for preventing collisions in multiple towers are mainly based on static parameters, ignoring dynamic collision risks, resulting in low construction safety.
By combining information on the static collision zone and dynamic obstacles of the tower crane, the system can plan a path in real time and execute avoidance actions, thus achieving a combination of static and dynamic collision avoidance.
This significantly reduces the risk of collisions between tower cranes and between tower cranes and obstacles, improving construction safety and operational efficiency.
Smart Images

Figure CN123105474A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tower crane control technology, and more specifically to a method and system for preventing collisions between multiple tower cranes. Background Technology
[0002] When multiple tower cranes are operating simultaneously on a construction site, the large size of the tower cranes, the numerous moving parts, and the overlapping movement spaces of each tower crane can easily lead to collisions between tower cranes and between tower cranes and surrounding obstacles, seriously threatening construction safety.
[0003] Currently, collision avoidance measures for multi-tower operations are mainly based on fixed parameters of the tower cranes, such as boom length, maximum slewing radius, and pre-defined fixed working areas. Potential collision zones are determined by calculating the maximum motion envelope that the tower crane might occupy when stationary, and then the collision zone is avoided. Essentially, this only considers the spatial occupancy of the tower crane in its static limit posture, ignoring dynamic collision risks.
[0004] Therefore, existing multi-tower collision avoidance methods still have a high risk of collision. Summary of the Invention
[0005] The purpose of this invention is to provide a method and system for preventing collisions between multiple towers. This method combines static and dynamic collision prevention to greatly reduce the risk of collisions.
[0006] To achieve the above objectives, the first aspect of this application provides a method for preventing collisions between multiple towers, comprising: Obtain the static collision area of each tower crane; When any tower crane is used as a working tower crane, the planned path of the working tower crane is determined based on the task information and the static collision area of each tower crane. When the tower crane is performing its work tasks according to the planned path, the movement information of moving obstacles is acquired in real time, and based on the movement information of the moving obstacles, it is determined whether the tower crane is at risk of collision. In the event of a collision risk with the working tower crane, the tower crane is controlled to perform an avoidance maneuver.
[0007] In this embodiment of the application, obtaining the static collision area of each tower crane includes: Obtain the static parameters of each tower crane; Based on the static parameters of each tower crane, the motion envelope of each tower crane at any slewing angle and lifting height is calculated to obtain the static collision area of each tower crane.
[0008] In this embodiment of the application, determining the planned path of the working tower crane based on the task information and the static collision area of each tower crane includes: Based on the static collision zones of each tower crane, the passable work area is determined; Based on the task information, path planning is performed in the accessible area of the task to obtain the planned path of the tower crane.
[0009] In this embodiment of the application, the real-time acquisition of motion information of moving obstacles includes: Real-time detection of obstacle information around the working tower crane; Based on the work map and obstacle information around the tower crane, moving obstacles were identified; Based on the current location information and historical trajectory information of the moving obstacle, the motion information of the moving obstacle is predicted.
[0010] In this embodiment of the application, the motion information of the moving obstacle includes the motion trajectory of the moving obstacle; The determination of whether the tower crane faces a collision risk based on the motion information of the moving obstacle includes: Determine whether the trajectory of the moving obstacle intersects with the planned path of the tower crane; If it is determined that the trajectory of the moving obstacle intersects with the planned path of the working tower crane, it is determined whether the intersection point is within the braking safety range of the working tower crane to obtain a first judgment result; If the first determination result is that the working tower crane is within the safe braking range, then it is determined that the working tower crane is at risk of collision.
[0011] In this embodiment of the application, controlling the working tower crane to perform an avoidance maneuver when there is a collision risk includes: In the event of a collision risk with the tower crane, the tower crane shall be stopped from operation until the moving obstacle is moved away from the planned path of the tower crane.
[0012] In this embodiment of the application, the process of determining the safe braking range of the tower crane includes: Based on the motion information of the tower crane, the braking range is determined; Based on the braking range and the preset safety value, the braking safety range of the working tower crane is obtained.
[0013] In this embodiment of the application, it also includes: Based on the static collision areas of each tower crane, it is determined whether there is a static collision risk area, and a second judgment result is obtained; Based on the first judgment result and the second judgment result, a reminder message is generated.
[0014] The second aspect of this application provides a multi-tower collision avoidance system, including a server and multiple tower crane edge terminals, each tower crane edge terminal corresponding to one tower crane; The edge of the tower crane is used to acquire the static collision area of each tower crane; when any tower crane is used as a working tower crane, the planned path of the working tower crane is determined based on the work task information and the static collision area of each tower crane; when the working tower crane performs the work task according to the planned path, the motion information of the moving obstacles is acquired in real time and the motion information of the moving obstacles is sent to the server. The server is used to determine whether the working tower crane has a collision risk based on the movement information of the moving obstacle; if the working tower crane has a collision risk, it controls the working tower crane to perform an avoidance action.
[0015] In this embodiment, the tower crane edge includes a lidar sensor, a mapping module, and an active control module; The mapping module is used to construct the operational map; The lidar sensor is used to detect obstacle information around the tower crane in real time; The active control module is used to identify moving obstacles based on the operation map and obstacle information around the tower crane, and to predict the movement information of the moving obstacles based on their current location information and historical trajectory information.
[0016] The above technical solution acquires the static collision zones of each tower crane. When any tower crane is used as a working crane, its planned path is determined based on the task information and the static collision zones of each crane. While the working crane is performing its task according to the planned path, the movement information of moving obstacles is acquired in real time, and the crane is assessed for collision risk based on this information. If a collision risk exists, the crane is controlled to perform an avoidance maneuver. The planned path of the working crane fully considers the static collision zones of each crane, preventing collisions with obstacles within these zones, thus achieving static collision avoidance. Furthermore, the system continuously assesses whether the working crane will collide with moving obstacles. If a collision risk exists, the crane is controlled to perform an avoidance maneuver, reducing the risk of collisions with dynamic obstacles and achieving dynamic collision avoidance. The entire process combines static and dynamic collision avoidance, significantly reducing collision risk and contributing to construction safety.
[0017] Other features and advantages of the embodiments of the present invention will be described in detail in the following detailed description section. Attached Figure Description
[0018] The accompanying drawings are provided to further illustrate embodiments of the present invention and form part of the specification. They are used together with the following detailed description to explain the embodiments of the present invention, but do not constitute a limitation thereof. In the drawings: Figure 1 The schematic diagram illustrates a flowchart of a method for preventing collisions between multiple towers according to an embodiment of this application; Figure 2 A static collision avoidance diagram according to an embodiment of this application is illustrated schematically; Figure 3 A schematic diagram illustrating dynamic collision avoidance according to an embodiment of this application is shown. Figure 4 This illustration schematically shows a dynamic and static combined anti-collision fusion strategy according to an embodiment of this application; Figure 5 The schematic diagram illustrates the overall architecture of the integrated collision avoidance system according to an embodiment of this application. Detailed Implementation
[0019] The specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are for illustration and explanation only and are not intended to limit the scope of the present invention.
[0020] It should be noted that the acquisition, transmission, storage, use, and processing of data in the technical solution of this application all comply with relevant laws and regulations. In the embodiments of this application, certain existing industry solutions such as software, components, and models may be mentioned. These should be considered exemplary, intended only to illustrate the feasibility of implementing the technical solution of this application, and do not imply that the applicant has already used or necessarily used such solutions.
[0021] It should be noted that if the embodiments of this application involve directional indicators (such as up, down, left, right, front, back, etc.), the directional indicators are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicators will also change accordingly.
[0022] Furthermore, if the embodiments of this application involve descriptions such as "first" or "second," these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, features defined with "first" or "second" may explicitly or implicitly include at least one of those features. Additionally, the technical solutions of various embodiments can be combined with each other, but this must be based on the ability of those skilled in the art to implement them. If the combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed in this application.
[0023] Please refer to Figure 1 , Figure 1 The schematic diagram illustrates a flowchart of a method for preventing collisions between multiple towers according to an embodiment of this application. This embodiment provides a method for preventing collisions between multiple towers, including the following steps: Step 110: Obtain the static collision area of each tower crane; In this embodiment, the static collision zone of each tower crane can be obtained by collision prediction based on the tower crane's geometric parameters and a fixed working area. It can be set based on experience or calculated. This static collision zone can be determined once the tower crane's position is determined and will not change during operation.
[0024] Please refer to Figure 2 , Figure 2 A schematic diagram illustrating static collision avoidance according to an embodiment of this application is provided. In some embodiments, in order to accurately obtain the static collision area of each tower crane, obtaining the static collision area of each tower crane includes: First, obtain the static parameters of each tower crane; In this embodiment, the aforementioned static parameters include: tower crane center coordinates, boom length, slewing radius, maximum slewing angle, lifting height range, and fixed operating area boundaries. The static parameters of each tower crane can be obtained in advance based on its own relevant information, and will not be elaborated upon here.
[0025] Then, based on the static parameters of each tower crane, the motion envelope of each tower crane at any slewing angle and lifting height is calculated to obtain the static collision area of each tower crane.
[0026] In this embodiment, based on static parameters such as the tower center coordinates, boom length, slewing radius, maximum slewing angle, and lifting height range of each tower crane, the continuous slewing angle range and lifting height range are discretized into a finite number of posture combinations according to a set step size. For each combination, the projection contour of key moving components such as the boom on the horizontal plane is calculated, and the corresponding lifting height range is added to form the motion envelope of the three-dimensional space under that posture. After traversing all discrete postures, the static collision area covered by the tower crane under all working conditions is obtained.
[0027] By making full use of the static parameters of tower cranes, the motion envelope under different combinations of slewing angles and lifting heights can be accurately calculated, thereby forming a refined static collision zone, which helps to provide a more accurate basis for judging collision prevention for multiple tower cranes.
[0028] Step 120: When any tower crane is used as a working tower crane, determine the planned path of the working tower crane based on the task information and the static collision area of each tower crane. In this embodiment, in a multi-tower operation scenario, any tower crane can perform operations. The tower crane performing the operation can be referred to as the working tower crane. Based on the task information and the static collision areas of each tower crane, the planned path of the working tower crane can be determined, allowing it to execute the task according to the planned path. The task information includes: starting position, target position, etc., where the starting position can also be the current position of the working tower crane.
[0029] In some embodiments, determining the planned path of the working tower crane based on the task information and the static collision area of each tower crane includes: First, based on the static collision zones of each tower crane, the passable work area is determined; In this embodiment, the tower crane operating area can be divided into a grid (e.g., 0.4m × 0.4m resolution, which can be set based on experience). Combined with the static collision areas of each tower crane, a passable grid map of the operating area is generated, thus obtaining the passable operating area. This passable operating area can refer to the area within the tower crane operating area after removing the static collision areas of all tower cranes except the working tower crane.
[0030] Then, based on the task information, path planning is performed in the accessible area of the task to obtain the planned path of the tower crane.
[0031] In this embodiment, in order to move from the starting position to the target position, a planned path for the working tower crane can be planned. This planned path must avoid the static collision zones of each tower crane, resulting in a collision-free planned path. The specific process of the above path planning can be implemented using existing technologies, and will not be elaborated here.
[0032] Furthermore, the planned path can be smoothed to ensure that the first and second derivatives of the path curve are smooth, preventing irregular paths such as those resembling a gate and ensuring smooth velocity and acceleration curves. The path smoothing process described above is existing technology and will not be elaborated upon further here.
[0033] By determining the passable area for operation based on the static collision zones of each tower crane, and using the task information, the planned path for the working tower crane can be quickly obtained. In actual testing, based on industry experience, when the tower crane boom length is less than 70m and the tower height is less than 90m, the time required for the above path planning is less than 10s.
[0034] Step 130: When the working tower crane is performing its work task according to the planned path, the movement information of the moving obstacles is acquired in real time, and based on the movement information of the moving obstacles, it is determined whether the working tower crane has a collision risk. In this embodiment, please refer to Figure 3 , Figure 3 This diagram schematically illustrates a dynamic collision avoidance system according to an embodiment of this application. After obtaining a planned path, the tower crane performs its work tasks according to the planned path. During the work tasks, the movement information of moving obstacles can be acquired in real time. These moving obstacles can refer to dynamically changing obstacles, such as cargo lifted by other tower cranes outside the group of tower cranes. This information can be obtained in real time using a sensing system on the tower crane, including lidar, vision sensors, etc. The movement information of the moving obstacles includes the speed and direction of the moving obstacles. This movement information can be the movement information at the current moment.
[0035] In some embodiments, the real-time acquisition of motion information of moving obstacles includes: First, real-time detection of obstacle information around the working tower crane; In this embodiment, lidar sensors can be installed at the end of the boom and on the upper part of the jib of each tower crane to scan obstacles around the crane in real time. The lidar sensor's scanning frequency can be set according to actual conditions. For example, based on experience, the lidar scanning frequency can be set to no less than 5Hz, capable of identifying obstacles larger than 5cm. Alternatively, a millimeter-wave radar and vision fusion scheme can be used to achieve obstacle detection through multi-sensor fusion, thereby reducing hardware costs. The above-mentioned sensor fusion for obstacle detection is existing technology and will not be elaborated further here.
[0036] Then, based on the work map and obstacle information around the tower crane, moving obstacles are identified; In this embodiment, the aforementioned work map can be pre-built before the work task is carried out. For example, a 3D point cloud map of the tower crane work area can be built using SLAM technology. Based on experience, the mapping resolution can reach 0.4m, the global mapping frequency can reach more than 3Hz, and the global mapping time does not exceed 10 minutes. The obstacle information around the working tower crane is acquired in real time. The obstacle information around the working tower crane can be compared with the obstacle information in the work map to determine whether the obstacle exists in the work map. If it exists, it means that it is not a dynamic obstacle; otherwise, it means that it is a moving obstacle.
[0037] Finally, based on the current location information and historical trajectory information of the moving obstacle, the motion information of the moving obstacle is obtained.
[0038] In this embodiment, because the obstacle information around the working tower crane is acquired in real time, obstacle information around the working tower crane at multiple moments can be obtained. Its movement trajectory can be tracked to obtain historical trajectory information, which includes the position information at multiple historical moments. For example, at the first moment, the moving obstacle is at position A; at the second moment, the moving obstacle is at position B; and at the current moment, the moving obstacle is at position C. Based on the current position information and historical trajectory information of the moving obstacle, combined with the interval of obstacle information acquisition, the running trend information at the next moment can be predicted. The running trend information includes movement direction, speed, position, etc. Through multiple iterative predictions, based on the multiple predicted running trend information, the movement trajectory of the moving obstacle can be obtained, that is, the movement information of the moving obstacle can be obtained. The above prediction can be achieved using existing trajectory prediction methods, which will not be elaborated further here.
[0039] By using the operation map and real-time detection of obstacle information around the tower crane, moving obstacles can be accurately identified. Then, based on the current location information and historical trajectory information of the moving obstacles, the running trend information of the moving obstacles can be predicted in advance, thus obtaining the movement information of the moving obstacles. This helps to improve the accuracy and reliability of collision risk assessment.
[0040] After obtaining the movement information of the moving obstacle, it is possible to determine whether the working tower crane will collide with the moving obstacle, i.e., whether there is a risk of collision.
[0041] In some embodiments, the motion information of the moving obstacle includes the trajectory of the moving obstacle. Accordingly, determining whether the tower crane has a collision risk based on the motion information of the moving obstacle includes: First, determine whether the trajectory of the moving obstacle intersects with the planned path of the tower crane; In this embodiment, the above determination can be made by comparing each point on the trajectory of the moving obstacle with each point on the planned path of the working tower crane. If there are points in the same position, it means there is an intersection; otherwise, it means there is no intersection. If the intersection is at a position already traversed by the working tower crane, the intersection is discarded.
[0042] Then, if it is determined that the trajectory of the moving obstacle intersects with the planned path of the working tower crane, it is determined whether the intersection point is within the braking safety range of the working tower crane to obtain the first judgment result; In this embodiment, due to the inherent mechanical structure and physical characteristics of the tower crane, it cannot stop immediately during operation; there is a braking range. This braking range can refer to the distance or angle required for the mechanism to brake. Here, the mechanism refers to the tower crane's luffing mechanism, slewing mechanism, and hoisting mechanism. For example, if the tower crane's slewing mechanism, at its highest speed (e.g., fourth gear), requires a slewing angle of 40° from triggering the braking command to complete stillness, then the braking range can be defined as the current slewing angle plus 40°. To reduce the risk of collision with moving obstacles after the tower crane stops, the aforementioned safe braking range can be greater than the actual braking range. The aforementioned safe braking range of the working tower crane can be set based on experience or determined based on the current speed, load, and deceleration of the mechanism. The coordinates of the intersection point determine whether the crane is within the safe braking range. The first determination result includes whether the crane is within or outside the safe braking range.
[0043] The process of determining the braking safety range of the tower crane includes: The first step is to determine the braking range based on the motion information of the tower crane. In this embodiment, the above-mentioned operating information includes the current speed, load, and deceleration of the working tower crane. The determination process may involve pre-calibrating the corresponding braking range under different speeds, loads, and decelerations of the mechanism, and then matching the braking range based on the current motion information.
[0044] The second step is to obtain the braking safety range of the working tower crane based on the braking range and the preset safety value.
[0045] In this embodiment, the aforementioned preset safety value can be pre-set according to actual conditions, including distance values, angle values, etc. For example, it can be set to 0.4m based on experience. The braking safety range can be the braking range plus the preset safety value. In this way, when the intersection point is located between the braking range and the braking safety range, it can be ensured that after braking, there is still a distance between the working tower crane and the intersection point, further reducing the risk of collision.
[0046] The braking range is determined based on the motion information of the working tower crane, and the braking safety range of the working tower crane obtained by combining it with the preset safety value is more reliable.
[0047] Then, if the first judgment result is that the working tower crane is within the safe braking range, it is determined that the working tower crane has a collision risk.
[0048] In this embodiment, if the first judgment result is within the braking safety range of the working tower crane, it indicates that there is a risk of collision between the moving obstacle and the working tower crane; otherwise, it indicates that it is safe.
[0049] By determining whether the trajectory of the moving obstacle intersects with the planned path of the working tower crane, and if it is determined that the trajectory of the moving obstacle intersects with the planned path of the working tower crane, it is determined whether the intersection is within the braking safety range of the working tower crane. This allows for early prediction of whether the working tower crane is at risk of collision, which helps to avoid collisions in advance and reduce the risk of collision.
[0050] Step 140: If there is a collision risk with the working tower crane, control the working tower crane to perform an avoidance maneuver.
[0051] In this embodiment, a unified anti-collision server can be set up to manage the operation of multiple tower cranes. If there is a collision risk, an avoidance command can be issued to the tower crane, and the tower crane will perform an avoidance action according to the avoidance command.
[0052] In some embodiments, controlling the working tower crane to perform an avoidance maneuver when there is a collision risk includes: In the event of a collision risk with the tower crane, the tower crane shall be stopped from operation until the moving obstacle is moved away from the planned path of the tower crane.
[0053] In this embodiment, controlling the tower crane to stop operation includes, but is not limited to, controlling the tower crane to stop slewing, stop hook retraction, and stop luffing. After the tower crane stops, it waits for the moving obstacle to move away from the planned path of the tower crane before continuing to perform the operation task according to the planned path. Determining whether the moving obstacle is moving away from the planned path of the tower crane can be achieved by acquiring information such as the position, speed, and direction of movement of the moving obstacle in real time. Based on the position, it can be determined whether the moving obstacle has passed the intersection point and whether the direction of movement is away from the planned path.
[0054] By controlling the tower crane to stop operation until the moving obstacle moves away from the planned path of the tower crane when there is a risk of collision, the risk of collision can be reduced while the operation can continue to follow the planned path.
[0055] In the above implementation process, the static collision zones of each tower crane are acquired. When any tower crane is used as a working crane, its planned path is determined based on the task information and the static collision zones of each crane. While the working crane is performing its task according to the planned path, the movement information of moving obstacles is acquired in real time, and based on this information, it is determined whether the working crane faces a collision risk. If a collision risk exists, the working crane is controlled to perform an avoidance maneuver. The planned path of the working crane fully considers the static collision zones of each crane, ensuring that it does not collide with obstacles within these zones, thus achieving static collision avoidance. Furthermore, it is determined in real time whether the working crane will collide with moving obstacles. If a collision risk exists, the crane is controlled to perform an avoidance maneuver, thereby reducing the risk of collision with dynamic obstacles and achieving dynamic collision avoidance. The entire process combines static and dynamic collision avoidance, a combined static and dynamic collision avoidance method that significantly reduces collision risk and helps ensure construction safety. This method can coordinate the movement paths of each tower crane according to the task, improving the efficiency of group tower crane operations while reducing the risk of collisions.
[0056] In some embodiments, it also includes: First, based on the static collision areas of each tower crane, it is determined whether there are any static collision risk areas, and a second judgment result is obtained; In this embodiment, when the static collision zones of two tower cranes overlap, they can be marked as static collision risk areas. That is, it can be determined whether the static collision zones of each tower crane overlap to determine whether a static collision risk area exists. The second determination result includes: static collision zones do not overlap and static collision zones overlap.
[0057] Then, based on the first judgment result and the second judgment result, a reminder message is generated.
[0058] In this embodiment, multiple risk levels can be preset. For example, the risk levels are divided into three levels: safe (static collision zones do not overlap and there are no dynamic obstacles), warning (static collision zones overlap or a dynamic obstacle is detected but not within the braking safety distance), and danger (dynamic obstacle enters the braking safety distance range). The first judgment result includes being within the braking safety range of the working tower crane (i.e., entering the braking safety distance) and not being within the braking safety range of the working tower crane (i.e., not entering the braking safety distance). If the first judgment result is entering the braking safety distance, it indicates that there is a collision risk, that is, the collision risk level is danger, and a danger warning message can be generated; if the first judgment result is not entering the braking safety distance or the second judgment result is that the static collision zones overlap, the collision risk level can be determined to be warning, and a warning warning message can be generated; if there are no dynamic obstacles and the second judgment result is that the static collision zones do not overlap, it indicates that it is safe, that is, the collision risk level is safe, and a safe warning message can be generated. The generated warning message can be sent to the staff to remind them to pay attention.
[0059] By determining whether there is a static collision risk zone and combining this with the previously determined dynamic obstacle's entry into the braking safety distance, the collision risk level can be determined, thereby generating a warning message. This helps remind staff to take precautions and improves the safety of multi-tower operations.
[0060] Please refer to Figure 4 , Figure 4 This diagram illustrates a combined static and dynamic collision avoidance strategy according to an embodiment of this application. In practice, two layers of collision avoidance protection can be configured: a first layer (static protection layer) and a second layer (dynamic protection layer). The static protection layer serves as a safety baseline, providing all-weather collision risk area restrictions based on the tower crane's static parameters. The dynamic protection layer provides real-time protection, offering dynamic collision warnings and proactive obstacle avoidance based on real-time perception data. A fusion layer is also included, combining dynamic and static protection to determine risk levels and execute proactive obstacle avoidance.
[0061] Please refer to Figure 5 , Figure 5 This schematically illustrates the overall architecture of a comprehensive anti-collision system according to an embodiment of this application. This embodiment provides a multi-tower anti-collision system, including a server and multiple tower crane edge terminals, each tower crane edge terminal corresponding to one tower crane. The edge of the tower crane is used to acquire the static collision area of each tower crane; when any tower crane is used as a working tower crane, the planned path of the working tower crane is determined based on the work task information and the static collision area of each tower crane; when the working tower crane performs the work task according to the planned path, the motion information of the moving obstacles is acquired in real time and the motion information of the moving obstacles is sent to the server. The server is used to determine whether the working tower crane has a collision risk based on the movement information of the moving obstacle; if the working tower crane has a collision risk, it controls the working tower crane to perform an avoidance action.
[0062] In this embodiment, the aforementioned server can be a centralized server that manages the anti-collision logic calculations for tower crane operations, stores information such as the position coordinates of each tower crane and the map of the work area, and issues coordination and scheduling instructions to the edge terminals of each tower crane. Wireless communication can be used between the server and the edge terminals of each tower crane to ensure the real-time performance and reliability of instruction transmission. Wireless communication can be 433MHz wireless communication, 5G private network, or WiFi 6, etc., to improve communication bandwidth and reliability and support larger-scale tower crane collaboration. The edge terminals of the tower cranes can perform tracking control according to the planned path, with a control frequency of no less than 5Hz. During tracking, the maximum slewing speed can reach more than level 3, and the average horizontal deviation from the target point is no greater than 1.0m.
[0063] Through unified scheduling on the server side, the entire system combines static and dynamic collision avoidance, i.e., dynamic and static collision avoidance fusion, which greatly reduces the risk of collision and helps to improve construction safety.
[0064] In some embodiments, the tower crane edge end includes a lidar sensor, a mapping module, and an active control module; The mapping module is used to construct the operational map; The lidar sensor is used to detect obstacle information around the tower crane in real time; The active control module is used to identify moving obstacles based on the operation map and obstacle information around the tower crane, and to predict the movement information of the moving obstacles based on their current location information and historical trajectory information.
[0065] In this embodiment, lidar sensors can be installed at the end of the jib and the upper part of the boom of each tower crane to scan obstacles around the crane in real time. The lidar scanning frequency is no less than 5 Hz, and it can identify obstacles larger than 5 cm. The mapping module can be a SLAM mapping module, specifically using SLAM technology to construct a 3D point cloud map of the tower crane's operating area. The mapping resolution can reach 0.4 m, the global mapping frequency can reach 3 Hz or higher, and the global mapping time should not exceed 10 minutes. The active control module is used for moving object detection. It can detect moving objects (such as goods hoisted by other tower cranes) in the operating area in real time through time series analysis of lidar data and track their movement trajectories. The detection frequency is no less than 5 Hz. Based on the current position and tracking trajectory of the moving object, its future movement trend can be predicted, that is, the movement information of the moving obstacle can be predicted.
[0066] By setting up a lidar sensor, mapping module, and active control module, dynamic obstacles can be perceived in real time and their movement information can be accurately predicted.
[0067] The aforementioned tower crane edge also includes an RTK positioning module and a path planning module. The path planning module can generate a safe movement path based on anti-collision commands; the active control module can also perform path tracking control. In construction site environments where RTK signals are limited, the aforementioned RTK positioning module can be replaced with a visual positioning and inertial navigation fusion solution.
[0068] For example, the tower crane is equipped with an RTK positioning module at its edge, and the system has completed automatic calibration, obtaining the transformation relationship between the RTK coordinate system, the work map coordinate system, and the tower crane's 0-degree direction. When identifying dynamic obstacles, firstly, the 3D point cloud data of the surrounding environment is collected in real time by the lidar sensor. This point cloud data is located in the radar coordinate system with the radar as the origin. The active control module simultaneously acquires the geodetic coordinates output by the RTK positioning module and the tower crane's slewing angle, luffing angle, and lifting height collected by the encoder. Using the transformation parameters obtained from automatic calibration, combined with the current tower crane attitude and RTK positioning results, the composite transformation matrix from the radar coordinate system to the work map coordinate system is calculated in real time. Through this transformation matrix, the coordinates of each point in the current frame's radar point cloud are transformed to the work map coordinate system, resulting in a global point cloud in the work map coordinate system. Subsequently, the global point cloud is spatially compared with the pre-generated work map by the mapping module: laser points that coincide spatially with known background objects such as buildings and material stockpiles in the work map are identified as static obstacles; point cloud clusters whose positions continuously change during multi-frame scanning and cannot be matched with the work map are identified and marked as moving obstacles. During this process, the RTK positioning module provides an absolute spatial reference, and in conjunction with the calibrated coordinate system transformation relationship, reliably achieves dynamic obstacle identification.
[0069] The aforementioned method for determining the transformation relationship between the RTK coordinate system, the work map coordinate system, and the tower crane's 0-degree direction can be achieved by having the tower crane execute specific movements (such as 360-degree rotation or lifting to a specific height) according to a preset action sequence. The tower crane performs these movements simultaneously, collecting RTK positioning data, LiDAR scanning data, and encoder data. After the movement is completed, using the RTK positioning data as the absolute reference and combining it with the encoder data, the offset between the RTK and the tower crane's rotation center, as well as the rotation angle between the RTK coordinate system and the tower crane's 0-degree direction, are calculated. Simultaneously, LiDAR observations of the same environment under different postures are used to calculate the installation parameters of the LiDAR and the tower crane. This ultimately determines the precise transformation relationship between the RTK coordinate system, the work map coordinate system, and the tower crane's 0-degree direction.
[0070] Those skilled in the art will understand that embodiments of this application can be provided as methods, systems, or computer program products. Therefore, this application can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, this application can take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0071] This application is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of this application. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart... Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.
[0072] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.
[0073] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.
[0074] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0075] Memory may include non-persistent memory in computer-readable media, such as random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM. Memory is an example of computer-readable media.
[0076] Computer-readable media includes both permanent and non-permanent, removable and non-removable media that can store information using any method or technology. Information can be computer-readable instructions, data structures, modules of programs, or other data. Examples of computer storage media include, but are not limited to, phase-change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technologies, CD-ROM, digital versatile optical disc (DVD) or other optical storage, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other non-transferable medium that can be used to store information accessible by a computing device. As defined herein, computer-readable media does not include transient computer-readable media, such as modulated data signals and carrier waves.
[0077] It should also be noted that the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus. Unless otherwise specified, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes that element.
[0078] The above are merely embodiments of this application and are not intended to limit the scope of this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of the claims of this application.
Claims
1. A method for preventing collisions between multiple towers, characterized in that, include: Obtain the static collision area of each tower crane; When any tower crane is used as a working tower crane, the planned path of the working tower crane is determined based on the task information and the static collision area of each tower crane. When the tower crane is performing its work tasks according to the planned path, the movement information of moving obstacles is acquired in real time, and based on the movement information of the moving obstacles, it is determined whether the tower crane is at risk of collision. In the event of a collision risk with the working tower crane, the tower crane is controlled to perform an avoidance maneuver.
2. The method for preventing collisions between multiple towers according to claim 1, characterized in that, The process of obtaining the static collision area of each tower crane includes: Obtain the static parameters of each tower crane; Based on the static parameters of each tower crane, the motion envelope of each tower crane at any slewing angle and lifting height is calculated to obtain the static collision area of each tower crane.
3. The method for preventing collisions between multiple towers according to claim 1, characterized in that, The process of determining the planned path of the working tower crane based on the task information and the static collision area of each tower crane includes: Based on the static collision zones of each tower crane, the passable work area is determined; Based on the task information, path planning is performed in the accessible area of the task to obtain the planned path of the tower crane.
4. The method for preventing collisions between multiple towers according to claim 1, characterized in that, The real-time acquisition of motion information of moving obstacles includes: Real-time detection of obstacle information around the working tower crane; Based on the work map and obstacle information around the tower crane, moving obstacles were identified; Based on the current location information and historical trajectory information of the moving obstacle, the motion information of the moving obstacle is predicted.
5. The method for preventing collisions between multiple towers according to claim 1, characterized in that, The motion information of the moving obstacle includes the motion trajectory of the moving obstacle; The determination of whether the tower crane faces a collision risk based on the motion information of the moving obstacle includes: Determine whether the trajectory of the moving obstacle intersects with the planned path of the tower crane; If it is determined that the trajectory of the moving obstacle intersects with the planned path of the working tower crane, it is determined whether the intersection point is within the braking safety range of the working tower crane to obtain a first judgment result; If the first determination result is that the working tower crane is within the safe braking range, then it is determined that the working tower crane is at risk of collision.
6. The method for preventing collisions between multiple towers according to claim 5, characterized in that, In the event of a collision risk, controlling the tower crane to perform an avoidance maneuver includes: In the event of a collision risk with the tower crane, the tower crane shall be stopped from operation until the moving obstacle is moved away from the planned path of the tower crane.
7. The method for preventing collisions between multiple towers according to claim 5, characterized in that, The process of determining the braking safety range of the tower crane includes: Based on the motion information of the tower crane, the braking range is determined; Based on the braking range and the preset safety value, the braking safety range of the working tower crane is obtained.
8. The method for preventing collisions between multiple towers according to claim 5, characterized in that, Also includes: Based on the static collision areas of each tower crane, it is determined whether there is a static collision risk area, and a second judgment result is obtained; Based on the first judgment result and the second judgment result, a reminder message is generated.
9. A multi-tower anti-collision system, characterized in that, This includes a server-side component and multiple tower crane edge terminals, with each tower crane edge terminal corresponding to one tower crane. The edge of the tower crane is used to acquire the static collision area of each tower crane; when any tower crane is used as a working tower crane, the planned path of the working tower crane is determined based on the work task information and the static collision area of each tower crane; when the working tower crane performs the work task according to the planned path, the motion information of the moving obstacles is acquired in real time and the motion information of the moving obstacles is sent to the server. The server is used to determine whether the tower crane is at risk of collision based on the motion information of the moving obstacle; In the event of a collision risk with the working tower crane, the tower crane is controlled to perform an avoidance maneuver.
10. The multi-tower anti-collision system according to claim 9, characterized in that, The tower crane edge includes a lidar sensor, a mapping module, and an active control module; The mapping module is used to construct the operational map; The lidar sensor is used to detect obstacle information around the tower crane in real time; The active control module is used to identify moving obstacles based on the operation map and obstacle information around the tower crane, and to predict the movement information of the moving obstacles based on their current location information and historical trajectory information.