A modification method for extending the service life of tailings dams

By constructing a large platform in front of the tailings dam, implementing zoned ore discharge around the dam perimeter and tailings, setting up independent spillways, and modifying the drainage well-flood tunnel system, the contradiction between insufficient tailings dam capacity and flood control safety was resolved, thereby extending the service life of the tailings dam and improving its safety and stability.

CN123109180APending Publication Date: 2026-11-17CHINA MINMETALS CHANGSHA MINING RES INST +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611266761.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-20
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The contradiction between insufficient tailings dam capacity and flood control safety is prominent. Existing technologies that rely on increasing the height of the dam have limitations and insufficient economic feasibility. How can we optimize the use of reservoir space, construct flood control and drainage channels, and enhance the safety reserves of the dam without significantly increasing the height of the dam, so as to achieve a synergistic unity between effective release of reservoir capacity and flood control safety?

Method used

By constructing a large platform in front of the tailings dam, separating ore discharge around the dam perimeter and tailings, setting up an independent spillway, and functionally upgrading the drainage well-flood tunnel, four technical measures are systematically integrated to optimize the use of space in the dam area and enhance flood control capabilities and safety reserves.

Benefits of technology

It significantly increases the effective storage capacity of tailings dams, enhances the safety and stability of dams and their flood control capabilities, extends the service life of tailings dams, and achieves synergistic protection of storage capacity and flood control safety, avoiding the rigid constraints of dam heightening and the problem of excessive engineering investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109180A_ABST
    Figure CN123109180A_ABST
Patent Text Reader

Abstract

This application provides a method for extending the service life of a tailings dam, including: constructing a large platform in front of the dam, creating a platform with sufficient width and anti-sliding capacity in the area in front of the tailings dam; separating ore discharge around the dam perimeter and tail end, changing the traditional centralized ore discharge method to a separate ore discharge process around the dam perimeter and tail end based on the safety premise of the large platform in front of the dam; setting up an independent spillway, creating an independent spillway on one side of the dam head as a dedicated flood control and drainage channel for the tailings dam; and functionally modifying the existing drainage well-flood tunnel system in the middle and tail end of the dam area to give it both backwater and flood control functions. This application achieves a coordinated unity of effective dam capacity release and flood control safety assurance without relying on a significant increase in dam height, by optimizing the spatial utilization pattern of the dam area, constructing an independent flood control and drainage channel, and simultaneously improving the dam's safety reserves.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of tailings dam safety technology, specifically relating to a modification method for extending the service life of tailings dams. Background Technology

[0002] In recent years, with the continuous increase in requirements for the safe operation and ecological environmental protection of tailings dams, most operating metal and non-metal mines have nearly exhausted the remaining effective storage capacity of their supporting tailings dams after decades of continuous mining and tailings storage, and the available storage space is extremely limited. However, many mines still retain considerable recoverable resource reserves in their deep and peripheral areas, and the main body of the mine still has a long recoverable service life. In comparison, there is a significant mismatch and disparity between the designed service life of tailings dams and the actual recoverable life of the mines, and the contradiction of "the mine is still there, but the storage capacity is exhausted" is becoming increasingly prominent.

[0003] Current technologies for extending the service life of tailings dams primarily rely on increasing dam height and capacity. However, this approach faces multiple rigid constraints and systemic contradictions during implementation. First, factors such as insufficient dam foundation bearing capacity, decreased dam stability, and stringent seismic safety assessments limit the effective scope for increasing dam height. Furthermore, current technical regulations impose strict quantitative limits on the final accumulation elevation, making the approach of simply increasing dam height to obtain storage capacity impractical in most mines. Second, even in areas with limited space for increasing dam height, the project involves substantial investment, lengthy construction periods, and often complex social coordination issues such as land acquisition and relocation, resulting in severely limited economic feasibility. Third, under the current tailings dam operation model, the tailings dam area often contains large amounts of unutilized sedimentary dry beaches and dead storage areas around the dam, leading to low capacity utilization efficiency and further exacerbating the capacity shortage.

[0004] More importantly, there is an inherent contradiction between the aforementioned reservoir capacity issue and the flood control safety of tailings dams. If the goal is simply to maximize reservoir capacity and raise the operating water level, it will inevitably reduce the flood control capacity, decrease the tailings dam's ability to withstand floods exceeding standard levels, and increase the risk of dam overflow and collapse. Conversely, if the flood control capacity is reserved too conservatively, it will further exacerbate the predicament of insufficient effective reservoir capacity. How to effectively tap the potential of existing reservoir capacity, properly coordinate the relationship between reservoir capacity utilization and flood control safety, and ensure the long-term stability of the dam without significantly increasing the dam height has become an urgent technical challenge to be solved in this field. Summary of the Invention

[0005] The purpose of this invention is to overcome the above-mentioned shortcomings of the prior art and provide a renovation method for extending the service life of tailings dams. The aim is to achieve effective release of reservoir capacity and coordinated protection of flood control safety without relying on a significant increase in the height of the dam body, by optimizing the spatial utilization pattern of the reservoir area, constructing an independent flood control and water discharge channel, and simultaneously improving the safety reserve of the dam body.

[0006] To achieve the above objectives, the technical solution adopted by this invention is as follows: A method for extending the service life of tailings dams includes the following steps: S1: Construction of a large platform in front of the dam: Construct a large platform with sufficient width and anti-sliding capacity in the area in front of the tailings dam. S2: Separate ore discharge around the reservoir perimeter and tail of the reservoir. Based on the premise of safety of the large platform in front of the dam, the traditional centralized ore discharge method in front of the dam is changed to the separate ore discharge process around the reservoir perimeter and tail of the reservoir. S3: Independent spillway setting: An independent spillway is set up on one side of the dam in the reservoir area as a dedicated flood control and water discharge channel for the tailings dam; S4. Functional renovation of drainage wells and flood discharge tunnels: The existing drainage well and flood discharge tunnel system in the middle and tail of the reservoir area will be functionally renovated to enable it to have both water return and flood control functions.

[0007] The technical solution of this application integrates and coordinates four technical means: the construction of a large platform in front of the dam, the zoned ore discharge around the reservoir and tail, the setting of an independent spillway, and the functional transformation of drainage wells and flood discharge tunnels. Without relying on a significant increase in the height of the dam, it achieves a significant increase in the effective storage capacity of the tailings dam, a comprehensive improvement in the safety reserve of the dam, and an effective guarantee of flood control capabilities, thereby matching the service life of the tailings dam with the mine's exploitable life.

[0008] As a further improvement of the present invention, the large platform in front of the dam is constructed by layering and compacting a mixture of tailings sand and soil and rock. The platform construction material is compacted in layers, and the compaction coefficient is not lower than the design value. A seepage-proof membrane is laid at the contact surface between the platform and the dam body or at a specific layer inside the platform to form a seepage barrier.

[0009] As a further improvement of the present invention, the width of the platform top surface is not less than the design calculation value, and the platform outer slope ratio is not steeper than 1:2.5.

[0010] In the technical solution of this application, the large platform in front of the dam functions through the following three mechanisms: First, the phreatic line of the dam is lowered. The layered compaction and embankment construction of the platform, combined with the laying of the impermeable membrane, effectively prevents atmospheric precipitation from seeping down the dam surface, reducing the continuous infiltration of external water sources into the aquifer of the dam. At the same time, it significantly extends the seepage path (seepage diameter) of the tailings dam phreatic line, forcing the seepage inside the dam to bypass at the large platform and be discharged in an orderly manner, thereby effectively reducing the pore water pressure inside the dam and controlling the phreatic line depth below the control phreatic line specified in the "Code for Design of Tailings Facilities" (GB 50863). The effective reduction of the phreatic line directly weakens the seepage pressure and hydrostatic buoyancy inside the dam, significantly improving the dam's anti-sliding stability safety factor.

[0011] Secondly, to resist the erosion of torrential rain and floods, under extreme torrential rain and flood conditions, the water level in the reservoir rises rapidly. The wave rise caused by wind and waves, combined with the increase in water height due to wind backflow, will cause the water in the reservoir to directly act on the upstream slope of the tailings dam. The large platform in front of the dam forms a natural isolation buffer zone between the dam body and the water in the reservoir. Its wide-top platform structure can effectively dissipate energy and block the wave rise, so that the wave energy is greatly attenuated in the platform section, avoiding the direct action of torrential rain and floods and their wave loads on the main dam body. At the same time, drainage cross slopes and intercepting ditches are set on the top surface of the platform to orderly guide the water on the platform surface to the outside of the reservoir, preventing the water from soaking the dam foot for a long time.

[0012] Third, it provides secondary support. As a secondary support structure on the downstream side of the dam, the large platform can play a role in blocking and bearing even if the upstream dam body undergoes local deformation due to extreme working conditions, preventing slippage and providing additional safety redundancy for the dam body.

[0013] After stability calculation, the dam body's anti-sliding stability safety factor meets the minimum safety factor requirements of the "Code for Design of Tailings Facilities" (GB 50863) for tailings dams of the corresponding grade under normal operation, flood operation and seismic conditions.

[0014] As a further improvement of the present invention, S2 specifically involves setting up ore discharge points around the tailings pond area and at the tail end of the pond area, and discharging the tailings slurry in an orderly manner to the pond periphery and tail end areas that are difficult to utilize in traditional ore discharge methods through a combination of pipeline transportation and decentralized ore discharge.

[0015] As a further improvement of the present invention, the ore discharge method adopts one or more combinations of the following: horizontal ore discharge method, underwater ore discharge method on both sides of the reservoir, or ore discharge method in the tributary.

[0016] In the technical solution of this application, through the aforementioned zoned tailings discharge method around the reservoir perimeter and tailings, tailings are evenly distributed throughout the entire reservoir area, the sedimentary surface of the reservoir tends to be flat, and the dead storage areas existing under traditional discharge methods (including the dry sedimentary beach areas around the reservoir and the unused areas at the tailings) are effectively activated and incorporated into the storage range; at the same time, the long-term unused storage space below the normal production water level within the reservoir is also fully utilized. As a result, the overall reservoir capacity utilization rate is significantly improved, and the effective storage capacity is substantially increased without raising the dam.

[0017] As a further improvement of the present invention, S3 specifically refers to the spillway being an open spillway, constructed of masonry blocks or concrete, and located on one side of the dam head in the reservoir area.

[0018] As a further improvement of the present invention, the cross-sectional dimensions and discharge capacity of the spillway are determined by hydrological calculation based on the flood control standards corresponding to the tailings dam's grade.

[0019] As a further improvement of the present invention, the elevation of the spillway bottom plate is set according to the flood season limit water level determined by flood control calculation, the inlet is equipped with diversion facilities, and the outlet is connected to the downstream energy dissipation facilities.

[0020] The technical solution of this application, through the construction of an independent spillway, enables the tailings dam to possess a flood control and drainage channel independent of the tailings discharge system. During the flood season, floodwaters in the reservoir area are discharged independently through the spillway, unaffected by tailings storage operations, ensuring sufficient flood control capacity and unimpeded flood discharge. Compared with the traditional method of relying on a drainage well-flood tunnel system for flood discharge, the independent spillway avoids the risk of the flood discharge inlet being buried by tailings, significantly improving the tailings dam's ability to cope with excessive floods.

[0021] As a further improvement of the present invention, S4 specifically retains the flood discharge and water intake functions on the basis of the existing drainage well structure, while adding backwater collection and transportation facilities.

[0022] As a further improvement of the present invention, during the non-flood season, the drainage well-flood tunnel system operates as a return water facility, which collects the clarified water in the reservoir in an orderly manner and transports it through the tunnel to the return water pool of the mineral processing plant for recycling in mineral processing production; during the flood season, the system switches to a flood control and drainage channel, working in conjunction with the independent spillway to jointly undertake the flood control and drainage tasks of the reservoir area.

[0023] The technical solution in this application achieves "dual-purpose drainage" through modification—allowing the existing drainage system to reuse its function over time without significantly increasing engineering investment. During the non-flood season, it serves the production water recycling, reducing the consumption of clean water in the ore dressing plant; during the flood season, it serves flood control safety, ensuring the safety of the tailings dam during the flood season.

[0024] The technical effects of this invention are as follows: This invention integrates four technical measures: the construction of a large platform in front of the dam, zoned ore discharge around the reservoir perimeter and tail, the establishment of an independent spillway, and the functional modification of the drainage well-flood tunnel system. This integration produces the following comprehensive synergistic effect, demonstrating an overall technical efficiency greater than the sum of its parts (1+1>2): 1. A complete technical closed loop of safety prerequisites → reservoir capacity release → flood control guarantee → functional reuse, with four measures organically linked according to the sequential logic of "safety first, capacity expansion second, security third, and efficiency improvement"—the large platform in front of the dam creates a safe prerequisite for ore release around the reservoir and at the tail end; the independent spillway after the reservoir capacity expansion solves the flood control contradictions brought about by the expansion; the drainage system renovation realizes functional reuse and forms a dual flood control pattern with the spillway. The four measures are interconnected and mutually supportive, forming a complete technical closed loop.

[0025] 2. The lifespan can be extended without relying on increasing the height of the dam. The entire process of this invention does not involve a significant increase in the height of the dam, thus completely avoiding a series of rigid constraints such as insufficient bearing capacity of the dam foundation, decreased stability of the dam body, and the rigid restrictions on the height of the increase in the current specifications. This provides a practical and feasible technical solution for a large number of in-service tailings dams that cannot be increased in height.

[0026] 3. The unity of safety and efficiency: While achieving the core goal of extending the service life of tailings dams, this invention simultaneously improves the safety and stability of the dam body and the flood control safety guarantee capability, and takes into account the comprehensive utilization of water resources and the saving of engineering investment. The comprehensive benefits are significantly better than the single dam body heightening and capacity expansion scheme, and it has broad prospects for promotion and application. Attached Figure Description

[0027] To more clearly illustrate the technical solution of this application, the accompanying drawings used in this application will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0028] Figure 1 This is a schematic plan view of the tailings dam of the present invention.

[0029] Figure 2 Diagram of the large platform structure.

[0030] Figure 3 This is a schematic diagram of the beach ditch.

[0031] Figure 4 This is a diagram of the geomembrane embedding structure on the side of the mountain.

[0032] Figure 5 This is an elevation view of the drainage well renovation project.

[0033] Figure 6 This is a plan projection of the drainage well renovation.

[0034] Figure 7 This is a longitudinal section of the tailings dam.

[0035] Figure 8 This is a cross-sectional view of the spillway.

[0036] The text labels in the diagram represent: 1. Large platform; 2. Drainage ditch; 3. Return water pipe; 4. Drainage well; 5. Tunnel; 6. Return water conveying pipeline; 7. Main ore discharge pipe at the tail of the reservoir; 8. Branch ore discharge pipe at the tail of the reservoir; 11. Shaft base; 12. Column; 13. Ring beam; 14. Arch cover plate; 15. Arch plate; 16. Ladder; 17. Rockfill slope; 18. Cover plate; 19. Rubber waterstop; 20. Cast-in-place C25 concrete foundation. Detailed Implementation

[0037] The embodiments of the technical solution of this application will now be described in detail with reference to the accompanying drawings. These embodiments are only used to more clearly illustrate the technical solution of this application and are therefore merely examples, and should not be used to limit the scope of protection of this application.

[0038] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains; the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the application; the terms “comprising” and “having”, and any variations thereof, in the specification, claims, and foregoing description of the drawings are intended to cover non-exclusive inclusion.

[0039] In the description of the embodiments of this application, technical terms such as "first" and "second" are used only to distinguish different objects and should not be construed as indicating or implying relative importance or implicitly specifying the number, specific order, or primary and secondary relationship of the indicated technical features. In the description of the embodiments of this application, "multiple" means two or more, unless otherwise explicitly defined.

[0040] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.

[0041] In the description of the embodiments of this application, the technical terms "center," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," and "circumferential" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing the embodiments of this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the embodiments of this application.

[0042] Those skilled in the art can understand the specific meaning of the above terms in the embodiments of this application according to the specific circumstances.

[0043] For ease of explanation, the following embodiments will be described using an example of a modification method for extending the service life of a tailings dam according to an embodiment of this application.

[0044] Please refer to Figures 1-8This application discloses a modification method for extending the service life of tailings ponds, comprising the following steps: S1: Construction of a large platform in front of the dam: Construct a large platform with sufficient width and anti-sliding capacity in the area in front of the tailings dam. S2: Separate ore discharge around the reservoir perimeter and tail of the reservoir. Based on the premise of safety of the large platform in front of the dam, the traditional centralized ore discharge method in front of the dam is changed to the separate ore discharge process around the reservoir perimeter and tail of the reservoir. S3: Independent spillway setting: An independent spillway is set up on one side of the dam in the reservoir area as a dedicated flood control and water discharge channel for the tailings dam; S4. Functional renovation of drainage wells and flood discharge tunnels: The existing drainage well and flood discharge tunnel system in the middle and tail of the reservoir area will be functionally renovated to enable it to have both water return and flood control functions.

[0045] In the above implementation method, through the systematic integration and synergistic effect of four technical means—construction of a large platform in front of the dam, zoned ore discharge around the reservoir and tail, setting up an independent spillway, and functional transformation of drainage wells and flood discharge tunnels—a significant increase in the effective storage capacity of the tailings dam, a comprehensive improvement in the safety reserve of the dam, and an effective guarantee of flood control capacity are achieved without relying on a significant increase in the height of the dam body. This ensures that the service life of the tailings dam matches the exploitable life of the mine.

[0046] Furthermore, in some implementation examples, the large platform in front of the dam is constructed by layering and compacting a mixture of tailings sand and soil and rock. The platform construction material is compacted in layers, and the compaction coefficient is not lower than the design value. A seepage-proof membrane is laid at the contact surface between the platform and the dam body or at a specific layer inside the platform to form a seepage barrier.

[0047] Furthermore, in some implementation examples, the width of the platform top surface is not less than the design calculation value, and the platform outer slope ratio is not steeper than 1:2.5.

[0048] In the above implementation method, the large platform in front of the dam functions through the following three mechanisms: First, the phreatic line of the dam is lowered. The layered compaction and embankment construction of the platform, combined with the laying of the impermeable membrane, effectively prevents atmospheric precipitation from seeping down the dam surface, reducing the continuous infiltration of external water sources into the aquifer of the dam. At the same time, it significantly extends the seepage path (seepage diameter) of the tailings dam phreatic line, forcing the seepage inside the dam to bypass at the large platform and be discharged in an orderly manner, thereby effectively reducing the pore water pressure inside the dam and controlling the phreatic line depth below the control phreatic line specified in the "Code for Design of Tailings Facilities" (GB 50863). The effective reduction of the phreatic line directly weakens the seepage pressure and hydrostatic buoyancy inside the dam, significantly improving the dam's anti-sliding stability safety factor.

[0049] Secondly, to resist the erosion of torrential rain and floods, under extreme torrential rain and flood conditions, the water level in the reservoir rises rapidly. The wave rise caused by wind and waves, combined with the increase in water height due to wind backflow, will cause the water in the reservoir to directly act on the upstream slope of the tailings dam. The large platform in front of the dam forms a natural isolation buffer zone between the dam body and the water in the reservoir. Its wide-top platform structure can effectively dissipate energy and block the wave rise, so that the wave energy is greatly attenuated in the platform section, avoiding the direct action of torrential rain and floods and their wave loads on the main dam body. At the same time, drainage cross slopes and intercepting ditches are set on the top surface of the platform to orderly guide the water on the platform surface to the outside of the reservoir, preventing the water from soaking the dam foot for a long time.

[0050] Third, it provides secondary support. As a secondary support structure on the downstream side of the dam, the large platform can play a role in blocking and bearing even if the upstream dam body undergoes local deformation due to extreme working conditions, preventing slippage and providing additional safety redundancy for the dam body.

[0051] After stability calculation, the dam body's anti-sliding stability safety factor meets the minimum safety factor requirements of the "Code for Design of Tailings Facilities" (GB 50863) for tailings dams of the corresponding grade under normal operation, flood operation and seismic conditions.

[0052] Furthermore, in some implementation examples, S2 specifically involves setting up ore discharge points around the tailings pond area and at the tail end of the pond area, and using a combination of pipeline transportation and decentralized ore discharge to orderly discharge the tailings slurry to the pond periphery and tail end areas that are difficult to utilize in traditional ore discharge methods.

[0053] Furthermore, in some implementation examples, the ore discharge method adopts one or more combinations of the following: horizontal ore discharge method, underwater ore discharge method on both sides of the reservoir, or tributary ditch ore discharge method.

[0054] In the above embodiments, through the zonal tailings discharge method around the reservoir perimeter and tailings, tailings are evenly distributed throughout the entire reservoir area, the sedimentary surface of the reservoir tends to be flat, and the dead storage areas existing under traditional discharge methods (including the dry sedimentary beach areas around the reservoir and the unused areas at the tailings) are effectively activated and incorporated into the storage range; at the same time, the long-term unused storage space below the normal production water level within the reservoir is also fully utilized. As a result, the overall reservoir capacity utilization rate is significantly improved, and the effective storage capacity is substantially increased without raising the dam.

[0055] In some implementation examples, S3 specifically refers to the spillway being an open spillway, constructed of masonry blocks or concrete, and located on one side of the dam head in the reservoir area.

[0056] In some implementation examples, the cross-sectional dimensions and discharge capacity of the spillway are determined by hydrological calculations based on the flood control standards corresponding to the tailings dam's grade.

[0057] In some implementation examples, the elevation of the spillway bottom slab is set according to the flood season limit water level determined by flood control calculations, diversion facilities are installed at the inlet, and downstream energy dissipation facilities are connected at the outlet.

[0058] It should be noted that the independent spillway provides the tailings dam with a flood control and drainage channel independent of the tailings discharge system. During the flood season, floodwaters from the reservoir area are discharged independently through the spillway, unaffected by tailings storage operations, ensuring sufficient flood control capacity and smooth flood discharge. Compared with the traditional method of relying on drainage well-drainage tunnel systems for flood discharge, the independent spillway avoids the risk of the flood inlet being buried by tailings, significantly improving the tailings dam's ability to cope with excessive flooding.

[0059] Furthermore, in some implementation examples, S4 specifically retains the flood discharge and water intake functions of the existing drainage well structure, while adding backwater collection and transportation facilities.

[0060] In some implementation examples, during the non-flood season, the drainage well-flood tunnel system operates as a return water facility, systematically collecting clarified water from the reservoir and transporting it through the tunnel to the ore dressing plant's return water pool for recycling in ore dressing production. During the flood season, the system switches to a flood control and drainage channel, working in conjunction with an independent spillway to jointly undertake flood control and drainage tasks in the reservoir area. This modification achieves "dual-purpose tunnel"—allowing the existing drainage system to reuse its function over time without significantly increasing engineering investment. During the non-flood season, it serves the recycling of production water, reducing the ore dressing plant's clean water consumption; during the flood season, it serves flood control safety, ensuring the tailings dam's safety during the flood season.

[0061] Specific embodiments are listed below. It should be noted that the embodiments described below are exemplary and are only used to explain this application, and should not be construed as limiting this application. Where specific technologies or conditions are not specified in the embodiments, they shall be performed in accordance with the technologies or conditions described in the literature in this field or in accordance with the product manual.

[0062] This embodiment provides a detailed explanation of a modification method for extending the service life of tailings ponds.

[0063] like Figure 1-8 As shown, this embodiment modifies an already constructed and operational tailings dam and solves the following technical problems: First, regarding the issues of dam stability assurance and pre-flood protection, without significantly increasing the dam height, or even without increasing the dam height at all, a large platform 1 with sufficient width, anti-sliding capacity, and comprehensive protection functions is constructed by optimizing the dam-front embankment construction process and dam building methods. The large platform 1 includes a drainage ditch 2 and a return water pipe 3 (grout discharge pipe). The structural diagram of the large platform and its ancillary facilities is shown below. Figure 2-4 As shown, the longitudinal section of the tailings dam after the construction of the new large platform 1 is as follows. Figure 7As shown, the slope in front of the large platform dam faces the reservoir tail, with a slope of 5‰~10‰, and forms a shape like... Figure 7 The riprap slope shown at point 17 is specifically a 30cm dry-laid riprap slope protection; the large platform in front of the dam can play a synergistic role in the following two aspects: (I) Lowering the phreatic line of the dam body and improving its internal stability: The large platform 1 is constructed by layering and compacting a mixture of tailings sand and soil in front of the dam. Its compaction density is high, and its permeability coefficient is much lower than that of the original loose deposits in the dam body. Simultaneously, an impermeable membrane is laid at the contact surface between the platform and the dam body, or at specific layers within the platform, forming an effective seepage barrier. Through this construction, on the one hand, atmospheric precipitation can be effectively prevented from seeping down the dam surface, reducing the continuous infiltration of external water sources into the aquifer of the dam body; on the other hand, and more importantly, the platform significantly extends the seepage path (i.e., seepage diameter) of the tailings dam's phreatic line, forcing the seepage inside the dam body to bypass the large platform and be discharged in an orderly manner, thereby effectively reducing the pore water pressure inside the dam body and controlling the phreatic line depth within safe limits. The effective reduction of the phreatic line directly weakens the seepage pressure and hydrostatic buoyancy inside the dam body, significantly improving the dam's anti-sliding stability safety factor and eliminating the risk of seepage instability caused by an excessively high phreatic line.

[0064] (II) To resist the rise of waves during torrential rain and floods and protect the dam from erosion, under torrential rain and flood conditions, the water level in the reservoir rises rapidly. The rise of waves caused by wind and waves, combined with the increase in water height due to wind backflow, will cause the water in the reservoir to directly face the upstream slope of the tailings dam, resulting in continuous wave impact and cyclic erosion. Without effective protection, the high-frequency wave impact will erode the protective layer of the dam slope and the dam filling material, causing slope damage or even gradual dam failure. The large platform 1 set up in front of the dam in this invention spatially constitutes the connection between the dam body and the water in the reservoir. The natural buffer zone between the two sides, with its wide-topped platform structure, can effectively dissipate energy and impede wave rise, causing wave energy to be significantly attenuated in the platform section, avoiding the direct action of rainstorms, floods and their wave loads on the main dam body. The top surface of the platform can be combined with drainage cross slope and intercepting ditch design to orderly guide the water accumulated on the platform surface to the outside of the reservoir. The large platform 1 plays an effective role in isolation and protection in physical space, avoiding possible slope damage or even dam failure accidents that may occur during the continuous erosion of the tailings dam by rainstorms and floods, and significantly improving the flood control safety redundancy under extreme working conditions.

[0065] The large platform 1 in front of the dam, through the dual mechanisms of "internal seepage control" and "external flood protection," not only enhances the dam's bearing capacity in terms of internal mechanical stability but also improves its ability to withstand extreme hydrodynamic conditions in terms of external environmental protection. The establishment of this safety premise creates a solid technical foundation for the subsequent scientific regulation of reservoir water levels, rational utilization of the beach area, and safe implementation of mining operations in the reservoir perimeter and tail area. This allows the dam itself to accommodate higher operating water levels and withstand greater loads without relying on the traditional approach of significantly increasing the dam height, thus laying a solid safety foundation for the full release of the effective reservoir capacity of the entire reservoir area.

[0066] Secondly, regarding the issue of fully utilizing the reservoir's storage capacity; how to incorporate the long-unused areas around and at the tailings of the reservoir under traditional tailings discharge methods into the effective storage range, and improve the overall reservoir capacity utilization rate by systematically changing the ore discharge process and discharge method, thereby obtaining additional effective storage capacity without increasing the dam height, is another important technical problem that this invention aims to solve.

[0067] Specifically, traditional tailings discharge methods typically involve centralized tailings discharge in front of the dam. Tailings slurry is discharged into the reservoir from the top of the dam or a specific point in front of the dam. Under this method, coarse particles in the tailings slurry are rapidly deposited near the discharge point to form a beach, while fine particles extend into the reservoir with the water flow. Because the discharge point is fixed or only moves within a local area in front of the dam, tailings are concentrated in the area in front of the dam. Meanwhile, large areas around the reservoir (i.e., the perimeter of the reservoir) and at the tail end of the reservoir (i.e., the tail end of the reservoir) are in a state where tailings slurry cannot reach them for a long time, forming so-called "dead reservoir capacity" or "ineffective reservoir capacity." Although the reservoir capacity space in these areas is included in the total capacity statistics, it is actually idle because tailings cannot be effectively stored, resulting in a serious waste of reservoir capacity resources.

[0068] Even more unfavorable is that the concentrated ore discharge in front of the dam leads to uneven sedimentation slopes on the beach, causing the beach surface in front of the dam to rise rapidly, while the area around the reservoir and at the tail end remains in a state of low water level or dryness for a long time. This not only exacerbates the unfavorable situation of concentrated loads in front of the dam and raising the dam's phreatic line, but also results in generally low reservoir capacity utilization efficiency throughout the entire reservoir area. According to industry statistics, the actual capacity utilization rate of some tailings ponds is only 60% to 75% of the designed capacity, and a large amount of effective capacity is wasted.

[0069] To address the aforementioned problems, this invention changes the single-path dependence of traditional centralized tailings discharge in front of the dam, adopting a zoned tailings discharge process around the reservoir and at the tail end. Specifically, the main tailings discharge pipe 7 and branch tailings discharge pipe 8 are laid at suitable locations around the reservoir area. The tailings slurry is evenly discharged into the reservoir perimeter and tail end areas through dispersed discharge points. Simultaneously, by controlling the tailings slurry concentration, alternating the discharge points, and rationally arranging the discharge sequence, the tailings slurry achieves full-area coverage deposition within the reservoir area. Through this method, the dry beach areas around the reservoir and the dead storage areas at the tail end, which are difficult to reach in traditional tailings discharge, are effectively activated and included in the daily storage range. The long-term idle storage space below the normal production water level is also fully utilized. As a result, the overall reservoir capacity utilization rate is significantly improved, and additional effective storage capacity is obtained without raising the dam, directly extending the service life of the tailings dam.

[0070] Furthermore, the uniform sedimentation across the entire tailings dam surface resulting from ore discharge around the reservoir and at its tail end helps improve water level distribution within the reservoir and reduces sediment concentration in front of the dam. This fundamentally prevents the rise of the phreatic line caused by excessive loading in front of the dam, further solidifying the safety prerequisite established by the large platform in front of the dam. This invention, through a systematic change in the ore discharge process, transforms traditionally "dead reservoir capacity" into "effective reservoir capacity," achieving a considerable increase in reservoir capacity with minimal engineering investment, and providing a second technical path for extending the service life of tailings dams.

[0071] Third, regarding the issue of flood control and safety assurance for tailings ponds; how to independently set up a spillway on one side of the dam in the reservoir area, so that the tailings pond has a completely independent and dedicated flood control and drainage channel that is not disturbed by tailings storage operations, and ensure sufficient flood control capacity and smooth flood discharge during the flood season, thereby effectively eliminating potential flood control safety hazards caused by the expansion of reservoir capacity, is another important technical problem that this invention aims to solve.

[0072] Specifically, existing tailings dam flood control systems generally rely on drainage well-flood tunnel systems as the main flood discharge channels. Although this system has a certain flood discharge capacity under normal operating conditions, its inherent structure determines that it has the following insurmountable limitations: Firstly, drainage well 4 is located in the reservoir area as an inlet. As the elevation of the tailings pile rises, drainage well 4 is gradually submerged or buried by the tailings, and its discharge capacity decreases accordingly. In the later stages, it is often necessary to continuously raise the wellhead or add new wells to maintain the flood discharge capacity, which increases the construction difficulty and operational risks.

[0073] Secondly, and more importantly, during the storage operations in the reservoir area, the drainage well-flood discharge tunnel system often intersects and interferes with each other's flood discharge channels and tailings discharge paths. The ore discharge operation may block the area around drainage well 4, reducing water collection efficiency. The dynamic relationship between the inlet elevation of flood discharge tunnel 5 and the elevation of the tailings sedimentation beach is complex. If the beach height is not properly controlled, the flood discharge inlet may be blocked, resulting in ineffective flood discharge during the flood season and seriously threatening the safety of the tailings dam during the flood season.

[0074] Third, in some tailings ponds, the drainage well-flood tunnel system also needs to take into account the function of returning water. During the non-flood season, it is used to collect clarified water in the pond for mineral processing and reuse. This requires maintaining a certain water level in the pond during the non-flood season. However, when the flood season comes, if the water level cannot be reduced to the flood season limit water level in time, it will directly encroach on the flood control capacity and reduce the tailings pond's ability to resist design floods or even floods exceeding the standard.

[0075] Building upon the inherent defects of the aforementioned flood control system, this invention further achieves a significant increase in effective reservoir capacity through ore discharge around the reservoir perimeter and tail. With the expanded capacity, the total amount of floodwater requiring regulation during the flood season increases accordingly, leading to a greater demand for flood control storage capacity. If the existing flood control path, primarily based on drainage wells and flood discharge tunnels, continues to be used, the inherent contradiction between reservoir capacity expansion and flood control safety will be further intensified—the two will form a zero-sum game in their competition for reservoir space. Specifically, raising the operating water level to obtain more effective storage capacity inevitably compresses the flood control storage capacity; conversely, lowering the operating water level to reserve sufficient flood control storage capacity prevents the newly added effective storage capacity from being fully utilized.

[0076] To address the aforementioned contradictions, this invention includes a separate spillway on one side of the dam in the reservoir area, serving as a dedicated flood control and drainage channel for the tailings dam. Specifically, as follows... Figure 8 The diagram shows a cross-sectional view of the spillway. The bottom of the spillway is a cast-in-place C25 concrete base layer, and the spillway itself is a cast-in-place C30 reinforced concrete structure with a rubber waterstop 19 installed inside. The upper part of the spillway is a cover plate 18. This spillway adopts an open overflow structure and is located at a suitable topographical position on one side of the reservoir dam head. The height of its inlet bottom plate is set according to the flood season limit water level determined by flood control calculations. The design of the spillway has the following technical advantages: (i) The flood discharge is completely independent and not affected by the tailings storage. The spillway is located on one side of the dam head and is spatially separated from the tailings storage area of ​​the tailings dam. Its inlet does not change with the change of tailings accumulation elevation, and the water intake conditions are stable. No matter how the tailings discharge operation is carried out, the spillway always maintains unobstructed flood discharge capacity, which fundamentally avoids the risk of the drainage well being blocked by tailings.

[0077] (ii) Sufficient flood control capacity is guaranteed, releasing the potential for capacity expansion; the existence of independent spillways ensures that the water level in the reservoir can be strictly controlled below the flood control limit during the flood season, and the flood control capacity is reliably guaranteed; under the premise that flood control safety is fully guaranteed, the newly added effective capacity around the reservoir and at the tail of the reservoir can be safely used for normal storage during the non-flood season, so that "capacity expansion" and "flood control safety" are unified from opposition, and both can be taken into account.

[0078] (iii) The spillway has sufficient discharge capacity to effectively cope with floods exceeding the standard. The cross-sectional dimensions of the spillway are determined through rigorous hydrological calculations based on the design flood control standard and the verification flood control standard corresponding to the tailings dam's grade. Its discharge capacity can meet the safe discharge requirements under the design flood condition, and it still has sufficient safety redundancy under the verification flood condition. Even in the event of a flood exceeding the standard, the spillway can still undertake the flood discharge task within a certain range, buying valuable time for downstream emergency response.

[0079] By setting up the aforementioned independent spillway, this invention constructs a dedicated, stable, and ample flood control and drainage channel for the expanded tailings dam, enabling the tailings dam to extend its service life while simultaneously improving rather than weakening its flood control safety capabilities, ultimately achieving the dual goals of "expansion" and "safety".

[0080] Regarding the functional reuse of drainage and flood discharge facilities and the comprehensive utilization of water resources, this invention proposes to functionally modify the existing drainage well-flood discharge tunnel system so that it can serve as a water return facility for mineral processing water circulation during the non-flood season, and switch to a flood control and drainage channel during the flood season, achieving "one tunnel for two uses and functional reuse". This is another important technical problem that this invention aims to solve, saving on engineering investment while improving the comprehensive utilization level of water resources.

[0081] Specifically, most existing tailings ponds are equipped with drainage well-flood discharge tunnel systems. These systems are designed to discharge floodwaters into the ponds during the flood season to ensure the safety of the tailings ponds during the flood season. However, these systems are idle or operate inefficiently for most of the non-flood season. Drainage well 4 is only used as a water level control facility for a small amount of drainage, while flood discharge tunnel 5 is basically unused. The low utilization rate of the facilities results in a hidden waste of project investment.

[0082] Meanwhile, mineral processing in mines consumes a large amount of industrial water. Tailings pond clarified water, as an important source of return water for mineral processing, has a recycling rate that directly affects the water resource costs and dependence on external water intake in mining operations. During non-flood seasons, the inflow to tailings ponds is low, evaporation and leakage losses are relatively small, and the volume of clarified water within the ponds is relatively stable, providing good conditions for return water. However, in traditional designs, drainage well-flood tunnel systems lack dedicated return water collection and transportation functions. If used directly for return water, the following challenges arise: Firstly, the four inlets of the drainage wells are typically located at different elevations, and conventional... In the drainage state, water can only be drawn from the uppermost inlet, resulting in a single water layer. It is impossible to select the optimal water intake layer based on the water quality stratification within the reservoir, which may lead to the return of turbid water with high suspended solids content, affecting mineral processing production indicators. On the other hand, if water is drawn from the drainage well-flood tunnel system for a long period during the non-flood season, a certain operating water level in the reservoir needs to be maintained. However, this system also undertakes flood discharge tasks during the flood season, and the water level needs to be quickly lowered to the flood season limit water level before the flood season. There is a lack of effective control measures for the water level switching between "return water intake" and "flood discharge and reservoir emptying", which can easily lead to untimely reservoir emptying before the flood season and encroachment on the flood control capacity.

[0083] More importantly, there is a clear temporal division of labor and functional complementarity between the aforementioned drainage well-flood tunnel system and the independently set spillway in the third measure of the present invention. The spillway, as a dedicated flood discharge channel, mainly undertakes the task of flood discharge during the flood season. After the renovation, the drainage well-flood tunnel system focuses on the function of water return during the non-flood season, while retaining the auxiliary flood discharge capacity during the flood season. The two operate in staggered time and are independent of each other in space, together forming an integrated facility system for tailings dam water resource management and flood control.

[0084] To address the aforementioned problems, this invention provides a functional upgrade to the existing drainage well-flood tunnel system, with the following measures: The water intake layer can be adjusted and modified. Layered water intake devices or openable and closable water intake gates can be set at the water inlets at different elevations of the drainage well. This allows operators to select the layer with the best water quality for water intake and reuse based on the water quality monitoring results of the water body in the reservoir. This ensures that the quality of the reused water meets the requirements of mineral processing production and avoids the impact of fluctuations in the quality of the reused water on mineral processing indicators.

[0085] The system employs a system for switching between return water and flood discharge modes. A dedicated return water pipeline 6 is laid between the drainage well and the return water pool of the ore dressing plant, and a mode-switching valve group is installed to form an independent return water loop: "drainage well → return water pipeline → return water pool". During non-flood seasons, the return water loop is activated, and the system operates in return water mode. Clarified water from the reservoir is continuously or intermittently transported to the return water pool of the ore dressing plant for production recycling, significantly reducing the amount of fresh water taken out. Before the flood season, the system lowers the water level in the reservoir to the flood season limit level within a predetermined time through the control system, completing the switch from "return water mode" to "flood discharge mode" to ensure that the flood control capacity is fully released. When floods arrive during the flood season, the system operates in flood discharge mode, and the entire cross-section of the drainage well-flood discharge tunnel is unobstructed for flood discharge. After the flood season ends, the system switches back to return water mode in a timely manner according to the water level and inflow. Through the above dynamic switching control, the contradiction between return water intake and pre-flood reservoir emptying is effectively coordinated.

[0086] The modified drainage well-drainage tunnel system retains its original flood discharge function while retaining its auxiliary flood discharge capacity. During the flood season, it can work in conjunction with the independently set spillway to form a dual flood control and drainage pattern of "main spillway discharge and auxiliary drainage well-tunnel discharge", which further enhances the overall flood control safety redundancy of the tailings dam.

[0087] The renovated drainage well, such as Figure 5-6 As shown, the structure includes a well base 11, which connects to the tunnel 5. The upper part of the well base 11 is an arch cover plate 14, the arch cover plate 14 is a ring beam 13, and the upper part of the ring beam 13 is a column 12. Both the cover plate 14 and the column 12 are lined with C30 concrete. A ladder 16 is also installed at the opening of the drainage well 4. The original arch plate 15 has been completely removed.

[0088] This invention enables the long-term idle or inefficiently operating drainage well-flood tunnel system to achieve functional reuse over time, without constructing new dedicated water return facilities or increasing substantial engineering investment. During the non-flood season, it serves as a water recycling system for mineral processing, improving the utilization rate of tailings pond water return and reducing mine water consumption and production costs. During the flood season, it serves flood control, ensuring the safety of the reservoir area during the flood season. The two functions operate in staggered timeframes, without interference, and with reliable switching, truly achieving "one tunnel, two uses." This effectively saves on the engineering investment of constructing new water return facilities while simultaneously improving the cascade and comprehensive utilization level of water resources, resulting in significant economic and social benefits.

[0089] Through the overall implementation of the above technical solutions, this invention achieves synergistic effects in four aspects: dam safety, reservoir capacity release, flood control, and water resource utilization. With enhanced dam stability, dead reservoir capacity in the perimeter and tail area is activated, significantly increasing effective capacity and extending service life to match the mine's exploitable lifespan. An independent spillway system ensures flood control safety during the flood season, eliminating potential flood risks caused by reservoir capacity expansion. The modification of the return water facilities enables the drainage system to reuse its functions over time, balancing production water needs with flood control requirements. Thus, this invention systematically resolves the prominent contradiction between insufficient tailings dam capacity and safe production without significantly increasing dam height or violating policy and standard restrictions, providing reliable technical support for the continuous and stable mining operations of mining enterprises.

[0090] In the above embodiments, the following economic and resource benefits were achieved by functionally modifying the existing drainage well-flood tunnel system: 1. Save on investment in new water return facilities: This invention, without building a new dedicated water return facility, transforms the existing drainage well-flood tunnel system to perform water return functions during non-flood seasons, thus avoiding the civil engineering, equipment procurement and installation costs required to build a new independent water return system, and significantly reducing project investment.

[0091] 2. The utilization rate of recycled water has been significantly improved, and the consumption of fresh water has been greatly reduced. The upgraded drainage well-flood tunnel system, through the stratified water intake device, can select the layer with the best water quality for water intake and reuse based on the stratified water quality monitoring results in the reservoir, ensuring that the quality of recycled water meets the requirements of mineral processing production. During the non-flood season, it operates continuously or intermittently in recycled water mode, transporting the clarified water in the reservoir to the recycled water pool of the mineral processing plant for production recycling, which greatly improves the utilization rate of recycled water in the tailings dam and reduces the amount of fresh water taken from outside the mine and the cost of clean water consumption.

[0092] 3. Realizing full-time functional reuse of the drainage system, this invention enables the drainage well-flood tunnel system to achieve functional reuse in the time dimension—serving the mineral processing water cycle as a return water facility during the non-flood season, and serving as a flood control and drainage channel to ensure the safety of the reservoir area during the flood season; the two functions operate in staggered time, do not interfere with each other, and switch reliably, transforming the system resources that were originally idle or inefficiently operated for a long time into continuous production benefits and safety guarantees, truly realizing "one tunnel for two uses", with significant economic and social benefits.

[0093] In summary, this invention, through the systematic integration of four technical means—construction of a large platform in front of the dam, zoned ore discharge around the reservoir perimeter and tail, establishment of an independent spillway, and functional modification of the drainage well-flood tunnel system—achieves the following comprehensive synergistic effect, demonstrating an overall technical effect of 1+1>2: A complete technical loop is established, encompassing four measures: safety first, capacity release, flood control, and functional reuse. These measures are organically linked according to the sequence of "safety first, capacity expansion second, security third, and efficiency enhancement third." The large platform in front of the dam creates a safe environment for ore release around the reservoir and at its tail end; the independent spillway after capacity expansion resolves the flood control issues arising from the expansion; and the drainage system upgrade enables functional reuse and forms a dual flood control pattern with the spillway. These four measures are interconnected and mutually supportive, constituting a complete technical loop.

[0094] This invention extends the service life of tailings dams without relying on increasing their height. The entire process does not involve significantly increasing the height of the dam, thus completely avoiding a series of rigid constraints such as insufficient bearing capacity of the dam foundation, decreased dam stability, the "overhead dam" policy ban, and the rigid restrictions on the height of the dam in current regulations. This provides a practical and feasible technical solution for a large number of in-service tailings dams that cannot be heightened or expanded.

[0095] This invention achieves a balance between safety and efficiency. While extending the service life of tailings dams, it simultaneously enhances the safety and stability of the dam body and the flood control capability. It also takes into account the comprehensive utilization of water resources and savings in engineering investment. Its overall benefits are significantly better than a single dam heightening and expansion scheme, and it has broad prospects for promotion and application.

[0096] It should be noted that the above-described embodiments are merely examples. Any embodiments that have the same structure and achieve the same effect as the technical concept within the scope of this application are included in the scope of this application. Furthermore, without departing from the spirit of this application, various modifications that can be conceived by those skilled in the art to the embodiments, and other ways of constructing by combining some of the constituent elements of the embodiments, are also included in the scope of this application.

Claims

1. A method for extending the service life of tailings dams, characterized in that, Includes the following steps: S1: Construction of a large platform in front of the dam: Construct a large platform with sufficient width and anti-sliding capacity in the area in front of the tailings dam. S2: Separate ore discharge around the reservoir perimeter and tail of the reservoir. Based on the premise of safety of the large platform in front of the dam, the traditional centralized ore discharge method in front of the dam is changed to the separate ore discharge process around the reservoir perimeter and tail of the reservoir. S3: Independent spillway setting: An independent spillway is set up on one side of the dam head in the reservoir area as a dedicated flood control and water discharge channel for the tailings dam; S4. Functional renovation of drainage wells and flood discharge tunnels: The existing drainage well and flood discharge tunnel system in the middle and tail of the reservoir area will be functionally renovated to enable it to have both water return and flood control functions.

2. The renovation method for extending the service life of a tailings dam according to claim 1, characterized in that, The large platform in front of the dam is constructed by layering and compacting a mixture of tailings sand and soil. The platform construction material is compacted in layers, and the compaction coefficient is not lower than the design value. A seepage-proof membrane is laid at the contact surface between the platform and the dam body or at a specific layer inside the platform to form a seepage barrier.

3. The renovation method for extending the service life of a tailings dam according to claim 2, characterized in that, The width of the platform top surface shall not be less than the design calculation value, and the slope ratio of the platform shall not be steeper than 1:2.

5.

4. A method for extending the service life of a tailings dam according to claim 2, characterized in that, S2 specifically involves setting up ore discharge points around the tailings pond area and at the tail end of the pond area. Through a combination of pipeline transportation and decentralized ore discharge, the tailings slurry is discharged in an orderly manner to the pond periphery and tail end areas that are difficult to utilize in traditional ore discharge methods.

5. A method for extending the service life of a tailings dam according to claim 4, characterized in that, The ore discharge method adopts one or more combinations of the following: horizontal ore discharge method, underwater ore discharge method on both sides of the reservoir, or ore discharge method in the tributary.

6. A method for extending the service life of a tailings dam according to claim 2, characterized in that, S3 specifically refers to the spillway being an open spillway, constructed using masonry blocks or concrete, and located on one side of the dam head in the reservoir area.

7. A method for extending the service life of a tailings dam according to claim 6, characterized in that, The cross-sectional dimensions and discharge capacity of the spillway are determined by hydrological calculations based on the flood control standards corresponding to the tailings dam's grade.

8. A method for extending the service life of a tailings dam according to claim 7, characterized in that, The elevation of the spillway bottom slab is set according to the flood season limit water level determined by flood control calculations. The inlet is equipped with diversion facilities, and the outlet is connected to the downstream energy dissipation facilities.

9. A method for extending the service life of a tailings dam according to claim 2, characterized in that, Specifically, S4 involves retaining the flood discharge and water intake functions of the existing drainage well structure while adding backwater collection and transportation facilities.

10. A method for extending the service life of a tailings dam according to claim 9, characterized in that, During the non-flood season, the drainage well-flood tunnel system operates as a return water facility, collecting the clarified water in the reservoir in an orderly manner and transporting it through the tunnel to the return water pool of the mineral processing plant for recycling in mineral processing production; during the flood season, the system switches to a flood control and drainage channel, working in conjunction with the independent spillway to jointly undertake the flood control and drainage tasks of the reservoir area.