A smart green mine monitoring and control system
The intelligent green mine monitoring system monitors equipment status and material flow in real time, predicts potential bottlenecks, and performs collaborative scheduling, solving the problem of poor coordination between equipment in traditional mine monitoring systems and achieving stable and continuous operation of mine production.
Patent Information
- Application Number
- CN202611344656.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-01
- Publication Date
- 2026-11-17
AI Technical Summary
In traditional mine monitoring systems, data and control relationships between various production equipment are relatively scattered, resulting in poor coordination between equipment and problems such as upstream equipment waiting, downstream equipment being overloaded, or equipment operating without load.
The intelligent green mine monitoring and control system includes a central control platform, equipment status acquisition module, production capacity calculation module, production bottleneck identification module, equipment collaborative scheduling module, distributed equipment control module, anomaly diagnosis module, energy monitoring module, and environmental monitoring module. By establishing a dynamic production chain mapping relationship, it monitors equipment status and material flow in real time, predicts potential bottlenecks, and performs collaborative scheduling and equipment collaborative control.
It effectively reduces the risk of material backlog and sudden overload shutdowns in the mining production process, enables accurate identification of production equipment and rational scheduling of task resources, and ensures the continuous and stable operation of the entire process chain.
Smart Images

Figure CN123113750A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of mine monitoring technology, and in particular to a smart and green mine monitoring and control system. Background Technology
[0002] As the scale of mine production continues to expand, the mine production process has gradually evolved from a single mining operation into a complex production system that includes multiple production links such as mining, loading, transportation, conveying, crushing, screening, drainage, ventilation, dust removal, and energy supply.
[0003] In traditional mining production methods, various types of production equipment are typically equipped with separate control systems for different production areas. Mining equipment is managed by the mining area control system, transportation equipment by the transportation dispatch system, crushing equipment by the crushing control system, while ventilation, drainage, dust removal, and energy equipment use relatively independent control methods.
[0004] While the above control methods can achieve automatic control of a single device or a single production unit, the data and control relationships between different production devices are relatively dispersed.
[0005] For example, in the process of ore transportation, the production output of mining equipment directly affects the workload of transportation equipment, the operating status of transportation equipment affects the feed rate of crushing equipment, and the processing capacity of crushing equipment further affects the working status of screening equipment. When the production capacity of one piece of equipment changes, if other equipment cannot adjust synchronously, problems such as upstream equipment waiting, downstream equipment being overloaded, or equipment running idle may easily occur.
[0006] Existing mine monitoring systems mainly address the issues of equipment status data acquisition and anomaly alarms.
[0007] To address this, we designed a smart and green mine monitoring system. Summary of the Invention
[0008] The purpose of this invention is to solve related technical problems by proposing a smart and green mine monitoring system.
[0009] To achieve the above objectives, the present invention adopts the following technical solution:
[0010] A smart green mine monitoring and control system includes a central control platform, and an equipment status acquisition module, a production task management module, a production capacity calculation module, a production bottleneck identification module, an equipment collaborative scheduling module, a distributed equipment control module, an anomaly diagnosis module, an energy monitoring module, and an environmental monitoring module, which are respectively connected to the central control platform.
[0011] The equipment status acquisition module is used to acquire the equipment operating status parameters and material physical property parameters of the mining production equipment. The equipment operating status parameters include at least the equipment load status, operating temperature, vibration status and operating current, and the material physical property parameters include at least the material size and material moisture content.
[0012] The production capacity calculation module corrects the basic operating capacity based on the rated production capacity of the production equipment and the equipment operating status parameters. It then corrects the basic operating capacity based on the physical health status of the production equipment and corrects the operating capacity based on the physical characteristics of the materials. Finally, it corrects the operating capacity after the health status correction based on the physical characteristics of the materials to obtain the real-time effective production capacity of the production equipment under the current operating conditions and material conditions.
[0013] The production bottleneck identification module establishes a dynamic production chain topology based on the mining production process, including production equipment nodes, material flow nodes, intermediate storage nodes, and production task nodes. It records the material transfer time lag in the material transfer path between adjacent production equipment. Based on the real-time effective production capacity and the change status of storage capacity in the intermediate storage area, it performs feedforward analysis on the transfer status of material flow in the production chain to determine the current production bottleneck and predict the formation time of potential production bottlenecks.
[0014] The equipment collaborative scheduling module determines the advance sending time of collaborative control commands based on the formation time of potential production bottlenecks, the material transmission time delay of the corresponding material transmission path, and the control response time of related production equipment. It also generates collaborative control parameters with time advance for the production equipment upstream of the potential production bottleneck according to the material transmission direction.
[0015] The distributed device control module controls multiple production devices to coordinate and adjust their operating speed, feed rate, or production task volume according to the collaborative control parameters, so that the upstream material input capacity matches the processing capacity of the potential production bottleneck before it is formed.
[0016] The anomaly diagnosis module is used to detect the fault status and capacity limitation status of production equipment, and to trigger production topology reconfiguration when production equipment malfunctions or capacity is continuously limited.
[0017] The energy monitoring module and the environmental monitoring module acquire the energy consumption status of the production equipment and the environmental status of the production area, respectively, and use the energy consumption status and environmental status as constraints for production equipment scheduling and production topology adjustment.
[0018] The central control platform updates the material transfer time delay, real-time effective production capacity, and effective buffer capacity of the intermediate storage area based on the deviation between the actual equipment operation results of the current control cycle and the prediction results of the previous control cycle. The updated results are then used for production bottleneck prediction and equipment collaborative control in the next control cycle, forming an adaptive closed-loop control that continuously executes production capacity calculation, bottleneck prediction, advance control, operation feedback, and parameter updates.
[0019] Preferably, the central control platform includes an equipment resource management unit;
[0020] The equipment resource management unit establishes a mining equipment resource table, which records at least the equipment number, equipment type, production area, rated production capacity, real-time effective production capacity, equipment operating status, equipment load rate, current production task, and equipment maintenance status.
[0021] The central control platform classifies production equipment in normal operation and production equipment in reduced operation with remaining production capacity into the schedulable equipment set according to the equipment resource table, and determines the task execution equipment from the schedulable equipment set according to the production tasks generated by the production task management module.
[0022] When a production device malfunctions or its real-time effective production capacity falls below a preset capacity threshold, the equipment resource management unit will remove the corresponding production device from the set of schedulable devices or re-register it according to the limited production capacity.
[0023] Preferably, the distributed equipment control module includes multiple regional control nodes, which include mining area control nodes, transportation area control nodes, crushing area control nodes, and screening area control nodes.
[0024] The mining area control node connects the mining equipment and loading equipment; the transportation area control node connects the transportation equipment and conveying equipment; the crushing area control node connects the crushing equipment; and the screening area control node connects the screening equipment.
[0025] The central control platform sends production tasks, collaborative control parameters, and corresponding advance sending times to each regional control node. Each regional control node performs centralized control on the production equipment within its corresponding production area based on the received collaborative control parameters and feeds back the equipment execution results and real-time equipment status data to the central control platform.
[0026] Preferably, the production capacity calculation module determines the real-time effective production capacity of mining equipment, loading equipment, transportation equipment, conveying equipment, crushing equipment, and screening equipment in the order of basic capacity correction, equipment health status correction, and material characteristic correction.
[0027] The equipment status acquisition module obtains the real-time operating current of the production equipment through the current detection device, and performs basic capacity conversion of the rated production capacity of the equipment based on the correspondence between the real-time operating current and the rated current of the equipment.
[0028] The equipment status acquisition module obtains the operating temperature and vibration status of the production equipment through temperature detection and vibration detection devices. When the operating temperature or vibration status exceeds the corresponding normal range but does not meet the fault shutdown conditions, the production equipment is identified as a restricted operating state, and the basic operating capacity is reduced in a gradient.
[0029] The equipment status acquisition module obtains the material size and humidity through the material characteristic detection device. When the material size or humidity reaches the corresponding material processing limit, the operating capacity after the equipment health status correction is further corrected by the material characteristics to obtain the real-time effective production capacity of the production equipment.
[0030] Preferably, the central control platform includes a dynamic production chain mapping unit and a predictive analysis unit;
[0031] The dynamic production chain mapping unit establishes a dynamic mapping topology for the mine production chain. The dynamic mapping topology includes at least production equipment nodes, material flow nodes, intermediate storage nodes, and production task nodes, and establishes corresponding material transmission paths based on the material transmission relationships between each production equipment.
[0032] The predictive analysis unit determines the arrival time of the impact of changes in production equipment capacity propagation to the upstream feeding stage and the downstream processing stage based on the real-time effective production capacity changes of each production equipment and the material transmission time lag of the corresponding material transmission path, and forms the time-series propagation relationship of production capacity changes based on the arrival time of the impact.
[0033] When the capacity gap caused by the decline in the real-time effective production capacity of the production equipment will lead to insufficient downstream processing capacity during the predicted period corresponding to the arrival time of the impact, the production link corresponding to the production equipment will be marked as a potentially restricted link.
[0034] Preferably, an intermediate storage area is provided between production stages, and the intermediate storage area includes a storage silo, a material level detection device, and a material flow detection device;
[0035] The material level detection device is used to obtain the real-time material level, remaining storage capacity and material level change status of the storage silo; the material flow detection device is used to obtain the feeding rate of the material entering the storage silo and the discharge rate of the material exiting the storage silo.
[0036] The predictive analysis unit determines the material level change trend in the storage bin based on the feed rate and discharge rate, and determines the predicted material increment by combining the real-time effective production capacity of upstream production equipment and the real-time processing capacity of downstream production equipment.
[0037] When the predicted increase in material can be absorbed by the remaining storage capacity of the storage silo within the preset prediction time, the current production parameters of the upstream production equipment are maintained.
[0038] When the predicted increase in material exceeds the remaining storage capacity of the storage silo, or when the predicted material level reaches the preset high material level warning state, the production bottleneck identification module will identify the corresponding downstream production equipment as a potential production bottleneck, and determine the formation time of the potential production bottleneck based on the material level change trend of the storage silo and the material transmission time lag.
[0039] Preferably, the equipment collaborative scheduling module determines the control command lead time of each upstream production equipment based on the formation time of potential production bottlenecks, the material transmission time delay of the material transmission path, and the control response time of the corresponding production equipment.
[0040] The equipment coordination scheduling module determines the adjustment equipment step by step from the potential production bottleneck upstream according to the material flow direction, and adjusts the operating speed, feeding amount or task of at least one of the conveying equipment, transport equipment, loading equipment and mining equipment in sequence through the distributed equipment control module.
[0041] When the real-time load status of the potential production bottleneck returns to the preset normal range and the material level in the intermediate storage area returns to the preset adjustment range, the equipment collaborative scheduling module gradually restores the operating parameters of the relevant production equipment according to the preset restoration order, so as to avoid the sudden increase in material flow caused by the simultaneous restoration of multiple upstream production equipment.
[0042] Preferably, the central control platform includes a production topology reconfiguration unit;
[0043] When the anomaly diagnosis module detects that any production equipment has malfunctioned or that the real-time effective production capacity is continuously lower than the preset capacity threshold, the central control platform will mark the corresponding production equipment as unschedulable equipment or derated scheduling equipment.
[0044] The production topology reconfiguration unit determines candidate alternative production paths based on the upstream production equipment, downstream production equipment, intermediate storage area, standby production equipment, and material transfer path corresponding to unschedulable or derated scheduled equipment.
[0045] The production topology reconfiguration unit determines the target production path based on the real-time effective production capacity of the production equipment corresponding to the candidate alternative production path, the current task volume, and the remaining buffer capacity of the intermediate storage area. It then adjusts the operating status of the transportation equipment, conveying equipment, and standby production equipment through the distributed equipment control module, so that the faulty equipment can re-establish material transfer connections with its upstream and downstream production links in the production process.
[0046] Preferably, the energy monitoring module acquires the operating power and energy consumption per unit output of the production equipment, and the equipment status acquisition module also acquires the real-time load status of the production equipment through the load detection device.
[0047] When there are multiple production devices capable of performing the same production task, the central control platform determines the task allocation order based on the real-time effective production capacity, real-time load status and unit output energy consumption of each production device, and prioritizes allocating production tasks to production devices with lower unit output energy consumption and remaining production capacity.
[0048] The environmental monitoring module includes dust sensors and hazardous gas sensors installed in the mining, transportation, crushing, and screening areas. When the environmental parameters of any production area reach the preset environmental threshold, the central control platform increases the operating capacity of the corresponding environmental treatment equipment and reduces the operating load of the corresponding production equipment in the abnormal environmental area or transfers some production tasks to other production areas where the environmental parameters are within the normal range.
[0049] Preferably, the central control platform includes a parameter update unit;
[0050] The central control platform reacquires equipment status data, material flow data, storage bin level data, energy consumption data, and environmental status data according to the preset control cycle, and compares the actual production bottleneck formation time, actual material flow, and actual storage bin level change status of the current control cycle with the prediction results corresponding to the previous control cycle.
[0051] When the deviation between the actual time of production bottleneck formation and the predicted time of production bottleneck formation exceeds the preset deviation range, the parameter update unit corrects the material transmission time delay in the dynamic production chain mapping unit based on the actual material flow change results.
[0052] When the deviation between the actual output capacity of the production equipment and the predicted real-time effective production capacity exceeds the preset capacity deviation range, the parameter update unit updates the real-time effective production capacity parameters of the corresponding production equipment according to the equipment status change results.
[0053] When the deviation between the actual material level change in the storage bin and the predicted material level change exceeds the preset buffer deviation range, the parameter update unit updates the effective buffer capacity parameter of the storage bin and uses the updated material transfer time delay, real-time effective production capacity and effective buffer capacity for the production bottleneck prediction and equipment collaborative scheduling in the next control cycle, thereby forming a cross-control cycle prediction result correction and collaborative control parameter update.
[0054] The beneficial effects of this invention are as follows:
[0055] 1. This invention establishes a mapping relationship between production equipment, material flow, task nodes, and intermediate storage nodes through a dynamic production chain mapping unit, and uses the material transmission time delay of the material transmission path and the control response time of the equipment as the basis for collaborative control. Before the downstream equipment or silo actually enters an overload or high material level state, the system can comprehensively consider the impact arrival time and equipment control response sequence, and issue collaborative adjustment parameters to the upstream equipment in advance. This breaks the limitations of traditional independent control of a single piece of equipment and post-event response, and effectively reduces the risk of material accumulation and sudden overload shutdown in the mining production process.
[0056] 2. This system not only calculates the basic operating capacity of the equipment based on current and load, but also performs gradient correction by combining sub-health parameters such as vibration intensity and heating rate, and introduces physical characteristics such as average material size and humidity to further calculate the equipment's processing capacity, thereby obtaining a real-time effective production capacity that closely reflects the actual engineering situation. This overcomes the problem of the disconnect between traditional quota production capacity calculation and actual operating conditions, and provides a reliable data foundation for the accurate identification of production bottlenecks and the rational scheduling of task resources.
[0057] 3. This system uses the intermediate storage area as a dynamic buffer node, and combines the material level change trend with the remaining capacity to determine whether it is necessary to immediately trigger the equipment flow restriction or increase the feeding capacity, effectively absorbing short-term capacity fluctuations. When flow restriction or restoration is required, the equipment collaborative scheduling module adopts a step-by-step reverse control timing from downstream to upstream, avoiding sudden changes in material flow and equipment current surges caused by multiple upstream equipment slowing down or resuming operation at the same time, thus ensuring the continuous and stable operation of the entire process chain. Attached Figure Description
[0058] Figure 1 This is the overall logical flowchart of the system;
[0059] Figure 2 This is a block diagram of the internal units of the central control platform.
[0060] Figure 3 Block diagram of distributed control, regional nodes, and field devices;
[0061] Figure 4 This is a block diagram of the sensing, detection, energy, and environment subsystems.
[0062] In the diagram: 1. Central Control Platform; 2. Equipment Status Acquisition Module; 3. Production Task Management Module; 4. Production Capacity Calculation Module; 5. Production Bottleneck Identification Module; 6. Equipment Cooperative Scheduling Module; 7. Distributed Equipment Control Module; 8. Anomaly Diagnosis Module; 9. Energy Monitoring Module; 10. Environmental Monitoring Module; 11. Equipment Resource Management Unit; 12. Dynamic Production Chain Mapping Unit; 13. Predictive Analysis Unit; 14. Production Topology Reconstruction Unit; 15. Parameter Update Unit; 16. Regional Control Node; 17. Mining Area Control Node; 18. Transportation Area Control Node; 19. Crushing Area 20. Control Node; 21. Screening Area Control Node; 22. Mining Equipment; 23. Loading Equipment; 24. Transportation Equipment; 25. Conveying Equipment; 26. Crushing Equipment; 27. Screening Equipment; 28. Standby Production Equipment; 29. Intermediate Storage Area; 30. Storage Silo; 31. Material Level Detection Device; 32. Material Flow Detection Device; 33. Material Characteristic Detection Device; 34. Material Transfer Path; 35. Current Detection Device; 36. Temperature Detection Device; 37. Vibration Detection Device; 38. Load Detection Device; 39. Dust Sensor; 40. Harmful Gas Sensor; 41. Environmental Treatment Equipment. Detailed Implementation
[0063] System overall architecture and module connection relationships;
[0064] Reference Figure 1-2 The schematic diagram of the system structure of the present invention shown includes a central control platform 1, and several modules connected to the central control platform 1, including an equipment status acquisition module 2, a production task management module 3, a production capacity calculation module 4, a production bottleneck identification module 5, an equipment collaborative scheduling module 6, a distributed equipment control module 7, an anomaly diagnosis module 8, an energy monitoring module 9, and an environmental monitoring module 10. Data interaction between these modules is achieved through industrial Ethernet, fiber optic ring networks, or 5G wireless communication networks, covering production processes such as mining, loading, transportation, conveying, crushing, screening, dust removal, and ventilation.
[0065] The central control platform 1, as the core decision-making unit of the system, has a built-in equipment resource management unit 11. When the system starts, the equipment resource management unit 11 establishes a mining equipment resource table, which records information such as the equipment number, equipment type, production area, rated production capacity, real-time effective production capacity, current operating status, real-time load rate, current task being executed, and maintenance status of the production equipment.
[0066] Based on the equipment resource table, the central control platform 1 establishes the mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25, screening equipment 26 and standby production equipment 27 that are in normal operation as a set of schedulable equipment according to their operating status, and uses it as the basis for subsequent production task allocation and equipment collaborative control.
[0067] The distributed equipment control module 7 consists of multiple regional control nodes 16, each corresponding to a specific mining production area; among which the regional control nodes 16 include mining area control node 17, transportation area control node 18, crushing area control node 19 and screening area control node 20.
[0068] The mining area control node 17 is connected to the mining equipment 21 and the loading equipment 22, and is used to receive production tasks and control parameters issued by the central control platform 1, and to centrally control the mining equipment 21 and the loading equipment 22; the transportation area control node 18 is connected to the transportation equipment 23 and the conveying equipment 24, and is used to execute transportation tasks and the control parameters corresponding to the conveying tasks; the crushing area control node 19 is connected to the crushing equipment 25, and is used to control the operating status and feeding status of the crushing equipment 25; the screening area control node 20 is connected to the screening equipment 26, and is used to control the operating status and processing tasks of the screening equipment 26.
[0069] Each regional control node 16 receives production tasks and equipment control parameters from the central control platform 1 and centrally controls multiple production equipment within its corresponding production area. On the other hand, it feeds back the equipment execution results and equipment status data to the central control platform 1, forming a two-way data path between the central control platform 1 and each production area.
[0070] Furthermore, the present invention establishes a dynamic production chain mapping relationship corresponding to the mining production process in the central control platform 1, and maintains and updates the dynamic production chain mapping relationship through the dynamic production chain mapping unit 12.
[0071] The dynamic production chain mapping relationship established by the dynamic production chain mapping unit 12 includes at least production equipment nodes, material flow nodes, task nodes, intermediate storage nodes, and connection relationships between equipment, and records the corresponding material transmission delay, allowable conveying capacity, and control response time for the material transmission path 33 between adjacent production equipment.
[0072] Among them, the production equipment node is used to represent the real-time operating status of mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25 and screening equipment 26; the material flow node is used to represent the material flow direction, real-time material flow rate and material physical properties between different production areas; the intermediate storage node is used to represent the current material level, remaining capacity and material feeding and discharging rate of the storage bins 29, transfer bins or intermediate storage areas 28 set between adjacent production links; and the task node is used to represent the task quantity, task completion progress and task deadline corresponding to the current production task.
[0073] The storage silo 29 is equipped with a material level detection device 30 to obtain the current material level and material level change status of the storage silo 29; a material flow detection device 31 is installed on the material transmission path 33 to obtain the real-time conveying status of the material; and a material characteristic detection device 32 is also installed at the corresponding position of the material transmission path 33 to obtain the material particle size, block size, moisture content and other material physical characteristics.
[0074] The central control platform 1 establishes a dynamic production chain mapping relationship based on the dynamic production chain mapping unit 12, thereby forming a relationship between production equipment, material flow, intermediate storage area 28, and production tasks.
[0075] When the operating capacity, operating status, or production efficiency of any mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25, or screening equipment 26 changes, the dynamic production chain mapping unit 12 analyzes the impact range of the state change propagating upstream and downstream along the material transmission path 33 according to the dynamic production chain mapping relationship, and assesses the impact of the state change on the intermediate storage area 28, related production tasks, and energy and environmental conditions.
[0076] This transforms production control from state control of individual production equipment to correlation control of the entire production chain, enabling changes in equipment state to propagate and be analyzed along the production process, providing a data foundation for subsequent bottleneck prediction, task reconfiguration, and collaborative control.
[0077] Production task decomposition and initial allocation under normal operating conditions;
[0078] After the system receives the total production task for a set time period from the mine dispatch center, the production task management module 3 starts the task decomposition process.
[0079] Production Task Management Module 3 breaks down the total production task into mining tasks, loading tasks, transportation tasks, conveying tasks, crushing tasks, and screening tasks according to the mining production process sequence, namely mining, loading, transportation, conveying, crushing and screening, and establishes the process dependencies between each production task.
[0080] For example, after the mining equipment 21 completes the mining task, the loading equipment 22 performs the loading task; after the loading equipment 22 completes the loading, the transportation equipment 23 performs the transportation task; after the transportation equipment 23 transports the material to the conveying equipment 24, the conveying equipment 24 then transports it to the crushing equipment 25; after the crushing equipment 25 completes the crushing process, the screening equipment 26 performs the screening process.
[0081] Subsequently, the production capacity calculation module 4 reads the equipment resource table in the equipment resource management unit 11 to obtain the rated production capacity of the mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25 and screening equipment 26.
[0082] The production capacity calculation module 4 simultaneously acquires the equipment operating status parameters collected by the equipment status acquisition module 2, including load rate, operating efficiency, equipment fault status and historical operating data, and determines the real-time effective production capacity of each production equipment accordingly.
[0083] The equipment status acquisition module 2 acquires the current, temperature, vibration and load status of the production equipment through the current detection device 34, temperature detection device 35, vibration detection device 36 and load detection device 37 respectively.
[0084] The real-time effective production capacity of production equipment changes dynamically with the operating status of the production equipment.
[0085] For example, when a crushing machine 25 with a rated processing capacity of 500 tons / hour is currently operating at 80% load and 95% efficiency, the production capacity calculation module 4 calculates its rated production capacity based on the current operating status to obtain the corresponding real-time effective production capacity.
[0086] Furthermore, the production capacity calculation module 4 determines the real-time effective production capacity of each production device through step-by-step cascaded correction logic.
[0087] First, the production capacity calculation module 4 determines the current load status of the production equipment based on the real-time operating current collected by the current detection device 34 and the rated operating current of the equipment, and obtains the basic operating capacity in combination with the rated production capacity of the production equipment.
[0088] Then, the production capacity calculation module 4 uses the temperature detection device 35 and the vibration detection device 36 to obtain the real-time operating temperature and vibration intensity of key parts of the production equipment.
[0089] When the vibration intensity and operating temperature are within the preset normal range, the production capacity calculation module 4 does not deduct the basic operating capacity.
[0090] When the vibration intensity exceeds the upper limit of the normal range but does not reach the fault shutdown threshold, or when the rate of increase of the operating temperature exceeds the preset heating rate threshold, the anomaly diagnosis module 8 will determine the corresponding production equipment as a restricted operating state. The production capacity calculation module 4 will perform gradient correction on the basic operating capacity according to the degree of exceedance of the vibration and temperature states to obtain the equipment health correction capacity.
[0091] Finally, for the crushing equipment 25, screening equipment 26 and conveying equipment 24, the production capacity calculation module 4 also obtains the physical characteristics of the materials entering the corresponding equipment through the material characteristic detection device 32.
[0092] The material characteristic detection device 32 can use 3D LiDAR, industrial vision sensors or other detection devices that can acquire the physical characteristics of materials to obtain the average block size, particle size, material hardness estimate and material moisture content of the material.
[0093] When the average size of the material exceeds the preset standard size, or the material moisture exceeds the preset adhesion threshold, the production capacity calculation module 4 determines that the current material processing difficulty has increased, and further corrects the equipment health correction capability according to the changes in material characteristics, and outputs the real-time effective production capacity of the production equipment under the current material conditions.
[0094] Furthermore, the production capacity calculation module 4 can also dynamically classify the real-time effective production capacity based on the duration and trend of changes in the production equipment capacity and the changes in material input of adjacent production equipment.
[0095] The central control platform 1 acquires the real-time effective production capacity of the production equipment according to the preset sampling cycle, and the predictive analysis unit 13 forms a capacity status sequence.
[0096] When the real-time effective production capacity of the production equipment continues to decline within multiple adjacent sampling periods, the prediction and analysis unit 13 marks the production equipment as a capacity decline state; when the real-time effective production capacity changes within a preset fluctuation range, the production equipment is marked as a capacity fluctuation state; when the real-time effective production capacity remains stable, the production equipment is marked as a capacity stable state.
[0097] Meanwhile, the production capacity calculation module 4 compares the current effective production capacity of the production equipment with its upstream material input capacity and downstream material processing capacity.
[0098] When the current effective production capacity of the production equipment is not lower than the processing capacity of the downstream equipment, but its capacity decline trend is expected to form a capacity gap within the preset prediction time window, the prediction analysis unit 13 marks the production equipment as a potential restricted equipment.
[0099] In the above manner, the production capacity calculation module 4 and the predictive analysis unit 13 output the real-time effective production capacity that the production equipment can currently execute, as well as the production equipment capacity change trend and potential capacity gap status, so that the production bottleneck identification module 5 can distinguish between the production bottleneck that has been formed and the potential production bottleneck that may be formed.
[0100] Production bottleneck identification and coordinated equipment control;
[0101] Based on this, the production bottleneck identification module 5 compares the total real-time effective production capacity of all production equipment corresponding to each production stage according to the process sequence of mining, loading, transportation, conveying, crushing and screening. The production stage with lower production capacity is identified as the current production bottleneck stage, and the corresponding production equipment is identified as the bottleneck equipment.
[0102] The equipment collaborative scheduling module 6 generates corresponding equipment control parameters based on the real-time effective production capacity and workload of each production equipment.
[0103] The equipment control parameters include operating speed, feed rate, workload, and start / stop sequence.
[0104] The central control platform 1 sends the equipment control parameters to the corresponding regional control nodes 16 through the distributed equipment control module 7.
[0105] Each regional control node 16 centrally controls the mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25, and screening equipment 26 within its corresponding production area based on the received equipment control parameters, enabling different types of production equipment to operate in coordination.
[0106] Upstream and downstream feeding constraints and coordinated adjustment based on bottleneck identification;
[0107] During production, the equipment status acquisition module 2 continuously collects the operating status of each production device.
[0108] Among them, the current detection device 34 is used to collect the operating current of the production equipment, the temperature detection device 35 is used to collect the operating temperature of the production equipment, the vibration detection device 36 is used to collect the vibration status of the production equipment, and the load detection device 37 is used to collect the real-time load status of the production equipment.
[0109] The above equipment status data is sent to the central control platform 1 in real time. When the real-time load rate of a certain production equipment increases, the production capacity calculation module 4 recalculates the real-time effective production capacity of the production equipment based on the equipment status change. When the production bottleneck identification module 5 detects that the total effective production capacity of a certain production link is lower than the output capacity of its upstream production link, it identifies the production equipment corresponding to that production link as a new bottleneck equipment.
[0110] Once the bottleneck equipment is identified, the equipment collaborative scheduling module 6 uses the current real-time effective production capacity of the bottleneck equipment as its input capacity reference and establishes a feeding constraint relationship between the bottleneck equipment and its upstream production equipment.
[0111] Based on the amount of material that the bottleneck equipment can currently process, the equipment collaborative scheduling module 6 reversely determines the corresponding task volume and operating speed of the upstream transportation equipment 23, conveying equipment 24, loading equipment 22 and mining equipment 21.
[0112] During the adjustment process, the equipment coordination scheduling module 6 adjusts the equipment in a way that is passed from downstream to upstream. First, it adjusts the conveying equipment 24 connected to the bottleneck equipment, then adjusts the transportation equipment 23, and then adjusts the loading equipment 22 and the mining equipment 21 to reduce the material backlog caused by the continuous entry of upstream materials into the bottleneck equipment.
[0113] The central control platform 1 sends the above adjustment parameters to the corresponding area control node 16 through the distributed device control module 7, and the corresponding area control node 16 executes them synchronously.
[0114] When the load rate of the bottleneck equipment recovers to the preset range due to the reduction of upstream feeding, the equipment collaborative scheduling module 6 gradually restores the operating parameters of the mining equipment 21, loading equipment 22, transportation equipment 23 and conveying equipment 24 according to the preset recovery order.
[0115] Spatiotemporal feedforward bottleneck prediction;
[0116] Furthermore, the production bottleneck identification module 5 performs spatiotemporal feedforward bottleneck prediction through the predictive analysis unit 13.
[0117] The dynamic production chain mapping unit 12 pre-establishes the production topology relationship including mining, loading, transportation, conveying, crushing and screening production links in the central control platform 1, and records the corresponding material transmission time delay for the material transmission path 33 between adjacent production equipment.
[0118] For example, the material transmission path 33 between the conveying equipment 24 and the crushing equipment 25 has a corresponding material transmission time delay. The prediction and analysis unit 13 determines the time required for the material to enter the crushing equipment 25 from the conveying equipment 24 based on the material flow rate collected by the material flow detection device 31 and the transmission parameters of the material transmission path 33.
[0119] Meanwhile, the central control platform 1 obtains the real-time material level height and material level change rate of the storage silo 29 through the material level detection device 30, and judges its buffering capacity based on the remaining capacity of the storage silo 29.
[0120] When the feeding rate of the upstream equipment is greater than the processing rate of the downstream equipment, the prediction and analysis unit 13 predicts whether the storage silo 29 will reach the high material level warning state within the preset prediction window based on the material level change trend.
[0121] When it is predicted that the storage bin 29 will reach the high material level warning state within the time range corresponding to the material transmission time lag, even if the downstream crushing equipment 25 is not currently overloaded, the production bottleneck identification module 5 will identify the crushing equipment 25 as a potential feedforward bottleneck equipment and output an advance adjustment command to the equipment collaborative scheduling module 6.
[0122] On the other hand, when it is predicted that the material level in the storage bin 29 will continue to decline and may reach a low level, the production bottleneck identification module 5 will identify the corresponding production equipment as a potential material shortage risk equipment, and the equipment coordination scheduling module 6 will improve the feeding capacity of the upstream equipment.
[0123] Bottleneck propagation path and control response time coordination;
[0124] Furthermore, the production bottleneck identification module 5 establishes the temporal relationship of changes in production equipment capacity propagating along the mine's production process chain.
[0125] For any production equipment, when its real-time effective production capacity decreases, the dynamic production chain mapping unit 12 obtains the corresponding material transfer delay based on the material transfer path 33 between the production equipment and its upstream and downstream production equipment.
[0126] Predictive analysis unit 13 performs time offset analysis on the changes in production equipment capacity based on the material conveying direction.
[0127] For example, when the real-time effective production capacity of the crushing equipment 25 decreases from the first processing capacity to the second processing capacity, the prediction and analysis unit 13 predicts the amount of material input entering the crushing equipment 25 after the material transmission delay according to the material transmission delay corresponding to the material transmission path 33 between the conveying equipment 24 and the crushing equipment 25, and compares the predicted material input with the second processing capacity of the crushing equipment 25.
[0128] When the predicted material input is higher than the second processing capacity of the crushing equipment 25, the production bottleneck identification module 5 determines that the crushing equipment 25 is at risk of overload.
[0129] The predictive analysis unit 13 further determines the arrival time of the impact of different upstream production equipment based on the material transfer path 33 between the transportation equipment 23, the loading equipment 22, and the mining equipment 21 and the crushing equipment 25.
[0130] The central control platform 1 forms a bottleneck propagation path based on the arrival time of the impact of different production equipment, and the equipment coordination scheduling module 6 determines the adjustment time of the corresponding production equipment according to the arrival time of the impact, so that the control parameters of the upstream production equipment are pre-adjusted before the bottleneck equipment 25 actually enters the restricted state.
[0131] Furthermore, the central control platform 1 establishes corresponding control response time parameters for different types of production equipment through the parameter update unit 15.
[0132] The control response time parameter is used to represent the time required from the issuance of a control command from the central control platform 1 to the time when the operating parameters of the corresponding production equipment reach the target state.
[0133] When generating equipment control parameters, the equipment collaborative scheduling module 6 uses the equipment control response time and the material transmission delay corresponding to the material transmission path 33 as the basis for control timing.
[0134] For mining equipment 21 and transportation equipment 23 with long control response times, the equipment coordination scheduling module 6 sends control commands to reduce operating speed or workload in advance; for conveying equipment 24 with short control response times, feeding adjustment is performed when the predicted bottleneck formation time is approaching.
[0135] When the bottleneck risk is eliminated, the equipment collaborative scheduling module 6 gradually restores the operating parameters of the production equipment according to the control response time of each production equipment and the recovery sequence.
[0136] Dynamic buffer control of intermediate storage area;
[0137] Furthermore, the central control platform 1 uses the intermediate storage area 28 as a dynamic buffer node in the production chain.
[0138] The material level detection device 30 installed in the storage silo 29 acquires the current material level, remaining capacity and material level change status of the storage silo 29, and the material flow detection device 31 acquires the material feeding rate and discharge rate of the material entering the storage silo 29.
[0139] The central control platform 1 determines the material level change trend of the intermediate storage area 28 based on the current feeding rate and discharging rate, and determines the duration of the intermediate storage area 28 absorbing the difference in production capacity between upstream and downstream based on the remaining capacity of the storage bin 29.
[0140] When the output capacity of the upstream production equipment is higher than the processing capacity of the downstream production equipment, the central control platform 1 determines whether the intermediate storage area 28 has remaining buffer capacity.
[0141] If the remaining buffer capacity can cover the material increment formed by the capacity difference within the preset prediction time window, the central control platform 1 will not reduce the operating speed of the upstream production equipment and will use the intermediate storage area 28 to absorb the capacity difference.
[0142] When it is predicted that the intermediate storage area 28 will reach the preset high material level within the time range corresponding to the material transmission time delay and the equipment control response time, the central control platform 1 will start the flow restriction control of the upstream equipment.
[0143] When the material level in the intermediate storage area 28 drops and reaches the preset low material level, the central control platform 1 increases the feeding capacity of the upstream production equipment or restores the production equipment that is in a derated operation state.
[0144] This allows the actual remaining capacity of the intermediate storage area 28 to participate in the scheduling of production equipment, distinguishing between short-term capacity fluctuations that can be absorbed by the storage buffer and capacity imbalances that need to be adjusted.
[0145] Multi-load threshold graded response and backup buffer mechanism;
[0146] This invention sets up a graded response strategy to address the different load levels of bottleneck equipment;
[0147] The central control platform 1 presets a first load threshold and a second load threshold, wherein the second load threshold is higher than the first load threshold. When the real-time load rate of the bottleneck device reaches the first load threshold, the equipment coordination scheduling module 6 reduces the operating speed or feeding amount of the conveying equipment 24 connected to the bottleneck device. When the real-time load rate of the bottleneck device reaches the second load threshold, the equipment coordination scheduling module 6 further reduces the workload of the transport equipment 23 and the loading equipment 22, and transfers some production tasks to the standby production equipment 27 or the intermediate storage area 28.
[0148] The standby production equipment 27 forms a standby production relationship with the production equipment in the current production line. When the original production equipment experiences a decrease in capacity or a failure, the central control platform 1 can control the standby production equipment 27 to start operation through the distributed equipment control module 7.
[0149] Through the aforementioned graded response mechanism, bottleneck equipment can adopt corresponding control strategies under different load conditions, thereby reducing the impact of adjustment frequency on the production process.
[0150] Production task reconfiguration and capacity rebalancing under equipment failure conditions;
[0151] When the anomaly diagnosis module 8 detects a malfunction in any of the mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25, or screening equipment 26, or when the real-time effective production capacity of the production equipment is lower than the preset capacity threshold, the central control platform 1 marks the corresponding production equipment as unschedulable equipment or derated scheduling equipment. For malfunctioning production equipment, the central control platform 1 removes it from the set of schedulable equipment through the equipment resource management unit 11. For derated production equipment, the production capacity calculation module 4 redetermines its available production capacity based on the current equipment status.
[0152] Based on this, the production capacity calculation module 4 recalculates the current real-time effective production capacity of the entire production system, taking the remaining normal production equipment and derated production equipment as the objects.
[0153] The production task management module 3 re-decomposes and allocates the unfinished production tasks based on the recalculated real-time effective production capacity. When the production capacity of the remaining production equipment can cover at least part of the unfinished production tasks, the production task management module 3 allocates the unfinished production tasks to the remaining production equipment. When the remaining production capacity is insufficient to cover all unfinished production tasks, the central control platform 1 adjusts the production target based on the current remaining production capacity.
[0154] Furthermore, when the anomaly diagnosis module 8 detects a fault in the production equipment, the central control platform 1 reconstructs the current production topology through the production topology reconstruction unit 14.
[0155] The production topology includes the material flow relationship between production equipment, the transportation path relationship, the conveying direction relationship, the connection relationship of intermediate storage area 28, and the connection relationship of standby production equipment 27.
[0156] The production topology reconfiguration unit 14 first determines the upstream and downstream production equipment sets of the faulty production equipment in the current production topology, and then determines the candidate production paths that can replace the faulty production equipment based on the real-time effective production capacity of the remaining production equipment, the current task load of the equipment, the remaining capacity of the intermediate storage area 28, and the energy status.
[0157] When there are multiple candidate production paths, the equipment collaborative scheduling module 6 selects the production path that can satisfy the unfinished production tasks and is unlikely to cause other production equipment to form new bottlenecks.
[0158] When the unit output energy consumption or environmental conditions of the equipment corresponding to the candidate production path are different, the equipment collaborative scheduling module 6 further selects the production path with relatively low unit output energy consumption and environmental conditions within the preset range.
[0159] After determining the target production path, the central control platform 1 synchronously adjusts the corresponding regional control nodes 16 through the distributed equipment control module 7, so that the transportation equipment 23 changes its transportation task, the conveying equipment 24 changes its conveying direction or feeding path, and controls the standby production equipment 27 to enter the operating state.
[0160] At the same time, the production topology reconfiguration unit 14 re-establishes the material connection relationship between the upstream and downstream of the faulty production equipment, forming a new production path.
[0161] Energy consumption monitoring and inefficient operation identification and optimization;
[0162] During the operation of production equipment and the reconfiguration of production tasks, the energy monitoring module 9 acquires real-time operating power and energy consumption per unit output data of each production equipment.
[0163] The energy monitoring module 9 associates the real-time operating power of each production equipment with the real-time effective production capacity determined by the production capacity calculation module 4, and determines the energy consumption status corresponding to the production task executed by the equipment unit based on the current task volume.
[0164] The central control platform 1 establishes the comprehensive operating status of the equipment based on the equipment's real-time effective production capacity and energy consumption per unit output.
[0165] When two or more production equipment can perform the same production task, the equipment coordination scheduling module 6 compares the remaining production capacity of each production equipment with the unit energy consumption required for each production equipment to complete the corresponding production task.
[0166] For production equipment with similar real-time effective production capacity but different energy consumption per unit output, the equipment collaborative scheduling module 6 prioritizes assigning production tasks to production equipment with relatively lower energy consumption per unit output.
[0167] For production equipment with low energy consumption per unit output but a load rate close to the preset high load threshold, the equipment collaborative scheduling module 6 restricts the increase of its task volume and allocates the remaining tasks to other production equipment.
[0168] Without reducing the production task completion rate, for equipment such as conveying equipment 24 that can improve energy utilization efficiency by adjusting the operating speed, the central control platform 1 appropriately adjusts its operating frequency so that the operating speed is adapted to the actual feeding amount.
[0169] For production lines with backup production equipment 27, the central control platform 1 will transfer some production tasks from production equipment with relatively low energy efficiency to backup production equipment 27 or other production equipment with higher energy efficiency.
[0170] When the total production task is low, if the conveying capacity of a certain conveying device 24 is lower than the standby threshold and continues for a set time, the central control platform 1 will switch the corresponding conveying device 24 to standby mode, maintain the monitoring function, and stop the main drive equipment from running.
[0171] Environmental status monitoring is linked to environmental constraints of production parameters;
[0172] The environmental monitoring module 10 is equipped with dust sensors 38 and hazardous gas sensors 39 in the mining area, transportation area, crushing area and screening area respectively. The dust sensor 38 is used to collect the dust concentration in the corresponding production area, and the hazardous gas sensor 39 is used to collect the hazardous gas concentration in the corresponding production area. The dust sensor 38 and the hazardous gas sensor 39 send the collected environmental status parameters to the central control platform 1.
[0173] When the central control platform 1 determines that the dust concentration or harmful gas concentration in any production area reaches the preset environmental threshold, it identifies the corresponding abnormal environmental area and controls the environmental treatment equipment 40 to increase its operating power to enhance the dust removal or ventilation capacity of the corresponding production area.
[0174] Meanwhile, the central control platform 1 reduces the operating load of the crushing equipment 25, conveying equipment 24, or transport equipment 23 corresponding to the area of environmental anomaly through the equipment collaborative scheduling module 6, based on the degree of environmental anomaly, thereby reducing the amount of dust or harmful gases generated.
[0175] Furthermore, the central control platform 1 maps the environmental status parameters obtained by the environmental monitoring module 10 to the corresponding production areas and production equipment through the dynamic production chain mapping unit 12; when the dust concentration or harmful gas concentration in a certain area increases, the central control platform 1 determines whether the current production task can be transferred to other production areas where the environmental status meets the preset requirements.
[0176] When there is an alternative production area, the equipment collaborative scheduling module 6 selects the production task execution area based on the real-time effective production capacity of the production equipment in the alternative area, the transportation distance, the remaining capacity of the intermediate storage area 28, and the energy consumption status.
[0177] When there is no alternative production area to meet the production task requirements, the central control platform 1 reduces the operating load of production equipment with relatively high dust or harmful gas generation in the abnormal environmental area, while improving the operating capacity of the environmental treatment equipment 40; when the dust sensor 38 and the harmful gas sensor 39 detect that the environmental parameters have returned to the normal range and stabilized for a set time, the central control platform 1 gradually restores the operating load of the relevant production equipment.
[0178] Therefore, environmental conditions, as one of the constraints for production task path selection and equipment task allocation, participate in the mine production organization process.
[0179] Continuous iteration and cyclic feedback of integrated closed-loop control;
[0180] The above control process is continuously executed in a loop according to the control cycle preset by the central control platform 1. In each control cycle, the central control platform 1 first obtains status data from the equipment status acquisition module 2, the energy monitoring module 9 and the environmental monitoring module 10.
[0181] Among them, the equipment status acquisition module 2 acquires the operating status of each production equipment through the current detection device 34, temperature detection device 35, vibration detection device 36 and load detection device 37; the energy monitoring module 9 acquires the energy consumption status of the production equipment; and the environmental monitoring module 10 acquires environmental status parameters through the dust sensor 38 and the harmful gas sensor 39.
[0182] Subsequently, the production capacity calculation module 4 recalculates the real-time effective production capacity of each production equipment, the production bottleneck identification module 5 re-judges the current production bottleneck and potential production bottleneck, the prediction and analysis unit 13 predicts the bottleneck propagation process, the production topology reconstruction unit 14 judges whether the production topology needs to be re-established based on the changes in equipment status, and the equipment collaborative scheduling module 6 generates new equipment collaborative control parameters based on the calculation results.
[0183] Finally, the central control platform 1 sends the updated equipment control parameters to the corresponding regional control nodes 16 through the distributed equipment control module 7.
[0184] Each area control node 16 controls the corresponding mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25, screening equipment 26, and standby production equipment 27 to execute control parameters.
[0185] After execution, the equipment status data is collected by the equipment status acquisition module 2 and fed back to the central control platform 1, thus entering the next control cycle.
[0186] Furthermore, after each production control cycle, the central control platform 1 compares the bottleneck prediction results generated by the prediction and analysis unit 13 in the previous control cycle with the actual operating results of the production equipment.
[0187] When the deviation between the actual bottleneck formation time and the predicted bottleneck formation time exceeds the preset range, the parameter update unit 15 corrects the material transmission time delay, production equipment control response time, or production equipment effective production capacity change trend of the corresponding material transmission path 33.
[0188] When the actual material level change in the intermediate storage area 28 deviates from the predicted result, the parameter update unit 15 updates the effective buffering capacity parameter of the intermediate storage area 28 based on the actual material level change data collected by the material level detection device 30.
[0189] In the next control cycle, the production bottleneck identification module 5 uses the updated parameters from the parameter update unit 15 to re-execute the bottleneck propagation prediction, and the equipment collaborative scheduling module 6 redetermines the production equipment control parameters and control lead based on the corrected prediction results.
[0190] The predicted results are corrected by the actual operating results, so that the central control platform 1 forms an adaptive closed-loop control process of "status acquisition, capacity calculation, bottleneck prediction, early control, result verification, parameter correction, and re-prediction".
[0191] Through the above control methods, the intelligent green mine monitoring and control system of the present invention can dynamically analyze and adjust the production chain when the operating status of mining equipment 21, loading equipment 22, transportation equipment 23, conveying equipment 24, crushing equipment 25 and screening equipment 26 changes. This is achieved through the dynamic production chain mapping unit 12, predictive analysis unit 13, production topology reconstruction unit 14 and parameter update unit 15.
[0192] Meanwhile, the equipment collaborative scheduling module 6 and the distributed equipment control module 7 realize the collaborative control of equipment between different production areas, and the energy monitoring module 9 and the environmental monitoring module 10 enable energy consumption and environmental status to participate in the allocation of production tasks, forming a feedback control between production tasks, equipment operation, material flow, energy consumption and environmental status.
[0193] This enables the mining production system to automatically adjust production tasks, production paths, and equipment operating parameters under dynamic conditions such as fluctuations in equipment status, changes in production tasks, equipment failures, changes in material characteristics, changes in energy consumption, and changes in environmental parameters. This reduces the risks of ineffective equipment operation, energy waste, and environmental anomalies while maintaining production continuity.
[0194] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.
Claims
1. A smart green mine monitoring and control system, comprising a central control platform (1), and connected to the central control platform (1) an equipment status acquisition module (2), a production task management module (3), a production capacity calculation module (4), a production bottleneck identification module (5), an equipment collaborative scheduling module (6), a distributed equipment control module (7), an anomaly diagnosis module (8), an energy monitoring module (9), and an environmental monitoring module (10). The equipment status acquisition module (2) is used to collect the load, operating temperature, vibration, operating current, material size and humidity of the production equipment; the production capacity calculation module (4) is used to make step-by-step corrections based on the rated production capacity of the equipment, the operating status of the equipment and the characteristics of the material to obtain the real-time effective production capacity of the production equipment under the current working conditions. The production bottleneck identification module (5) establishes a dynamic production chain topology including production equipment nodes, material flow nodes, intermediate storage nodes and production task nodes according to the mining production process, and records the material transmission time delay of the material transmission path (33) between production equipment. Based on the real-time effective production capacity and the storage change status of the intermediate storage area (28), it predicts the material flow transmission status and determines the current or potential production bottleneck and its formation time. The equipment collaborative scheduling module (6) determines the control lead time based on the potential production bottleneck formation time, material transmission time delay and equipment control response time, and sends collaborative control parameters to the upstream production equipment of the bottleneck according to the material flow direction; the distributed equipment control module (7) adjusts the operating speed, feeding amount or production task of multiple production equipment according to the collaborative control parameters so that the upstream material input capacity matches the downstream processing capacity. The anomaly diagnosis module (8) triggers production topology reconfiguration when equipment fails or continuously dwindles; the energy monitoring module (9) and the environmental monitoring module (10) respectively acquire the energy consumption status and the environmental status of the production area, and use them as constraints for equipment scheduling and topology adjustment. The central control platform (1) updates the material transmission time delay, real-time effective production capacity and effective buffering capacity of intermediate storage area (28) based on the deviation between the actual operation results of the current control cycle and the prediction results of the previous control cycle, and uses the updated results for bottleneck prediction and collaborative control in the next control cycle to form an adaptive closed-loop control of prediction, advance control, operation feedback and parameter update.
2. A smart green mine monitoring and control system according to claim 1, characterized in that, The central control platform (1) includes an equipment resource management unit (11), which is used to establish a set of schedulable equipment based on the equipment operating status, real-time effective production capacity and maintenance status, and to adjust the equipment scheduling status when the equipment fails or is derated.
3. A smart green mine monitoring and control system according to claim 1, characterized in that, The distributed equipment control module (7) includes mining, transportation, crushing and screening area control nodes (16). Each area control node is connected to the corresponding production equipment and receives production tasks and collaborative control parameters issued by the central control platform (1).
4. A smart green mine monitoring and control system according to claim 1, characterized in that, The production capacity calculation module (4) performs basic capacity correction based on operating current, health capacity correction based on temperature and vibration status, and material characteristic correction based on material size and humidity.
5. A smart green mine monitoring and control system according to claim 4, characterized in that, The central control platform (1) includes a dynamic production chain mapping unit (12) and a predictive analysis unit (13), which is used to determine the temporal propagation relationship of capacity changes based on changes in production equipment capacity, material transmission time delay and changes in storage, and to identify potentially restricted production links.
6. A smart green mine monitoring and control system according to claim 1, characterized in that, The intermediate storage area (28) includes a storage bin (29), a material level detection device (30), and a material flow detection device (31), which are used to obtain the storage capacity, the feed rate and the material level change, and to identify potential production bottlenecks when the predicted material increment exceeds the remaining storage capacity.
7. A smart green mine monitoring and control system according to claim 1, characterized in that, The equipment coordination scheduling module (6) determines the adjustment equipment level by level from the potential production bottleneck to the upstream according to the material flow direction, and adjusts at least one of the conveying, transporting, loading and mining equipment in sequence; after the bottleneck is removed, the operating parameters are restored in the preset order.
8. A smart green mine monitoring and control system according to claim 1, characterized in that, The central control platform (1) includes a production topology reconfiguration unit (14), which determines candidate alternative production paths based on faulty equipment, standby production equipment (27), intermediate storage area (28) and material transfer path (33), and selects the target production path.
9. A smart green mine monitoring and control system according to claim 1, characterized in that, The energy monitoring module (9) acquires equipment energy consumption, and the central control platform (1) allocates tasks based on real-time effective production capacity, load status and unit output energy consumption; the environmental monitoring module (10) acquires environmental parameters of the production area, and adjusts equipment load or transfers production tasks when environmental parameters exceed the threshold.
10. A smart green mine monitoring and control system according to claim 1, characterized in that, The central control platform (1) includes a parameter update unit (15), which updates the material transmission delay, real-time effective production capacity and effective buffer capacity based on the actual bottleneck formation time, material flow, storage changes and the deviation between the equipment output capacity and the prediction results, and is used for the next control cycle.