A method for intelligent inspection of a broadcast television station room based on space-time analysis

By establishing a power supply and signal link topology model and combining it with the equipment operation status index, the impact index and impact degree are calculated, which solves the problem of low inspection efficiency in the broadcasting and television station equipment room and realizes automatic identification of equipment hidden dangers and scientific operation and maintenance decisions.

CN123163979APending Publication Date: 2026-11-24CHENGDU KAITENG SIFANG DIGITAL RADIO & TELEVISION EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611323287.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-28
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies result in low efficiency of equipment room inspections at radio and television stations, a lack of equipment correlation analysis and hazard classification assessment, difficulty in predicting the impact of equipment failures on broadcasting, and the inability of automated monitoring systems to comprehensively analyze equipment status changes and signal transmission links.

Method used

By establishing power supply topology models and signal link topology models, and combining them with equipment operating status indices, the impact index and intensity of equipment on broadcast tasks are calculated, thereby enabling automatic assessment of equipment hazard levels and maintenance strategies.

Benefits of technology

It enables comprehensive monitoring and automatic identification of equipment in the computer room, improves inspection efficiency and the scientific nature of operation and maintenance decisions, accurately predicts the impact of equipment failures on broadcasting, and provides emergency early warning and tiered handling strategies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123163979A_ABST
    Figure CN123163979A_ABST
Patent Text Reader

Abstract

A spatiotemporal analysis-based intelligent inspection method for broadcast television station equipment rooms, relating to the field of intelligent monitoring technology, includes: establishing a power supply topology model based on the power supply and distribution connection relationships between equipment in the equipment room; establishing a signal link topology model based on the signal transmission connection relationships between equipment; acquiring the operating status index of each device at multiple sampling times; calculating the power supply status of each working device and the overall broadcast operation index at each sampling time based on the two topology models and the operating status index; determining the impact index based on the difference in the overall broadcast operation index before and after a change in the operating status of any device; determining the impact degree based on the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails; determining the hazard level based on the impact index and impact degree and outputting a maintenance strategy. This method addresses the technical problems of low efficiency and lack of equipment correlation analysis and hazard classification assessment in traditional equipment room inspection methods.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of intelligent monitoring technology, specifically to an intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis. Background Technology

[0002] As the core hub for the transmission and broadcasting of radio and television signals, the equipment room of a radio and television station houses key equipment such as transmitters, switchers, power supply and distribution systems, antenna feeder systems, signal processing equipment, and precision air conditioning. Its operational stability is directly related to the transmission quality and coverage effect of radio and television signals.

[0003] Currently, data center inspections are mainly divided into two modes: manual inspection and automated monitoring. Manual inspection relies on personnel to regularly inspect the equipment status on-site through visual inspection, instrument testing, and sound judgment, and is still the mainstream operation and maintenance method for many stations. Automated monitoring systems, on the other hand, monitor the indicators of individual devices by collecting real-time data on the data center's power environment and transmitter operating parameters and issuing anomaly alarms.

[0004] However, both of these models have significant drawbacks. Manual inspections are inefficient and lack real-time performance, making it difficult to detect early signs of equipment degradation. For special sites such as high-altitude stations and remote relay stations, the cost of manpower remains high and it is difficult to achieve routine coverage. Automated monitoring systems also have many limitations: they can only monitor and alarm for single devices, lacking correlation analysis of signal transmission links and power supply systems; they lack analysis of historical trends in equipment status, making it difficult to determine the impact of equipment degradation on the overall broadcast, and their early warning capabilities are insufficient; and they lack hypothetical scenario analysis under conditions of complete equipment failure, making it impossible to predict the impact of a single device failure on the broadcast.

[0005] Therefore, we propose a method that can cover various terrains, comprehensively analyze data center equipment, and accurately predict data center equipment failures. Summary of the Invention

[0006] The purpose of this invention is to provide an intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis, which solves the technical problems of low efficiency, lack of equipment correlation analysis and hidden danger classification assessment in traditional computer room inspection methods.

[0007] This invention is achieved through the following technical solution: A method for intelligent inspection of broadcast television station computer rooms based on spatiotemporal analysis, specifically including: Establish a power supply topology model based on the power supply and distribution connection relationship between the equipment in the computer room, and establish a signal link topology model based on the signal transmission connection relationship between the equipment in the computer room. Obtain the operating status index of each device at multiple sampling times; Based on the power supply topology model, signal link topology model, and operating status index at each sampling time, calculate the power supply status of each working device at each sampling time, as well as the overall broadcast operating index. Based on the difference in the overall broadcast operation index before and after a change in the operating status of any device, determine the impact index of the change in the operating status of the device on the broadcast task; For any given device, the impact of the device failure on the broadcast task is determined by the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails. The hazard level of each device is determined based on its impact index and impact intensity, and a maintenance strategy corresponding to the hazard level is output.

[0008] Furthermore, the power supply topology model is a directed graph with power supply and distribution equipment and working equipment as nodes and the power supply and distribution connection relationship between the equipment as directed edges; The signal link topology model is a directed graph with signal processing equipment and working equipment as nodes and the signal transmission connection relationship between the devices as directed edges.

[0009] Furthermore, the calculation process involving the power supply status of the working device is as follows:

[0010]

[0011] in, Indicates equipment The usage status, This refers to the operating status index of each device along the power supply path. This is the status index of the power supply path input. This is the power supply status index for the working equipment.

[0012] Furthermore, the specific calculation steps for the overall broadcast operation index include: Based on the power supply status and operating status index of each working device node in the signal link topology model, calculate the output status index of each working device node; The signal link topology model is decomposed into series sub-links and parallel sub-links, and the state index of each sub-link is calculated separately. Treat all sub-links as equivalent to serial links and calculate the overall broadcast operation index.

[0013] Furthermore, for any working device node Its output state index is:

[0014] in This is the power supply status index for the working equipment. This is the operating status index of the equipment; The state index of the parallel sub-link is:

[0015] The state index of the serial sub-link is:

[0016] The overall broadcast performance index is:

[0017] in This represents the state index of each sub-link.

[0018] Furthermore, for any device The formula for calculating the influence index is as follows:

[0019] in, For equipment The overall broadcast performance index before the change For equipment The overall broadcast performance index after the change, while the remaining equipment remains in the same operating state as before the change; when hour, .

[0020] 7. Furthermore, for any device The formula for calculating the impact intensity is:

[0021] in, For the current sampling time device The overall broadcast operation index For hypothetical devices The overall broadcast performance index when the equipment fails and other equipment remains in its current state. when = hour, 1.

[0022] Furthermore, the hazard rating is divided as follows: when or At that time, it is classified as a Level 1 hazard, and an emergency response strategy is required. when or At that time, it was classified as a Level 2 hazard, and the corresponding rectification strategy was adopted; when and At that time, it was classified as a Level 3 hidden danger, corresponding to a key focus strategy; when and At that time, it was classified as a Level 4 hazard, corresponding to a continuous observation strategy; when and At that time, there is no risk.

[0023] Furthermore, the equipment operating status index is obtained by fitting the equipment's operating parameters, which include the transmitter's output power, VSWR, operating temperature, and at least one of the power supply and distribution equipment's voltage, current, and frequency.

[0024] A smart inspection system for broadcast television station computer rooms based on spatiotemporal analysis includes: The model building module establishes a power supply topology model based on the power supply and distribution connection relationship between the equipment in the computer room, and establishes a signal link topology model based on the signal transmission connection relationship between the equipment in the computer room. The data acquisition module is used to acquire the operating status index of each device at multiple sampling times; The preliminary calculation module calculates the power supply status of each working device at each sampling time, as well as the overall broadcast operation index, based on the power supply topology model, signal link topology model, and the operating status index at each sampling time. The impact index calculation module determines the impact index of the change in the operating status of any device on the broadcast task based on the difference between the overall broadcast operation index before and after the change in the operating status of any device. The impact calculation module determines the impact of a device failure on the broadcast task based on the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails. The hazard assessment module determines the hazard level of each device based on its impact index and impact intensity, and outputs the maintenance strategy corresponding to the hazard level.

[0025] The technical solution of the present invention has at least the following advantages and beneficial effects: This invention discloses an intelligent inspection method for broadcast television station equipment rooms based on spatiotemporal analysis. By integrating dual-domain topology modeling of the power supply domain and signal domain, state tracking at multiple sampling times, and dual-dimensional quantitative analysis of equipment-level impacts and shocks, it achieves comprehensive monitoring of the equipment room and improves the inspection efficiency of the equipment room through comprehensive analysis.

[0026] The joint construction of power supply topology and signal link topology provides a unified spatial description framework for system-level correlation analysis of equipment in the data center. On this basis, the time-series calculation of the overall broadcast operation index quantifies the comprehensive health status of the broadcast link at each sampling moment into a comparable numerical indicator, enabling the isolated impact of equipment status changes on broadcast tasks to be accurately separated and quantitatively assessed. Furthermore, by distinguishing between the actual degradation impact and potential failure impact of equipment, and using both to determine the level of hidden dangers, a closed-loop maintenance decision-making process from early warning to graded handling is ultimately formed. This achieves automatic identification, quantitative assessment, and prioritization of hidden dangers in data center equipment without the need for manual experience-based judgment, effectively improving the coverage of data center inspections and the scientific nature of operation and maintenance decisions.

[0027] Based on this, the feasibility of the solution and its adaptability to different equipment configurations are further enhanced by specifically constructing the topology model as a directed graph structure, decomposing the overall broadcast operation index into a progressive calculation of serial and parallel sub-links, and limiting the operation status index to the fitted values ​​of specific equipment operation parameters. Attached Figure Description

[0028] Figure 1 This is a schematic diagram of the process of an intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to the present invention. Figure 2 This is a schematic diagram of the structure of an intelligent inspection system for a broadcast television station computer room based on spatiotemporal analysis, according to the present invention. Figure 3 This is a schematic diagram of an electronic device structure according to the present invention. Detailed Implementation

[0029] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. The components of the embodiments of the present invention described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.

[0030] Example 1 like Figure 1 The method for intelligent inspection of broadcast television station computer rooms based on spatiotemporal analysis, as shown, specifically includes: S1. Establish a power supply topology model based on the power supply and distribution connection relationship between the equipment in the computer room, and establish a signal link topology model based on the signal transmission connection relationship between the equipment in the computer room; The equipment in the equipment room of a broadcasting and television station is closely related in two dimensions: power supply and signal. An anomaly in a single device often triggers a chain reaction through the power supply path or signal path. The joint construction of the power supply topology model and the signal link topology model can organize the dispersed equipment in the equipment room into a computable structured description according to their actual relationship in the power supply domain and the signal domain.

[0031] The power supply topology model outlines the power supply paths between mains power, diesel generators, ATS, distribution cabinets, UPS, and voltage stabilizers, and between transmitters and microwave equipment, identifying series, parallel, and redundant backup relationships within these paths to form a complete framework for describing power transmission. The signal link topology model, on the other hand, outlines the signal flow directions and primary / backup relationships between satellite receivers, microwave decoders, audio distributors, stream switchers, and transmitters, forming a framework for describing signal transmission. These two models together provide a foundation for subsequent system-level analysis of the impact of equipment status changes on broadcasting.

[0032] Specifically, the power supply topology model is a directed graph with power distribution equipment and working equipment as nodes and the power supply and distribution connection relationship between the equipment as directed edges; the signal link topology model is a directed graph with signal processing equipment and working equipment as nodes and the signal transmission connection relationship between the equipment as directed edges. After adopting the directed graph structure, the input and output directions of the power supply path and the direction of signal flow can be uniquely determined by the direction of the directed edges. The series and parallel relationships between different power supply paths or signal paths can be directly identified by the connection pattern between the nodes in the graph, so that the subsequent power supply status calculation and broadcast operation index calculation can be recursively performed on a unified graph structure.

[0033] S2. Obtain the operating status index of each device at multiple sampling times; A single-moment equipment operating status index can only reflect the instantaneous health level at that moment and cannot reveal the evolution trend of equipment performance over time. However, by continuously acquiring the operating status index at multiple sampling moments, the changes in equipment status are included in the observation scope of the time dimension, allowing the degradation trajectory of equipment performance to be continuously tracked, providing a data source for subsequent impact analysis based on time-series differences. At the same time, the multi-sampling-moment tracking method also allows the method to adapt to different degradation rates of different equipment—for slowly aging equipment, its gradual anomalies can be identified through long-term trends; for sudden failures, the jumps between adjacent moments can be captured in a timely manner.

[0034] In a preferred implementation, the equipment operating status index is obtained by fitting the equipment's operating parameters, specifically using a normalized weighted linear weighting method. For any equipment, the measured values ​​of its operating parameters are normalized to the [0,1] interval according to a preset normal operating range, and then linearly weighted and summed according to preset weights to obtain the equipment's operating status index at the current sampling time. In actual deployment, the upper and lower limits of the normal range of each operating parameter and the weight coefficients can be pre-calibrated by maintenance personnel based on the specific equipment model, factory parameters, and historical operating statistics in the computer room, and can be dynamically adjusted according to seasonal changes or equipment aging. The operating status indices of each equipment at multiple sampling times are structured and stored according to the equipment identifier and sampling timestamp to form time series data, which can be used for subsequent calculations of influence indices and impact levels.

[0035] The operating parameters include the transmitter's output power, VSWR, operating temperature, and at least one of the voltage, current, and frequency of the power supply and distribution equipment. These operating parameters are physical quantities that can be directly obtained in the daily monitoring of the computer room. They can be integrated into the calculation process of this method without the need for additional dedicated sensors, thus reducing deployment costs.

[0036] S3. Based on the power supply topology model, signal link topology model, and operating status index at each sampling time, calculate the power supply status of each working device at each sampling time, as well as the overall broadcast operating index. In the power supply domain, the power supply status of the working equipment is the fundamental input for subsequent broadcast operation index calculations. If the working equipment is not properly powered, its output status should be zero regardless of its own operation status index; otherwise, the overall broadcast operation index will be artificially inflated, masking the true broadcast risks. When calculating the status index at the input end of the power supply path, the maximum value is used to aggregate the parallel input sources. This approach reflects the actual working characteristics of the redundant power supply structure—as long as any one of the main input sources is working normally, the power supply path input end is in a powered state, without the need for multiple sources to supply power simultaneously. When calculating the power supply status of the working equipment, the aggregated result at the input end passes through each power supply and distribution device sequentially along the power supply path. The status indices of each series node are multiplied, and a status index of any node being zero will result in the final power supply status being zero. This is consistent with the physical law that a series node failure in an actual power supply line leads to a downstream power outage.

[0037] In the signal domain, the calculation of the overall broadcast operation index aggregates the individual state indices and power supply state indices of each device in the signal link according to their position and role in the link. Signal links differ from simple series connections; they also include various structural forms such as primary / backup parallel connections and signal source redundancy. Different aggregation methods are required for different structures. For parallel paths, the maximum value of the state indices of each branch is taken as the state index of that parallel sub-link. This reflects the redundancy characteristic of a parallel structure where signal output can be maintained as long as any primary branch is normal. For series paths, the product of the state indices of all series nodes is taken as the state index of that series sub-link. This reflects the transmission characteristic that any single-point failure in a series structure will lead to the interruption of the entire path. Decomposing the entire signal link into multiple series-parallel sub-link groups and then equating it to a large series progressive calculation method can not only meet the computational needs of complex link structures but also ensure that the calculation results accurately reflect the multi-redundancy, multi-path structural characteristics of the broadcast system and the differences in the contribution of each device. This lays the foundation for subsequent precise quantification of the impact of individual devices on the broadcast.

[0038] Furthermore, the calculation process involving the power supply status of the working device is as follows:

[0039]

[0040] in, Indicates equipment The usage status, This refers to the operating status index of each device along the power supply path. This is the status index of the power supply path input. This is the power supply status index for the working equipment.

[0041] The specific calculation steps for the overall broadcast operation index include: Based on the power supply status and operating status index of each working device node in the signal link topology model, calculate the output status index of each working device node; The signal link topology model is decomposed into series sub-links and parallel sub-links, and the state index of each sub-link is calculated separately. Treat all sub-links as equivalent to serial links and calculate the overall broadcast operation index; Specifically, for each working device node in the signal link topology model to output a signal normally, two conditions must be met simultaneously: the device itself must be in normal operating condition, and the device must be powered normally. Therefore, the output state index of a single working device node is given by the product of its power supply state index and its own operating state index, where any factor being zero indicates that the node has no signal output. Based on this, it is necessary to differentiate the paths with different structural forms in the signal link. This is because the parallel structure and the series structure have fundamentally different fault propagation characteristics—in the parallel structure, as long as any one of the main branches is working normally, broadcasting can be maintained; therefore, the state index of the parallel sub-link is the maximum value of the state indices of each branch. In the series structure, the signal flows through each node sequentially, and a failure of any node will cause signal interruption; therefore, the state index of the series sub-link is the product of the state indices of all nodes. The overall broadcast operation index is calculated by progressively aggregating the entire signal link according to the series-parallel relationship and finally equating it to a single large series link. This progressive calculation method allows the overall broadcast operation index to truly reflect the multi-redundancy and multi-path structural characteristics of the broadcast system, providing an accurate system-level benchmark for subsequent quantitative assessment of the impact of each device on broadcasting. Furthermore, for any working device node Its output state index is:

[0042] in This is the power supply status index for the working equipment. This is the operating status index of the equipment; The state index of the parallel sub-link is:

[0043] The state index of the serial sub-link is:

[0044] The overall broadcast performance index is:

[0045] in The state index of each sub-link, or equal to , or equal to .

[0046] S4. Based on the difference in the overall broadcast operation index before and after any equipment operation status change, determine the impact index of the equipment operation status change on the broadcast task; Because the operating status indices of multiple devices may change simultaneously, the direct difference between the overall broadcast operating index after the change of any one device and the overall broadcast operating index before the change is actually the superposition result of the changes in the overall broadcast operating index caused by the combined changes of multiple devices, and cannot be directly attributed to a single device. Therefore, when calculating the impact index of a certain device, it is necessary to update the operating status index of that device to the changed value, while freezing the operating status indices of all other devices to their values ​​before the change. This ensures that the difference between the recalculated overall broadcast operating index and the benchmark value originates entirely from the single-variable change of that device, thereby eliminating the coupling interference caused by the simultaneous changes of other devices. The above calculation is presented in the form of a ratio rather than an absolute difference, which makes the relative severity represented by the same absolute change comparable at different benchmark overall broadcast operating index levels. When the benchmark value... This indicates that the broadcast system is completely paralyzed, and at this point, changes to the equipment no longer have a measurable impact; therefore, a time limit is set. This is used to identify the extreme case. The impact index ranges from [-1, 1], where a positive value indicates that the change in equipment status has an optimizing effect on the broadcast task, and a negative value indicates a degrading effect.

[0047] As needed, for any device The formula for calculating the influence index is as follows:

[0048] in, For equipment The overall broadcast performance index before the change For equipment The overall broadcast performance index after the change, while the remaining equipment remains in the same operating state as before the change; when hour, .

[0049] S5. For any given device, determine the impact of the device failure on the broadcast task based on the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails. The impact index reflects the isolated impact of actual changes in equipment on broadcasting, representing a quantitative assessment of a past event. However, in actual operation and maintenance, personnel need to understand in advance the severe consequences of complete equipment failure on broadcasting, so as to prepare contingency plans before the equipment is completely damaged. Therefore, this method quantifies the potential damage ceiling of a single device to broadcasting tasks by assuming the failure of a single device (i.e., setting the device's operating status index to 0) and recalculating the overall broadcasting operating index. Other devices remain in their current actual state during this calculation, ensuring that the calculated impact reflects the true consequences of the device failure under the current system state—the impact of the same device failure differs under different system redundancy states (e.g., whether the backup transmitter is in hot or cold standby). The impact is expressed as a ratio representing the proportion of loss in the overall broadcasting operating index after equipment failure, ranging from [0,1]. The closer the value is to 1, the stronger the damage to broadcasting from the equipment failure, and the higher the maintenance priority. The impact index reflects the "actual degree of degradation," while the impact reflects the "potential damage ceiling." Both assess equipment risk from different dimensions, providing complementary information for subsequent hazard rating.

[0050] In addition, for any device The formula for calculating the impact intensity is:

[0051] in, For the current sampling time device The overall broadcast operation index For hypothetical devices The overall broadcast performance index when the equipment fails and other equipment remains in its current state. when = hour, 1.

[0052] S6. Determine the hazard level of each device based on its impact index and impact intensity, and output the maintenance strategy corresponding to the hazard level; Impact Index and Impact Severity assess equipment risk from two complementary dimensions: the Impact Index reveals the actual impact of current equipment degradation or optimization on broadcasting, while the Impact Severity reveals the upper limit of potential damage that equipment could cause if it were to completely fail. This method integrates these two dimensions into a unified five-level hazard classification standard, enabling maintenance personnel to uniformly prioritize and manage the risks of all equipment, avoiding situations where decisions rely on personal experience due to fragmented information or a lack of unified standards. The higher the hazard rating, the more urgent the corresponding response strategy—Level 1 hazards correspond to emergency handling, requiring immediate intervention to prevent impending broadcast accidents; Level 2 hazards correspond to rectification, requiring repair within a certain timeframe; Level 3 hazards correspond to key monitoring, requiring continuous tracking of their development; Level 4 hazards correspond to continuous observation, requiring only recording of their operational status; and no risk indicates that the equipment is currently safe and the impact of failure is controllable, requiring no action. This classification method ensures that the allocation of maintenance resources matches the equipment risk level, avoiding situations where low-risk equipment occupies too many maintenance resources while high-risk equipment is neglected.

[0053] Specifically, the hazard rating is divided as follows: when or At that time, it is classified as a Level 1 hazard, and an emergency response strategy is required. when or At that time, it was classified as a Level 2 hazard, and the corresponding rectification strategy was adopted; when and At that time, it was classified as a Level 3 hidden danger, corresponding to a key focus strategy; when and At that time, it was classified as a Level 4 hazard, corresponding to a continuous observation strategy; when and At that time, there is no risk.

[0054] Example 2 A smart inspection system for broadcast television station computer rooms based on spatiotemporal analysis, such as Figure 2 As shown, its architecture design follows the complete method flow described in Example 1, mapping the method steps into six functional modules. These modules are connected through standardized data interfaces. The core design idea of ​​this system is to extract the correlation analysis capability between power supply topology and signal link topology from manual experience and solidify it into the software system in a modular way. This allows different stations to adapt to the system without repeatedly developing algorithm logic during deployment; they only need to adjust the input parameters of the topology model according to the actual equipment configuration in the data center. Specifically, this includes: The model building module establishes a power supply topology model based on the power supply and distribution connections between equipment in the computer room, and a signal link topology model based on the signal transmission connections between equipment in the computer room. This module organizes device nodes and connections in the form of a directed graph. Nodes in the power supply topology model include two categories: power supply and distribution equipment and working equipment. Directed edges represent the flow of electrical energy from power supply and distribution equipment to working equipment. Nodes in the signal link topology model include two categories: signal processing equipment and working equipment. Directed edges represent the flow of signals from upstream equipment to downstream equipment. This module internally includes a device type identification submodule and a connection relationship parsing submodule. The former is responsible for classifying devices in the input device list according to their roles, while the latter is responsible for converting the input connection relationship data into edges in the graph structure. The final output is a directed graph data structure that can be directly traversed and computed by subsequent modules.

[0055] The data acquisition module is used to acquire the operating status index of each device at multiple sampling times. This module supports reading real-time monitoring data from the existing environmental monitoring system or equipment network management system in the computer room via standard industrial communication protocols. It also provides a historical data import interface, enabling the system to perform retrospective analysis using existing historical monitoring records.

[0056] The operating status index output by this module is stored in a structured manner according to the device identifier and sampling time, forming a two-dimensional data matrix of device-time, which provides standardized data input for subsequent spatial domain calculation steps.

[0057] The preliminary calculation module calculates the power supply status of each working device and the overall broadcast operation index at each sampling time, based on the power supply topology model, signal link topology model, and the operating status index at each sampling time. Internally, this module recursively calculates along the topology by traversing a directed graph. First, it independently calls the power supply domain calculation submodule for each sampling time, calculating the power supply status of each working device sequentially from the input end of each power supply path according to the power supply topology model. Then, it calls the signal domain calculation submodule, calculating the overall broadcast operation index by aggregating the results layer by layer according to the series and parallel structure of the signal link topology model. The sequence of overall broadcast operation indices output by this module forms the time-series data foundation for subsequent impact analysis.

[0058] The impact index calculation module determines the impact index of a device's operational status change on the broadcast task based on the difference between the overall broadcast operation index before and after the change. Internally, this module calculates independently for each device. For each target device, it first extracts the operational status index and the corresponding overall broadcast operation index at two points before and after the change from the data acquisition and preliminary calculation modules. Then, it recalculates the overall broadcast operation index under the condition that "other devices are frozen at their pre-change state." The recalculated result is then compared with the original baseline value to obtain the impact index. This strategy of calculating independently for each device while keeping the states of other devices constant is essentially an approximation of extracting the isolated impact of a single variable in a multivariate coupled system. A positive impact index indicates that the change in the device has an improving effect on the broadcast, while a negative value indicates a deteriorating effect, providing maintenance personnel with a scientific basis for judging whether a change in device status is acceptable.

[0059] The impact calculation module, for any given device, determines the impact of a device failure on the broadcast task based on the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device's failure. This module shares the same set of interface definitions as the impact index calculation module, but internally employs a "hypothetical failure" strategy rather than an "actual change" strategy. Specifically, the target device's operating status index is artificially set to 0, while keeping the actual status of other devices unchanged at the current moment. The overall broadcast operation index is then recalculated, and the difference between the recalculated result and the current actual overall broadcast operation index is normalized to obtain the impact. The impact output by this module reflects the potential upper limit of damage caused by the device failure under the current system state, forming a complementary risk assessment dimension to the impact index.

[0060] The hazard assessment module determines the hazard level of each device based on its impact index and impact severity, and outputs a corresponding maintenance strategy. Internally, this module implements a five-level hazard assessment engine, which comprehensively rates each device based on the range of impact index and impact severity values. The maintenance strategies output by the module are presented in the form of a device list. Maintenance personnel can directly view the hazard level ranking of all devices and corresponding handling suggestions through a visual interface, thereby prioritizing the handling of high-risk devices with limited human resources and shifting from a reactive to a proactive maintenance model.

[0061] Example 3 As attached Figure 3 An electronic device shown includes: Processor, memory, communication interface; The memory is used to store the executable instructions of the processor; The processor is configured to execute the aforementioned intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis by executing the executable instructions.

[0062] A readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the above-mentioned intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis.

[0063] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A method for intelligent inspection of broadcast television station computer rooms based on spatiotemporal analysis, characterized in that, Specifically, it includes: Establish a power supply topology model based on the power supply and distribution connection relationship between the equipment in the computer room, and establish a signal link topology model based on the signal transmission connection relationship between the equipment in the computer room. Obtain the operating status index of each device at multiple sampling times; Based on the power supply topology model, signal link topology model, and operating status index at each sampling time, calculate the power supply status of each working device at each sampling time, as well as the overall broadcast operating index. Based on the difference in the overall broadcast operation index before and after a change in the operating status of any device, determine the impact index of the change in the operating status of the device on the broadcast task; For any given device, the impact of the device failure on the broadcast task is determined by the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails. The hazard level of each device is determined based on its impact index and impact intensity, and a maintenance strategy corresponding to the hazard level is output.

2. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 1, characterized in that, The power supply topology model is a directed graph with power supply and distribution equipment and working equipment as nodes and the power supply and distribution connection relationship between equipment as directed edges; The signal link topology model is a directed graph with signal processing equipment and working equipment as nodes and the signal transmission connection relationship between the devices as directed edges.

3. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 1, characterized in that, The calculation process involving the power supply status of the working equipment is as follows: in, Indicates device The usage status, This refers to the operating status index of each device along the power supply path. This is the status index of the power supply path input. This is the power supply status index for the working equipment.

4. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 1, characterized in that, The specific calculation steps for the overall broadcast operation index include: Based on the power supply status and operating status index of each working device node in the signal link topology model, calculate the output status index of each working device node; The signal link topology model is decomposed into series sub-links and parallel sub-links, and the state index of each sub-link is calculated separately. Treat all sub-links as equivalent to serial links and calculate the overall broadcast operation index.

5. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 4, characterized in that, For any working device node Its output state index is: in This is the power supply status index for the working equipment. This is the operating status index of the equipment; The state index of the parallel sub-link is: The state index of the serial sub-link is: The overall broadcast performance index is: in This represents the state index of each sub-link.

6. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 5, characterized in that, For any device The formula for calculating the influence index is as follows: in, For equipment The overall broadcast performance index before the change For equipment The overall broadcast performance index after the change, while the remaining equipment remains in the same operating state as before the change; when hour, .

7. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 6, characterized in that, For any device The formula for calculating the impact intensity is: in, For the current sampling time device The overall broadcast operation index For hypothetical devices The overall broadcast performance index when the equipment fails and other equipment remains in its current state. when = hour, 1.

8. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 7, characterized in that, The hazard rating is classified in the following manner: when or At that time, it is classified as a Level 1 hazard, and an emergency response strategy is required. when or At that time, it was classified as a Level 2 hazard, and the corresponding rectification strategy was adopted; when and At that time, it was classified as a Level 3 hidden danger, corresponding to a key focus strategy; when and At that time, it was classified as a Level 4 hazard, corresponding to a continuous observation strategy; when and At that time, there is no risk.

9. The intelligent inspection method for broadcast television station computer rooms based on spatiotemporal analysis according to claim 1, characterized in that, The equipment operating status index is obtained by fitting the equipment's operating parameters, which include the transmitter's output power, VSWR, operating temperature, and at least one of the power supply and distribution equipment's voltage, current, and frequency.

10. A smart inspection system for broadcast television station computer rooms based on spatiotemporal analysis, characterized in that, include: The model building module establishes a power supply topology model based on the power supply and distribution connection relationship between the equipment in the computer room, and establishes a signal link topology model based on the signal transmission connection relationship between the equipment in the computer room. The data acquisition module is used to acquire the operating status index of each device at multiple sampling times; The preliminary calculation module calculates the power supply status of each working device at each sampling time, as well as the overall broadcast operation index, based on the power supply topology model, signal link topology model, and the operating status index at each sampling time. The impact index calculation module determines the impact index of the change in the operating status of any device on the broadcast task based on the difference between the overall broadcast operation index before and after the change in the operating status of any device. The impact calculation module determines the impact of a device failure on the broadcast task based on the difference between the current overall broadcast operation index and the recalculated overall broadcast operation index after the device fails. The hazard assessment module determines the hazard level of each device based on its impact index and impact intensity, and outputs the maintenance strategy corresponding to the hazard level.