Wind speed detection device for mine laneway ventilation
By designing an adjustable wind speed detection device, the problem of fixed detection height in mine shaft ventilation was solved, realizing flexible adjustment and cleanliness of wind speed detection, and improving the convenience and accuracy of detection.
Patent Information
- Application Number
- CN202420965583.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-07
- Publication Date
- 2024-12-10
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing mine shaft ventilation velocity detection devices have a fixed detection height, which is difficult to adjust quickly, resulting in time-consuming and labor-intensive operation and a lack of timeliness.
A wind speed detection device was designed, comprising a cross plate, a cross beam, a slide rail, a micro motor, gears, and an anemometer. The micro motor drives the gears to rotate, thereby adjusting the position of the anemometer. The device is equipped with electric rollers and limit rails, allowing for multi-directional adjustment within the mine. A blower and a fan are also included for cleaning, ensuring the flexibility and cleanliness of wind speed detection.
The height and position of the wind speed detection device can be flexibly adjusted, improving the timeliness and convenience of detection. The cleaning mechanism ensures the cleanliness of the anemometer, thereby improving the accuracy and reliability of the detection.
Smart Images

Figure CN222145036U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of wind speed detection devices, in particular to a wind speed detection device for mine shaft and tunnel ventilation. Background Art
[0002] A mine specifically refers to an area rich in valuable minerals such as mineral materials and oil, but they are often buried deep inside a mountain or underground and need to be excavated before they can be mined. Because the mines are deep and long, for safety reasons, it is necessary to monitor the wind speed and direction in different areas of the mines in real time. Wind speeds that are too fast or too slow are not good, and should be stabilized at a certain value to ensure smooth airflow in the surrounding working environment.
[0003] In the past, wind speed detection devices were often fixed directly on the top of the mine, and the length of accessories such as brackets was mostly determined to be unchangeable. If the detection height changed, it would be difficult to make changes in time, requiring workers to manually operate in time, which was time-consuming and labor-intensive, and lacked timeliness.
[0004] Now, a new type of wind speed detection device for mine shaft ventilation is proposed to solve the above problems. Utility Model Content
[0005] The utility model aims to provide a wind speed detection device for mine shaft ventilation to solve the problem of fixed detection height in the above background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a wind speed detection device for mine shaft ventilation, comprising a cross plate and a cross beam, a slideway is provided between the two sides of the front end of the cross beam, and the cross plate is movably inserted in the slideway, a bracket is fixed at the central groove at the front end of the cross plate, and a micro motor is installed on the left side of the bracket, a mounting plate is movably connected between the two sides inside the bracket, and a motor is installed at the upper right corner inside the mounting plate, a side gear is movably connected to the right side of the top of the mounting plate, and a main gear is movably connected to the left side of the top of the mounting plate, a screw rod is longitudinally connected between the main gear and the mounting plate, and a sleeve is sleeved at the bottom of the screw rod, an anemometer is installed at the bottom of the sleeve, a guide rod is welded at the front end above the screw rod, and a sleeve block is welded at the upper left side of the front end of the mounting plate.
[0007] Preferably, the motor can control the side gear to rotate in situ, and the side gear is meshed and connected to the right side of the main gear.
[0008] Preferably, the surface texture of the screw rod can mesh with the internal thread groove of the main gear, and the guide rod is embedded in the sleeve block.
[0009] Preferably, the micro motor can control the mounting plate to rotate back and forth between the brackets, and the anemometer can rotate in situ below the casing.
[0010] Preferably, a frame is welded to the rear of the outside of both sides of the horizontal plate, and an electric roller is installed in the frame, a limited position rail is opened between the two sides of the bottom of the slide, and suspension rods are welded on both sides of the top of the beam, and a positioning block is sleeved on the outside of the suspension rod, the surface of the positioning block is meshed with a second bolt, and one side of the positioning block is meshed with a first bolt.
[0011] Preferably, the bottom of the electric roller is embedded in the limiting rail, and the electric roller can slide left and right along the inner wall of the limiting rail.
[0012] Preferably, a shell is fixedly connected to the center of the top of the cross beam, and an air hole is opened in the upper left corner of the rear of the shell, a blower is installed on the left side of the top of the outer shell, and a fan is installed in the upper right corner of the rear of the shell, a box body is welded to the right side of the top of the shell, and air-permeable nets are installed inside both sides of the box body, a cover plate is inserted above the box body, and a tube body is fixedly inserted between the top of the cover plate and the air inlet of the fan, and a screen frame is welded to the bottom of the cover plate.
[0013] Preferably, the screen frame is placed vertically in the box, and the air-permeable net is symmetrically fixed in the inner walls on both sides of the box.
[0014] Compared with the prior art, the utility model has the following beneficial effects: the wind speed detection device for mine shaft ventilation not only realizes the adjustment of the height of the detection device and the change of the horizontal position of the detection device, but also realizes the cleaning of the anemometer;
[0015] (1) An anemometer is installed at the bottom of the casing. After the motor is started, the side gear is rotated to turn the main gear on the left. Since the guide rod is embedded in the casing block, when the main gear rotates to engage the screw rod, it can pass through the circular notch of the mounting plate and press down the screw rod with the anemometer. The anemometer is fixed to the bottom of the screw rod by means of the casing. The device is fixed on the inner wall of the mine in advance. The real-time wind speed in the tunnel can be evaluated by the rotation speed of the electronic anemometer, thereby achieving the purpose of detecting wind speeds at different high and low positions;
[0016] (2) By opening a limit rail between the two sides of the bottom of the slideway, adjusting the position of the positioning block along the suspension rod in advance, locking the suspension rod and the positioning block with the second bolt, and fixing the crossbeam between the two sides of the mine tunnel with the first bolt, the electric rollers on the two side frames behind the cross plate are started to slide horizontally along the embedded limit rails, thereby realizing the multi-directional adjustment of the detection device. Even if there are holes on the inner wall of the pit for air supply, detection can be carried out close to this place;
[0017] (3) A box is welded on the right side of the top of the shell, and the mounting plate is flipped by a micro motor on the left side of the bracket. The anemometer and other objects are screwed into the shell at the center of the beam, and then the blower is started to inject air from the air hole, and the air is then extracted by the fan on the right side, forcing the anemometer to rotate inside the shell. The dirt on its surface is blown away by the blower and injected into the box from the pipe body through the suction of the fan. The screen frame at the bottom of the closed cover is also embedded in the box to filter garbage, and the excess air is discharged from the air permeable net on the side. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a front view cross-sectional structural schematic diagram of the utility model;
[0019] Figure 2 This is a schematic diagram of the front cross-sectional structure of the mounting plate of the utility model;
[0020] Figure 3 For the utility model Figure 1 A partial cross-section at the center is an enlarged structural diagram;
[0021] Figure 4 It is a schematic diagram of the front cross-sectional structure of the box body of the present utility model.
[0022] In the figure: 1. horizontal plate; 2. horizontal beam; 3. positioning block; 4. first bolt; 5. second bolt; 6. suspension rod; 7. slideway; 8. limit rail; 9. anemometer; 10. casing; 11. bracket; 12. shell; 13. fan; 14. box body; 15. tube body; 16. breathable net; 17. blower; 18. air hole; 19. micro motor; 20. mounting plate; 21. motor; 22. side gear; 23. sleeve block; 24. guide rod; 25. screw rod; 26. frame; 27. electric roller; 28. screen frame; 29. main gear; 30. cover plate. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] Example 1: Please refer to Figure 1-4A wind speed detection device for mine shaft ventilation comprises a horizontal plate 1 and a horizontal beam 2, a slideway 7 is provided between the two sides of the front end of the horizontal beam 2, and the horizontal plate 1 is movably inserted in the slideway 7, a bracket 11 is fixed at the central groove of the front end of the horizontal plate 1, and a micro motor 19 is installed on the left side of the bracket 11, a mounting plate 20 is movably connected between the two sides inside the bracket 11, and a motor 21 is installed at the upper right corner inside the mounting plate 20, a side gear 22 is movably connected to the right side of the top of the mounting plate 20, a main gear 29 is movably connected to the left side of the top of the mounting plate 20, a screw rod 25 is longitudinally connected between the main gear 29 and the mounting plate 20, and a sleeve 10 is sleeved at the bottom of the screw rod 25, an anemometer 9 is installed at the bottom of the sleeve 10, a guide rod 24 is welded at the front end above the screw rod 25, and a sleeve block 23 is welded at the upper left of the front end of the mounting plate 20;
[0025] The motor 21 can control the side gear 22 to rotate in place, the side gear 22 is meshed and connected to the right side of the main gear 29, the surface texture of the screw rod 25 can mesh with the internal thread groove of the main gear 29, the guide rod 24 is embedded in the sleeve block 23, the micro motor 19 can control the mounting plate 20 to rotate back and forth between the brackets 11, and the anemometer 9 can rotate in place below the sleeve 10;
[0026] Specifically, Figure 1 and Figure 2 As shown, after starting the motor 21, the side gear 22 is rotated, thereby turning the main gear 29 on the left side. Since the guide rod 24 is embedded in the sleeve block 23, when the main gear 29 rotates to engage the screw rod 25, it can pass through the circular groove of the mounting plate 20 and press down the screw rod 25 with the anemometer 9. The anemometer 9 is fixed to the bottom of the screw rod 25 by means of the sleeve 10. The device is fixed on the inner wall of the mine in advance, and the real-time wind speed in the tunnel can be evaluated by the electronic anemometer 9 The machine selects the rotation speed.
[0027] Embodiment 2: A frame 26 is welded to the rear of both sides of the outside of the horizontal plate 1, and an electric roller 27 is installed in the frame 26. A limit rail 8 is provided between the two sides of the bottom of the slideway 7. A suspension rod 6 is welded to both sides of the top of the horizontal beam 2, and a positioning block 3 is sleeved on the outside of the suspension rod 6. The surface of the positioning block 3 is meshed with a second bolt 5, and one side of the positioning block 3 is meshed with a first bolt 4. The bottom of the electric roller 27 is embedded in the limit rail 8, and the electric roller 27 can slide left and right along the inner wall of the limit rail 8;
[0028] Specifically, Figure 1 and Figure 3 As shown, the position of the positioning block 3 is pre-adjusted along the suspension rod 6, and after the suspension rod 6 and the positioning block 3 are locked with the second bolt 5, the first bolt 4 is used to fix the crossbeam 2 between the two sides of the mine hole, and the electric rollers 27 on the frames 26 on both sides of the rear of the cross plate 1 are started to slide horizontally along the embedded limit rails 8, thereby realizing the multi-directional adjustment of the detection device.
[0029] Embodiment 3: A shell 12 is fixedly connected to the center of the top of the crossbeam 2, and an air hole 18 is opened at the upper left corner of the rear of the shell 12, a blower 17 is installed on the left side of the top of the shell 12, a fan 13 is installed at the upper right corner of the rear of the shell 12, a box 14 is welded to the right side of the top of the shell 12, and air-permeable nets 16 are installed inside both sides of the box 14, a cover plate 30 is inserted above the box 14, and a pipe body 15 is fixedly inserted between the top of the cover plate 30 and the air inlet of the fan 13, a screen frame 28 is welded to the bottom of the cover plate 30, the screen frame 28 is vertically placed in the box 14, and the air-permeable nets 16 are symmetrically fixed to the inner walls on both sides of the box 14;
[0030] Specifically, Figure 1 and Figure 4 As shown, the mounting plate 20 is flipped by the micro motor 19 on the left side of the bracket 11, and the anemometer 9 and other objects are screwed into the housing 12 at the center of the beam 2, and then the blower 17 is started to inject airflow from the air hole 18, and the airflow is then extracted by the fan 13 on the right side, forcing the anemometer 9 to rotate inside the housing 12, and the dirt on its surface is blown away by the blower 17, and injected into the box body 14 from the tube body 15 through the suction of the fan 13, and the screen frame 28 at the bottom of the closing cover 30 is also embedded in the box body 14, and the excess airflow is discharged from the air permeable net 16 on the side, and the garbage stays in the screen frame 28.
[0031] Working principle: When the utility model is used, the position of the positioning block 3 is adjusted along the suspension rod 6 in advance, and after the suspension rod 6 and the positioning block 3 are locked with the second bolt 5, the first bolt 4 is used to fix the crossbeam 2 between the two sides of the mine hole, and the electric rollers 27 on the two side frames 26 behind the cross plate 1 are started to slide horizontally along the embedded limit rails 8, and then the side gear 22 is rotated after the motor 21 is started, thereby turning the main gear 29 on the left side. Because the guide rod 24 is embedded in the sleeve block 23, it can pass through the circular notch of the mounting plate 20 when the main gear 29 rotates to engage the screw rod 25, and press down the screw rod 25 with the anemometer 9. The anemometer 9 is installed and fixed at the bottom of the screw rod 25 by means of the sleeve 10. The device is fixed on the inner wall of the mine cave, and can evaluate the real-time wind speed in the tunnel by selecting the rotation speed of the electronic anemometer 9. After the end, the mounting plate 20 is flipped by the micro motor 19 on the left side of the bracket 11, and the anemometer 9 and other objects are screwed into the shell 12 at the center of the beam 2, and then the blower 17 is started to inject airflow from the air hole 18, and the airflow is then extracted by the fan 13 on the right, forcing the anemometer 9 to rotate inside the shell 12, and the dirt on its surface is blown away by the blower 17, and injected into the box body 14 from the tube body 15 through the suction of the fan 13, and the screen frame 28 at the bottom of the closed cover plate 30 is also embedded in the box body 14, and the excess airflow is discharged from the air permeable net 16 on the side, and the garbage stays in the screen frame 28.
[0032] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
Claims
1. A wind speed detection device for mine shaft ventilation, comprising a horizontal plate (1) and a horizontal beam (2), characterized in that: A slideway (7) is provided between the two sides of the front end of the crossbeam (2), and a cross plate (1) is movably inserted in the slideway (7), a bracket (11) is fixed to the central groove of the front end of the cross plate (1), and a micro motor (19) is installed on the left side of the bracket (11), a mounting plate (20) is movably connected between the two sides inside the bracket (11), and a motor (21) is installed at the upper right corner of the mounting plate (20), and the right side of the top of the mounting plate (20) is movably connected to the motor (21). A side gear (22) is connected, a main gear (29) is movably connected to the left side of the top of the mounting plate (20), a screw rod (25) is longitudinally connected between the main gear (29) and the mounting plate (20), and a sleeve (10) is sleeved at the bottom of the screw rod (25), an anemometer (9) is installed at the bottom of the sleeve (10), a guide rod (24) is welded to the front end above the screw rod (25), and a sleeve block (23) is welded to the upper left of the front end of the mounting plate (20).
2. A wind speed detection device for mine shaft ventilation according to claim 1, characterized in that: The motor (21) can control the side gear (22) to rotate in situ, and the side gear (22) is meshed and connected to the right side of the main gear (29).
3. A wind speed detection device for mine shaft ventilation according to claim 1, characterized in that: The surface texture of the screw rod (25) can mesh with the internal thread groove of the main gear (29), and the guide rod (24) is embedded in the sleeve block (23).
4. A wind speed detection device for mine shaft ventilation according to claim 1, characterized in that: The micro motor (19) can control the mounting plate (20) to rotate forward and backward between the brackets (11), and the anemometer (9) can rotate in situ below the sleeve (10).
5. A wind speed detection device for mine shaft ventilation according to claim 1, characterized in that: A frame (26) is welded to the rear of both sides of the outside of the horizontal plate (1), and an electric roller (27) is installed in the frame (26). A limit rail (8) is provided between the two sides of the bottom of the slideway (7). A suspension rod (6) is welded to both sides of the top of the horizontal beam (2), and a positioning block (3) is sleeved on the outside of the suspension rod (6). The surface of the positioning block (3) is meshed with a second bolt (5), and one side of the positioning block (3) is meshed with a first bolt (4).
6. A wind speed detection device for mine shaft ventilation according to claim 5, characterized in that: The bottom of the electric roller (27) is embedded in the limiting rail (8), and the electric roller (27) can slide left and right along the inner wall of the limiting rail (8).
7. A wind speed detection device for mine shaft ventilation according to claim 1, characterized in that: A shell (12) is fixedly connected to the center of the top of the crossbeam (2), and an air hole (18) is opened at the upper left corner of the rear of the shell (12); a blower (17) is installed on the left side of the top of the shell (12), and a fan (13) is installed at the upper right corner of the rear of the shell (12); a box (14) is welded to the right side of the top of the shell (12), and air-permeable nets (16) are installed inside both sides of the box (14); a cover plate (30) is inserted above the box (14), and a pipe body (15) is fixedly inserted between the top of the cover plate (30) and the air inlet of the fan (13); and a screen frame (28) is welded to the bottom of the cover plate (30).
8. A wind speed detection device for mine shaft ventilation according to claim 7, characterized in that: The screen frame (28) is placed vertically in the box body (14), and the air-permeable net (16) is symmetrically fixed in the inner walls on both sides of the box body (14).