Double-box-body independent control high-temperature test box

Through the design of the high-temperature test chamber independently controlled by the dual-box, the distribution cabinet is unified in control and circulation air duct to maintain the temperature stability, which solves the problems of large area, complex wiring and uneven temperature in traditional high-temperature test chambers, and achieves a compact layout. Simplify wiring and improve test accuracy.

CN222152066UActive Publication Date: 2024-12-13GUANG ZHOU CLIMATE EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420216094.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-12-13
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

Traditional high-temperature test chambers cover a large area, and the wiring of multiple test chambers is complex, which increases the difficulty of operation and the risk of failure, and uneven temperatures lead to test errors.

Method used

Design a dual-box independent high-temperature test chamber, and the two test chambers are controlled uniformly through the distribution cabinet, with built-in circulating air duct and driving components to reduce wiring complexity, and maintain the temperature in the test chamber through the heater and circulating air duct. .

Benefits of technology

Reduces space occupation, simplifies wiring and wiring, achieves independent control of each test chamber, reduces energy waste and temperature fluctuations, and improves the accuracy and safety of the test.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222152066U_ABST
    Figure CN222152066U_ABST
Patent Text Reader

Abstract

The utility model discloses a double-box independent control high-temperature test box, which comprises a first test box, a second test box and a power distribution cabinet, the first test box, the second test box and the power distribution cabinet are sequentially connected and arranged side by side, a driving assembly and a heater are arranged in each of the first test box and the second test box, and a controller is arranged on the power distribution cabinet. And the driving assembly and the heater are electrically connected with the controller. Through the design, the occupied area is reduced, the layout of equipment is more compact, the first test box and the second test box are controlled by the same power distribution cabinet, and the connection and wiring work between the first test box and the second test box is simplified; secondly, each test box is internally provided with a driving assembly and a heater, the power distribution cabinet can control the driving assembly and the heater in each test box to achieve independent control, each test box can be independently heated according to needs, and energy waste is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of test boxes, and more specifically to a high-temperature test box with double boxes and independent control. Background Art

[0002] High temperature test chamber is one of the quality testing equipment for industrial products and materials. Its working principle is mainly to detect the performance of products or materials by controlling temperature and air humidity. High temperature test chamber is suitable for the adaptability test of electrical, electronic, instrumentation and other products, parts and materials during storage, transportation and use under high temperature and hot and humid alternating environment; it is a reliability test equipment for various electronic, electrical, electrical, plastic and other raw materials and devices to conduct heat resistance, moisture resistance, dryness resistance test and quality control engineering, especially suitable for high temperature resistance and hot and humid cycle test of products such as optical fiber, LED, crystal, inductor, PCB, battery, computer, mobile phone, etc.

[0003] Traditional single high temperature test chambers occupy a large area. When multiple products need to be tested at the same time, multiple high temperature test chambers need to be purchased, which further increases the floor space and increases the space requirements. This not only increases the cost of use, but also may limit the scale and efficiency of the test in an environment with limited space. Secondly, when multiple high temperature test chambers are used together, wiring becomes a complex problem. In traditional single high temperature test chambers, each test chamber has its own independent control system and circuit. Each test chamber needs to be connected to power supply, sensor, control circuit, etc. When multiple test chambers work at the same time, various circuits are intertwined, which is easy to cause confusion and errors. This not only increases the difficulty and pressure of the operator's work, but also increases the risk of equipment failure or safety accidents caused by incorrect wiring. Therefore, operators need to have professional electrical knowledge to ensure the correct connection of various sensors, power supplies, control circuits, etc. In addition, the wiring and management of multiple high temperature test chambers also increase the difficulty of maintenance and troubleshooting. Utility Model Content

[0004] In order to overcome the deficiencies of the prior art, the utility model provides a double-box independently controlled high-temperature test box, which greatly reduces the space occupied and makes wiring convenient and quick.

[0005] The technical solution of the utility model is as follows: a double-box independently controlled high-temperature test box, including a first test box, a second test box and a distribution cabinet, the first test box, the second test box and the distribution cabinet are connected in sequence and arranged side by side, the first test box and the second test box are both provided with a drive component and a heater, the distribution cabinet is provided with a controller, and the drive component and the heater are both electrically connected to the controller.

[0006] Furthermore, the first test box and the second test box each include a first box body and a second box body, the first box body and the second box body are nested, and a circulating air duct is formed in the gap between the first box body and the second box body, the driving assembly and the heater are both arranged in the circulating air duct, the interior of the second box body is hollow to form a test cavity for placing samples, and the opposite side walls of the second box body are provided with ventilation holes to connect the test cavity and the circulating air duct.

[0007] Furthermore, the driving assembly includes an impeller and a volute, the impeller is arranged in the volute, and the volute is arranged on the inner top surface of the first casing.

[0008] Furthermore, a first exhaust fan and a first circulation fan are disposed on the top of the first test box and the top of the second test box, an exhaust duct of the first exhaust fan is connected to the test chamber, and the first circulation fan is connected to the impeller.

[0009] Furthermore, the front ends of the first test box and the second test box are both provided with double doors, the double doors include a first box door and a second box door, and the first box door and the second box door are symmetrically arranged.

[0010] Furthermore, the first door and the second door are both provided with an observation window in the form of a long strip, and the observation window is used to observe the state of the sample in the test chamber.

[0011] Furthermore, the first door and the second door each include an outer door panel, an inner door panel and a door lock, the inner side of the outer door panel is fixedly connected to the inner door panel, the outer side of the outer door panel is provided with a handle, and the door lock is nested on the outer door panel and the inner door panel.

[0012] Furthermore, the first test box and the second test box are both connected to the double door via hinges.

[0013] Furthermore, the bottom of the first test box and the bottom of the second test box are both provided with moving wheels.

[0014] The utility model according to the above scheme has the following beneficial effects: a double-box independently controlled high-temperature test box, including a first test box, a second test box and a power distribution cabinet, the first test box, the second test box and the power distribution cabinet are connected in sequence and arranged side by side, the first test box and the second test box are both provided with a drive component and a heater, the power distribution cabinet is provided with a controller, and the drive component and the heater are both electrically connected to the controller. This design not only reduces the floor space, but also makes the layout of the equipment more compact, the first test box and the second test box are controlled by the same power distribution cabinet, simplifying the connection and wiring work between the first test box and the second test box; secondly, each test box is provided with a drive component and a heater, the power distribution cabinet can control the drive component and the heater in each test box separately to achieve independent control, and each test box can be heated separately as needed, avoiding energy waste. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0016] Figure 1 It is a three-dimensional structural schematic diagram of a double-box independently controlled high-temperature test box in an embodiment of the utility model;

[0017] Figure 2 This is a schematic diagram of the internal structure of a double-box independently controlled high-temperature test box in an embodiment of the utility model;

[0018] Figure 3 The figure is a schematic diagram of the internal wind direction circulation flow of a double-box independently controlled high temperature test box in an embodiment of the utility model.

[0019] In the figure, 1. first test box; 2. second test box; 3. distribution cabinet; 31. controller; 41. drive assembly; 42. heater; 51. first box body; 52. second box body; 521. test chamber; 61. first exhaust fan; 62. first circulation fan; 7. double door; 71. first box door; 72. second box door; 8. observation window; 9. moving wheel. DETAILED DESCRIPTION

[0020] The following detailed description and drawings of the embodiments of the present invention are used to illustrate the principle of the present invention, but cannot be used to limit the scope of the present invention, that is, the present invention is not limited to the embodiments described.

[0021] In the description of the present invention, it should be noted that, unless otherwise specified, "multiple" means two or more than two; the terms "upper", "lower", "left", "right", "inner", "outer", etc., indicating directions or positional relationships, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", etc., are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0022] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0023] In order to better understand the present invention, the present invention is further described below in conjunction with the accompanying drawings and embodiments:

[0024] See also Figure 1 to Figure 3 As shown, the embodiment of the utility model provides a double-box independently controlled high-temperature test box, including a first test box 1, a second test box 2 and a power distribution cabinet 3. The first test box 1, the second test box 2 and the power distribution cabinet 3 are connected in sequence and arranged side by side. The first test box 1 and the second test box 2 are both provided with a drive component 41 and a heater 42. The power distribution cabinet 3 is provided with a controller 31. The drive component 41 and the heater 42 are both electrically connected to the controller 31. This design not only reduces the floor space, but also makes the layout of the equipment more compact. The first test box 1 and the second test box 2 are controlled by the same power distribution cabinet 3, which simplifies the connection and wiring work between the first test box 1 and the second test box 2. Secondly, each test box is provided with a drive component 41 and a heater 42. The power distribution cabinet 3 can control the drive component 41 and the heater 42 in each test box to achieve independent control. Each test box can be heated separately as needed, avoiding energy waste.

[0025] The existing test box generally has a heating element installed in the test chamber 521 of the test box, and the air in the test chamber 521 is heated by the heating element. Such a design easily causes the temperature in the test chamber 521 to gradually decrease from the heating element to the surrounding areas, making it difficult to ensure the consistency of the temperature of each area in the test chamber 521, and easily causing large temperature fluctuations in the test chamber 521.

[0026] Based on the above problems, this embodiment also makes the following improvements, specifically:

[0027] The first test box 1 and the second test box 2 both include a first box 51 and a second box 52, the first box 51 and the second box 52 are nested, and a circulating air duct is formed in the gap between the first box 51 and the second box 52, the driving component 41 and the heater 42 are both arranged in the circulating air duct, the second box 52 is hollow inside to form a test chamber 521 for placing samples, and the two opposite side walls of the second box 52 are both provided with vents to connect the test chamber 521 and the circulating air duct. Specifically, the heater 42 is used to heat the air in the circulating air duct, and the driving component 41 drives the air heated by the heater 42 to flow in the circulating air duct and the test chamber 521 of the second box 52, so that the hot air circulates, thereby reducing the temperature fluctuation in the test chamber 521, helping to maintain the temperature stability in the test chamber 521, and avoiding the test error caused by temperature fluctuation; secondly, the circulation of hot air in the test chamber 521 helps to ensure that the temperature of each part in the test chamber 521 is uniform, so as to obtain more accurate and reliable test results.

[0028] Preferably, the driving assembly 41 includes an impeller and a volute, the impeller is arranged in the volute, and the volute is arranged on the inner top surface of the first box body 51. Specifically, the impeller is arranged in the volute, which can effectively drive the air circulation; the volute guides the airflow to flow along a specific path, enhances the fluidity of the air, ensures that the air circulation in the test chamber 521 is smoother and more uniform, reduces the safety hazards caused by air stagnation or vortex, and improves the safety of the operation of the high temperature test box with independent control of the double boxes.

[0029] Preferably, a first exhaust fan 61 and a first circulation fan 62 are disposed on the top of the first test box 1 and the top of the second test box 2. The exhaust duct of the first exhaust fan 61 is connected to the test chamber 521, and the first circulation fan 62 is connected to the impeller.

[0030] Preferably, the front ends of the first test box 1 and the second test box 2 are both provided with double doors 7, and the double doors 7 include a first door 71 and a second door 72, and the first door 71 and the second door 72 are symmetrically arranged. Specifically, the first door 71 and the second door 72 are both provided with an observation window 8 in the shape of a long strip, and the observation window 8 is used to observe the state of the sample in the test chamber 521. The first door 71 and the second door 72 each include an outer door panel, an inner door panel and a door lock, the inner side of the outer door panel is fixedly connected to the inner door panel, the outer side of the outer door panel is provided with a handle, and the door lock is nested on the outer door panel and the inner door panel, and the first test box 1 and the second test box 2 are both connected to the double doors 7 by hinges.

[0031] Preferably, the bottom of the first test box 1 and the bottom of the second test box 2 are both provided with moving wheels 9. Specifically, the moving wheels 9 enable the dual-box independently controlled high-temperature test box to be easily moved on a flat ground, which provides convenience for the user when carrying, moving or rearranging the dual-box independently controlled high-temperature test box, thereby improving work efficiency.

[0032] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all these improvements and changes should fall within the scope of protection of the claims attached to the utility model.

[0033] The above is an exemplary description of the utility model patent in conjunction with the accompanying drawings. It is obvious that the implementation of the utility model patent is not limited to the above-mentioned method. As long as various improvements are made by adopting the method concept and technical solution of the utility model patent, or the concept and technical solution of the utility model patent are directly applied to other occasions without improvement, they are all within the protection scope of the utility model.

Claims

1. A dual-chamber independently controlled high temperature test chamber, characterized in that: include: A first test box (1), a second test box (2) and a power distribution cabinet (3), wherein the first test box (1), the second test box (2) and the power distribution cabinet (3) are connected in sequence and arranged side by side, wherein a drive component (41) and a heater (42) are arranged in the first test box (1) and the second test box (2), and a controller (31) is arranged on the power distribution cabinet (3), and the drive component (41) and the heater (42) are electrically connected to the controller (31).

2. A dual-chamber independently controlled high temperature test chamber as claimed in claim 1, characterized in that: The first test box (1) and the second test box (2) both comprise a first box body (51) and a second box body (52); the first box body (51) and the second box body (52) are nested, and a circulating air duct is formed in the gap between the first box body (51) and the second box body (52); the driving component (41) and the heater (42) are both arranged in the circulating air duct; the interior of the second box body (52) is hollow to form a test cavity (521) for placing a sample; and opposite side walls of the second box body (52) are both provided with ventilation holes to connect the test cavity (521) and the circulating air duct.

3. A dual-chamber independently controlled high temperature test chamber as claimed in claim 2, characterized in that: The driving assembly (41) comprises an impeller and a volute, the impeller is arranged in the volute, and the volute is arranged on the inner top surface of the first housing (51).

4. A dual-chamber independently controlled high temperature test chamber as claimed in claim 3, characterized in that: A first exhaust fan (61) and a first circulation fan (62) are both provided at the top of the first test box (1) and the top of the second test box (2); the exhaust duct of the first exhaust fan (61) is connected to the test chamber (521), and the first circulation fan (62) is connected to the impeller.

5. A dual-chamber independently controlled high temperature test chamber as claimed in claim 2, characterized in that: The front ends of the first test box (1) and the second test box (2) are both provided with double doors (7), the double doors (7) comprising a first box door (71) and a second box door (72), and the first box door (71) and the second box door (72) are symmetrically arranged.

6. A dual-chamber independently controlled high temperature test chamber as claimed in claim 5, characterized in that: The first box door (71) and the second box door (72) are both provided with an observation window (8) in the form of a long strip, and the observation window (8) is used to observe the state of the sample in the test chamber (521).

7. A dual-chamber independently controlled high temperature test chamber as claimed in claim 5, characterized in that: The first box door (71) and the second box door (72) both include an outer door panel, an inner door panel and a door lock, the inner side of the outer door panel is fixedly connected to the inner door panel, the outer side of the outer door panel is provided with a handle, and the door lock is nested on the outer door panel and the inner door panel.

8. A dual-chamber independently controlled high temperature test chamber as claimed in claim 5, characterized in that: The first test box (1) and the second test box (2) are both connected to the double door (7) via hinges.

9. A dual-chamber independently controlled high temperature test chamber as claimed in claim 1, characterized in that: The bottoms of the first test box (1) and the second test box (2) are both provided with moving wheels (9).