Edge protection structure

By using the middle section of the three-stage pulling screw to connect the inner rod and the pull-ring screw to fix the wire rope and safety net, the problems of complex and poor stability of the edge and hole protection measures in construction are solved, and safe and reliable edge protection are achieved , reduces construction costs and improves safety.

CN222253244UActive Publication Date: 2024-12-27THE FIRST COMPARY OF CHINA EIGHTH ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421065821.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-16
Publication Date
2024-12-27
Estimated Expiration
2034-05-16

AI Technical Summary

Technical Problem

During construction, the horizontal protection measures at the edge and openings are complicated, unreliable connections and poor stability, resulting in frequent fall accidents at high places.

Method used

The inner rod is connected in the middle of the three-stage pulling screw. The wire rope and safety net are fixed by threaded connection and pull-up screws. The stop rubber pad and elastic connecting clips are combined to form a stable front-facing protective structure to ensure the safety belt and Reliable installation and use of safety nets.

Benefits of technology

It realizes safe and reliable, fast installation and dismantling, and convenient operation, which reduces construction costs and improves construction safety and material utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222253244U_ABST
    Figure CN222253244U_ABST
Patent Text Reader

Abstract

The utility model discloses an edge protection structure which comprises a plurality of connecting inner rods penetrating through a hole edge beam, pull ring screws are connected to the two ends of each connecting inner rod in a threaded mode, a steel wire rope is fixedly connected between the pull ring screws located on the inner side of the hole edge beam, and a safety lock catch of a safety belt is hooked on the steel wire rope. The plurality of pull ring screws located on the outer side of the hole edge beam and the plurality of pull ring screws located on the outer side of the hole edge beam on the opposite side are jointly connected with a safety net; the connecting inner rod is the middle section of the three-section type opposite-pull screw rod used in the construction process. The edge protection structure has the advantages that the edge protection structure is installed through the middle section, namely the connecting inner rod, of the three-section type opposite-pull screw rod poured in the edge beam in the construction process, safety and reliability are achieved, assembly and disassembly are fast, operation is convenient, turnover use can be achieved, and the effects of reducing cost and improving efficiency are fully achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of edge protection in building construction, in particular to an edge protection structure, and more particularly to an edge protection structure for a hole opening. Background Art

[0002] As the country continues to increase the implementation of energy conservation, emission reduction and green mountains and clear waters, more and more enterprises and institutions are promoting the work concept of "reducing costs and increasing efficiency". How to achieve effective breakthroughs in "reducing costs and increasing efficiency" from subtle and routine aspects is the common goal of everyone. For construction companies, the construction site has a higher potential to explore low-carbon and energy-saving construction processes or methods. At the same time, the construction industry in my country is a high-risk industry. In the window period of rapid economic development, safety issues cannot be ignored. Therefore, safety must be put first on the road to promoting low-carbon energy conservation.

[0003] In construction work, falling from height is one of the most frequent safety accidents. How to do a good job of horizontal protection of edges and openings and effectively implement protective measures is also an important issue on the construction site. For example, there is no reliable hanging point for the safety belt of the edge operation, there is no soft protection at the horizontal opening of the atrium or the protective measures are not in place, there will be the risk of falling from height.

[0004] Traditional safety protection measures are complicated to set up. Most of them are just for the sake of simplifying the procedures and do not play a protective role. In addition, the safety protection measures have shortcomings such as unreliable connection and poor stability. For this situation, we provide an edge protection structure. Starting from safety, green and low carbon, material turnover, standardized production and mass production, we make full use of the inner section of the three-section tie screw used to fix the edge beam formwork during the construction process, that is, to connect the inner rod to install the protection structure, thereby solving the safety protection problem of edge operations. Utility Model Content

[0005] In order to overcome the problems in the prior art that the safety protection measures are complicated to set up, most of them are just for simplification of procedures and do not play a protective role, and the safety protection measures have unreliable connections and poor stability, the embodiment of the utility model provides an edge protection structure. The technical solution is as follows:

[0006] A structure for protecting an edge, comprising a plurality of connecting inner rods penetrating through a tunnel edge beam, wherein both ends of the connecting inner rods are threadedly connected with pull-ring screws, a steel wire rope is fixedly connected between the plurality of pull-ring screws located on the inner side of the tunnel edge beam, a safety buckle hook of a safety belt is hung on the steel wire rope, and a plurality of pull-ring screws located on the outer side of the tunnel edge beam and a plurality of pull-ring screws on the outer side of the tunnel edge beam on the opposite side are connected to a safety net; the connecting inner rod is the middle section of a three-section tension screw used in the construction process, and the safety buckle hook of the safety belt is hung on the steel wire rope for convenience of movement by workers, thus avoiding the problem of the safety belt being hung at a fixed point and causing the safety belt to remain unchanged in movement; the safety belt and the safety net are both installed and fixed by using the connecting inner rods remaining after removing the connecting outer rods at both ends of the three-section tension screw, which not only saves materials but also is relatively stable after installation.

[0007] Furthermore, sleeves are fixed at both ends of the connecting inner rod, and the other end of the sleeve is threadedly connected to one end of the pull ring screw, so that the sleeve is convenient for installing or replacing the pull ring screw.

[0008] Furthermore, the sleeve outer shell is provided with a stop rubber pad, and the rubber pad is convenient for fixing the inner rod to prevent it from moving.

[0009] Furthermore, the stopping rubber pad is in a truncated cone shape, and the large circular surface of the stopping rubber pad faces the outside of the edge beam and is tightly attached to the inner side surface of the edge beam template.

[0010] Furthermore, an L-shaped plate is connected to the straight rod section of the pull ring screw, and the L-shaped plate is a right-angle plate, and one outer side surface of the L-shaped plate is in contact with the wall surface of the side beam of the opening, and a connecting clip is fixed on the other outer side surface of the L-shaped plate, and the connecting clip can be clipped onto the straight rod section of the pull ring screw. The L-shaped plate can provide a certain supporting force for the pull ring screw to prevent the pull ring screw from being deformed when an object falls onto the safety net.

[0011] Furthermore, the connecting clamp is arranged axially along the pull ring screw, the cross-section of the connecting clamp is arc-shaped and the edges on both sides are bent outwards, and the edges of the connecting clamp are bent outwards to facilitate clamping to the straight rod section of the pull ring screw.

[0012] Furthermore, the connecting clamp is an elastic member.

[0013] Furthermore, the safety net is hung in the annular holes of several pull ring screws through safety lock hooks.

[0014] Furthermore, steel wire ropes are tied between several pull ring screws on the outer side of the opening edge beam and horizontally interwoven into a net. The safety net is laid on the interwoven steel wire ropes. The steel wire ropes are tied into a net, which indirectly enhances the tolerance of the safety net and prevents the impact force of the object from being fully applied to the safety net when an object falls, making the safety net more easily damaged.

[0015] The beneficial effect of the technical solution provided by the embodiment of the utility model is that the device uses the middle section of the three-section tension screw cast inside the edge beam during the construction process to connect the inner rod to install the edge protection structure, which is not only safe and reliable, quick to install and disassemble, and easy to operate, but also can be used in a turnover manner to fully achieve the effect of "reducing costs and increasing efficiency";

[0016] The device is provided with pull-ring screws on both sides of the opening side beam to connect with the inner rod, and a safety belt is connected to the pull-ring screw on the inner side of the side beam, and a safety net is connected to the pull-ring screw on the outer side of the side beam, thereby achieving the effect of one component having multiple uses. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the following is a brief introduction to the drawings used in the embodiments. Obviously, the drawings listed below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the utility model;

[0019] Figure 2 yes Figure 1 A schematic diagram of the structure enlargement in the middle;

[0020] Figure 3 This is a schematic diagram of the safety belt hanging of an embodiment of the utility model;

[0021] Figure 4 This is a schematic diagram of the three-stage tension screw connection before the outer rod is removed in the embodiment of the utility model;

[0022] Figure 5 This is a schematic diagram of the structure of the connecting card in the embodiment of the utility model;

[0023] Figure 6 It is a schematic diagram of the use status of the safety net of the embodiment of the utility model.

[0024] In the attached drawings, the components represented by each number are listed as follows: 1. Connecting inner rod; 2. Pull ring screw; 3. Wire rope; 4. Safety net; 5. Stop rubber pad; 6. L-shaped plate; 7. Connecting clip; 10. Opening side beam. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the present invention more clear, the implementation mode of the present invention will be further described in detail below with reference to the accompanying drawings.

[0026] See also Figures 1 to 6The embodiment of the utility model provides an edge protection structure, including a plurality of connecting inner rods 1 that pass through the opening edge beams 10, with pull ring screws 2 threadedly connected at both ends of the connecting inner rods 1, a steel wire rope 3 is fixedly connected between the plurality of pull ring screws 2 located on the inner side of the opening edge beam 10, the safety buckle hook of the safety belt is hung on the steel wire rope 3, and a plurality of pull ring screws 2 located on the outer side of the opening edge beam 10 and a plurality of pull ring screws on the outer side of the opening edge beam 10 on the opposite side are connected to a safety net 4; the connecting inner rod 1 is the middle section of the three-section tension screw used in the construction process.

[0027] Sleeves are fixed at both ends of the connecting inner rod 1, and the other end of the sleeve is threadedly connected to one end of the pull ring screw 2.

[0028] A stop rubber pad 5 is disposed on the sleeve outer cover. The stop rubber pad 5 is in a truncated cone shape, and the large circular surface of the stop rubber pad 5 faces the outside of the edge beam 10 and is in close contact with the inner side surface of the edge beam template.

[0029] An L-shaped plate 6 is connected to the straight rod section of the pull ring screw 2. The L-shaped plate 6 is a right-angle plate, and one outer side surface of the L-shaped plate 6 is in contact with the wall surface of the opening edge beam 10. A connecting clip 7 is fixed to the other outer side surface of the L-shaped plate 6, and the connecting clip 7 can be clipped onto the straight rod section of the pull ring screw 2.

[0030] The connecting clamp 7 is arranged axially along the pull ring screw 2 , and the cross section of the connecting clamp 7 is arc-shaped with the edges on both sides bent outwards.

[0031] Wherein, the connecting clamp 7 is an elastic member.

[0032] The safety net 4 is hung in the annular holes of a plurality of pull ring screws 2 through safety lock hooks.

[0033] Steel wire ropes 3 are tied between a plurality of pull ring screws 2 on the outer side of the opening edge beam 10 and horizontally interwoven with each other to form a net, and a safety net 4 is laid on the interwoven steel wire ropes 3 .

[0034] In addition, a steel wire rope 3 is laid out every 2 m on the outside of the opening edge beam 10 using a pull ring screw 2, and the steel wire ropes 3 are interwoven horizontally and vertically on the same horizontal plane, and then a safety net 4 is laid above the steel wire ropes 3.

[0035] Instructions for use: During the construction process, after the concrete is formed and the formwork is removed, the outer rod portion of the three-section tension screw is removed, and the ring screw 2 is threadedly connected to the middle section of the three-section tension screw, that is, the two ends of the inner rod 1 connected, wherein the side walls of the two ends of the inner rod 1 that are exposed to the side beam 10 of the opening are convenient for connecting the ring screw 2; then the L-shaped plate 6 is clamped to the straight rod section of the ring screw 2 on both sides of the opening side beam 10 through the connecting clamp 7, so that it provides a certain supporting force for the ring screw 2 to avoid the problem of bending and deformation of the ring screw 2 when the force is too large, and then on the inner side of the opening side beam 10 A steel wire rope 3 is tied between multiple pull ring screws 2, and the safety buckle hook of the safety belt is hung on the steel wire rope 3 on the inner side of the hole edge beam 10. The safety buckle can slide on the steel wire rope 3, which is convenient for the workers to move during work and avoids the safety belt being hung at only a fixed point. The hanging point needs to be changed constantly during the construction process. A steel wire rope 3 is laid every 2m on the outside of the hole edge beam 10 using pull ring screws 2, and the steel wire ropes 3 are interwoven horizontally and vertically on the same horizontal plane. Then a safety net 4 is laid above the steel wire rope 3, and the periphery of the safety net 4 is hung in the annular hole of the pull ring screws 2 through a plurality of safety buckle hooks.

[0036] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An edge protection structure, characterized in that: It comprises a plurality of connecting inner rods (1) passing through the opening side beams (10), the two ends of the connecting inner rods (1) being threadedly connected with pull ring screws (2), a steel wire rope (3) being fixedly connected between the plurality of pull ring screws (2) located on the inner side of the opening side beams (10), the safety buckle hook of the safety belt being hung on the steel wire rope (3), the plurality of pull ring screws (2) located on the outer side of the opening side beams (10) and the plurality of pull ring screws on the outer side of the opening side beams (10) on the opposite side being connected with a safety net (4); the connecting inner rod (1) is the middle section of a three-section tension screw used in the construction process.

2. The edge protection structure according to claim 1, characterized in that: Sleeves are fixed to both ends of the connecting inner rod (1), and the other end of the sleeve is threadedly connected to one end of the pull ring screw (2).

3. The edge protection structure according to claim 2, characterized in that: The sleeve outer shell is provided with a stop rubber pad (5).

4. The edge protection structure according to claim 1, characterized in that: An L-shaped plate (6) is connected to the straight rod section of the pull ring screw (2), and the L-shaped plate (6) is a right-angle plate, and one outer side surface of the L-shaped plate (6) is in contact with the wall surface of the opening edge beam (10), and a connecting clamp (7) is fixed to the other outer side surface of the L-shaped plate (6), and the connecting clamp (7) can be clamped onto the straight rod section of the pull ring screw (2).

5. The edge protection structure according to claim 4, characterized in that: The connecting clamp (7) is arranged axially along the pull ring screw (2); the connecting clamp (7) has an arc-shaped cross section and the edges on both sides are bent outwards.

6. The edge protection structure according to claim 5, characterized in that: The connecting clamp (7) is an elastic member.

7. The edge protection structure according to any one of claims 1 to 3, characterized in that: The safety net (4) is hung in the annular holes of a plurality of the pull ring screws (2) via safety lock hooks.

8. The edge protection structure according to any one of claims 1 to 3, characterized in that: Steel wire ropes (3) are tied between a plurality of pull ring screws (2) on the outside of the opening edge beam (10) and are horizontally interwoven to form a net, and the safety net (4) is laid on the interwoven steel wire ropes (3).