Aluminum fluoride production device
By installing detachable splicing plates and partitions on the fluidized bed reactor of the aluminum fluoride production device, the problems of material reflow and partition wear in the prior art are solved, and rapid disassembly and replacement are achieved, improving the operating convenience and airtightness of the device.
Patent Information
- Application Number
- CN202421355873.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-06-14
AI Technical Summary
When the existing aluminum fluoride production equipment uses a fluidized bed reactor for air drum separation, some materials are reflowed due to different flow rates, causing particles to remix, and the partitions are worn and dirty, making it inconvenient to disassemble and replace.
A flexible disassembleable aluminum fluoride production device is designed. By installing splicing plates and partitions on the fluidized bed reactor, the combined structure of connecting blocks, movable grooves, screws and panels is used to enable the splicing plates and partitions to be quickly disassembled and replaced to avoid the impact of partition wear.
The partition is quickly disassembled and replaced, avoiding the anti-mixing effect from wear and dirt, and the structure is simple and easy to operate, taking into account the sealing properties of the fluidized bed reactor.
Smart Images

Figure CN222677985U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of chemical processing, and specifically relates to an aluminum fluoride production device. Background Art
[0002] Aluminum fluoride, with the molecular formula of AlF3, is a colorless triclinic white powder. Anhydrous aluminum fluoride is a large hexagonal hexahedral crystal, which is an ionic crystal. The production and preparation of aluminum fluoride can be roughly divided into two categories: dry process and wet process. The dry process uses hydrogen fluoride gas that has been simply dusted and deacidified to react with aluminum hydroxide, and then mixes it with dry aluminum hydroxide, sends it into a fluidized bed reactor to mix with a catalyst, and separates the gas phase from the solid particles during the fluid movement, and finally obtains the aluminum fluoride product.
[0003] In the prior art, when aluminum fluoride is separated by air drum using a fluidized bed reactor, due to the uneven flow velocity on the flow section, a part of the material near the edge flows in the opposite direction and becomes a backflow, causing particle remixing. A common solution is to add a partition inside the fluidized bed reactor to prevent the particles from flowing back during movement. The long-term collision between the particles and the partition will cause the partition to wear and become dirty. However, the partition is installed inside the fluidized bed reactor, and it is extremely inconvenient to disassemble and replace. Utility Model Content
[0004] The purpose of the utility model is to provide an aluminum fluoride production device. By arranging flexibly detachable splicing plates and partitions on a fluidized bed reactor, the partitions can be disassembled, replaced and maintained in a timely manner, thereby avoiding the anti-backmixing effect being affected by worn and dirty partitions. The device has a simple structure and is easy to operate, while taking into account the airtightness of the fluidized bed reactor.
[0005] The technical solution adopted by the utility model is as follows:
[0006] A device for producing aluminum fluoride comprises a fluidized bed reactor, a splicing plate, an L-shaped plate and a partition, wherein the fluidized bed reactor is arranged in a plurality of groups, two of the fluidized bed reactors are fixedly connected by a connecting block, the splicing plates are arranged in a plurality of groups, one group is two symmetrical ones, the splicing plate can be detachably assembled between the two fluidized bed reactors, a movable groove is provided through the middle of the connecting block, a screw is threadedly connected to the middle of the movable groove, one end of the screw is rotatably connected to an insert plate located inside the movable groove, the splicing plate is movably engaged with the connecting block, an insert block is fixedly connected to both ends of the splicing plate, a slot for inserting and engaging the insert plate is provided through the splicing plate and the insert block, an insert column is fixedly connected to one side of the splicing plate, the partition is movably inserted between the two L-shaped plates, and an insert groove three is provided on the outer wall of the partition for inserting and engaging the insert column.
[0007] The L-shaped plate is symmetrically fixedly assembled on one side of the splicing plate, and sealing rings are symmetrically slidably arranged on both sides of the splicing plate and located on both sides of the L-shaped plate.
[0008] One side of the L-shaped plate is provided with a through-type embedding groove for the sealing ring to slide and embed.
[0009] The bottom of the sealing ring is symmetrically fixedly connected with a sliding block, and one side of the splicing plate is provided with sliding grooves in an array for the sliding blocks to slide.
[0010] One end of the two sliding blocks is located inside the splicing plate and is fixedly connected with a connecting rod, and a spring column is elastically connected between the two connecting rods.
[0011] One side of the two connecting rods is fixedly connected with a rack, and the two racks are arranged in a mirror-symmetrical manner.
[0012] The outer wall of the splicing plate is rotatably connected to a rotating handle, one end of the rotating handle is located inside the splicing plate and is fixedly connected with a gear, and the gear is meshed and connected with the two racks at the same time.
[0013] Two embedding grooves for the sealing ring to slide and fit are symmetrically provided on both sides of the partition.
[0014] The technical effect achieved by the utility model is as follows: by arranging the flexibly detachable splicing plates and partitions on the fluidized bed reactor, the partitions can be disassembled, replaced and maintained in time, thus avoiding the anti-backmixing effect being affected by the worn and dirty partitions, and the structure is simple and easy to operate, while taking into account the airtightness of the fluidized bed reactor. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is an overall appearance diagram of the aluminum fluoride production device provided in the embodiment of the utility model;
[0016] Figure 2 It is a structural display diagram of the splicing plate and the partition provided in the embodiment of the utility model;
[0017] Figure 3 It is a structural disassembly diagram of the splicing plate and the partition provided in the embodiment of the utility model;
[0018] Figure 4 yes Figure 3 A partial enlarged view of the middle A;
[0019] Figure 5 yes Figure 3 A partial enlarged view of point B in the middle;
[0020] Figure 6 It is a structural dissection diagram of a splicing plate provided in an embodiment of the utility model;
[0021] Figure 7 yes Figure 6 A partial enlarged view of point C in the middle.
[0022] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0023] 1. Fluidized bed reactor; 101. Connecting block; 102. Movable groove; 103. Screw; 104. Panel; 2. Joint plate; 201. Sealing ring; 202. Sliding groove; 203. Embedded column; 204. Sliding block; 205. L-shaped plate; 206. Embedded groove one; 207. Embedded block; 208. Slot; 209. Rotating handle; 210. Connecting rod; 211. Spring column; 212. Rack; 213. Gear; 3. Partition plate; 301. Embedded groove two; 302. Embedded groove three. DETAILED DESCRIPTION
[0024] In order to make the purpose and advantages of the utility model more clear, the utility model is specifically described in combination with the following embodiments. It should be understood that the following text is only used to describe one or several specific implementations of the utility model, and does not strictly limit the protection scope of the specific request of the utility model.
[0025] like Figure 1-5 As shown, an aluminum fluoride production device includes a fluidized bed reactor 1, a splicing plate 2, an L-shaped plate 205 and a partition 3. The fluidized bed reactor 1 is set to be a plurality of fluidized bed reactors 1, and two fluidized bed reactors 1 are fixedly connected by a connecting block 101. The splicing plates 2 are set to be a plurality of groups, and a group is two symmetrical ones. The splicing plates 2 are detachably assembled between the two fluidized bed reactors 1. A movable groove 102 is opened through the middle of the connecting block 101, and a screw 103 is threadedly connected to the middle of the movable groove 102. The screw 103 One end of the splicing plate 2 is rotatably connected with an inlay plate 104 located inside the movable groove 102, the splicing plate 2 is movably engaged with the connecting block 101, both ends of the splicing plate 2 are fixedly connected with engaging blocks 207, a slot 208 for inserting and engaging the inlay plate 104 is provided between the splicing plate 2 and the engaging block 207, an embedding column 203 is fixedly connected to one side of the splicing plate 2, the partition plate 3 is movably inserted between the two L-shaped plates 205, and the outer wall of the partition plate 3 is provided with an embedding groove 302 for the embedding column 203 to be embedded and engaged.
[0026] According to the above structure, the connecting block 101 connects several fluidized bed reactors 1 into one, slides the partition 3 between the two L-shaped plates 205, and makes the embedding groove 302 engage with the embedding column 203 to fix the position of the partition 3, and inserts the two splicing plates 2 between the two fluidized bed reactors 1 opposite to each other. When the two embedding blocks 207 are fitted, the insert plate 104 is pushed to move in the movable groove 102 by rotating the screw 103, so that the insert plate 104 is fitted with the two embedding blocks 207, and at the same time, the insert plate 104 is inserted into the slot 208 to fix the two splicing plates 2.
[0027] See attached Figure 3-7 The L-shaped plate 205 is symmetrically fixedly assembled on one side of the splicing plate 2. The two sides of the splicing plate 2 and the two sides of the L-shaped plate 205 are symmetrically slidably provided with sealing rings 201. One side of the L-shaped plate 205 is provided with a through-type embedding groove 206 for the sealing ring 201 to slide and fit. The bottom of the sealing ring 201 is symmetrically fixedly connected with a sliding block 204. One side of the splicing plate 2 is provided with a sliding groove 202 for the sliding block 204 to slide in an array. One end of the two sliding blocks 204 and located inside the splicing plate 2 are connected together. A connecting rod 210 is fixedly connected to the two connecting rods 210, and a spring column 211 is elastically connected between the two connecting rods 210. A rack 212 is fixedly connected to one side of the two connecting rods 210. The two racks 212 are arranged in a mirror-symmetrical manner. The outer wall of the splicing plate 2 is rotatably connected to a rotating handle 209. One end of the rotating handle 209 is fixedly connected to the inside of the splicing plate 2 with a gear 213. The gear 213 is meshed with the two racks 212 at the same time. The partition 3 has symmetrical grooves 301 on both sides for the sealing ring 201 to slide and fit.
[0028] According to the above structure, when the splicing plate 2 is inserted between the two fluidized bed reactors 1, the rotating handle 209 is rotated to drive the gear 213 to rotate, and the gear 213 drives the two racks 212 to move toward each other. The racks 212 will pull the connecting rod 210 and shrink the spring column 211. The movement of the connecting rod 210 drives the sliding block 204 to slide on the inner wall of the sliding groove 202. The sliding block 204 drives the sealing ring 201 to move, and pulls the sealing ring 201 to fit the L-shaped plate 205. The sealing ring 201 is embedded in the embedding groove 1 206, and the embedding groove 2 301 makes room for the sealing ring 201 to move downward. The above steps shrink the sealing ring 201 to The interior of the splicing plate 2 can make the splicing plate 2 smoothly inserted into the fluidized bed reactor 1 without being hindered by the sealing ring 201. After loosening the rotating handle 209, the elastic force of the spring column 211 causes the connecting rod 210 to rebound, thereby popping out the sealing ring 201 to fit the inner wall of the fluidized bed reactor 1, thereby enhancing the airtightness of the splicing plate 2; the utility model can timely disassemble, replace and maintain the partition 3 by arranging the flexibly detachable splicing plate 2 and partition 3 on the fluidized bed reactor 1, thereby avoiding the anti-backmixing effect being affected by the worn and dirty partition 3, and the structure is simple and easy to operate, taking into account the airtightness of the fluidized bed reactor 1.
[0029] The working principle of the utility model is as follows: the connecting block 101 connects several fluidized bed reactors 1 into one, the partition 3 is slidably inserted between the two L-shaped plates 205, so that the embedding groove 302 is embedded with the embedding column 203, the position of the partition 3 is fixed, and the two splicing plates 2 are inserted into the two fluidized bed reactors 1 oppositely. When the two embedding blocks 207 are fitted, the insert plate 104 is pushed to move in the movable groove 102 by rotating the screw 103, so that the insert plate 104 is fitted with the two embedding blocks 207, and the insert plate 104 is inserted into the slot 208 to fix the two splicing plates 2; when the splicing plate 2 is inserted between the two fluidized bed reactors 1, the rotating handle 209 is rotated to drive the gear 213 to rotate, and the gear 213 drives the two racks 212 to move oppositely, and the racks 2 12 will pull the connecting rod 210 and shrink the spring column 211. The movement of the connecting rod 210 drives the sliding block 204 to slide on the inner wall of the sliding groove 202. The sliding block 204 drives the sealing ring 201 to move, and pulls the sealing ring 201 to fit the L-shaped plate 205. The sealing ring 201 is embedded in the embedding groove 1 206, and the embedding groove 2 301 makes room for the sealing ring 201 to move downward. The above steps shrink the sealing ring 201 to the inside of the splicing plate 2, so that the splicing plate 2 can be smoothly inserted into the fluidized bed reactor 1 without being hindered by the sealing ring 201. After the rotating handle 209 is released, the elastic force of the spring column 211 causes the connecting rod 210 to rebound, thereby popping out the sealing ring 201 to fit the inner wall of the fluidized bed reactor 1, thereby enhancing the airtightness of the splicing plate 2.
[0030] The above is only a preferred embodiment of the present invention. It should be noted that, for ordinary technicians in the technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be regarded as the protection scope of the present invention. The structures, devices and operating methods not specifically described and explained in the present invention shall be implemented according to the conventional means in the field unless otherwise specified and limited.
Claims
1. An aluminum fluoride production device, comprising a fluidized bed reactor (1), a splicing plate (2), an L-shaped plate (205) and a partition (3), characterized in that: The fluidized bed reactors (1) are provided in a plurality of pieces, two of the fluidized bed reactors (1) are fixedly connected via a connecting block (101), the splicing plates (2) are provided in a plurality of groups, one group of which is symmetrically two, the splicing plates (2) are detachably assembled between the two fluidized bed reactors (1), a movable groove (102) is provided through the middle of the connecting block (101), a screw rod (103) is threadedly connected to the middle of the movable groove (102), and one end of the screw rod (103) is rotatably connected to a panel (104) located inside the movable groove (102). ), the splicing plate (2) is movably engaged with the connecting block (101), the two ends of the splicing plate (2) are fixedly connected with engaging blocks (207), a slot (208) is provided between the splicing plate (2) and the engaging block (207) for the inserting plate (104) to be inserted and engaged, an embedding column (203) is fixedly connected to one side of the splicing plate (2), the partition plate (3) is movably engaged between the two L-shaped plates (205), and an outer wall of the partition plate (3) is provided with an embedding groove (302) for the embedding column (203) to be inserted and engaged.
2. An aluminum fluoride production device according to claim 1, characterized in that: The L-shaped plate (205) is symmetrically fixedly assembled on one side of the splicing plate (2), and sealing rings (201) are symmetrically slidably arranged on both sides of the splicing plate (2) and located on both sides of the L-shaped plate (205).
3. An aluminum fluoride production device according to claim 2, characterized in that: One side of the L-shaped plate (205) is provided with a through-type embedding groove (206) for the sealing ring (201) to be slidably embedded therein.
4. An aluminum fluoride production device according to claim 2, characterized in that: The bottom of the sealing ring (201) is symmetrically fixedly connected with a sliding block (204), and one side of the splicing plate (2) is provided with sliding grooves (202) in an array for the sliding blocks (204) to slide.
5. An aluminum fluoride production device according to claim 4, characterized in that: One end of the two sliding blocks (204) and located inside the splicing plate (2) are fixedly connected to a connecting rod (210), and a spring column (211) is elastically connected between the two connecting rods (210).
6. An aluminum fluoride production device according to claim 5, characterized in that: One side of each of the two connecting rods (210) is fixedly connected to a rack (212), and the two racks (212) are arranged in a mirror-symmetrical manner.
7. An aluminum fluoride production device according to claim 6, characterized in that: The outer wall of the splicing plate (2) is rotatably connected to a rotating handle (209), one end of the rotating handle (209) is fixedly connected to a gear (213) located inside the splicing plate (2), and the gear (213) is meshedly connected to the two racks (212) at the same time.
8. An aluminum fluoride production device according to claim 2, characterized in that: Two embedding grooves (301) for the sealing ring (201) to slide and fit are symmetrically provided on both sides of the partition (3).