Amusement magic net crossing mountain head
By adopting a cross-mountain design in the Sky Magic Net and using pile foundation structure and main traction cable to fix the protective net, the problem of shaking of the protective net is solved, and tourists can freely move on the protection net and improve the amusement experience.
Patent Information
- Application Number
- CN202422247199.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2025-07-11
- Estimated Expiration
- 2034-09-13
AI Technical Summary
The existing Sky Magic Net's protective net is simple to fix, resulting in large shaking range, making it inconvenient for tourists to move on it, and the experience is poor.
The cross-mountain design is adopted, and the steel frame platform is fixed between the two hills by pile foundation structure and main traction structure. The protective net is fixed on the steel frame platform and is tensioned through the pile foundation structure and the main traction cable. Combined with the corridor structure and auxiliary poles, the stability of the protective net is enhanced.
It reduces the shaking of the protective net, and visitors can run, jump and crawl freely on the protective net, enriching the entertainment methods and improving the amusement experience.
Smart Images

Figure CN223082238U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of amusement facilities, in particular to an amusement magic net spanning mountain tops. Background Art
[0002] With the enrichment of people's entertainment life, various entertainment facilities have also been added in many tourist attractions. Especially in some natural scenic spots, while people are getting close to nature, they can participate in various entertainment activities to enhance the amusement experience.
[0003] The sky magic net is a new type of high-altitude amusement facility, mainly an aerial amusement venue built between landforms such as cliffs and valleys. It is widely popular due to its special high-altitude experience. However, currently, the sky magic net mainly builds the protective net on the suspension cables. The fixing method of the protective net is simple, and the protective net itself is a flexible structure. When people walk on it, it is easy to shake, and the shaking amplitude is too large, resulting in the main movement method of tourists on the magic net being crawling, and they can only sit on the net when resting, so the amusement experience is not good. In view of this, we propose an amusement magic net spanning mountain tops. Content of the Utility Model
[0004] The purpose of the utility model is to solve the problems that the fixing method of the protective net of the existing sky magic net is simple, people are easy to shake when walking on it, and the shaking amplitude is too large, and to propose an amusement magic net spanning mountain tops.
[0005] In order to achieve the above purpose, the utility model adopts the following technical scheme:
[0006] An amusement magic net spanning mountain tops, comprising a main structure and a safety net installed below the main structure. The main structure includes a main traction structure suspended between two mountain tops, a steel frame platform arranged on the main traction structure, and a protective net. One side of the steel frame platform is provided with a corridor structure for entering and leaving the steel frame platform and the mountain top.
[0007] Furthermore, the main structure also includes a pile foundation structure installed on the mountain top, and the main traction structure is fixedly installed between the two pile foundation structures.
[0008] Furthermore, the pile foundation structure includes a pile foundation column poured inside the mountain top and a pile foundation cap poured on the top of the pile foundation column. The two ends of the main traction structure are fixedly connected with the pile foundation cap.
[0009] Furthermore, the main traction structure includes a main traction cable and a traction cable fixing rod. The two ends of the main traction cable are respectively connected with the pile foundation cap, and the corridor structure and the steel frame platform are fixedly installed on the main traction cable.
[0010] Further, there are multiple main towing cables, and the main towing cables are fixedly connected to the towing cable fixing rods, so that two adjacent main towing cables are parallel to each other.
[0011] Further, the steel frame platform includes longitudinal beams, cross beams, vertical beams, and auxiliary braces. The longitudinal beams and cross beams form a frame structure. Vertical beams are arranged around the frame structure, and auxiliary braces are arranged inside the frame. The longitudinal beams, cross beams, and auxiliary braces are fixedly connected to the main towing cables.
[0012] Further, the corridor structure includes a corridor towing cable, a corridor floor, and a corridor safety net pulling rope. A corridor floor is arranged on the top of the main towing cable. A corridor towing cable is arranged above the corridor floor. A corridor safety net pulling rope and a safety net are connected between the corridor towing cable and the main towing cable.
[0013] Compared with the prior art, the present utility model provides a cross-mountain amusement magic net, which has the following beneficial effects:
[0014] For the cross-mountain amusement magic net of the present utility model, during construction, the safety net is fixed on the steel frame platform and tightened through the steel frame platform. The steel frame platform is fixed between two mountains through the main towing structure. Tourists enter and exit the steel frame platform through the corridor structure. Compared with the prior art, the safety net and the steel frame platform can be loosely connected, and tourists can crawl on the safety net. The safety net and the steel frame platform can also be tightly connected to reduce the shaking of the safety net. Tourists can freely run, jump, walk, and stand on the safety net, enriching the entertainment methods of tourists and enhancing the amusement experience.
[0015] Other advantages, objectives, and features of the present utility model will be described to some extent in the subsequent specification; and to some extent, based on the study of the following text, it will be obvious to those skilled in the art; or, it can be taught from the practice of the present utility model. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 is the front view schematic diagram of the overall structure of the present utility model;
[0017] Figure 2 is the three-dimensional schematic diagram of the overall structure of the present utility model;
[0018] Figure 3 is of the present utility model Figure 2 partial structure schematic diagram
[0019] Figure 4 is the schematic diagram of the main towing structure of the present utility model;
[0020] Figure 5 is of the present utility model Figure 4Schematic enlarged view of part A structure in the present utility model;
[0021] Figure 6 Schematic installation effect view of the auxiliary towing cable of the present utility model;
[0022] Figure 7 of the present utility model Figure 6 Schematic enlarged view of part B structure in the present utility model;
[0023] Figure 8 Schematic three-dimensional view of the corridor structure of the present utility model;
[0024] Figure 9 of the present utility model Figure 8 Schematic enlarged view of part C structure in the present utility model.
[0025] In the figure:
[0026] 1. Main body structure; 2. Safety net; 201. Safety net pile column; 202. Safety net pocket; 3. Main towing structure; 301. Main towing cable; 302. Towing cable fixing rod; 4. Auxiliary towing structure; 401. Auxiliary towing cable; 402. Main protective net pulling rope; 5. Pile foundation structure; 501. Pile foundation pile column; 502. Pile foundation cap; 503. Rest platform; 504. Oblique pulling pile column; 505. Load-bearing pile column; 6. Corridor structure; 601. Corridor towing cable; 602. Corridor floor; 603. Corridor pile column; 604. Corridor protective net pulling rope; 7. Protective net; 8. Steel frame platform; 801. Longitudinal beam; 802. Cross beam; 803. Vertical beam; 804. Auxiliary strut. Specific implementation mode
[0027] Next, the technical solutions in the embodiments of the present utility model will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the embodiments.
[0028] Refer to Figure 1-9 , a cross-mountain amusement magic net of the present utility model includes a main body structure 1 and a safety net 2 installed below the main body structure 1. The safety net 2 includes safety net pile columns 201 and a safety net pocket 202. Two groups of safety net pile columns 201 are respectively embedded in the mountain heads, and the four corners of the safety net pocket 202 are respectively connected to the safety net pile columns 201. The boundary of the safety net pocket 202 is located outside the corridor structure 6 and the steel frame platform 8.
[0029] The main body structure 1 includes a main towing structure 3, a steel frame platform 8, and a protective net 7 suspended between two mountain heads. A steel frame platform 8 is fixed in the middle of the main towing structure 3. A corridor structure 6 is installed on one side of the steel frame platform 8. The two ends of the corridor structure 6 are respectively connected to the steel frame platform 8 and the mountain head. Tourists enter and exit between the mountain head and the steel frame platform 8 through the corridor structure 6.
[0030] A protective net 7 is installed on the corridor structure 6 and the steel frame platform 8. The corridor structure 6 mainly has corridor floors 602 installed on the bottom surface, and protective nets 7 installed on both sides. Protective nets 7 are installed on the bottom surface and the surrounding side surfaces of the steel frame platform 8, and tourists can move on the protective net 7 of the steel frame platform 8.
[0031] The main structure 1 also includes a pile foundation structure 5 installed on the mountain top. The main traction structure 3 is fixedly installed between the two pile foundation structures 5. The two pile foundation structures 5 are embedded in the top of the mountain top, and respectively fix and tension the main traction structure 3 from both ends, suspending between the two mountain tops.
[0032] The pile foundation structure 5 includes pile foundation columns 501 and pile foundation caps 502. The lower part of the pile foundation columns 501 is embedded in the mountain top, the pile foundation caps 502 are embedded in the top of the mountain top, the upper part of the pile foundation columns 501 is embedded in the pile foundation caps 502, and both ends of the main traction structure 3 are fixedly connected to the pile foundation caps 502, so that the pile foundation structure 5 is fixedly installed on the mountain top.
[0033] The pile foundation structure 5 also includes a rest platform 503. The rest platform 503 is integrally formed with the pile foundation cap 502 on the side close to the corridor structure 6. The functions of the rest platform 503 are: one is to enhance the overall stability effect of the pile foundation structure 5, and the other is to increase the activity area, rest area and queuing space at the entrance / exit position of the corridor structure 6.
[0034] The main traction structure 3 includes a main traction cable 301, a traction cable fixing rod 302 and a first pull rod. The first pull rod is embedded inside the pile foundation cap 502. Both ends of the main traction cable 301 are tensioned and connected to the first pull rod respectively. The corridor structure 6 and the steel frame platform 8 are fixedly installed on the main traction cable 301.
[0035] Specifically, when constructing the pile foundation cap 502, the first pull rod is pre-embedded, and a pre-embedded steel cable is fixedly connected to the first pull rod. A special connector for the steel wire rope is installed at the end of the pre-embedded steel cable far from the first pull rod, and the main traction cable 301 is connected to the pre-embedded steel cable using a special connector.
[0036] There are multiple main traction cables 301. The main traction cables 301 are fixedly connected to the traction cable fixing rods 302, so that two adjacent main traction cables 301 are parallel to each other.
[0037] In addition to increasing the structural strength of the main traction structure 3, the multiple main traction cables 301 can also increase the contact area with the corridor structure 6 and the steel frame platform 8, and the supporting effect on the corridor structure 6 and the steel frame platform 8 is more stable.
[0038] The main towing cable 301 extends from one pile foundation structure 5 to another pile foundation structure 5. The towing cable fixing rod 302 is perpendicular to the main towing cable 301 and fixes multiple main towing cables 301 together, making the multiple main towing cables 301 parallel at equal intervals, which can reduce the sway amplitude of the main towing cable 301 in the horizontal direction.
[0039] The steel frame platform 8 includes longitudinal beams 801, cross beams 802, vertical beams 803, and auxiliary struts 804. The longitudinal beams 801 and cross beams 802 form a square frame structure. Vertical beams 803 are welded to the four sides of the frame structure, and protective nets 7 are arranged between adjacent two vertical beams 803 inside the frame structure.
[0040] Auxiliary struts 804 are welded inside the frame. The auxiliary struts 804 are mainly used to assist in tensioning the protective net 7 at the bottom. There are multiple auxiliary struts 804, and their arrangement is determined according to the following requirements: for the activity area where the protective net 7 needs to maintain a relaxed effect, the distance between the auxiliary struts 804 and the frame structure is larger, and the entertainment effect of the protective net 7 in this area is similar to that of the existing sky magic net. For the activity area where the protective net 7 needs to maintain a tensioned effect, the distance between the auxiliary struts 804 and the frame structure is smaller, so that the protective net 7 has a better tensioning and supporting effect, reduces swaying, and enables tourists to walk and run freely on the protective net 7 in this area.
[0041] The longitudinal beams 801, cross beams 802, and auxiliary struts 804 are fixedly connected to the main towing cable 301 through U-shaped bolts.
[0042] The corridor structure 6 includes a corridor towing cable 601, a corridor floor 602, corridor pile columns 603, and a corridor guard net guy rope 604. The corridor floor 602 is fixed to the top of the main towing cable 301. The corridor towing cable 601 is installed above the corridor floor 602. A protective net 7 and a corridor guard net guy rope 604 are connected between the corridor towing cable 601 and the main towing cable 301. The function of the corridor guard net guy rope 604 is to reduce the situation of mutual swinging between the corridor towing cable 601 and the main towing cable 301, increase the stability of the connection between the corridor towing cable 601 and the main towing cable 301, and prevent the protective net 7 from being torn.
[0043] The corridor pile columns 603 are fixedly installed on the top of the pile foundation cap 502. There are a total of eight corridor pile columns 603, which are respectively installed on the pile foundation caps 502 on both sides. Two corridor pile columns 603 tow one corridor towing cable 601, and the four corridor towing cables 601 are divided into two groups. Each group of corridor towing cables 601 tows one corridor structure 6.
[0044] Two groups of corridor pile columns 603 connected to the corridor floor 602 respectively form an entrance and an exit, and the other end of the corridor floor 602 is connected to the steel frame platform 8.
[0045] A secondary traction structure 4 is also installed above the main traction structure 3, and the secondary traction structure 4 includes a secondary traction rope 401, a main protective net rope 402, and a second pull rod. The pile foundation column 501 includes a diagonal pile column 504 and a load-bearing pile column 505. The load-bearing pile column 505 is mainly responsible for connecting the top of the mountain and the pile foundation pedestal 502. In addition to connecting the top of the mountain and the pile foundation pedestal 502, the top of the diagonal pile column 504 extends upward to above the pile foundation pedestal 502. The two ends of the secondary traction rope 401 pass around the top of the diagonal pile column 504, and then are tensioned downward to be connected to the second pull rod.
[0046] The second pull rod is also pre-buried in the pile foundation pedestal 502. A special connector for the wire rope is also installed on the top of the second pull rod. The auxiliary traction rope 401 and the second pull rod are connected by a special connector to achieve the effect of oblique support.
[0047] A protective net 7 is also installed between the auxiliary traction rope 401 and the main traction rope 301 to form a main protective net, which is located outside the corridor structure 6 and the steel frame platform 8.
[0048] In the present application, there are a total of five main traction ropes 301 at the bottom of each group of corridor structures 6. The corridor structure 6 is installed on the three middle main traction ropes 301, and a protective net 7 and a corridor protective net pull rope 604 are installed between the auxiliary traction rope 401 and the outer main traction rope 301.
[0049] Working principle: When in use, tourists line up on the rest platform 503, enter the steel frame platform 8 from the corridor structure 6 on the entrance side to carry out activities, and then perform recreational activities such as running, jumping, walking, crawling, etc. in different areas on the steel frame platform 8 as needed, and then return to the rest platform 503 from the corridor structure 6 on the exit side.
[0050] The main traction ropes 301 arranged in parallel at equal intervals are initially fixed together with the steel frame platform 8 to reduce the swinging and shaking caused by the main traction ropes 301 being installed alone. Then, the protective net 7 is tensioned to different degrees through the steel frame platform 8 to change the supporting effect of the protective net 7 on tourists, so that tourists can get different recreational experiences.
[0051] In the present application, facilities such as a maze and an observation deck surrounded by a protective net 7 can also be installed on the steel frame platform 8, and stable support is obtained by the cooperation between the main traction structure 3 and the steel frame platform 8.
[0052] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
[0053] In the description of this specification, the descriptions referring to terms such as "one embodiment", "some embodiments", "examples", "specific examples", or "some examples", etc. mean that the specific features, structures, materials, or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present utility model. In this specification, the schematic expressions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described can be combined in a suitable manner in any one or more embodiments or examples. In addition, without contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.
[0054] Although the embodiments of the present utility model have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present utility model. Those of ordinary skill in the art can make changes, modifications, substitutions, and variations to the above embodiments within the scope of the present utility model.
Claims
1. An amusement magic net spanning over mountains, comprising a main structure (1) and a safety net (2) installed below the main structure (1), characterized in that, The main body structure (1) includes a main traction structure (3) suspended between two mountain peaks, a steel frame platform (8) and a protective net (7) arranged on the main traction structure (3). One side of the steel frame platform (8) is provided with a corridor structure (6) for entering and exiting between the steel frame platform (8) and the mountain peak.
2. The amusement magic net spanning mountain tops according to claim 1, wherein The main body structure (1) further includes a pile foundation structure (5) installed on the mountain peaks, and the main traction structure (3) is fixedly installed between the two pile foundation structures (5).
3. A cross-mountain amusement magic net according to claim 2, characterized in that, The pile foundation structure (5) includes a pile foundation column (501) poured inside the mountain peak and a pile foundation cap (502) poured on the top of the pile foundation column (501). Both ends of the main traction structure (3) are fixedly connected to the pile foundation cap (502).
4. A cross-mountain amusement magic net according to claim 3, characterized in that, The main traction structure (3) includes a main traction cable (301) and a traction cable fixing rod (302). Both ends of the main traction cable (301) are respectively connected to the pile foundation cap (502), and the corridor structure (6) and the steel frame platform (8) are fixedly installed on the main traction cable (301).
5. A cross-mountain amusement magic net according to claim 4, characterized in that, There are multiple main traction cables (301), and the main traction cables (301) are fixedly connected to the traction cable fixing rod (302) to make two adjacent main traction cables (301) parallel to each other.
6. A cross-mountain amusement magic net according to claim 4, characterized in that, The steel frame platform (8) includes longitudinal beams (801), cross beams (802), vertical beams (803), and auxiliary struts (804). The longitudinal beams (801) and cross beams (802) form a frame structure. Vertical beams (803) are arranged around the frame structure, and auxiliary struts (804) are arranged inside the frame. The longitudinal beams (801), cross beams (802), and auxiliary struts (804) are fixedly connected to the main traction cable (301).
7. A cross-mountain amusement magic net according to claim 4, characterized in that, The corridor structure (6) includes a corridor traction cable (601), a corridor floor (602), and a corridor protective net pull rope (604). A corridor floor (602) is arranged on the top of the main traction cable (301). A corridor traction cable (601) is arranged above the corridor floor (602). A corridor protective net pull rope (604) and a protective net (7) are connected between the corridor traction cable (601) and the main traction cable (301).