Telescopic temporary supporting device
Through the telescopic temporary support device, the combination of support legs and telescopic adjustment parts is used to solve the complex and cumbersome problems of installation in the construction of large-span floor bearing plate support, and achieve efficient and low-cost construction results.
Patent Information
- Application Number
- CN202422530373.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2025-08-12
- Estimated Expiration
- 2034-10-18
AI Technical Summary
The existing support structure is complex, cumbersome, low efficiency and high cost in the construction of floor bearing plates, especially when supporting large-span floor bearing plates.
The retractable temporary support device is adopted, including support legs, telescopic support and telescopic adjustment parts. By adjusting the height and length of the support, support for the floor bearing plate is achieved, construction steps are simplified, and material and manpower needs are reduced.
It improves construction efficiency, reduces construction costs, is suitable for building bearing plates with different spans, simplifies the construction process, and enhances the stability and reliability of the support system.
Smart Images

Figure CN223215007U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of construction technology, and in particular to a retractable temporary support device. Background Art
[0002] With the rapid development of steel structure construction, construction projects have placed higher demands on construction schedules. Factory-based production of steel structural components has met these demands. At the same time, ordinary concrete floor slabs have gradually been replaced by steel truss floor decks. During the construction of steel frame floor slabs, steel truss floor decks can be installed directly on steel beams, requiring only tying and welding before concrete pouring can begin.
[0003] However, for some floor deckings with larger spans, the floor deckings need to be supported to improve their strength. Existing support structures mostly involve building steel pipe racks on the ground to the bottom of the floor deckings to support the floor deckings. However, the support structure needs to be built at a high height, which makes the construction complex, cumbersome, inefficient, and increases costs. Utility Model Content
[0004] In order to improve the problem that the height of the floor deck support structure is too high, which leads to complex and cumbersome construction, low efficiency and increased costs, the present application provides a retractable temporary support device.
[0005] The present application provides a retractable temporary support device that adopts the following technical solution:
[0006] A retractable temporary support device comprises several groups of support legs, wherein the groups of support legs are spaced apart along the length direction of a steel frame beam, and each group of support legs is evenly arranged on two opposite steel frame beam bottom plates. Each group of support legs is provided with a retractable support member, and the retractable support member is connected to the support legs on the two steel frame beam bottom plates through a retractable adjustment member. A plurality of uniformly distributed members are cross-arranged on several of the retractable support members, and the retractable adjustment member can adjust the height of the retractable support member so that the uniformly distributed members can support the floor decking.
[0007] By adopting the above technical solution, when supporting a large-span floor deck, the supporting legs are installed on the bottom plate of the steel frame beam, the telescopic adjusting piece is installed on the telescopic supporting piece, and then the telescopic adjusting piece is installed on the supporting legs, and the telescopic supporting piece is placed under the floor deck, and then the uniformly distributed piece is set on the telescopic supporting piece, and finally the height of the telescopic supporting piece is adjusted by the telescopic adjusting piece so that the uniformly distributed piece abuts against the bottom of the floor deck to achieve support for the floor deck. Compared with the existing support structure construction method, this solution does not require the construction of cumbersome steel pipe scaffolding, saving manpower and material resources, and its construction efficiency is high, saving construction period and reducing construction costs.
[0008] In a specific possible implementation scheme, the telescopic support member includes a support beam and a support tube. The support beam is slidably inserted into the support tube to adjust the length of the telescopic support member. A fastening bolt is threaded on the support tube, and the fastening bolt can tighten and fix the support beam on the support tube.
[0009] By adopting the above technical solution, the length of the support beam inserted into the support tube can be adjusted to support floor slabs of different spans; the support beam is fixed by tightening bolts to improve the installation stability between the support beam and the support tube.
[0010] In a specific possible implementation manner, there are a plurality of fastening bolts, and the fastening bolts are evenly spaced along the length direction of the support tube.
[0011] By adopting the above technical solution, the support beam is locked and fixed by adjusting the corresponding fastening bolts according to the different lengths of the support beam extending out of the support tube, so that the support beam and the support tube are fixed more firmly.
[0012] In a specific embodiment, the fastening bolts are arranged at the bottom of the support cylinder.
[0013] By adopting the above technical solution, the fastening bolt is arranged at the bottom of the support tube, which makes it easy to screw the fastening bolt.
[0014] In a specific feasible implementation scheme, the telescopic adjustment member includes a lead screw and an adjusting nut, one end of the lead screw is arranged on the support beam or the support tube, the support leg is provided with a mounting hole for inserting the lead screw, and the adjusting nut is threadedly sleeved on the lead screw, and the adjusting nut can abut against the support leg to adjust the length of the lead screw extending out of the mounting hole.
[0015] By adopting the above technical solution, when adjusting the height of the telescopic support member, the lead screw is inserted into the mounting hole, and then the adjusting nut is rotated to change the position of the adjusting nut on the lead screw to adjust the length of the lead screw extending out of the mounting hole, thereby adjusting the height of the telescopic support member; the lead screw supports the telescopic support member by abutting the adjusting nut against the support leg.
[0016] In a specific possible implementation scheme, the support beam and the support cylinder are both provided with bolt holes for the screw thread to be inserted.
[0017] By adopting the above technical solution, the lead screw is screwed into the bolt hole, thereby improving the convenience of installing the lead screw and the support beam or support cylinder.
[0018] In a specific embodiment, the uniformly distributed pieces are square timbers.
[0019] In a specific possible implementation manner, the square timbers are arranged crosswise with the support beams or the support tubes.
[0020] In summary, this application includes at least one of the following beneficial technical effects:
[0021] 1. When supporting a large-span floor deck, the support legs are installed on the bottom plate of the steel frame beam, the telescopic adjustment piece is installed on the telescopic support piece, and then the telescopic adjustment piece is installed on the support legs. The telescopic support piece is placed under the floor deck, and then the uniform distribution piece is set on the telescopic support piece. Finally, the height of the telescopic support piece is adjusted by the telescopic adjustment piece so that the uniform distribution piece abuts against the bottom of the floor deck to achieve support for the floor deck. Compared with the existing support structure construction method, this solution does not require the installation of cumbersome steel pipe scaffolding, saving manpower and material resources, and its construction efficiency is high, saving construction time and reducing construction costs;
[0022] 2. The telescopic support consists of two parts: the support beam and the support tube. Its length can be freely adjusted, and the support height can be adjusted by the adjustable screw rods at both ends. It is suitable for the construction of floor decks of different sizes.
[0023] 3. All accessories in the temporary support device of this solution are manufactured in the prefabrication yard according to the drawings. During on-site construction, they only need to be installed and adjusted according to the installation sequence, which reduces the construction steps and difficulty and improves the construction efficiency of workers. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural schematic diagram of a retractable temporary support device according to an embodiment of the present application.
[0025] Figure 2 It is along Figure 1 Sectional view along line AA.
[0026] Figure 3 yes Figure 2 Enlarged view of part B in the middle.
[0027] Explanation of the accompanying reference numerals: 1. Support leg; 2. Steel frame beam; 21. Top plate; 22. Bottom plate; 23. Connecting plate; 3. Telescopic support member; 31. Support beam; 32. Support tube; 33. Fastening bolt; 4. Telescopic adjustment member; 41. Lead screw; 42. Adjusting nut; 43. Bolt hole; 44. Mounting hole; 5. Uniformly distributed member; 51. Square timber; 6. Floor decking. DETAILED DESCRIPTION
[0028] The following is combined with Figure 1-3 This application is described in further detail.
[0029] The embodiment of the present application discloses a retractable temporary support device.
[0030] Reference Figure 1 A retractable temporary support device includes a plurality of groups of support legs 1, which are arranged at intervals along the length direction of a steel frame beam 2. The steel frame beam 2 is an H-shaped steel beam consisting of a top plate 21, a bottom plate 22, and a connecting plate 23. The top plate 21 and the bottom plate 22 are arranged in parallel, and the two are fixedly connected by a connecting plate 23. In this embodiment, two adjacent steel frame beams 2 and two groups of support legs 1 are taken as an example. The number of support legs 1 in each group is two. The two support legs 1 in the same group are respectively arranged on the bottom plates 22 of the two steel frame beams 2. The support legs 1 and the bottom plates 22 of the steel frame beams 2 are detachably connected by bolts to facilitate the disassembly and assembly of the support legs 1. The two support legs 1 in the same group are provided with a retractable support member 3. The retractable support member 3 is connected to the two support legs 1 by a retractable adjustment member 4. A plurality of uniformly distributed members 5 are cross-arranged on the two retractable support members 3. The height of the retractable support member 3 can be adjusted by the retractable adjustment member 4 so that the uniformly distributed members 5 can support the floor deck 6.
[0031] When supporting the floor decking 6 with a large span, the two supporting legs 1 of the same group are respectively installed on the bottom plates 22 of the two steel frame beams 2 by bolts, the telescopic adjusting member 4 is installed on the telescopic supporting member 3, and then the telescopic adjusting member 4 is installed on the corresponding supporting leg 1, and the telescopic supporting member 3 is placed under the floor decking 6, and then the uniformly distributed member 5 is set on the telescopic supporting member 3, and finally the height of the telescopic supporting member 3 is adjusted by the telescopic adjusting member 4 so that the uniformly distributed member 5 abuts against the bottom of the floor decking 6 to support the floor decking 6. Compared with the existing support structure construction method, this solution does not require the construction of cumbersome steel pipe scaffolding, saving manpower and material resources, and its construction efficiency is high, saving construction period and reducing construction costs.
[0032] Reference Figure 1 、 Figure 2 The telescopic support member 3 in this embodiment includes a support beam 31 and a support tube 32. The cross-section of the support beam 31 is rectangular, and the support tube 32 is a rectangular tube that cooperates with the support beam 31. The support beam 31 is slidably inserted into the support tube 32, and by adjusting the length of the support beam 31 extending outward from the support tube 32, the length of the telescopic support member 3 can be adjusted. Its length can be freely adjusted to suit the use in different span working conditions.
[0033] Reference Figure 2 、 Figure 3The support tube 32 is threaded with a plurality of fastening bolts 33. In this embodiment, four fastening bolts 33 are used as an example. Each of the four fastening bolts 33 is disposed on the bottom wall of the support tube 32, making it easier for workers to tighten the fastening bolts 33. The four fastening bolts 33 are evenly spaced along the length of the support tube 32. Rotating the fastening bolts 33 secures the support beam 31 to the support tube 32. Depending on the length of the support beam 31 extending out of the support tube 32, the corresponding fastening bolts 33 are adjusted to tighten the support beam 31, further securing the support beam 31 to the support tube 32.
[0034] Reference Figure 2 、 Figure 3 The telescopic adjustment member 4 in this embodiment includes a lead screw 41 and an adjustment nut 42. In other embodiments, these may be replaced by a hydraulic cylinder. Bolt holes 43 are provided at the ends of the support beam 31 and the support tube 32 that are away from each other. The lead screw 41 is screwed into the bolt hole 43 to achieve a detachable connection with the support beam 31 or the support tube 32. The support leg 1 is provided with a mounting hole 44 for inserting the lead screw 41. When installing the lead screw 41 and the support leg 1, the lead screw 41 is inserted into the mounting hole 44 from top to bottom. The adjustment nut 42 is threaded onto the lead screw 41. The diameter of the adjustment nut 42 is larger than the diameter of the mounting hole 44, so that the adjustment nut 42 can abut against the support leg 1, thereby providing support for the telescopic support member 3. By changing the position of the adjustment nut 42 on the lead screw 41, the length of the lead screw 41 extending out of the mounting hole 44 can be adjusted, thereby adjusting the height of the telescopic support member 3.
[0035] Reference Figure 1 、 Figure 2 The uniformly distributed member 5 in this embodiment is a square timber 51, which is arranged crosswise with the support beam 31 or the support tube 32. The square timber 51 is arranged perpendicular to the support beam 31, which increases the stability of the overall structure. The square timber 51 is a long strip member with a rectangular cross-section, and the length is adjusted according to actual needs. The material is usually hard wood, which can withstand large loads and has good stability. An alternative feature of the square timber 51 can be a steel plate, which can also play the role of uniformly distributing the load, and its thickness and width are designed according to actual requirements. The support beam 31 and the support tube 32 provide support for the square timber 51, and the square timber 51 distributes the load evenly to the support beam 31 and the support tube 32, and disperses it to the entire temporary support device, ensuring the stability and reliability of the entire system. This design not only meets the construction requirements of steel truss floor slabs 6 of different spans, but also improves construction efficiency and reduces material and labor costs.
[0036] The implementation principle of a retractable temporary support device in an embodiment of the present application is as follows: by adopting the design of a retractable support beam 31 and a support tube 32, the length of the temporary support device is flexibly adjusted to meet the construction requirements of steel truss floor decking slabs 6 of different spans. At the same time, combined with the design of the height adjustment screw 41, the height of the entire temporary support device can be easily adjusted, which greatly facilitates the construction process and simplifies the construction process. This combination not only improves the adaptability and convenience of the temporary support device, but also enhances the overall stability and reliability of the support system, significantly improves construction efficiency and reduces construction costs. In addition, through the reasonable setting of the uniformly distributed parts 5, the uniform force on the floor decking slab 6 is further ensured, ensuring the reliability and safety of the entire temporary support device in actual application.
[0037] The above are all preferred embodiments of the present application, and are not intended to limit the scope of protection of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the scope of protection of the present application.
Claims
1. A retractable temporary support device, characterized in that: The invention comprises a plurality of groups of support legs (1), wherein the plurality of groups of support legs (1) are arranged at intervals along the length direction of the steel frame beam (2), and each group of support legs (1) is evenly arranged on the bottom plates (22) of two opposite steel frame beams (2). Each group of support legs (1) is provided with a telescopic support member (3), and the telescopic support member (3) is connected to the support legs (1) on the bottom plates (22) of the two steel frame beams (2) through a telescopic adjustment member (4). A plurality of uniformly distributed members (5) are cross-arranged on the plurality of telescopic support members (3), and the telescopic adjustment member (4) can adjust the height of the telescopic support member (3) so that the uniformly distributed member (5) can support the floor deck (6).
2. The retractable temporary support device according to claim 1, characterized in that: The telescopic support member (3) comprises a support beam (31) and a support tube (32); the support beam (31) is slidably inserted into the support tube (32) so as to be able to adjust the length of the telescopic support member (3); a fastening bolt (33) is threadedly connected to the support tube (32); the fastening bolt (33) can tightly fix the support beam (31) on the support tube (32).
3. The retractable temporary support device according to claim 2, characterized in that: The number of the fastening bolts (33) is several, and the several fastening bolts (33) are evenly spaced along the length direction of the support tube (32).
4. The retractable temporary support device according to claim 2, characterized in that: The fastening bolt (33) is arranged at the bottom of the support cylinder (32).
5. The retractable temporary support device according to claim 2, characterized in that: The telescopic adjustment member (4) comprises a lead screw (41) and an adjusting nut (42); one end of the lead screw (41) is arranged on the support beam (31) or the support tube (32); a mounting hole (44) for inserting the lead screw (41) is provided on the support leg (1); the adjusting nut (42) is threadedly sleeved on the lead screw (41); the adjusting nut (42) can abut against the support leg (1) to adjust the length of the lead screw (41) extending out of the mounting hole (44).
6. The retractable temporary support device according to claim 5, characterized in that: The support beam (31) and the support cylinder (32) are both provided with bolt holes (43) for threaded insertion of the lead screw (41).
7. The retractable temporary support device according to claim 2, characterized in that: The evenly distributed pieces (5) are square timbers (51).
8. The retractable temporary support device according to claim 7, characterized in that: The square timber (51) and the support beam (31) or the support tube (32) are arranged in a cross-like manner.