Steel beam component hoisting structure
By installing a four-sided platform on top of the steel beam component, the problems of low construction efficiency and major safety hazards caused by the reinstallation of the suspended platform during the installation of the steel beam component were solved, and efficient and safe four-sided bolt connection operation was achieved.
Patent Information
- Application Number
- CN202422503570.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-16
- Publication Date
- 2025-10-28
- Estimated Expiration
- 2034-10-16
AI Technical Summary
In the existing technology, when installing steel beam components, workers need to stand and work on all four sides of the top of the vertical steel beam at a high position, which leads to the reinstallation and adjustment of the suspended platform, reducing construction efficiency and increasing safety hazards.
Design a steel beam component hoisting structure including a four-sided platform. The platform consists of a load-bearing bottom pipe, a support pipe, platform steps, and guardrails, allowing workers to walk on the four sides of the steel beam and realize four-sided bolt connection operations.
It improves construction efficiency, reduces safety hazards, and avoids the need for reinstallation and adjustment of the suspended platform through the design of the four-sided platform.
Smart Images

Figure CN223482241U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to a steel beam component hoisting structure, belonging to the technical field of steel beam component hoisting. Background Technology
[0002] When steel beam components are installed and spliced to form a steel structure frame, the top four sides of the vertical steel beam components are connected by bolts. Therefore, workers need to stand on the top four sides of the vertical steel beam components to carry out their work.
[0003] The technology of providing a standing environment on steel beams is available in Chinese Patent Publication No. CN204826589U. Although the suspended platform can be installed on one side of the steel beam to create a standing environment through the suspension structure, when workers need to stand in the other three directions, the suspended platform needs to be reinstalled and adjusted. Since the steel structure frame is high above the ground, the reinstallation and adjustment of the suspended platform leads to a significant reduction in construction efficiency and safety hazards. Utility Model Content
[0004] To solve the above-mentioned technical problems, this utility model provides a steel beam component hoisting structure.
[0005] This utility model is achieved through the following technical solution.
[0006] This utility model provides a steel beam component hoisting structure, comprising:
[0007] Vertical steel beam components and four-sided platforms clamped and installed on the top of the vertical steel beam components.
[0008] The four platforms are equipped with lifting cables for connecting the construction tower crane.
[0009] The four-sided platform includes a load-bearing bottom pipe, pipe clamps, a support pipe, a front platform pedal, a rear platform pedal, a left platform pedal, and a right platform pedal.
[0010] The load-bearing bottom pipe consists of two spaced-apart pipes, each equipped with a pipe clamp to hold the vertical steel beam component.
[0011] The two load-bearing bottom pipes are fixed with receiving pipes at both ends. Front platform pedals and rear platform pedals are fixedly installed on the receiving pipes. Left platform pedals and right platform pedals are fixedly installed on both ends of the front platform pedals and rear platform pedals respectively. The front platform pedals, rear platform pedals, left platform pedals and right platform pedals are distributed on the four sides of the vertical steel beam components for workers to step on.
[0012] The receiving pipe end is fixed with a guardrail installation pipe, and the guardrail installation pipes are connected to each other through guardrail pipes.
[0013] The guardrail tubes are four tubes spaced at a certain height above the front platform tread, rear platform tread, left platform tread, and right platform tread. The guardrail installation tubes and the receiving tubes together form the guardrail body for protection.
[0014] The beneficial effects of this utility model are as follows: workers can walk on the front platform pedal, rear platform pedal, left platform pedal, and right platform pedal on the four sides of the vertical steel beam component, enabling workers to perform bolt connection operations on the top four sides of the vertical steel beam component and connect it to the horizontal steel beam component. This solves the problem that the suspended platform for the standing environment of the distributed steel beam on one side needs to be reinstalled and adjusted, which leads to reduced construction efficiency and significant safety hazards. Attached Figure Description
[0015] Figure 1 This is a structural schematic diagram of the vertical steel beam component and the horizontal steel beam component of this utility model when they are joined together;
[0016] Figure 2 This is a schematic diagram of the structure of the four-sided platform of this utility model on a vertical steel beam component;
[0017] Figure 3 This is a schematic diagram of the structure of the four-sided platform of this utility model;
[0018] In the diagram: 1-Vertical steel beam component; 2-Four-sided platform; 3-Suspension cable; 5-Horizontal steel beam component;
[0019] 21-Bottom support pipe; 22-Pipe clamp; 23-Support pipe; 24-Front platform step; 25-Rear platform step; 26-Left platform step; 27-Right platform step; 28-Guardrail installation pipe; 29-Guardrail pipe. Detailed Implementation
[0020] The technical solution of this utility model is further described below, but the scope of protection is not limited to what is described.
[0021] like Figures 1 to 3 As shown.
[0022] This application discloses a steel beam component hoisting structure, comprising:
[0023] The four-sided platform 2 is clamped and installed on the top of the vertical steel beam component 1. The four-sided platform 2 is connected to the construction tower crane through the lifting cable 3. The number of lifting cables 3 and the connection position are adapted according to the actual construction situation.
[0024] The four-sided platform 2 includes two spaced-apart load-bearing bottom pipes 21, each load-bearing bottom pipe 21 is equipped with a pipe clamp 22 for clamping the vertical steel beam component 1;
[0025] Two load-bearing bottom pipes 21 are fixed with receiving pipes 23 at both ends. Front platform pedals 24 and rear platform pedals 25 are fixedly installed on the receiving pipes 23. Left platform pedals 26 and right platform pedals 27 are fixedly installed on the front platform pedals 24 and rear platform pedals 25 respectively. The front platform pedals 24, rear platform pedals 25, left platform pedals 26 and right platform pedals 27 are distributed on the four sides of the vertical steel beam component 1 for workers to step on.
[0026] The end of the receiving pipe 23 is fixed with a guardrail installation pipe 28. The guardrail installation pipes 28 are connected by guardrail pipes 29. The guardrail pipes 29 are four in number, spaced apart at a certain height above the front platform pedal 24, rear platform pedal 25, left platform pedal 26, and right platform pedal 27. The guardrail installation pipes 28 and the receiving pipe 23 form a guardrail body for protection.
[0027] Workers can walk on the front platform pedal 24, rear platform pedal 25, left platform pedal 26, and right platform pedal 27 on the four sides of the vertical steel beam component 1, enabling them to bolt the top four sides of the vertical steel beam component 1 to connect with the horizontal steel beam component 5. This solves the problem that the suspended platform required to be reinstalled and adjusted when the standing environment is constructed on one side of the distributed steel beam, which leads to reduced construction efficiency and significant safety hazards.
[0028] This application discloses a method for hoisting and assembling steel beam components, comprising:
[0029] The bottom of the vertical steel beam component 1 is fixed, and the construction tower crane connects to the four-sided platform through the hoisting cable 3. At this time, the steel beam component hoisting structure is presented. The workers walk on the four-sided platform 2 on the top of the vertical steel beam component 1 to carry out bolt connection operations on the top four sides of the vertical steel beam component 1 to connect with the construction process of the horizontal steel beam component 5.
Claims
1. A steel beam component hoisting structure, characterized in that, include: Vertical steel beam member (1) and four-sided platform (2) clamped and installed on the top of vertical steel beam member (1); The four-sided platform (2) includes a load-bearing bottom tube (21), a tube buckle (22), a receiving tube (23), a front platform pedal (24), a rear platform pedal (25), a left platform pedal (26), and a right platform pedal (27).
2. The steel beam component hoisting structure as described in claim 1, characterized in that: The four-sided platform (2) is equipped with lifting cables (3) for connecting the construction tower crane.
3. The steel beam component hoisting structure as described in claim 1, characterized in that: The load-bearing bottom pipe (21) consists of two spaced-apart pipes, each of which is equipped with a pipe clamp (22) for clamping the vertical steel beam component (1).
4. The steel beam component hoisting structure as described in claim 1, characterized in that: The two load-bearing bottom pipes (21) are fixed with receiving pipes (23) at both ends. The receiving pipes (23) are fixedly installed with front platform pedals (24) and rear platform pedals (25). The front platform pedals (24) and rear platform pedals (25) are fixedly installed with left platform pedals (26) and right platform pedals (27) at both ends. The front platform pedals (24), rear platform pedals (25), left platform pedals (26), and right platform pedals (27) are distributed on the four sides of the vertical steel beam component (1) for workers to step on.
5. The steel beam component hoisting structure as described in claim 1, characterized in that: The end of the receiving pipe (23) is fixed with a guardrail installation pipe (28), and the guardrail installation pipes (28) are connected to each other through guardrail pipes (29).
6. The steel beam component hoisting structure as described in claim 5, characterized in that: The guardrail pipes (29) are four pipes spaced at a certain height above the front platform pedal (24), rear platform pedal (25), left platform pedal (26), and right platform pedal (27). The guardrail installation pipe (28) and the receiving pipe (23) together form the guardrail body for protection.