Modularized bridge deck runoff emergency treatment pond

Through modular design and multi-stage purification, the problem of poor purification effect of bridge runoff emergency treatment pool in daily rainwater runoff treatment has been solved, achieving efficient purification effect and convenient cleaning operation, and enhancing the stability of the equipment.

CN223723597UActive Publication Date: 2025-12-26CHINA ACAD OF TRANSPORTATION SCI +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520038332.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-08
Publication Date
2025-12-26
Estimated Expiration
2035-01-08

AI Technical Summary

Technical Problem

Existing emergency treatment ponds for bridge runoff are not effective in purifying daily rainwater runoff, especially when runoff is continuously flowing in and the sedimentation effect is not ideal.

Method used

The system adopts a modular design, including an inlet pool, a transition pool, and an outlet treatment pool. Through the combination of inlet pipes, distribution weirs, filter holes, and adsorption materials, it achieves multi-stage purification treatment of bridge surface runoff. The addition of ladders and reinforcement frames improves operational convenience and structural stability.

Benefits of technology

It improves the purification effect of the bridge deck runoff emergency treatment pool on daily rainwater runoff, enhances sedimentation and filtration capabilities, simplifies the cleaning process, and improves the durability of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223723597U_ABST
    Figure CN223723597U_ABST
Patent Text Reader

Abstract

The utility model relates to a modular bridge deck runoff emergency treatment pond, and relates to the field of bridge deck runoff emergency treatment.The device comprises a pond body, a first partition plate is fixedly connected to an inner cavity of the pond body, a second partition plate is fixedly connected to the front face of the first partition plate, a water distribution weir is fixedly connected to the right side of the second partition plate, and a water inlet pond is arranged on the left side of the second partition plate. The bridge floor runoff can be discharged into the inner cavity of the water inlet tank through the water inlet pipe, so that the bridge floor runoff overflows the water distribution weir and enters the inner cavity of the transition tank, large solid impurities are left in the inner cavity of the water inlet tank at the moment, and the bridge floor runoff penetrates through the filter holes and slowly enters the inner cavity of the discharge treatment tank; at the moment, the adsorption material in the discharge treatment pond can perform adsorption treatment on residual impurities in the bridge surface runoff, and the treated bridge surface can be discharged through the drainage pipe group, so that the situation that the bridge surface runoff emergency treatment pond has a poor purification treatment effect on daily rainwater runoff is avoided, and the purification effect of the bridge surface runoff emergency treatment pond is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of bridge deck runoff emergency treatment, in particular to a modular bridge deck runoff emergency treatment pool. BACKGROUND

[0002] The bridge deck runoff emergency treatment pool is a facility for treating bridge deck runoff pollution, mainly playing a role in dealing with sudden leakage of dangerous chemicals or other pollutant emissions to prevent serious pollution to the water body under the bridge and the surrounding ecological environment. The bridge deck runoff emergency treatment pool mostly uses oil separation and sedimentation measures to remove runoff pollutants, and has good removal effect on oil and easily sedimentable large particle pollutants.

[0003] At present, the bridge deck runoff is mostly treated by the bridge deck runoff emergency treatment pool. When the bridge deck runoff emergency treatment pool purifies the daily rainwater runoff, it is usually necessary to keep the pool in a long-time stationary state to achieve sufficient sedimentation and evaporation effect. When the runoff continues to flow in, the liquid in the pool is disturbed greatly, and the sedimentation effect is poor. Therefore, a modular bridge deck runoff emergency treatment pool is needed, which can set three modules with different structures and auxiliary components in the pool to purify the rainwater runoff, avoid poor purification effect of the bridge deck runoff emergency treatment pool on the daily rainwater runoff, and ensure the purification effect of the bridge deck runoff emergency treatment pool. CONTENT OF THE INVENTION

[0004] In order to solve the existing technical problems, the present application provides a modular bridge deck runoff emergency treatment pool.

[0005] The modular bridge deck runoff emergency treatment pool provided by the present application adopts the following technical scheme: a modular bridge deck runoff emergency treatment pool, comprising a pool body, a partition plate one is fixedly connected in the inner cavity of the pool body, a partition plate two is fixedly connected to the front surface of the partition plate one, a water distribution weir is fixedly connected to the right side of the partition plate two, a water inlet pool is arranged on the left side of the partition plate two, a transition pool is arranged on the right side of the partition plate two, a discharge treatment pool is arranged on the back surface of the partition plate one, a water inlet pipe is arranged on the left side of the pool body and penetrates into the inner cavity of the water inlet pool, a drain pipe group is arranged on the left side of the pool body, a fixing frame is fixedly connected to the top of the pool body, a liquid level monitor is fixedly connected to the top of the fixing frame, and three same filter holes are formed in the front surface of the partition plate one.

[0006] By adopting the above technical scheme, the bridge deck runoff is discharged into the inner cavity of the water inlet pool through the water inlet pipe, so that the bridge deck runoff flows over the water distribution weir into the inner cavity of the transition pool, at this time, the large solid impurities are left in the inner cavity of the water inlet pool, and the bridge deck runoff slowly enters the inner cavity of the discharge treatment pool through the filter hole, at this time, the bridge deck runoff is deposited in the discharge treatment pool, and the deposited bridge deck is discharged through the drain pipe group, thereby avoiding that the bridge deck runoff emergency treatment pool has poor purification treatment effect on daily rainwater runoff, and ensuring the purification effect of the bridge deck runoff emergency treatment pool.

[0007] Preferably, the front surface of the inner cavity of the transition pool and the back surface of the inner cavity of the discharge treatment pool are fixedly connected with a ladder, and the bottom of the ladder is not in contact with the pool body.

[0008] By adopting the above technical scheme, when the inner walls of the water inlet pool, the transition pool and the discharge treatment pool have many impurities, the user can enter the inside of the water inlet pool, the transition pool and the discharge treatment pool through the ladder to clean them, thereby avoiding the need to carry a ladder and other tools to enter the inside of the water inlet pool, the transition pool and the discharge treatment pool to clean them, and increasing the convenience of cleaning the inside of the water inlet pool, the transition pool and the discharge treatment pool.

[0009] Preferably, the drain pipe group comprises a drain pipe one penetratingly arranged on the left side of the pool body, a drain pipe two penetratingly arranged on the left side of the pool body, a drain valve arranged on the surface of the drain pipe one and the drain pipe two, a connecting pipe arranged on the left side of the pool body, and a water outlet pipe communicated with the left side of the connecting pipe.

[0010] Preferably, the pool body is fixedly connected with a reinforcing frame on the left side, and the reinforcing frame is sleeved on the surface of the connecting pipe.

[0011] By adopting the above technical scheme, when the connecting pipe is used for drainage, the reinforcing frame can limit and fix the connecting pipe, thereby avoiding that the water flow shakes the connecting pipe, preventing the connecting pipe from being broken due to the impact of the water flow, and increasing the firmness of the connecting pipe.

[0012] Preferably, the height of the second partition plate is lower than that of the first partition plate, the transition pool and the discharge treatment pool are communicated through the filter hole, the bottom of the inner cavity of the discharge treatment pool is paved with an adsorption material, and the top of the water distribution weir is concave-convex.

[0013] Preferably, the water inlet pipe is located at the lower left of the inner cavity of the water inlet pool, the drain pipe one is located below the drain pipe two, and the water outlet pipe is located below the drain pipe one.

[0014] Preferably, the fixing frame is L-shaped, the inner cavity of the filter hole is provided with a filter screen, and the filter hole is a square opening.

[0015] In summary, the present application includes at least one of the following beneficial technical effects:

[0016] 1、The utility model discloses a bridge deck runoff is arranged into the inner chamber of water inlet pool through the water inlet pipe, makes the bridge deck runoff enter the inner chamber of transition pool through the water distribution weir, at this moment, the large solid impurities can be left in the inner chamber of water inlet pool, and the bridge deck runoff can slowly enter the inner chamber of discharge treatment pool through the filter hole, at this moment, the adsorbing material in the discharge treatment pool can carry out adsorption treatment to the impurities remaining in the bridge deck runoff, and the treated bridge deck can be discharged through the drain pipe group, avoids that the bridge deck runoff emergency treatment pool is not good at the purification treatment effect of daily rainwater runoff, guarantees the purification effect of bridge deck runoff emergency treatment pool.

[0017] 2、The utility model discloses the setting of the ladder, when the inner wall of water inlet pool, transition pool and discharge treatment pool is more impurities, the user can enter the inside of water inlet pool, transition pool and discharge treatment pool and carry out the dredging through the ladder, avoids the need to carry the ladder and other tools and enters the inside of water inlet pool, transition pool and discharge treatment pool and carries out the dredging, increases the convenience of the dredging of the inside of water inlet pool, transition pool and discharge treatment pool.

[0018] 3、The utility model discloses the setting of the reinforcing frame, when the connecting pipe carries out drainage, and the reinforcing frame can limit and fix the connecting pipe, avoids that the water flow impact connecting pipe makes it sway, prevents the connecting pipe from breaking because of the impact of water flow, increases the firmness of connecting pipe. BRIEF DESCRIPTION OF DRAWINGS

[0019] Figure 1 It is the three-dimensional schematic view of the structure of the utility model.

[0020] Figure 2 It is the overhead schematic view of the structure of the utility model.

[0021] Figure 3 It is the front view cross section schematic view of the structure of the utility model.

[0022] Figure 4 It is the right view cross section schematic view of the structure of the utility model.

[0023] Mark the drawings: 1, pool body;2, baffle one;3, baffle two;4, water distribution weir;5, water inlet pool;6, transition pool;7, discharge treatment pool;8, water inlet pipe;9, drain pipe group;91, drain pipe one;92, drain pipe two;93, drain valve;94, connecting pipe;95, outlet pipe;10, fixed frame;11, liquid level monitor;12, filter hole;13, ladder;14, reinforcing frame. DETAILED DESCRIPTION

[0024] The following combines the drawings Figures 1-4 Make further detailed description to the present application.

[0025] Example one:

[0026] In combination Figure 1 , Figure 2 , Figure 3 and Figure 4 , the embodiment of the application discloses a modular bridge deck runoff emergency treatment pool, which comprises a pool body 1, the inner cavity of the pool body 1 is fixedly connected with a partition plate one 2, the front surface of the partition plate one 2 is fixedly connected with a partition plate two 3, the height of the partition plate two 3 is lower than that of the partition plate one 2, a transition pool 6 and a discharge treatment pool 7 are communicated through filter holes 12, the bottom of the inner cavity of the discharge treatment pool 7 is paved with adsorption material, the top of the water distribution weir 4 is concave-convex, the right side of the partition plate two 3 is fixedly connected with the water distribution weir 4, the left side of the partition plate two 3 is provided with a water inlet pool 5, the right side of the partition plate two 3 is provided with the transition pool 6, the front surface of the inner cavity of the transition pool 6 and the back surface of the inner cavity of the discharge treatment pool 7 are fixedly connected with a ladder 13, the bottom of the ladder 13 is not in contact with the pool body 1, through the setting of the ladder 13, when there are many impurities on the inner walls of the water inlet pool 5, the transition pool 6 and the discharge treatment pool 7, the user can enter the interiors of the water inlet pool 5, the transition pool 6 and the discharge treatment pool 7 through the ladder 13 to clean, avoiding the need to carry a ladder and other tools to enter the interiors of the water inlet pool 5, the transition pool 6 and the discharge treatment pool 7 to clean, thereby increasing the convenience of cleaning the interiors of the water inlet pool 5, the transition pool 6 and the discharge treatment pool 7, the back surface of the partition plate one 2 is provided with the discharge treatment pool 7, the left side of the pool body 1 is provided with a water inlet pipe 8, the water inlet pipe 8 is located at the lower left of the inner cavity of the water inlet pool 5, a first drainage pipe 91 is located below a second drainage pipe 92, a water outlet pipe 95 is located below the first drainage pipe 91, the water inlet pipe 8 penetrates into the inner cavity of the water inlet pool 5, the left side of the pool body 1 is provided with a drainage pipe group 9, the top of the pool body 1 is fixedly connected with a fixing frame 10, the fixing frame 10 is L-shaped, the inner cavity of the filter hole 12 is provided with a filter screen, the filter hole 12 is a square opening, the top of the fixing frame 10 is fixedly connected with a liquid level monitor 11, and three same filter holes 12 are formed in the front surface of the partition plate one 2.

[0027] Embodiment two

[0028] In combination Figure 3 and Figure 4 , the drainage pipe group 9 comprises the first drainage pipe 91 penetrating through the left side of the pool body 1, the second drainage pipe 92 penetrating through the left side of the pool body 1, the surfaces of the first drainage pipe 91 and the second drainage pipe 92 are provided with drainage valves 93, the left side of the pool body 1 is provided with a connecting pipe 94, the first drainage pipe 91 and the second drainage pipe 92 are communicated with the connecting pipe 94, the left side of the connecting pipe 94 is communicated with the water outlet pipe 95, the left side of the pool body 1 is fixedly connected with a reinforcing frame 14, the reinforcing frame 14 is sleeved on the surface of the connecting pipe 94, through the setting of the reinforcing frame 14, when the connecting pipe 94 is used for drainage, the reinforcing frame 14 can limit and fix the connecting pipe 94, avoiding that the connecting pipe 94 shakes due to water flow impact, preventing the connecting pipe 94 from being broken due to water flow impact, and increasing the firmness of the connecting pipe 94.

[0029] Working principle: when the utility model for use, the user through the inlet pipe 8 will bridge flow into the inner chamber of the inlet pool 5, bridge flow will be through the water distribution weir 4 into the inner chamber of the transition pool 6, at this time the solid impurities in bridge flow will be left in the inner chamber of the inlet pool 5, bridge flow enters the transition pool 6 will pass through the filter hole 12 into the inner chamber of the discharge treatment pool 7, filter hole 12 will be secondary filtration to bridge flow, make small impurities remain in the inner chamber of the transition pool 6, bridge flow enters the discharge treatment pool 7, the adsorbent material at the bottom of the discharge treatment pool 7 will be adsorbed to the residual impurities in bridge flow, after treatment, open the drain valve 93, can make drain pipe one 91, drain pipe two 92, connecting pipe 94 and outlet pipe 95 to bridge flow discharge, avoid the purification effect of bridge flow emergency treatment pool to daily rainwater runoff is poor, ensure the purification effect of bridge flow emergency treatment pool.

[0030] Summarized above: the modular bridge flow emergency treatment pool, through inlet pipe 8 will bridge flow into the inner chamber of the inlet pool 5, make bridge flow over the water distribution weir 4 into the inner chamber of the transition pool 6, at this time the solid impurities will be left in the inner chamber of the inlet pool 5, bridge flow will pass through the filter hole 12 slowly into the inner chamber of the discharge treatment pool 7, at this time the adsorbent material inside the discharge treatment pool 7 will be adsorbed to the residual impurities in bridge flow, the bridge after treatment will be discharged through the drain pipe group 9, avoid the purification effect of bridge flow emergency treatment pool to daily rainwater runoff is poor, ensure the purification effect of bridge flow emergency treatment pool.

[0031] The above are the preferred embodiments of the present application, not limited by the protection scope of the present application, therefore: all equivalent changes made according to the structure, shape, principle of the present application should be covered in the protection scope of the present application.

Claims

1. A modular bridge deck runoff emergency treatment pond, characterized by: The utility model relates to a water treatment device, including pool body (1), the inner chamber of pool body (1) is fixedly connected with baffle one (2), the front of baffle one (2) is fixedly connected with baffle two (3), the right side of baffle two (3) is fixedly connected with water distribution weir (4), the left side of baffle two (3) is provided with water inlet pool (5), the right side of baffle two (3) is provided with transition pool (6), the back of baffle one (2) is provided with discharge treatment pool (7), the left side of pool body (1) is provided with water outlet pipe group (9), the top of pool body (1) is fixedly connected with fixed frame (10), the top of fixed frame (10) is fixedly connected with liquid level monitor (11), the front of baffle one (2) is provided with three same filter holes (12).

2. A modular bridge deck runoff emergency treatment pond according to claim 1, characterized in that: The front of the inner chamber of the transition pool (6) and the back of the inner chamber of the discharge treatment pool (7) are fixedly connected with a ladder (13), and the bottom of the ladder (13) is not in contact with the pool body (1).

3. A modular bridge deck runoff emergency treatment pond according to claim 2, wherein: The water outlet pipe group (9) comprises a water outlet pipe one (91) penetrating through the left side of the pool body (1), a water outlet pipe two (92) penetrating through the left side of the pool body (1), a water outlet valve (93) arranged on the surface of the water outlet pipe one (91) and the water outlet pipe two (92), a connecting pipe (94) arranged on the left side of the pool body (1), and the water outlet pipe one (91) and the water outlet pipe two (92) are in communication with the connecting pipe (94), and the left side of the connecting pipe (94) is communicated with a water outlet pipe (95).

4. A modular bridge deck runoff emergency treatment pond according to claim 3, wherein: The left side of the pool body (1) is fixedly connected with a reinforcing frame (14), and the reinforcing frame (14) is sleeved on the surface of the connecting pipe (94).

5. A modular bridge deck runoff emergency treatment pond according to claim 4, wherein: The height of the baffle two (3) is lower than the height of the baffle one (2), the transition pool (6) and the discharge treatment pool (7) are in communication through the filter holes (12), the bottom of the inner chamber of the discharge treatment pool (7) is paved with an adsorbent material, and the top of the water distribution weir (4) is concave-convex.

6. A modular bridge deck runoff emergency treatment pond according to claim 5, wherein: The water inlet pipe (8) is located at the lower left of the inner chamber of the water inlet pool (5), the water outlet pipe one (91) is located below the water outlet pipe two (92), and the water outlet pipe (95) is located below the water outlet pipe one (91).

7. A modular bridge deck runoff emergency treatment pond according to claim 6, wherein: The fixed frame (10) is L-shaped, the inner chamber of the filter hole (12) is provided with a filter screen, and the filter hole (12) is a square opening.