Comprehensive platform for rapid seam pressing during installation of pressure steel pipe

By integrating jacks, working platforms, and rollers into a comprehensive platform, rapid seam pressing and welding of pressure steel pipes has been achieved, solving the problems of long construction cycles and difficulty in controlling precision in traditional methods, and improving construction efficiency and quality.

CN223776424UActive Publication Date: 2026-01-09CHINA POWER CONSTRUCTION 14TH BUREAU (GUANGDONG) NEW ENERGY EQUIPMENT MANUFACTURING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520790908.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-23
Publication Date
2026-01-09
Estimated Expiration
2035-04-23

AI Technical Summary

Technical Problem

Traditional pressure steel pipe installation methods involve long construction cycles, high labor intensity, difficulty in precision control, and difficulty in ensuring construction quality. They also lack efficient integrated operation methods and advanced auxiliary equipment.

Method used

Design an integrated platform that combines jacks, a working platform, rollers, and other components to enable the jacks to rotate omnidirectionally inside the pressure steel pipe, providing a safe and flexible construction environment and supporting rapid seam pressing and welding operations.

Benefits of technology

It improves the efficiency and accuracy of pressure steel pipe installation, provides a safe and stable construction platform, is suitable for hydropower stations and large-scale water transmission pipeline projects, simplifies the construction process, and improves construction quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223776424U_ABST
    Figure CN223776424U_ABST
Patent Text Reader

Abstract

The comprehensive platform comprises a supporting base, a working platform, positioning plates, shaft pipes, jacking pipes and jacks, the working platform is erected on the supporting base, rolling wheels are installed at the bottom of the supporting base, the positioning plates are installed in the middles of the two ends of the working platform, mounting holes are formed in the positioning plates, and the shaft pipes are rotationally connected into the mounting holes; the end of the shaft pipe is in threaded connection with a jacking pipe to form a T-shaped structure, and jacks are installed at the two ends of the jacking pipe respectively. The comprehensive operation platform is built to assist operation, a horizontal and safe construction platform can be provided in the circular steel pipe, equipment placement is facilitated, seam pressing, reinforcing, welding and construction of the welding procedure are facilitated, the jack can rotate in all directions in the pressure steel pipe, and therefore dead-corner-free operation is achieved; rapid seam pressing and comprehensive operation in the pressure steel pipe are achieved, and the flexibility and efficiency of the platform are improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of water conservancy and hydropower engineering, and particularly relates to a comprehensive platform for rapid joint pressing during installation of a pressure steel pipe. BACKGROUND

[0002] With the rapid development of modern water conservancy and hydropower engineering, the requirements for construction quality are increasingly strict, and construction technology needs to be continuously innovated. As a key water conveying component in a hydropower station, the installation quality of a pressure steel pipe directly relates to the safety and benefits of the entire project. The traditional pressure steel pipe installation method has problems such as a long construction period, high labor intensity, and difficult precision control, and has been difficult to meet the needs of modern engineering construction. Therefore, it is particularly urgent to develop an efficient, accurate, and rapid pressure steel pipe installation method.

[0003] The traditional pressure steel pipe installation method has many drawbacks: (1) The operation of the traditional installation process is relatively complex, the entire installation process takes a long time, and the work efficiency is low. Due to the lack of an efficient integrated operation mode, a large amount of time is consumed for each step, thereby lengthening the construction period. (2) The lack of advanced auxiliary equipment, the steel pipe installation often adopts a wedge pressing plate joint pressing process, the joint pressing precision is not high and is easy to cause a certain degree of damage to the base material, thereby affecting the overall strength and service life of the steel pipe. (3) The traditional installation method uses a simple construction platform for construction, and the disordered stacking of construction equipment becomes the norm, which is not conducive to the welding of the top girth joint, and the construction quality is difficult to guarantee. CONTENT OF THE NEW MODEL

[0004] To solve or partially solve the problems in the related art, the present application provides a comprehensive platform for rapid joint pressing during installation of a pressure steel pipe, which integrates a jack, a work platform, a roller, and other components into one, forms a highly integrated comprehensive platform, and enables the jack to rotate in all directions inside the pressure steel pipe, thereby realizing rapid joint pressing and comprehensive operation inside the pressure steel pipe.

[0005] The first aspect of the present application provides a comprehensive platform for rapid joint pressing during installation of a pressure steel pipe, which comprises a support base, a work platform, a positioning plate, a shaft pipe, a top pipe, and a jack. The support base is provided with the work platform, and the bottom is provided with a roller. The work platform is provided with the positioning plate at the middle of both ends. The positioning plate is provided with a mounting hole, and the shaft pipe is rotatably connected in the hole. The shaft pipe is threadedly connected with the top pipe to form a "T-shaped" structure, and the top pipe is provided with the jack at both ends.

[0006] The work platform is provided with a protective fence on the outside.

[0007] The support base is further provided with a storage platform at the bottom.

[0008] The mounting hole is connected with the shaft pipe through a bearing. The outer ring of a deep groove ball bearing is mounted in the mounting hole, and the inner ring is sleeved on the shaft pipe.

[0009] The technical scheme provided in the application can have the following beneficial effects:

[0010] The application provides a comprehensive platform for quickly pressing a joint of a pressure steel pipe. The comprehensive platform is used for assisting work, and a horizontal and safe construction platform is provided in the pressure steel pipe, which is beneficial to placing equipment and facilitates joint pressing, reinforcing and welding, and welding process construction. The jack can rotate in all directions in the pressure steel pipe, so that no dead angle work is realized, and the comprehensive platform is used for quickly pressing a joint in the pressure steel pipe. The flexibility and efficiency of the platform are improved, and the effect is obvious in pressure steel pipe joint pressing work of a hydropower station, a pumped storage power station and a large water pipeline project.

[0011] It should be understood that the foregoing general description and the following detailed description are only exemplary and explanatory and are not restrictive of the application. BRIEF DESCRIPTION OF DRAWINGS

[0012] The above and other objects, features and advantages of the present application will become more apparent from the following detailed description when taken in conjunction with the accompanying drawings in which like reference characters refer to like parts throughout the figures, and in which:

[0013] Figure 1 is a schematic view of a front view structure of the comprehensive platform shown in the embodiments of the application;

[0014] Figure 2 is a schematic view of a side view structure of the comprehensive platform shown in the embodiments of the application;

[0015] Figure 3 is a schematic view of a top view structure of the comprehensive platform shown in the embodiments of the application;

[0016] LIST OF REFERENCE NUMERALS

[0017] 1 - jack, 2 - support base, 3 - roller, 4 - positioning plate, 5 - work platform, 6 - shaft pipe, 7 - guardrail, 8 - top pipe, 9 - storage platform. DETAILED DESCRIPTION

[0018] The embodiments of the application will be described in greater detail below with reference to the accompanying drawings. Although the embodiments of the application are shown in the drawings, it should be understood that the application can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to make the application more thorough and complete, and to fully convey the scope of the application to those skilled in the art.

[0019] It should be understood that, although the terms "first", "second", "third", etc. can be used in this application to describe various information, these information should not be limited to these terms. These terms are only used to distinguish the same type of information from each other. For example, the first information can also be referred to as the second information, and similarly, the second information can also be referred to as the first information without departing from the scope of the application. Therefore, the features defined as "first", "second" can explicitly or implicitly include one or more features. In the description of the present application, the meaning of "a plurality of" is two or more, unless otherwise specifically limited.

[0020] In the description of the present application, it should be understood that the orientation or positional relationship indicated by the terms "length", "width", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present application and simplifying the description, and does not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation on the present application.

[0021] Unless otherwise specifically defined and limited, the terms "mounting", "connecting", "connecting", "fixing" and the like should be broadly understood, for example, it can be fixed connection, or detachable connection, or integral; it can be mechanical connection, or electrical connection; it can be directly connected, or indirectly connected through intermediate medium, it can be the internal communication of two elements or the interaction relationship of two elements. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.

[0022] The technical scheme of the embodiment of the present application is described in detail below in combination with the drawings.

[0023] A comprehensive platform for installing quick pressure joint of pressure steel pipe, comprising: a support base 2, a working platform 5, a positioning plate 4, a shaft pipe 6, a top pipe 8 and a jack 1. The support base 2 is provided with the working platform 5, the working platform 5 is assembled on site by using 8# channel steel, φ200mm galvanized steel pipe and galvanized steel grating as main materials, the working platform 5 is provided with a protective fence 7 on the outer side, the bottom is provided with a 10-inch rubber roller 3 as a moving and supporting, and the support base 2 is further provided with a storage platform 9. By designing the rubber roller 3 as a platform support, the comprehensive platform can move quickly in the inner wall of the pressure steel pipe, fully play the characteristics of plastic deformation of rubber material, and effectively protect the anticorrosive coating.

[0024] The positioning plate 4 is installed at both ends of the operation platform 5, so as to meet the full rotation of the jack 1 in the pressure steel pipe, realize the function of accurate pressing, and open the mounting hole with the same size on the positioning steel plate according to the size of the jacking pipe 8. The mounting hole is connected with the shaft pipe 6 through the bearing, the outer ring of the deep groove ball bearing is installed in the mounting hole, and the inner ring is sleeved on the shaft pipe 6. The positioning plate 4 is fixed in the middle of the comprehensive platform and connected through the shaft pipe 6 to keep the same horizontal height, so that it can rotate 360° around the connecting shaft steel pipe in the horizontal direction, thereby realizing the operation without dead angle.

[0025] The end of the shaft pipe 6 is threadedly connected with the jacking pipe 8 to form a "T-shaped" structure. In the subsequent use process, if the jacking pipe 8 or the shaft pipe 6 is damaged, one of the components can be replaced alone. The jacking pipe 8 is respectively installed with the jacks 1, and the screw jacks 1 are connected with the jacking pipe 8 to ensure the mechanical strength. The positioning plate 4 and the shaft pipe 6 are horizontally arranged on the comprehensive platform, so as to ensure that the jacks 1 can rotate around the axis in all directions and the stress is balanced in the pressing process, and the jacking pipe 8 will not be deformed due to uneven stress.

[0026] The shaft pipe 6 and the jacking pipe 8 are tightly connected through threads to form a relatively rigid whole structure. When the jacking pipe 8 is subjected to external force, the force will be transmitted to the shaft pipe 6 through the threaded connection. In the actual pressing process, the external force received by the shaft pipe 6 and the jacking pipe 8 is mainly the pressure along the axial direction, which can make the connection between the shaft pipe 6 and the jacking pipe 8 more closely, and limit the rotation of the shaft pipe 6 relative to the jacking pipe 8. At the same time, due to the supporting effect of the positioning plate 4 on the shaft pipe 6 and the stability of the whole comprehensive platform structure, when the shaft pipe 6 is subjected to the external force transmitted by the jacking pipe 8, it will be constrained by the positioning plate 4 and the platform structure, so that the shaft pipe 6 is fixed and no longer rotates when the jacking pipe 8 works.

[0027] In use, the jacks 1 are rotated to the pressing position, the construction personnel stand on the operation platform 5 to operate the screw jacks 1, so as to extend and support the pressure steel pipe, adjust the misalignment to achieve the pressing effect, and then weld and reinforce the pressing part directly when the misalignment meets the requirements. When the girth weld is welded, the comprehensive platform can be moved to the construction area, and the welding operation is carried out on the comprehensive platform.

[0028] According to the needs of the installation of the pressure steel pipe on site, different specifications of jacks 1, channel steels, galvanized steel pipes, rubber rollers 3 and other instruments can be selected. A safe, stable and movable comprehensive platform is provided for the installation, welding and construction equipment of the pressure steel pipe.

[0029] Finally, it is to be understood that the phraseology or terminology employed herein, such as "first" and "second", for example, are for descriptive purpose only and can not literally be the intended "first" and "second" as the entities or operations designated by these terms can involve the same entity or operation. Also, the terms "comprising", "including", or any other variation thereof, are intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but can include other elements not expressly listed or inherent to such process, method, article, or apparatus.

[0030] The units described as separate components can or can not be physically separate, and the components displayed as units can or can not be physical units, i.e., can be located in one place, or can be distributed to multiple network units. Part or all of the units can be selected according to actual needs to achieve the purpose of the embodiment.

[0031] In addition, the functional units in each embodiment of the present application can be integrated into one processing unit, or each unit can be physically present alone, or two or more units can be integrated into one unit. The integrated unit can be realized in the form of hardware or in the form of a software functional unit.

[0032] If the integrated unit is realized in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer readable storage medium. Based on this understanding, the technical solutions of the present application essentially or the part that contributes to the prior art or the whole or part of the technical solutions can be embodied in the form of a software product. The computer software product is stored in a storage medium and includes a number of instructions for causing a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the embodiments of the present application.

[0033] The embodiments of the present application have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes are obvious to those skilled in the art without departing from the scope and spirit of the described embodiments. The choice of terms used herein is intended to best explain the principles, practical applications, or improvements to the technology in the market, or to enable other ordinary skilled persons in the art to understand the embodiments disclosed herein.

Claims

1. A comprehensive platform for installing quick pressure joint of pressure steel pipe, characterized in that, Include: Support base, work platform, positioning plate, shaft tube, top pipe and jack, the support base is erected with the work platform, the bottom is equipped with the roller, the work platform both ends middle part is installed with the positioning plate, the positioning plate is equipped with the mounting hole and is connected with the shaft tube in the hole, the shaft tube end is screwed with the top pipe and forms the "T type" structure, the top pipe both ends are installed with the jack respectively.

2. The integrated platform for quick joint caulk of pressure pipes according to claim 1, characterized in that, The work platform outside is installed with the guardrail.

3. The integrated platform for quick joint caulk of pressure pipes according to claim 1, characterized in that, The support base bottom is also erected with the storage platform.

4. The integrated platform for quick joint caulk of pressure pipes according to claim 1, characterized in that, The mounting hole is connected with the shaft tube through the bearing, the outer ring of the deep groove ball bearing is installed in the mounting hole, and the inner ring is sleeved on the shaft tube.