Temporary wiring equipment for wind power construction
By designing a temporary overhead line erection device for wind power construction with pulleys, sliders, and a winding crank assembly, the problem of inaccurate height control in traditional equipment has been solved, enabling rapid and safe line erection and improving construction efficiency and safety.
Patent Information
- Application Number
- CN202520394678.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-07
- Publication Date
- 2026-02-13
- Estimated Expiration
- 2035-03-07
AI Technical Summary
In traditional wind power construction, the temporary overhead wire equipment lacks precise height control, resulting in low construction efficiency and potential safety hazards.
A temporary overhead line equipment was designed, comprising a mounting base, overhead line column, pulley components, T-shaped slide, T-shaped slider, and winding crank assembly. The equipment enables rapid and precise height adjustment of the overhead line arc pole through pulleys and pull ropes, and uses a counterweight ball to balance the tension, ensuring smooth operation of the equipment.
It improves construction efficiency, reduces manual labor intensity, enhances construction safety, and is suitable for temporary erection needs in various scenarios.
Smart Images

Figure CN223912217U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to the field of wind power construction technology, especially a temporary stringing equipment for wind power construction. BACKGROUND
[0002] In the process of wind power construction, temporary stringing is a very critical step, which involves safely and efficiently erecting power transmission lines to the predetermined position under different scenarios.
[0003] However, in the prior art, the traditional temporary stringing method and equipment have several shortcomings, which directly affect the construction efficiency and safety, such as: the traditional stringing equipment usually relies on simple manual method for height adjustment, lacks precise height control mechanism, and the construction personnel may need to use ladders, ropes and other tools to lift the line section by section, which not only takes time but also is difficult to accurately control. If this problem is not solved, it will lead to low construction efficiency and it is difficult to ensure that the erected line reaches the ideal height. For example, when wind power construction is carried out in the current complex terrain, if the stringing height cannot be quickly and accurately adjusted, the project progress may be delayed and the cost may be increased. In addition, inaccurate height setting may also lead to reduced power transmission efficiency and even cause safety hazards. SUMMARY
[0004] The utility model aims at providing a temporary stringing equipment for wind power construction to solve the problems raised in the background art.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical scheme: a temporary stringing equipment for wind power construction, comprising a mounting base and a stringing column welded to the top surface of the mounting base, an installation gap groove is formed at the top end of the stringing column, two pulley pieces are symmetrically installed between the inner walls on both sides of the installation gap groove, a T-shaped sliding groove is longitudinally formed below each pulley piece and on the outer wall of the stringing column, a T-shaped sliding block is longitudinally connected by sliding and clamping in each T-shaped sliding groove, a stringing arc-shaped rod for temporarily erecting the wind power construction line is integrally connected to the end of each T-shaped sliding block away from the stringing column, a pulling rope is wound around each pulley piece, one end of each pulling rope is connected to the T-shaped sliding block and hung, the other end of the pulling rope is wound around the pulley piece and then extends downward in the stringing column to pass through the winding crank handle assembly to wind and unwind the pulling rope, so that the stringing arc-shaped rod is driven to ascend and descend on the outside of the stringing column to adjust the height of the erected line and disassemble or erect the line.
[0006] Preferably, a rectangular through groove is formed in the lower part of the installation gap groove and in the stringing column, the installation gap groove and the rectangular through groove are longitudinally through and together form an inverted T-shaped gap structure.
[0007] Preferably, the T-shaped sliding block is integrally formed with a sliding block limiting clamp that matches the T-shaped sliding groove at one end away from the overhead line arc-shaped rod, and each of the overhead line arc-shaped rods has an arc shape structure with the arc center upward.
[0008] Preferably, the top end of each of the two T-shaped sliding grooves extends through the rectangular through groove, so that the sliding block limiting clamp of the T-shaped sliding block is mounted and dismounted from the rectangular through groove.
[0009] Preferably, the top surface of each of the T-shaped sliding blocks is welded with a lifting ring for hoisting connection of the pulling rope, and the bottom surface of each of the T-shaped sliding blocks is welded with a counterweight ball, so that the T-shaped sliding block can descend due to gravity when there is no upward pulling force.
[0010] Preferably, the lower end of the overhead line stand has a cavity inside for mounting a winding crank assembly, and the winding crank assembly drives the pulling and unwinding actions of the pulling rope in the cavity.
[0011] Preferably, the cavity is provided with detachable side plates on both sides and at both side outer walls of the overhead line stand, and each of the detachable side plates is embedded with a sealed bearing at the eccentric side.
[0012] Preferably, the winding crank assembly is provided with two groups and is arranged on the two detachable side plates respectively, so that each group of winding crank assemblies controls and drives one corresponding pulling rope.
[0013] Preferably, each of the winding crank assemblies comprises an L-shaped crank that is interference-fitted with the sealed bearing on one of the detachable side plates, and a winding shaft that is welded to the free end of the L-shaped crank.
[0014] Preferably, each of the winding shafts is fixedly connected with one corresponding pulling rope in the cavity, and the winding shaft is interference-fitted with the sealed bearing in the inner wall of the detachable side plate at one end away from the L-shaped crank.
[0015] Compared with the prior art, the technical effects and advantages of the utility model are as follows:
[0016] The temporary overhead line equipment for wind power construction can quickly and accurately adjust the height of the overhead line arc-shaped rod through the pulley, T-shaped sliding groove, T-shaped sliding block and pulling rope arranged in the installation gap groove. This allows the construction personnel to flexibly adjust the height of the line according to the actual situation on site, improving the construction efficiency. The design of the winding crank assembly allows the operator to easily control the winding and unwinding of the pulling rope, thereby driving the lifting of the overhead line arc-shaped rod. Compared with the traditional method, this method is simpler and more intuitive, reduces the labor intensity, and improves the work efficiency. In addition, the equipment does not need to use electrical devices, meets the temporary erection in different scenes, and improves the use efficiency.
[0017] The counterweight ball is used to balance the pulling force during the lifting, and prevents the sliding block limiting clamping head from being stuck in the T-shaped sliding groove, so that the smoothness of the equipment operation is increased, the safety of the operation process is ensured, and the risk of accidents is reduced. BRIEF DESCRIPTION OF DRAWINGS
[0018] In order to more clearly illustrate the specific embodiments of the present application or the technical solutions in the prior art, the drawings needed in the specific embodiments or the prior art description will be briefly introduced as follows. Obviously, the drawings in the following description are some embodiments of the present application, and those skilled in the art can also obtain other drawings according to these drawings without creative labor.
[0019] Figure 1 It is a structural schematic diagram of the present application;
[0020] Figure 2 It is a structural schematic diagram of the top end partial section of the pole of the present application;
[0021] Figure 3 It is a connection structural schematic diagram of the arc-shaped rod of the present application;
[0022] Figure 4 It is a structural schematic diagram of the present application Figure 1 It is an enlarged structural schematic diagram of A in the present application;
[0023] Figure 5 It is a connection structural schematic diagram of the winding shaft of the present application.
[0024] Explanation of reference signs:
[0025] In the figure: 1, mounting base; 2, pole; 3, support rib plate; 4, mounting notch groove; 5, arc-shaped rod; 6, pulley; 7, rectangular through slot; 8, T-shaped sliding groove; 9, threading hole; 10, T-shaped sliding block; 11, pulling rope; 12, lifting ring; 13, counterweight ball; 14, sliding block limiting clamping head; 15, detachable side plate; 16, L-shaped handle; 17, first limiting hole; 18, winding shaft; 19, sealing bearing; 20, second limiting hole. DETAILED DESCRIPTION
[0026] In the following description, a large number of specific details are given in order to provide a more thorough understanding of the present application. However, it is obvious to those skilled in the art that the present application can be implemented without one or more of these details. In other examples, in order to avoid confusion with the present application, some technical features known in the art are not described.
[0027] Unless the direction indicated by the definition alone, the above, below, left, right, front, back, internal and external and other directions referred to in this application are shown in the drawings of the present application, the upper, lower, left, right, front, back, internal and external and other directions, hereinafter.
[0028] The embodiment provides a kind of temporary stringing equipment for wind power construction as shown in Figures 1 to 5 The embodiment provides a kind of temporary stringing equipment for wind power construction as shown in
[0029] In the embodiment, rectangular through slot 7 is arranged in the lower part of installation gap groove 4 and in stringing column 2, installation gap groove 4 and rectangular through slot 7 are longitudinally through and together present inverted T-shaped gap structure.T-shaped block 10 is integrally formed with block limiting clamp 14 which is matched with T-shaped slot 8 at the end away from stringing arc-shaped rod 5, and each stringing arc-shaped rod 5 presents an arc shape structure with the arc center upward.
[0030] In the embodiment, the top end of the two T-shaped slots 8 extends through to the rectangular through slot 7, so that the block limiting clamp 14 of the T-shaped block 10 is installed and removed from the rectangular through slot 7. The top surface of each T-shaped block 10 is welded with a lifting ring 12 for hoisting connection of the pulling rope 11, and the bottom surface of each T-shaped block 10 is welded with a counterweight ball 13, so that the T-shaped block 10 can be lowered by gravity when there is no upward pulling force. The design of the counterweight ball 13 balances the pulling force of the lifting ring 12 when the T-shaped block 10 rises, preventing the block limiting clamp 14 from being stuck in the T-shaped slot 8.
[0031] In the embodiment, the lower end of the stringing column 2 has a cavity for mounting the winding crank assembly, and the winding crank assembly drives the pulling and unwinding action of the pulling rope 11 in the cavity. The two sides of the cavity and the two side outer walls of the stringing column 2 are mounted with detachable side plates 15 by screws, and the eccentric side of each detachable side plate 15 is embedded with a sealed bearing 19.
[0032] In this embodiment, two groups of winding crank assemblies are arranged on the two detachable side plates 15, so that each group of winding crank assemblies controls the driving of a corresponding one of the pull ropes 11. Each winding crank assembly comprises an L-shaped crank 16 in interference fit with the sealing bearing 19 on one of the detachable side plates 15, and a winding shaft 18 welded to the free end of the L-shaped crank 16.
[0033] In this embodiment, each winding shaft 18 is fixedly connected to a corresponding one of the pull ropes 11 in the chamber, and the end of the winding shaft 18 away from the L-shaped crank 16 is in interference fit with the sealing bearing 19 on the inner wall of the detachable side plate 15. The outer wall of each detachable side plate 15 is provided with a plurality of first limiting holes 17 arranged in a ring, and the free end of each L-shaped crank 16 is provided with a second limiting hole 20. When the position of the L-shaped crank 16 needs to be fixed and locked after the pull or winding is completed, a pin shaft or a bolt is passed through the second limiting hole 20 and one of the first limiting holes 17 to lock the position. A plurality of support ribs 3 are symmetrically welded between the top surface of the mounting base 1 and the outer wall of the stringing column 2. The inner bottom wall of the rectangular through slot 7 is symmetrically provided with two threading holes 9 for threading the two pull ropes 11, and each threading hole 9 extends downward to the chamber in the lower part of the stringing column 2 for the pull rope 11 to extend through the threading hole 9 to the chamber and be fixedly connected to the winding shaft 18.
[0034] Working principle:
[0035] The temporary stringing device for wind power construction is installed at a suitable position on the construction site, and the mounting base 1 is ensured to be stable. Then the stringing column 2 is welded on the mounting base 1 to ensure that the stringing column 2 is vertically stable. The T-shaped slider 10 is installed or adjusted through the rectangular through slot 7. One end of the T-shaped slider 10 is connected to the stringing arc-shaped rod 5, and the other end is connected to the T-shaped sliding slot 8 through the slider limiting clamp 14 to realize the function of moving up and down. At the same time, the counterweight ball 13 is welded at the bottom of the T-shaped slider 10 to provide a certain gravity for the slider to assist its downward movement.
[0036] The pull rope 11 is wound around the pulley 6 in the mounting gap groove 4, one end is connected to the lifting ring 12 on the T-shaped slider 10, and the other end is extended through the threading hole 9 to the chamber and fixed to the winding shaft 18. By rotating the L-shaped crank 16, the winding shaft 18 is driven to rotate, thereby controlling the winding and unwinding of the pull rope 11.
[0037] When the overhead line arc-shaped pole 5 needs to be lifted, the L-shaped handle 16 is rotated clockwise, the pulling rope 11 is tightened, and the T-shaped sliding block 10 and the overhead line arc-shaped pole 5 on the T-shaped sliding block 10 are moved upwards along the T-shaped sliding groove 8. When the overhead line arc-shaped pole 5 reaches the required height, the position of the L-shaped handle 16 can be locked by passing a pin shaft or a bolt through the second limiting hole 20 and one of the first limiting holes 17, so as to prevent the L-shaped handle 16 from being loosened accidentally. The line can be temporarily fixed on the overhead line arc-shaped pole 5, and the temporary line construction is completed.
[0038] When the overhead line arc-shaped pole 5 needs to be lowered or the position of the line needs to be adjusted, the locking state of the L-shaped handle 16 is released, the L-shaped handle 16 is rotated counterclockwise, and the pulling rope 11 is loosened. At this time, due to the action of the counterweight ball 13, the T-shaped sliding block 10 will slowly descend due to gravity until it reaches the predetermined position.
[0039] During use, if the internal components need to be inspected or repaired, the operation can be performed by removing the detachable side plate 15. The design of the sealing bearing 19 helps to reduce friction and prolong the service life of the equipment.
[0040] It should be noted that the relational terms herein such as one and two are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the terms "include", "contain" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements not only includes those elements, but also includes other elements not explicitly listed or inherent to such process, method, article or equipment. Without more limitations, the statement "including a limited element" does not exclude the presence of additional identical elements in the process, method, article or equipment including the element.
[0041] Although the embodiments of the utility model have been shown and described, it can be understood by those skilled in the art that various changes, modifications, replacements and variations can be made to the embodiments without departing from the principles and spirits of the utility model, and the scope of the utility model is defined by the appended claims and their equivalents.
Claims
1. A temporary stringing device for wind power construction, comprising a mounting base (1) and a stringing column (2) welded to the top surface of the mounting base (1), characterized in that: The top end of the pole (2) is provided with an installation gap groove (4), two pulley assemblies (6) are symmetrically installed between the inner walls of the installation gap groove (4), a T-shaped sliding groove (8) is longitudinally arranged below each pulley assembly (6) and on the outer wall of the pole (2), a T-shaped sliding block (10) is longitudinally connected in each T-shaped sliding groove (8), two T-shaped sliding blocks (10) are integrally connected with an arc-shaped pole (5) for temporarily erecting a wind power construction line at the end away from the pole (2), a pulling rope (11) is wound around each pulley assembly (6), one end of each pulling rope (11) is connected to the T-shaped sliding block (10) and hung, the other end of the pulling rope (11) is wound around the pulley assembly (6) and then downwardly extended in the pole (2) to drive the arc-shaped pole (5) to be lifted or lowered for adjusting the height of the erected line.
2. The temporary stringing apparatus for wind power construction of claim 1, wherein: A rectangular through groove (7) is arranged in the lower part of the installation gap groove (4) and in the pole (2), the installation gap groove (4) and the rectangular through groove (7) are longitudinally penetrated and together form an inverted T-shaped gap structure.
3. The temporary stringing apparatus for wind power construction of claim 2, wherein: The end of the T-shaped sliding block (10) away from the arc-shaped pole (5) is integrally formed with a sliding block limiting clamp (14) which is matched with the T-shaped sliding groove (8), each arc-shaped pole (5) has an arc shape with the arc center upward.
4. The temporary stringing apparatus for wind power construction of claim 3, wherein: The top end of each T-shaped sliding groove (8) extends through the rectangular through groove (7), so that the sliding block limiting clamp (14) of the T-shaped sliding block (10) can be installed and removed from the rectangular through groove (7).
5. The temporary stringing apparatus for wind power construction of claim 4, wherein: A lifting eye (12) is welded to the top surface of each T-shaped sliding block (10) for connecting the pulling rope (11), a counterweight ball (13) is welded to the bottom surface of each T-shaped sliding block (10), so that the T-shaped sliding block (10) can be lowered by gravity without upward pulling force.
6. The temporary stringing apparatus for wind power construction of claim 5, wherein: The lower end of the pole (2) has a cavity for installing a winding handle assembly, the winding handle assembly drives the pulling rope (11) to be pulled and unwound in the cavity.
7. The temporary stringing apparatus for wind power construction of claim 6, wherein: The two sides of the cavity and the two outer walls of the pole (2) are provided with detachable side plates (15) by screws, a sealed bearing (19) is embedded in the eccentric side of each detachable side plate (15).
8. The temporary stringing apparatus for wind power construction of claim 7, wherein: The winding handle assembly is provided with two groups and is arranged on the two detachable side plates (15) respectively, so that each group of winding handle assemblies controls and drives a corresponding pulling rope (11).
9. The temporary stringing apparatus for wind power construction of claim 8, wherein: Each winding handle assembly comprises an L-shaped handle (16) which is interference-fitted with the sealed bearing (19) on one of the detachable side plates (15) and a winding shaft (18) which is welded to the free end of the L-shaped handle (16).
10. The temporary stringing apparatus for wind power construction of claim 9, wherein: Each winding shaft (18) is fixedly connected with a corresponding pulling rope (11) in the cavity, the end of the winding shaft (18) away from the L-shaped handle (16) is interference-fitted with the sealed bearing (19) in the inner wall of the detachable side plate (15).