A prefabricated truss steel temporary bridge

By using multiple sets of detachable steel truss components and bolting technology, the problems of numerous steel temporary bridge components and long assembly time have been solved, enabling rapid assembly and efficient construction.

CN224954954UActive Publication Date: 2026-11-10LONG JIAN KE GONG (HEILONGJIANG) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522217582.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-10-21
Publication Date
2026-11-10
Estimated Expiration
2035-10-21

AI Technical Summary

Technical Problem

The existing steel temporary bridges have numerous components, and the assembly process is cumbersome and time-consuming, making it difficult to meet the timeliness requirements of emergency projects.

Method used

Multiple sets of detachable steel truss components are used, which can be quickly assembled through connecting components. These components include the main steel truss, diagonal web members, cross web members, and segmental bridge deck. They are assembled using bolted connections, which simplifies the construction process.

Benefits of technology

It shortened the setup time, reduced the need for manpower, ensured the timeliness of emergency projects, and improved assembly efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224954954U_ABST
    Figure CN224954954U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of bridge engineering technology, and in particular to a prefabricated truss steel temporary bridge. Specifically, it includes: multiple sets of steel truss components sequentially spliced ​​along the bridge length and width; any adjacent steel truss components are detachably connected via connecting components; diagonal web members are arranged between the longitudinal chords on the same side at both ends of the steel truss main body in the width direction; first cross web members are arranged between the longitudinal chords on the same side at the top of the steel truss main body in the height direction; second cross web members are arranged between the transverse chords on the same side at both ends of the steel truss main body in the length direction; a segmental bridge deck is provided at the top of the steel truss main body; a first bolted plate is arranged on the upper flange of the fixed end; a second bolted plate is arranged on the lower flange of the fixed end; and a third bolted plate is arranged on the web plate of the fixed end. This invention solves the problems of numerous components, cumbersome assembly processes, time-consuming construction and erection stages, the need for a large number of construction personnel, and the difficulty in meeting the timeliness requirements of emergency projects associated with steel temporary bridges.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of bridge engineering technology, and in particular to a prefabricated truss steel temporary bridge. Background Technology

[0002] In today's scenarios of transportation construction, emergency rescue, temporary projects, and special geographical environments, steel temporary bridges play a vital role, providing temporary passages for the passage of people and goods and addressing transportation needs in special circumstances.

[0003] However, some steel temporary bridges on the market currently have numerous components, and the assembly process is complicated. The construction and building stages are time-consuming and require a large number of construction workers, making it difficult to meet the timeliness requirements of emergency projects.

[0004] Therefore, how to provide a prefabricated truss steel temporary bridge that simplifies component composition and assembly process, saves construction time and labor costs, improves assembly efficiency, and ensures the timeliness of emergency projects is an urgent technical problem to be solved. Summary of the Invention

[0005] This utility model provides a prefabricated truss steel temporary bridge, which solves the problems of steel temporary bridges having many components, complicated assembly process, long construction and building time, requiring a large number of construction workers, and making it difficult to meet the timeliness requirements of emergency projects.

[0006] This utility model provides a prefabricated truss steel temporary bridge, comprising: multiple sets of steel truss components spliced ​​sequentially along the bridge length and bridge width, wherein any adjacent steel truss components can be detachably connected by connecting components; The steel truss assembly includes a steel truss body, diagonal web members, a first cross web member, and a second cross web member. The steel truss body includes longitudinal chords extending along its length and transverse chords extending along its width. The diagonal web members are arranged between the longitudinal chords on the same side at both ends of the steel truss body in the width direction. The first cross web member is arranged between the longitudinal chords on the same side at the top of the steel truss body in the height direction. The second cross web member is arranged between the transverse chords on the same side at both ends of the steel truss body in the length direction. A segmental bridge deck is provided at the top of the steel truss body. The connecting assembly includes a first bolt plate, a second bolt plate, and a third bolt plate. The mating ends of two adjacent longitudinal chords are a fixed end and a plug-in end, respectively. The first bolt plate is disposed on the upper flange of the fixed end, the second bolt plate is disposed on the lower flange of the fixed end, and the third bolt plate is disposed on the web of the fixed end. When two adjacent longitudinal chords are mated along their length direction, the plug-in end is bolted and fixed to the connecting assembly on the fixed end.

[0007] In one possible implementation, the steel truss body further includes vertical support rods extending in its vertical direction, the vertical support rods being connected between adjacent longitudinal chords.

[0008] In one feasible embodiment, two of each of the first, second, and third bolting plates are symmetrically arranged. The two first bolting plates are respectively located on the top and bottom surfaces of the upper flange of the fixed end, the two second bolting plates are respectively located on the top and bottom surfaces of the lower flange of the fixed end, and the two third bolting plates are respectively located on both sides of the web of the fixed end. Limiting grooves are provided on both the first bolting plate located on the bottom surface of the upper flange of the fixed end and the second bolting plate located on the top surface of the lower flange of the fixed end.

[0009] In one possible implementation, the connecting assembly further includes a fourth bolted plate and a fixing beam. The fourth bolted plate is disposed on the side wall of the longitudinal chord. When two steel truss assemblies are joined together in their width direction, two adjacent fourth bolted plates are fixedly connected to the fixing beam by bolts.

[0010] In one possible implementation, the connecting assembly further includes a fifth bolted plate and a connecting plate, the fifth bolted plate being disposed on the side wall of the longitudinal chord member, and when two steel truss assemblies are joined together along their width direction, two adjacent fifth bolted plates are connected and fixed to the bolts via the connecting plate.

[0011] In one possible implementation, the bottom surface of the segmental bridge deck is provided with a stiffening rib assembly, which abuts against the first cross web member when the segmental bridge deck is installed on the main body of the steel truss.

[0012] In one possible implementation, the stiffening rib assembly includes multiple horizontal ribs and multiple vertical ribs, which are arranged vertically and alternately on the bottom surface of the segmental bridge deck.

[0013] In one possible implementation, the horizontal cross-sections of the transverse ribs and the vertical ribs along their respective length directions are both "T" shaped.

[0014] In one possible implementation, a reinforcing plate is provided on the top of the fixed beam, and a reinforcing rib is provided on the bottom surface of the reinforcing plate. When two steel truss components are joined together along their length, the reinforcing plate is used to enhance the connection strength of two adjacent longitudinal chord members.

[0015] In one feasible embodiment, a plurality of guardrail supports are evenly arranged along the length of the longitudinal chord on the outer side of the top of the main body of the steel truss. Each guardrail support is bolted with a guardrail base, and each guardrail base is provided with a guardrail post. The plurality of guardrail posts are reinforced by guardrail beams.

[0016] The beneficial effects of this utility model are as follows: First, multiple sets of steel truss components are moved to a designated area for assembly. Then, the longitudinal chord insertion ends of subsequent steel truss components are aligned with the fixed ends of adjacent components, and bolts are temporarily installed at the first bolted plate on the upper flange, the third bolted plate on the web, and the second bolted plate on the lower flange of the fixed end for positioning. Next, after straightening and leveling the multiple sets of steel truss components as a whole, the bolts are tightened in a symmetrical sequence to complete the connection. Finally, after the steel temporary bridge is assembled, the bolt tightness is checked, and the entire steel temporary bridge is hoisted to the required area. Disassembly is carried out in the reverse order. By simplifying the basic components of the steel temporary bridge and assembling it by bolting, time is saved in the construction and erection stages, labor requirements are reduced, and the timeliness of emergency projects is guaranteed. This solves the problem that steel temporary bridges have numerous components, a cumbersome assembly process, and time-consuming construction and erection stages, requiring a large number of construction workers and making it difficult to meet the timeliness requirements of emergency projects. Attached Figure Description

[0017] To more clearly illustrate the specific embodiments of this utility model or the technical solutions in the prior art, the drawings used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of this utility model. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.

[0018] Figure 1 This is a perspective view of the steel truss assembly of a prefabricated steel temporary bridge according to the present invention. Figure 2 This is a perspective view of the docking of steel truss components on the same side of a prefabricated truss steel temporary bridge according to this utility model. Figure 3 This is an enlarged perspective view of region A of a prefabricated truss steel temporary bridge according to this utility model. Figure 4 This is an exploded perspective view of the steel truss assembly of a prefabricated steel temporary bridge according to the present invention. Figure 5 This is a perspective view of the fourth bolted plate and the fixed beam of a prefabricated truss steel temporary bridge according to this utility model. Figure 6 This is a perspective view of the segmental bridge deck of a prefabricated truss steel temporary bridge according to the present invention. Figure 7 This is a perspective view of the reinforcing plate of a prefabricated truss steel temporary bridge according to this utility model.

[0019] Explanation of reference numerals in the attached figures: 1. Steel truss assembly; 101. Steel truss main body; 1011. Longitudinal chord; 1012. Transverse chord; 1013. Vertical support rod; 102. Diagonal web member; 103. First cross web member; 104. Second cross web member; 2. Segmental bridge deck; 3. Connecting assembly; 301. First bolted plate; 302. Second bolted plate; 303. Third bolted plate; 304. Fourth bolted plate; 305. Fixed beam; 306. Fifth bolted plate; 307. Connecting plate; 4. Fixed end; 5. Inserted end; 6. Upper flange; 7. Lower flange; 8. Web plate; 9. Stiffening rib assembly; 901. Transverse rib; 902. Vertical rib; 10. Limiting groove; 11. Reinforcing plate; 12. Reinforcing rib; 13. Guardrail support; 14. Guardrail base; 15. Guardrail post; 16. Guardrail beam. Detailed Implementation

[0020] The technical solution of this utility model will be clearly and completely described below with reference to the embodiments. Obviously, the described embodiments are only some embodiments of this utility model, not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of this utility model.

[0021] In the description of this utility model, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", and "counterclockwise" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.

[0022] In the description of this utility model, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Therefore, a feature defined as "first" and "second" may explicitly or implicitly include one or more of the stated features. In the description of this utility model, "a plurality of" means two or more, unless otherwise explicitly specified.

[0023] See Figure 1 , Figure 2 and Figure 3This utility model provides a prefabricated truss steel temporary bridge, comprising: multiple sets of steel truss components 1 sequentially spliced ​​along the bridge length and width, with any adjacent steel truss components 1 detachably connected by connecting components 3. Each steel truss component 1 includes a steel truss body 101, diagonal web members 102, first cross web members 103, and second cross web members 104. The steel truss body 101 includes longitudinal chord members 1011 extending along its length and transverse chord members 1012 extending along its width. The diagonal web members 102 are positioned between the longitudinal chord members 1011 on the same side at both ends of the steel truss body 101 in the width direction. The first cross web members 103 are positioned between the longitudinal chord members 1011 on the same side at the top of the steel truss body 101 in the height direction. The second cross web members 104 are positioned between the transverse chord members 1012 on the same side at both ends of the steel truss body 101 in the length direction. A segmental bridge deck 2 is provided at the top of the steel truss body 101. The connecting assembly 3 includes a first bolting plate 301, a second bolting plate 302, and a third bolting plate 303. The mating ends of two adjacent longitudinal chords 1011 are a fixed end 4 and a plug-in end 5, respectively. The first bolting plate 301 is disposed on the upper flange 6 of the fixed end 4, the second bolting plate 302 is disposed on the lower flange 7 of the fixed end 4, and the third bolting plate 303 is disposed on the web 8 of the fixed end 4. When two adjacent longitudinal chords 1011 are mated along their length direction, the plug-in end 5 is bolted and fixed to the connecting assembly 3 on the fixed end 4.

[0024] The steel truss assembly 1 consists of multiple sets. The main body 101, diagonal web members 102, first cross web members 103, and second cross web members 104 are welded together at the factory. The longitudinal chord member 1011 has an I-shaped horizontal cross section along its length.

[0025] In the multiple sets of steel truss assemblies 1, the steel truss assemblies 1 located at the bridge abutment and bridge tail have only one end connected to other steel truss assemblies 1, so the end of their longitudinal chord 1011 furthest from the docking end does not need to be equipped with a plug-in end 5 or a fixed end 4. In the multiple sets of steel truss assemblies 1, the steel truss assemblies 1 located between the bridge abutment and bridge tail have both ends of their longitudinal chord 1011 as either fixed ends 4 or plug-in ends 5, or one fixed end 4 and one plug-in end 5. When two docking steel truss assemblies 1 are connected, it is sufficient to ensure that the docking position of the two longitudinal chords 1011 has one fixed end 4 and one plug-in end 5.

[0026] Specifically, first, multiple sets of steel truss components are moved to the designated area for assembly. Then, the insertion ends 5 of the longitudinal chord members 1011 of the subsequent steel truss component 1 are aligned with the fixed ends 4 of the adjacent components, and bolts are temporarily installed at the first bolted plate 301 of the upper flange 6, the third bolted plate 303 of the web 8, and the second bolted plate 302 of the lower flange 7 at the fixed ends 4. Next, after straightening and leveling the multiple sets of steel truss components 1 as a whole, the bolts are tightened symmetrically to complete the connection. Finally, after the temporary steel bridge is assembled, the tightness of the bolts is checked, and the entire temporary steel bridge is hoisted to the required area. Dismantling is performed by reversing the steps.

[0027] Preferably, the plug end 5 of the longitudinal chord 1011 can be transformed into a fixed end 4 by installing a first bolt plate 301, a second bolt plate 302, and a third bolt plate 303. The first bolt plate 301, the second bolt plate 302, and the third bolt plate 303 on the fixed end 4 are all detachable, improving the flexibility of conversion between the fixed end 4 and the plug end 5, thereby increasing the adaptability of the steel truss assembly 1.

[0028] Preferably, the standard section dimensions of the steel truss are 6m × 2.5m × 1.5m, ensuring that the height and width do not exceed the limits during vehicle transportation. The steel truss assembly 1 and the segmental bridge deck 2 are pre-treated with sandblasting to remove rust, increasing their service life.

[0029] In some embodiments, the steel truss body 101 further includes vertical support rods 1013 extending in its vertical direction, the vertical support rods 1013 being connected between adjacent longitudinal chords 1011.

[0030] Preferably, the diagonal web members 102 are arranged between the longitudinal chord members 1011 on the same side at both ends of the steel truss main body 101 in the width direction, and the vertical support members 1013 connected along the longitudinal chord members 1011 on the same side are symmetrically arranged. The arrangement of the vertical support members 1013 further improves the load-bearing capacity of the steel truss main body 101.

[0031] See Figure 3 In some embodiments, two first bolt plates 301, two second bolt plates 302, and three third bolt plates 303 are symmetrically arranged. The two first bolt plates 301 are located on the top and bottom surfaces of the upper flange 6 of the fixed end 4, respectively. The two second bolt plates 302 are located on the top and bottom surfaces of the lower flange 7 of the fixed end 4, respectively. The two third bolt plates 303 are located on both sides of the web 8 of the fixed end 4. Limiting grooves 10 are provided on the first bolt plate 301 located on the bottom surface of the upper flange 6 of the fixed end 4 and the second bolt plate 302 located on the top surface of the lower flange 7 of the fixed end 4.

[0032] When two adjacent longitudinal chord members 1011 are joined, the insertion end 5 of one longitudinal chord member 1011 is inserted into the fixed end 4 of the other longitudinal chord member 1011. The insertion end 5 is engaged in the limiting groove 10, and then the insertion end 5 and the fixed end 4 are fixed with bolts. During the joining process, the limiting groove 10 plays a role in positioning and limiting the insertion end 5. The joining position forms a three-dimensional constraint, making the force more even when the fixed end 4 and the insertion end 5 are connected.

[0033] See Figure 5 In some embodiments, the connecting assembly 3 further includes a fourth bolted plate 304 and a fixing beam 305. The fourth bolted plate 304 is disposed on the side wall of the longitudinal chord 1011. When two steel truss assemblies 1 are joined together along their width direction, two adjacent fourth bolted plates 304 are fixedly connected to bolts by the fixing beam 305.

[0034] During the connection process, the fixed beam 305 is bolted to the fourth bolted plate 304 on each of the two adjacent longitudinal chord members 1011. This enhances lateral stability and ensures its resistance to lateral deformation.

[0035] In some embodiments, the connecting assembly 3 further includes a fifth bolted plate 306 and a connecting plate 307. The fifth bolted plate 306 is disposed on the side wall of the longitudinal chord 1011. When two steel truss assemblies 1 are joined together along their width direction, two adjacent fifth bolted plates 306 are connected and fixed with bolts through the connecting plate 307.

[0036] During the docking process, the two sides of the connecting plate 307 are respectively bolted to the two fifth bolted plates 306 on the adjacent longitudinal chord 1011, which improves the stability of the connection between the two longitudinal chords 1011 and enhances their overall resistance to deformation under lateral force.

[0037] See Figure 6 In some embodiments, the bottom surface of the segmental bridge deck 2 is provided with stiffening rib assemblies 9. When the segmental bridge deck 2 is installed on the steel truss body 101, the stiffening rib assembly 9 abuts against the first cross web member 103. Further, the stiffening rib assembly 9 includes horizontal ribs 901 and vertical ribs 902, with multiple horizontal ribs 901 and vertical ribs 902 arranged vertically and alternately on the bottom surface of the segmental bridge deck 2. Further, the horizontal cross-sections of the horizontal ribs 901 and vertical ribs 902 along their respective length directions are both "T"-shaped.

[0038] Among them, the stiffening rib assembly 9 directly abuts against the first cross web member 103 to form a clear force transmission path, improving the local bearing capacity and vibration resistance of the segmental bridge deck 2. Multiple transverse ribs 901 and multiple vertical ribs 902 are arranged vertically and staggeredly to enhance the bending and shear stiffness of the segmental bridge deck 2 and suppress local buckling and warping of the segmental bridge deck 2.

[0039] The segmental bridge deck 2 can be connected to the top of the steel truss body 101 by integral welding or detachable methods such as bolting. When the segmental bridge deck 2 is connected to the steel truss body 101, the stiffening rib assembly 9 falls into the frame formed by the longitudinal chord 1011 and the transverse chord 1012, achieving precise coupling.

[0040] See Figure 7 In some embodiments, a reinforcing plate 11 is provided on the top of the fixed beam 305, and a reinforcing rib 12 is provided on the bottom surface of the reinforcing plate 11. When two steel truss assemblies 1 are joined together along their length, the reinforcing plate 11 is used to enhance the connection strength of two adjacent longitudinal chord members 1011, so as to reduce the stress concentration at the joint.

[0041] See Figure 4 In some embodiments, multiple guardrail supports 13 are evenly arranged along the length direction on the longitudinal chord 1011 on the outer side of the top of the steel truss body 101. Each guardrail support 13 is bolted with a guardrail base 14, and each guardrail base 14 is provided with a guardrail post 15. The multiple guardrail posts 15 are reinforced by guardrail beams 16.

[0042] Preferably, the guardrail posts 15 are 1.2m high, each guardrail beam 16 is 3m long, the upper guardrail beam 16 is 1.1m from the bridge surface, and the lower guardrail beam 16 is 0.3m from the bridge surface, which is convenient for resisting lateral impact forces.

[0043] The guardrail base 14 is detachably mounted on the guardrail support 13, thereby improving the efficiency of installation and dismantling of the guardrail post 15 and facilitating maintenance and replacement.

[0044] It should be noted that a pre-camber is added during the processing of steel truss component 1, and the bolts used for the bolting mentioned above are all high-strength bolts. The pre-camber and high-strength bolts are well known to those skilled in the art, so they will not be elaborated here.

[0045] Work process First, after transporting multiple sets of steel truss components 1 to the construction site, assembly work is carried out. When the multiple sets of steel truss components 1 are connected along their length, the insertion end 5 of the longitudinal chord 1011 of the subsequent steel truss component 1 is aligned with the fixed end 4 of the longitudinal chord 1011 of the adjacent steel truss component 1. Initial positioning is achieved at the first bolted plate 301 of the upper flange 6, the third bolted plate 303 of the web 8, and the second bolted plate 302 of the lower flange 7 using locating pins, followed by temporary fixing with bolts. The adjacent fifth bolted plate 306 is then connected to the bolts via a connecting plate 307.

[0046] Then, when multiple sets of steel truss components 1 are connected along their width direction, the adjacent fourth bolted plates 304 are connected to the bolts through the fixing beam 305, and the high-strength bolts at each connection position are tightened in a symmetrical sequence according to the specified torque value using a torque wrench, and the torque is tested to straighten and level the steel temporary bridge.

[0047] Finally, the steel temporary bridge is hoisted to the required area. The guardrail posts 15 are bolted to the guardrail supports 13 via the guardrail bases 14, and then the guardrail beams 16 are installed.

[0048] It should be noted that the crane, straightening and leveling device, and bolt torque detection device required for hoisting are all components known to those skilled in the art, and this application does not limit them. However, they are mentioned here for the sake of understanding the technical solution.

[0049] The steel truss assembly 1 of this application conforms to the standard dimensions, facilitating transportation and reducing transportation costs and difficulties. The stability of the steel truss assembly 1 structure is increased and its load-bearing capacity is enhanced through the vertical support rods 1013, diagonal web members 102, first cross web members 103, and second cross web members 104. The flexible connection and use of multiple sets of steel truss assemblies 1 can meet different span and load-bearing requirements.

[0050] Furthermore, the entire process utilizes bolted connections, which are simple and quick to operate, significantly shortening the installation period of the steel temporary bridge and meeting the needs of projects with tight deadlines. This completely avoids the safety hazards caused by welding processes inherent in traditional steel temporary bridge construction.

[0051] In the above embodiments, unless otherwise explicitly specified and limited, "above" or "below" the second feature can mean that the first feature is in direct contact with the second feature, or that the first feature is in indirect contact with the second feature through an intermediate medium. Furthermore, "above," "on top of," and "over" the second feature can mean that the first feature is directly above or diagonally above the second feature, or simply that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature can mean that the first feature is directly below or diagonally below the second feature, or simply that the first feature is at a lower horizontal level than the second feature.

[0052] It should be noted that when an element is referred to as being "fixed to" or "set on" another element, it can be directly on the other element or there may be an intervening element. When an element is considered to be "connected to" another element, it can be directly connected to the other element or there may be an intervening element. The terms "vertical," "horizontal," "upper," "lower," "left," "right," and similar expressions used herein are for illustrative purposes only and do not represent the only possible implementation.

[0053] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "method," "specific method," or "some methods," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or method is included in at least one embodiment or method of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or method. Furthermore, the specific features, structures, materials, or characteristics described may be combined in a suitable manner in any one or more embodiments or methods. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or methods described in this specification, as well as the features of different embodiments or methods.

[0054] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this utility model, and are not intended to limit it. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of this utility model.

Claims

1. A prefabricated truss steel temporary bridge, characterized in that, include: Multiple sets of steel truss components are spliced ​​sequentially along the length and width of the bridge, and any adjacent steel truss components can be detachably connected by connecting components; The steel truss assembly includes a steel truss body, diagonal web members, a first cross web member, and a second cross web member. The steel truss body includes longitudinal chords extending along its length and transverse chords extending along its width. The diagonal web members are arranged between the longitudinal chords on the same side at both ends of the steel truss body in the width direction. The first cross web member is arranged between the longitudinal chords on the same side at the top of the steel truss body in the height direction. The second cross web member is arranged between the transverse chords on the same side at both ends of the steel truss body in the length direction. A segmental bridge deck is provided at the top of the steel truss body. The connecting assembly includes a first bolt plate, a second bolt plate, and a third bolt plate. The mating ends of two adjacent longitudinal chords are a fixed end and a plug-in end, respectively. The first bolt plate is disposed on the upper flange of the fixed end, the second bolt plate is disposed on the lower flange of the fixed end, and the third bolt plate is disposed on the web of the fixed end. When two adjacent longitudinal chords are mated along their length direction, the plug-in end is bolted and fixed to the connecting assembly on the fixed end.

2. The prefabricated truss steel bridge according to claim 1, characterized in that, The main body of the steel truss also includes vertical support rods extending along its vertical direction, which are connected between adjacent longitudinal chords.

3. The prefabricated truss steel bridge according to claim 1, characterized in that, Two of each of the first, second, and third bolting plates are symmetrically arranged. The two first bolting plates are located on the top and bottom surfaces of the upper flange of the fixed end, respectively. The two second bolting plates are located on the top and bottom surfaces of the lower flange of the fixed end, respectively. The two third bolting plates are located on both sides of the web of the fixed end. Limiting grooves are provided on the first bolting plate located on the bottom surface of the upper flange of the fixed end and the second bolting plate located on the top surface of the lower flange of the fixed end.

4. The prefabricated truss steel temporary bridge according to claim 1, characterized in that, The connecting assembly further includes a fourth bolted plate and a fixing beam. The fourth bolted plate is disposed on the side wall of the longitudinal chord. When two steel truss assemblies are joined together along their width direction, two adjacent fourth bolted plates are fixed by bolts through the fixing beam.

5. The prefabricated truss steel temporary bridge according to claim 1, characterized in that, The connecting assembly further includes a fifth bolt plate and a connecting plate. The fifth bolt plate is disposed on the side wall of the longitudinal chord member. When two steel truss assemblies are joined together along their width direction, two adjacent fifth bolt plates are connected and fixed to the bolts through the connecting plate.

6. The prefabricated truss steel temporary bridge according to claim 5, characterized in that, The bottom surface of the segmental bridge deck is provided with stiffening rib assembly. When the segmental bridge deck is installed on the main body of the steel truss, the stiffening rib assembly abuts against the first cross web member.

7. The prefabricated truss steel temporary bridge according to claim 6, characterized in that, The stiffening rib assembly includes horizontal ribs and vertical ribs, and there are multiple horizontal ribs and multiple vertical ribs arranged vertically and alternately on the bottom surface of the segmental bridge deck.

8. The prefabricated truss steel temporary bridge according to claim 7, characterized in that, The horizontal cross-sections of both the transverse ribs and the vertical ribs along their respective length directions are "T" shaped.

9. The prefabricated truss steel temporary bridge according to claim 4, characterized in that, The top of the fixed beam is provided with a reinforcing plate, and the bottom surface of the reinforcing plate is provided with reinforcing ribs. When two steel truss components are joined together along their length, the reinforcing plate is used to enhance the connection strength of two adjacent longitudinal chord members.

10. The prefabricated truss steel temporary bridge according to claim 9, characterized in that, Multiple guardrail supports are evenly arranged along the length of the longitudinal chord on the outer side of the top of the main steel truss. Each guardrail support is bolted to a guardrail base, and each guardrail base is provided with a guardrail post. The multiple guardrail posts are reinforced by guardrail beams.