Aircraft electrical distribution networks with distributed architectures face challenges in managing faults, particularly short-circuits, which can lead to destructive currents and unacceptable loss of propulsion due to uncontrolled voltage collapse, as existing protection solutions are inadequate in isolating faults quickly enough.
A method that detects short-circuits and reconfigures the electrical distribution network to temporarily switch from a distributed to a segregated architecture, isolating faulty channels and redistributing power to prevent propagation of faults, using semiconductor power controllers (SSPCs) and switching devices to manage the transition.
This method effectively protects components, prevents total loss of propulsion, and ensures continued operation by isolating faults and maintaining power distribution to operational channels, even during flight.
Smart Images

Figure 1.1
Abstract
Description
Description Title: METHOD FOR CONTROLLING AND PROTECTING AN ELECTRICAL DISTRIBUTION NETWORK FOR AIRCRAFT PROPULSION CHARGES Technical field
[0001] This disclosure relates to the field of methods for controlling and protecting electrical distribution networks for aircraft propellant charges. Prior art
[0002] Generally speaking, in aeronautics, equipment is highly constrained in terms of mass and integration capacity. To optimize system mass and integration, electrical distribution networks used to power aircraft engines can feature so-called distributed architectures.
[0003] In this type of architecture, the batteries are connected in parallel to the high-voltage direct current (HVDC) network. In nominal mode, the voltages between the different batteries are balanced so that the batteries share power between the different loads. In the event of a battery loss, the propulsion loads are powered by the remaining batteries. This allows the batteries to be sized as close as possible to nominal operation, and thus optimizes battery mass. The electrical distribution network also becomes more integrated because the distribution box combines several loads with several batteries.
[0004] One of the difficulties with this type of architecture is fault management, particularly short circuits. In the event of a low-impedance short circuit, for example, a Li-ion battery can deliver a current of several thousand amperes in a few milliseconds. When the batteries are connected in parallel to the network, the phenomenon is amplified by the number of batteries in parallel, which has two consequences:
[0005] The first, direct consequence is that the currents involved in this type of short circuit can be destructive for aeronautical components existing on the market today, and active protection solutions are not capable of isolating the fault.
[0006] The second consequence is linked to the nature of the distributed distribution architecture. Indeed, unlike a segregated distribution architecture, which does not propagate the consequences of a short circuit to the entire propulsion network, in this type of architecture, the network voltage seen by all the engines will collapse over a sufficiently long period to cause the unacceptable loss of propulsion of the aircraft, all the engines linked to the bus no longer being powered due to an automatic protection linked to a bus voltage level that is too low. Summary
[0007] This disclosure improves the situation.
[0008] A method for controlling and protecting an electrical distribution network for aircraft propellant charges is proposed. The aircraft carries a number N of electrical sources and a number N of propellant charges. The aircraft also carries the electrical distribution network.
[0009] The electrical distribution network comprises a number N of high-voltage direct current (HVDC) power supply channels. Each channel has a rank j between 1 and N. Each channel comprises an input power line, an HVDC distribution bus of rank j and an output power line. The input power line is connected to the output power line via the HVDC distribution bus. Each channel of rank j comprises at least one protection element and one switching device on the input power line and one protection element and one switching device on the output power line.
[0010] The input power line is electrically connected to an electrical source and the output power line is electrically connected to a propellant charge.
[0011] Each distribution bus of rank j is further coupled to the distribution bus of rank j+1 via a semiconductor power controller (SSPC) which is closed in a nominal configuration of the electrical distribution network, so that in nominal configuration, the electrical power distribution network is capable of distributing to the propellant loads the electrical power received from the N electrical sources.
[0012] The process includes: - detection of a short circuit in the electrical power distribution network, - the reconfiguration of the electrical power distribution network according to an intermediate degraded configuration in which all the SSPCs are open, so that the channels are electrically isolated from each other, - in response to the detection that the short circuit occurs on a channel of rank k, the non-temporary opening of at least one switching member of the channel of rank k, - the reconfiguration of the distribution network according to a final degraded configuration, in which at least the HVDC distribution buses of rank other than rank k are recoupled between them and said at least one switching device of the rank k channel remains open.
[0013] The method is suitable for implementation when the aircraft is in flight and on the ground.
[0014] This process is particularly advantageous in that it allows a transition from a distributed electrical architecture to a temporary segregated electrical architecture while the distributed electrical architecture is reconfigured after isolation of the electrical fault.
[0015] In particular, the process has the dual advantage of protecting the electrical network components and preventing the spread of a fault that could lead to the total loss of the propulsion system.
[0016] The features set out in the following paragraphs may, optionally, be implemented, independently of each other or in combination with each other:
[0017] In one embodiment, for each channel of rank j, the input electrical line is electrically connected to the electrical source by an input connection, and the method further comprises, upon detection that the short circuit occurs on a channel of rank k, detecting that the short circuit occurs on the input connection of the channel of rank k. The switching member of the channel of rank k which is open is then that of the input electrical line of the channel of rank k. The reconfiguration of the distribution network is then controlled towards a first final degraded configuration, in which all the SSPCs are closed and the switching member of the input electrical line of the channel of rank k remains open.
[0018] Thanks to these characteristics, the fault at the arrival of the electrical source is isolated while retaining the advantages of the distribution of the remaining sources to all the propellant charges.
[0019] In one embodiment, the method further comprises, in response to the detection that the short circuit occurs on the channel of rank k, the temporary opening of the switching member of the output electrical line of said channel of rank k, said switching member of the output electrical line of the channel of rank k being closed in the first final degraded configuration.
[0020] Thanks to these characteristics, the propellant charge of the k-rank channel is disconnected until the electrical fault is isolated. Thus, the circuit downstream of the distribution network is protected from the discharge of the propellant charge inverter capacities.
[0021] In one embodiment, for each channel of rank j the output electrical line is electrically connected to the propellant charge by an output connection. The method further comprises, upon detection that the short circuit occurs on a channel of rank k, detecting that the short circuit occurs on the output connection of the channel of rank k. The switching member of the channel of rank k which is open is then that of the output electrical line of said channel of rank k. The reconfiguration of the distribution network is then controlled towards a second final degraded configuration, in which all the SSPCs are closed and said switching member of the output electrical line of said channel of rank k is open.
[0022] With these features, the fault in the propellant charge feed is isolated while retaining the benefits of source distribution to all remaining propellant charges.
[0023] In one embodiment, the aircraft carries, for each channel of rank j, a second propellant charge, the output electrical line being a first output electrical line, the propellant charge being a first propellant charge, the output connection being a first output connection, each channel of rank j further comprising a second output electrical line connected to the HVDC distribution bus of rank j, the second output electrical line comprising a protection element and a switching member, the second output electrical line being electrically connected to the second propellant charge by a second output connection.
[0024] Thanks to these characteristics, twice N propellant charges can be powered by N electrical sources.
[0025] In one embodiment, the method further comprises, upon detection that the short circuit occurs on said first output connection of the channel of rank k, the temporary opening of the switching member of the second electrical output line of said channel of rank k, said switching member of the second electrical output line of the channel of rank k being closed in the second final degraded configuration.
[0026] Thanks to these characteristics, the two propellant charges of the channel are disconnected while the propellant charge at which the electrical fault appeared is isolated.
[0027] In one embodiment, the distribution network further comprises an inter-bus electrical switch, the rank 1 HVDC distribution bus and the rank N HVDC distribution bus being connected via the inter-bus electrical switch which is open in the nominal configuration of the electrical distribution network.
[0028] The method further comprises, upon detection that the short circuit occurs on a channel of rank k, the detection that the short circuit occurs on the distribution bus of rank k, the switching member of the channel of rank k which is open is then that of the input electrical line of said channel of rank k.
[0029] The reconfiguration of the distribution network is then driven towards a third final degraded configuration, in which said switching device of the channel of rank k remains open and - if rank k is equal to 1, all SSPCs are closed between HVDC distribution buses of rank 2 to N, - if the rank is equal to N, all SSPCs are closed between the HVDC distribution buses of rank 1 to N-1, - for all other ranks k, all SSPCs are closed between the HVDC distribution buses of rank 1 to k-1 and between the buses of rank k+1 to N, and the inter-bus electrical switch is closed.
[0030] Thanks to these characteristics, the network can redistribute electrical energy between non-isolated channels after isolation of the channel of rank k.
[0031] In one embodiment, the method further comprises the non-temporary opening of the switching member of the output electrical line of said channel of rank k, said switching member of the output electrical line remaining open in the third final degraded configuration.
[0032] Thanks to these characteristics, the electrical source and the propellant charge of the faulty k-rank channel are isolated.
[0033] In one embodiment, the method further comprises the non-temporary opening of the switching member of the second output electrical line of the channel of rank k, said switching member of the second output electrical line remaining open in the third final degraded configuration.
[0034] Thanks to these characteristics, the electrical source and the propellant charges of the faulty k-rank channel are isolated.
[0035] Furthermore, an electrical distribution network is proposed comprising a number N of high voltage direct current (HVDC) power supply channels.
[0036] Each channel has a rank j between 1 and N, each channel has an input power line, an HVDC distribution bus of rank j and an output power line. The input power line is connected to the output power line via the HVDC distribution bus.
[0037] Each channel has at least one protection element and one switching member on the input power line and one protection element and one switching member on the output power line.
[0038] The input electrical line is capable of being electrically connected to an electrical source and the output electrical line is capable of being electrically connected to one or more propellant charges.
[0039] Each HVDC distribution bus of rank j is further coupled to the HVDC distribution bus of rank j+1 through a solid-state power controller (SSPC) which is closed in a nominal configuration of the power distribution network.
[0040] Thus, in nominal configuration, the electrical power distribution network is capable of distributing to the propulsion loads the electrical power received from the N electrical sources.
[0041] The electrical power distribution network is further capable of being reconfigured in the event of a short circuit on a channel of rank k according to an intermediate degraded configuration in which the SSPCs are open, so that the channels are electrically isolated from each other.
[0042] The electrical power distribution network is further capable of opening at least one switching device of the channel of rank k.
[0043] The electrical power distribution network is further capable of being reconfigured according to a final degraded configuration, in which at least the HVDC distribution buses of rank other than rank k are recoupled together and said at least one switching member of the rank k channel remains open.
[0044] According to another aspect, there is proposed a global supervision circuit of the network as described above comprising electronic cards configured to execute instructions for the implementation of all or part of the method as defined above, in particular to control the opening of the SSPCs and the switching devices. Brief description of the drawings
[0045] Other features, details and advantages will become apparent upon reading the detailed description below, and upon analyzing the attached drawings, in which: Fig. 1
[0046] [Fig. 1] is a diagram of an example of a reconfigurable electrical distribution network, in a nominal configuration. Fig. 2
[0047] [Fig. 2] is a diagram of a general control process for the network of Figure 1 in the event of an electrical fault occurring. Fig. 3
[0048] [Fig. 3] shows the network of Figure 1 in an intermediate degraded configuration. Fig. 4
[0049] [Fig. 4] is a diagram of the network of Figure 1 on which fault zones have been defined. Fig. 5
[0050] [Fig. 5] is a more detailed diagram of the control process of Figure 5 in which different branches of the process correspond to the different fault zones defined in Figure 4. Fig. 6
[0051] [Fig. 6] is a diagram of the network of Figure 1 in which a fault appears on a first zone. Fig. 7
[0052] [Fig. 7] is a schematic of the network of Figure 6 reconfigured in the intermediate degraded configuration. Fig. 8
[0053] [Fig. 8] is a diagram of the network of Figure 6 during a later stage of the control process of Figure 5. Fig. 9
[0054] [Fig. 9] is a schematic of the network of Figure 6 reconfigured into a first final degraded configuration. Fig. 10
[0055] [Fig. 10] is a diagram of the network of Figure 1 in which a fault appears on a second zone. Fig. 11
[0056] [Fig. 11] is a schematic of the network of Figure 10 reconfigured in the intermediate degraded configuration. Fig. 12
[0057] [Fig. 12] is a diagram of the network of Figure 10 during a later stage of the control process of Figure 5. Fig. 13
[0058] [Fig. 13] is a schematic of the network of Figure 10 reconfigured into a second final degraded configuration. Fig. 14
[0059] [Fig. 14] is a diagram of the network of Figure 1 in which a fault appears on a third zone. Fig. 15
[0060] [Fig. 15] is a schematic of the network of Figure 14 reconfigured in the intermediate degraded configuration. Fig. 16
[0061] [Fig. 16] is a diagram of the network of Figure 14 during a later stage of the control process of Figure 5. Fig. 17
[0062] [Fig. 17] is a schematic of the network of Figure 14 reconfigured into a third final degraded configuration. Description of the embodiments
[0063] In the remainder of the description, and to simplify the illustration, any electrical connection element in the open position will be represented by a rectangle containing a cross, while the same element in the closed position will be represented by the rectangle alone.
[0064] Reference is now made to Figure 1. An aircraft propulsion system comprises an electrical distribution network 1, a set of electrical sources 2 and a set of propellant charges 3. The propellant charges 3 are electric motors.
[0065] Figure 1 represents such an electrical distribution network 1 whose purpose is to efficiently distribute electrical energy from the set of electrical sources 2 to the set of propellant charges 3 in an aircraft in flight, for example an airplane.
[0066] Network 1 is shown in a nominal configuration. Nominal configuration means a normal configuration, in the absence of an electrical fault such as a short circuit, during aircraft flight.
[0067] For the purposes of illustration, network 1 has a number N=3 of 4 channels and two 3 propellant charges per 4 channel. It will appear that the description of network 1 can be adapted for any number N of 4 channels.
[0068] Channel 4 are high voltage direct current (HVDC) power channels.
[0069] As illustrated, each channel 4 has a rank j, where j can be 1, 2, or 3. Each channel 4 has an input power line 5, a distribution bus 6 of rank j, and two output power lines 7. The distribution bus 6 is an HVDC bus. The input power line 5 is connected to the two output power lines 7 via the distribution bus 6.
[0070] Each channel 4 comprises a switching member 8 on the input electrical line 5 and a switching member 9 on each of the two output electrical lines 7. The switching members 8, 9 are bipolar switching members which ensure the galvanic isolation and the respective connection of the electrical sources 2 and the propellant charges 3.
[0071] Each channel 4 is connected to one of the electrical sources 2 via an input connection 10. The input electrical line 5 is electrically connected to the input connection 10 which carries the electrical power from the electrical source 2 to the channel 4.
[0072] Each channel 4 is respectively connected to two propellant charges 3 via two respective output connections 1 1. The two output connections 1 1 are both electrically connected to the distribution bus 6 by the two output power lines 7.
[0073] The distribution bus 6 of channel 4 of rank j=1 is connected to the distribution bus 6 of channel 4 of rank j=2 via a semiconductor power controller (SSPC) 12.
[0074] As can be seen in Figure 1, SSPC 12 is closed in the nominal configuration of network 1.
[0075] The distribution bus 6 of channel 4 of rank j=2 is also connected to the distribution bus 6 of channel 4 of rank j=3 via a semiconductor power controller (SSPC) 12, also closed.
[0076] Thus, the channels 4 are interconnected via their distribution bus 6. In other words, the channels 4 are parallel. Thus, in nominal configuration, the network 1 is able to distribute to the propellant charges 3 the electrical power received from all the electrical sources 2.
[0077] As can be seen, the distribution bus 6 of channel 4 of rank j=1 is also connected to the distribution bus 6 of channel 4 of rank j=3 via an interbus electrical switch 13, which is itself open. The role of the interbus electrical switch 13 is to reconnect channels 1 and 3 to each other in the event of loss of the bus of rank j=2.
[0078] Network 1 is a reconfigurable network under the action of a global supervision circuit comprising several electronic cards (not shown). The global supervision circuit also comprises opening commands for the SSPCs 12, for the inter-bus electrical switch 13, and for the switching devices 8 and 9. The global supervision circuit also comprises current and voltage sensors. The SSPCs 12 also have their own current measurement.
[0079] The control process implemented for short-circuit management is described with reference to Figure 2.
[0080] In a first step 14, the supervision circuit is able to detect a short circuit on one of the channels 4 of rank j=k. The network 1 is then in nominal configuration.
[0081] In a second step 15, the supervision circuit then controls the network 1 to reconfigure it according to an intermediate degraded configuration in which the SSPCs 12 are open. The intermediate degraded configuration of the network 1 is represented with reference to Figure 3 where the SSPCs 12 are represented by a rectangle comprising a cross.
[0082] The SSPC 12 isolates the different 4 channels in about ten microseconds. Thus, in the intermediate degraded configuration, the 4 channels are electrically isolated from each other. In other words, the propulsion system then becomes segregated, which will make it possible to locate and clarify the fault on the channel 4 of rank j=k affected by the failure without impacting the other 4 channels.
[0083] Advantageously, the overall undervoltage generated by the short circuit lasts only a few microseconds, corresponding to the opening time of SSPC 12. As soon as the SSPC 12 are open, the system becomes segregated, and the lines not affected by the fault see their voltage return to a normal level, which allows the propellant charges 3 to remain operational.
[0084] Thus, the very short electrical transient is not perceived on the aerodynamic torque of propellant charge 3, the electrical protection of propellant charge 3 under voltage, which is slower than the opening of SSPC 12, should not put propellant charge 3 in fault.
[0085] Furthermore, advantageously, the current seen by the components at the faulty channel 4 remains the current of a single battery and not the current of the 3 batteries in parallel.
[0086] In a third step 16, a switching member of the channel of rank k is opened so as to isolate the corresponding electrical fault.
[0087] Once the fault is isolated, in a fourth step 17, the SSPCs 12 are closed so that the network 1 is reconfigured according to a final degraded configuration, in which the fault is isolated but the distribution properties of the network 1 are preserved.
[0088] Thus, once the faulty power line has been isolated, it is possible to reconnect the distribution buses 6 in order to parallelize the electrical sources 2 again, after analyzing the network 1 and the location of the fault.
[0089] This reconnection is done either by closing the SSPC 12, or by closing the inter-bus electrical switch 13 if the fault is at the level of the distribution bus of rank k=2.
[0090] Different mechanisms are involved in this process, depending on the areas of the propulsion system affected by the electrical fault. The different areas are represented with reference to Figure 4, which represents a propulsion system 18 comprising a protective housing 19 in which the network 1 is integrated. Elements identical to those presented with reference to Figure 1 are identified by the same reference numbers.
[0091] Figure 4 presents an additional level of detail. In particular, the “+” and “-” poles of each power line are represented.
[0092] In particular, it can be seen that each input power line 5 is protected by a protection element 20. The protection element 20 is a fuse.
[0093] In particular, we see that each output power line 7 is protected by a protection element 21. The protection element 21 is a pyroswitch fuse.
[0094] There are also on each of the input electrical lines 5 and each of the output electrical lines 7 current and voltage sensors 21 ensuring the management and protection of the entire network 1.
[0095] For each zone of the propulsion system, the implementation of the third step 16 and fourth step 17 of the control method is an implementation specific to the zone in which the electrical fault appears.
[0096] The first zone 22 comprises the electrical sources 2 and the input connections 10 connected to all the channels 4. The first zone 22 is located between the electrical sources 2 and the protective box 19.
[0097] The second zone 23 comprises all the output electrical lines 7 of all the channels 4. The second zone 23 is located between the protective housing 19 and the propellant charges 3.
[0098] The three third zones 24 each belonging to a channel 4 of rank j each respectively comprise the input electrical line 5 and the distribution bus 6 of channel 4. The third zones 24 are located in the protection box 19 and concern faults internal to the protection box 19.
[0099] Figure 5 represents the three different respective branches 25, 26 and 27 of the implementation of the control method, depending on the zone, respectively the first zone 22, the second zone 23, or one of the third zones 24, where the location of the short circuit is located. For the purposes of the description, it will be considered that a fault appears on channel 4 of rank j=k.
[0100] For branch 25 corresponding to a short circuit which appears on the first zone 22, the third step 16 of the method is a specific step 28. The specific step 28 comprises the opening of the fuse of the electrical source 2 connected to the channel 4 of rank k on which the short circuit appeared. In other words, the fuse of the defective wiring trips.
[0101] For branch 26 corresponding to a short circuit which appears on one of the third zones 24, the third step 16 of the method is a specific step 29. The specific step 29 comprises the opening of the protection element 20 of the input electrical line 5 of the channel 4 of rank j=k on which the short circuit appeared. In other words, the fuse of the defective wiring trips.
[0102] For branch 27 corresponding to a short circuit which appears on the second zone 23, the third step 16 of the method is a specific step 30. The specific step 30 comprises the opening of the protective element 21 of the output power line 7 of channel 4 of rank j=k on which the short circuit appeared. In other words, the fuse of the defective wiring trips.
[0103] Then, in a step 31 common to the three branches 25, 26 and 27, for channel 4 of rank j=k on which the short circuit appeared, the global supervision circuit then controls the opening of the two switching members 9 of the two output electrical lines 7. In other words, the global supervision circuit requests the stopping of the propellant charges associated with the bus of rank j=k.
[0104] When the fault is located between an electrical source 2 and the protection box 16, that is to say for the branch 25, a specific step 31 is implemented, in which the global supervision circuit then controls the opening of the switching member 8 of the input electrical line 5. In other words, the global supervision circuit isolates the electrical source 2 associated with the bus of rank j=k.
[0105] Then, the global supervision circuit checks in a step 32 whether it authorizes the closing of the SSPC 12. If so, in a step 33, the precharge lines are closed again and the global supervision circuit then controls the closing of the two switching members 9 of the two output electrical lines 7. In other words, the global supervision circuit restarts the propellant charges associated with the bus of rank j=k.
[0106] The aircraft flight mission then continues with network 1 in a first final degraded configuration, in which the SSPCs 12 are closed and the switching member 8 of the input electrical line 5 of channel 4 of rank j=k remains open. In other words, two electrical sources supply the six propellant charges.
[0107] In an advantageous option, if the global supervision circuit does not authorize, in step 32, the closing of the SSPC 12, then the flight mission of the aircraft continues by reconnecting the distribution buses of the two channels 4 not affected by the fault. In this case, two electrical sources 2 supply four propellant charges 3, and the faulty channel 4 of rank j=k is not reconnected.
[0108] An example of implementation of the control method when the fault is located between an electrical source 2 and the protective box 16 is described with reference to Figures 6 to 9.
[0109] Figure 6 represents the propulsion system 18 of Figure 1, when a fault appears on the input connection 10 of the channel of rank j=1. In other words, in this example, the rank k of the faulty channel 4 is rank 1. Generally, the fault can occur on the other two channels 4: in other words, the rank j=k could have taken the value j=2 or the value j=3. The fault is represented by a flash and the abnormal flow of electric currents in direction and intensity is represented by solid arrows.
[0110] During the first microseconds, the three electrical sources 2 and the propellant charges 3 will deliver electrical current into the fault, with a strong variation in intensity over time.
[0111] This current flow will very quickly cause the isolation of the channels 4 between them via the two SSPC 12, which is illustrated in Figure 7. We see in Figure 7 normal electric current flows represented by dotted arrows on channels of rank j=2 and j=3. As shown, the two SSPC 12 are open.
[0112] The configuration of network 1 is then one according to the intermediate degraded configuration in which the SSPCs 12 are open, so that the channels 4 are electrically isolated from each other.
[0113] Thus, the two propellant charges 3 linked to the distribution bus 6 of rank j=2 and to the distribution bus 6 of rank j=3 remain operational.
[0114] Indeed, the isolation of the fault is faster than the faulting of the propellant charges 3. Also, the dynamics of the engines should not generate a significant loss of thrust at the aircraft level.
[0115] However, the global supervision circuit requires the stopping of the propulsion charges 3 associated with the distribution bus of rank k=1, as shown in Figure 8. Indeed, during the fault, the capacities of the motor inverter will have discharged in the fault, so the motors are put into undervoltage protection.
[0116] The internal protection device of the electrical source 2 will also isolate the fault from the voltage source which cannot be stopped intrinsically.
[0117] Once the current has dropped to an acceptable level, the switching member 8 of the channel of rank k=1 is commanded open to galvanically isolate the short-circuited area.
[0118] In order to properly restart the propellant charges 3, the two switching devices of the channel of rank k=1 are commanded open. The protection devices 21 of the channel of rank k=1 do not isolate the propellant charges 3 during this operation, because they are unidirectional at the protection level and their function is to protect the circuit downstream of the network 1.
[0119] Once the fault is isolated, the global supervision circuit can reconfigure network 1 according to the first final degraded configuration.
[0120] More precisely, the global supervision circuit controls the closing of the two SSPC 12 using the internal precharging function of the SSPC 12, depending on the state of the electrical sources 2. An additional lock can be implemented at this level to be sure that the fault zone has been identified in the first zone 22 and that the fault is not in the third zone 24 of the channel of rank k=1: If the precharging of the distribution bus 6 of rank k=1 is not carried out in a given maximum time, it is considered that the distribution bus 6 of rank k=1 is faulty and can no longer be repowered.
[0121] Once the two SSPC 12 are closed, the switching members 9 of the propellant charges 3 of channel 4 of rank k=1 can be closed also using the associated precharge. The propellant charges 3 can thus be restarted on instruction from the global supervision circuit.
[0122] The final system configuration for the end of the aircraft mission is shown in Figure 9: the two remaining electrical sources 2 supply all the propellant charges 3.
[0123] For branch 27 of Figure 5, the fault is located between the protection box 16 and the propellant charges 3, on channel 4 of rank j=k. In this case, there is no step 31. The global supervision circuit checks directly in a step 34 whether it authorizes the closing of the SSPC 12.
[0124] If so, in a step 35, the precharge lines are closed. The global supervision circuit then controls the closing of the switching member 9 of the healthy output electrical line 7. In other words, the global supervision circuit restarts the propellant charge 3 not affected by the fault associated with the bus of rank k. On the other hand, the other propellant charge 3 associated with the bus of rank k remains isolated.
[0125] The aircraft flight mission then continues with a network 1 in a second final degraded configuration, in which the SSPCs 12 are closed and the switching member 9 of one of the two output electrical lines 7 of the channel 4 of rank k remains open. In other words, three electrical sources supply five propellant charges 3.
[0126] In an advantageous option, if the global supervision circuit does not authorize, in step 34, the closure of the SSPC 12, then the flight mission of the aircraft continues by reconnecting the distribution buses of the two channels 4 not affected by the fault. In this case, two electrical sources 2 supply four propellant charges 3, and the faulty channel 4 is not reconnected.
[0127] An example of implementation of the control method when the fault is located between the protective housing 16 and the propellant charges 3 is described with reference to Figures 10 to 13.
[0128] As can be seen in Figure 10, an electrical fault represented by a lightning bolt appears on the second output connection 1 1 of channel 4 of rank j=k=1.
[0129] In order to isolate the electrical source 2 from the faulty channel 4 of rank 1, the two SSPC 12 open, as shown in Figure 1 1 corresponding to an intermediate degraded configuration of the network 1.
[0130] In order to isolate the fault with respect to the distribution bus 6 of channel 4 of rank 1, the protection member 21 of the second output connection 1 1 will isolate the fault present on the wiring of the second propellant charge 3.
[0131] In order to disconnect the faulty rank 1 channel 4 motors, the global supervision circuit sends a request to stop the propellant charges 3 linked to the rank 1 distribution bus 6. The two switching devices 9 are then opened. The corresponding network 1 configuration is shown with reference to Figure 12.
[0132] The global supervision circuit then controls the reconfiguration of network 1 according to the second final degraded configuration shown in Figure 13.
[0133] In fact, the two SSPCs 12 are closed to return the network 1 to distributed configuration. In addition, the first propellant charge 3 which is not on the faulty line can be put back online according to the aircraft's needs by closing the corresponding switching device 9.
[0134] For branch 26 of the control method of Figure 5, the fault corresponds to one of the third zones 24. A specific step 31 identical to that of branch 25 is implemented. This corresponds to the case where the distribution bus 6 of rank k is faulty. The global supervision circuit then isolates the electrical source 2 associated with the bus of rank k.
[0135] The aircraft flight mission then continues with a network 1 in a third final degraded configuration, in which the switching devices 8 and 9 of channel 4 of rank k remain open and: - if rank k is equal to 1, SSPC 12 is closed between the rank 2 distribution bus and the rank 3 distribution bus, - if rank k is equal to 3, SSPC 12 is closed between the rank 1 distribution bus and the rank 2 distribution bus, - if rank k is equal to 2, the inter-bus electrical switch 13 is closed and the two SSPC 12 remain open.
[0136] An example of implementation of the control method when the fault is located on a distribution bus 6 is described with reference to Figures 14 to 17.
[0137] As can be seen in Figure 14, an electrical fault represented by a flash appears on distribution bus 6 of rank j=k=1.
[0138] Firstly, the global supervision circuit controls the isolation of channels 4 from each other to put network 1 in an intermediate degraded configuration shown in Figure 15. As in the previous cases, the two SSPC 12 will therefore open.
[0139] On channel 4 of rank 1, in order to isolate the electrical source 2, the protection member 20 of the input electrical line 5 will trip, as shown in Figure 16. The internal protection member of the electrical source 2 can also participate in the electrical isolation, depending on its dimensioning.
[0140] On channel 4 of rank 1, once the electric current has dropped to an acceptable level, the switching member 8 is commanded open to isolate the short-circuited zone from the electric source 2.
[0141] The configuration of network 1 following this step is shown in Figure 6.
[0142] Then, in order to disconnect the faulty rank 1 channel 4 engines, the global supervision circuit requires the stopping of the two propellant charges 3 associated with the distribution bus 6.
[0143] Once the current has dropped to an acceptable level, the two switching devices 9 will be commanded open to isolate the short-circuited area, in order to avoid any regeneration of the electric motors such as for example a freewheel mode following the aerodynamic thrust of the blades, also called in English "windmilling" in the fault.
[0144] The protection device 20 of the input electrical line 5 having isolated first, the fault is located in the third zone 24 corresponding to the first channel 4 of rank 1. The network logic then prohibits the reclosing of the first SSPC 12 between the first channel 4 of rank 1 and the second channel 4 of rank 2. The second SSPC 12 can be closed, so as to reconnect the second channel 4 of rank 2 with the third channel 4 of rank 3.
[0145] The configuration of network 1 to complete the mission is described in Figure 17 corresponding to the third final degraded configuration.
[0146] In this fault case, the two faulty engines of channel 4 of rank k=1 are irretrievably lost. In other words, two electrical sources 2 supply the four propellant charges 3 and one channel remains isolated and lost.
Claims
Demands
1. Method for controlling and protecting an electrical distribution network (1) for aircraft propulsion loads (3), the aircraft carrying a number N of electrical sources (2) and a number N of propulsion loads (3), the aircraft further carrying the electrical distribution network (1), the electrical distribution network (1) comprising a number N of high-voltage direct current (HVDC) power supply channels (4), each channel (4) having a rank j from 1 to N, each channel (4) comprising an input electrical line (5), an HVDC distribution bus (6) of rank j and an output electrical line (7), the input electrical line (5) being connected to the output electrical line (7) via the HVDC distribution bus (6),each j-rank channel (4) comprising at least one protection element (20) and one switching element (8) on the input power line (5) and one protection element (21) and one switching element (9) on the output power line (7), the input power line (5) being electrically connected to a power source (2) and the output power line being electrically connected to a propulsion load (3), each j-rank distribution bus (6) is further coupled to the j+1-rank distribution bus (6) via a solid-state power controller (SSPC) (12) which is closed in a nominal configuration of the power distribution network (1), so that in nominal configuration, the power distribution network (1) is capable of distributing to the propulsion loads (3) the electrical power received from the N power sources (2), The process involves: - the detection (14) of a short circuit in the electrical power distribution network (1), - the reconfiguration (15) of the electrical power distribution network (1) according to an intermediate degraded configuration in which all SSPCs (12) are open, so that the channels (4) are electrically isolated from each other, - In response to the detection that the short circuit occurs on a k-rank channel (4), the non-temporary opening (16) of at least one switching element (8, 9) of the k-rank channel (4), - the reconfiguration (14) of the distribution network according to a final degraded configuration, in which at least the HVDC distribution buses (6) of rank other than rank k are recoupled together and said at least one switching device (8, 9) of the channel (4) of rank k remains open.
2. A method according to claim 1, wherein, for each j-rank channel (4), the input power line (5) is electrically connected to the power source (2) via an input connection (10), the method further comprising, upon detection that a short circuit occurs on a k-rank channel (4), the detection (25) that the short circuit occurs on the input connection (10) of the k-rank channel (4), the switching element (8) of the k-rank channel that is opened is then that of the input power line (5) of the k-rank channel (4), and the reconfiguration of the distribution network is then driven towards a first configuration final degraded state, in which all SSPCs are closed and the switching device of the k-rank channel's incoming power line is opened.
3. Method according to claim 2, wherein the method further comprises: - in response to the detection that the short circuit occurs on the k-rank channel (4), the temporary opening of the switching element (9) of the output power line (7) of said k-rank channel, said switching element (9) of the output power line (7) of the k-rank channel (4) being closed in the first final degraded configuration.
4. A method according to claim 1 to 3, wherein, each j-rank channel (4) and the output power line (7) are electrically connected to the propulsion load (3) by an output connection (11), the method further comprising, upon detection that the short circuit occurs on the k-rank channel, the detection (27) that the short circuit occurs on the output connection (11) of the k-rank channel (4), the switching element (9) of the k-rank channel (4) which is open is then that of the output power line (7) of said k-rank channel, the reconfiguration of the distribution network (1) is then driven to a second final degraded configuration, in which all SSPCs (12) are closed and said switching element (9) of the output power line (7) of said k-rank channel (4) is open.
5. A method according to any one of claims 1 to 4, wherein the aircraft carries, for each j-rank channel (4), a second propellant charge (3), the output power line (7) being a first output power line, the propellant charge (3) being a first propellant charge, the output connection (11) being a first output connection, each j-rank channel further comprising a second output power line (7) connected to the j-rank HVDC distribution bus (6), the second output power line (7) comprising a protection element (21) and a switching element (9), the second output power line (7) being electrically connected to the second propellant charge (3) by a second output connection (11).
6. A method according to claim 5 taken in combination with claim 4, further comprising, upon detection (27) that the short circuit occurs on said first output connection (11) of said k-rank channel (4), the temporary opening of the switching element (9) of the second output electrical line (7) of said k-rank channel (4), said switching element (9) of the second output electrical line (7) of said k-rank channel being closed in the second final degraded configuration.
7. A method according to any one of claims 1 to 6, wherein the distribution network (1) further comprises an inter-bus electrical switch (13), the first-order HVDC distribution bus (6) and the second-order HVDC distribution bus (6) being connected via the inter-bus electrical switch (13) which is open in the nominal configuration of the electrical distribution network (1), the method further comprising, upon detection that the short circuit occurs on said channel of 18 rank k, the detection (26) that the short circuit occurs on the HVDC distribution bus (6) of rank k, the switching element (8) of the channel (4) of rank k which is open is then that of the input power line (5) of said channel of rank k, the reconfiguration of the distribution network (1) is then driven towards a third final degraded configuration, in which said switching element (8) of said channel (4) of rank k remains open and - if rank k is equal to 1, all SSPCs (12) are closed between the HVDC distribution buses (6) of rank 2 to N, - if the rank is equal to N, all SSPCs (12) are closed between the HVDC distribution buses (6) of rank 1 to N-1, - for all other ranks k, all SSPCs (12) are closed between the HVDC distribution buses (6) of rank 1 to k-1 and between the buses of rank k+1 to N, and the inter-bus electrical switch (13) is closed.
8. A method according to claim 7, wherein the method further comprises the non-temporary opening of the switching element (9) of the output power line (7) of said k-rank channel (4), said switching element (9) of said output power line (7) remaining open in the final third degraded configuration.
9. A method according to claim 7 taken in combination with claim 5, further comprising the non-temporary opening of the switching element (9) of the second output power line (7) of said k-rank channel (4), said switching element of said second output power line (7) remaining open in the final third degraded configuration.
10. Electrical distribution network (1) comprising N high-voltage direct current (HVDC) supply channels (4), each channel (4) having a rank j from 1 to N, each channel (4) comprising an input power line (5), a rank j HVDC distribution bus (6) and an output power line (7), the input power line (5) being connected to the output power line (7) via the HVDC distribution bus (6), each rank j channel (4) comprising at least one protection element (20) and one switching element (8) on the input power line (5) and one protection element (21) and one switching element (9) on the output power line (7), the input power line (5) being capable of being electrically connected to an electrical source (2) and the output power line (7) being capable of being electrically connected to a propellant load (3),Each j-rank HVDC distribution bus (6) is further coupled to the j+1-rank HVDC distribution bus (6) via a solid-state power controller (SSPC) (12) which is closed in a nominal configuration of the electrical distribution network (1), so that in nominal configuration, the electrical power distribution network (1) is capable of distributing to the propulsion loads (3) the electrical power received from the N electrical sources, 19 the electrical power distribution network (1) further being capable of being reconfigured (15) in the event of a short circuit on a k-rank channel (4) according to an intermediate degraded configuration in which all SSPCs (12) are open, so that the channels (4) are electrically isolated from each other, the electrical power distribution network (1) further being capable of opening at least one switching element (8, 9) of the k-rank channel (4), the electrical power distribution network (1) further being capable of being reconfigured (17) according to a final degraded configuration, in which at least the HVDC distribution buses (6) of a rank other than k are recoupled together and said at least one switching element (8, 9) of the k-rank channel (4) remains open.