Three-dimensional measurement method of member incorporated in structure
Patent Information
- Application Number
- JP2023012302
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-01-30
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2043-01-30
AI Technical Summary
Existing methods for surveying architectural structures like steel towers from a distance suffer from reduced accuracy due to the shadowing of components and the need for close proximity, leading to incomplete measurements and increased risk of human and equipment damage.
A three-dimensional surveying method using a combination of reference points with different height coordinates, photographic image data acquisition, and calibration of point cloud data to achieve high accuracy without requiring direct proximity to the structure.
Enables safe, efficient, and accurate measurement of structural members with millimeter-level precision from a remote location, reducing the need for dangerous on-site measurements.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a technique for surveying architectural structures such as steel towers and bridge piers, and more particularly to a technique for enabling the surveying of members incorporated into architectural structures from a remote position. [Background technology]
[0002] The materials used in architectural structures such as power transmission towers and communication towers may not only be standardized products, but may also be individually designed and manufactured. Even if standardized products that are widely used to some extent are used as materials, in architectural structures that have been erected for a long time, the details of the materials used may be unknown due to circumstances such as the loss of documents at the time of erection. For this reason, when a component of an architectural structure such as a tower needs to be replaced due to aging or corrosion, a worker must actually climb up to the location where the component is located and measure the target component directly. However, working at heights in tall architectural structures such as steel towers always involves the risk of human and material damage, such as a worker falling or a measuring device falling. For this reason, there has been a strong desire for the development of a method for measuring the shape and size of a component to be replaced, for example, from the ground, without a worker actually climbing up to the location where the component needs to be replaced.
[0003] Conventional methods for measuring the size of an object from a distance include measuring the shape of the object by emitting laser light using a laser scanner or laser tracker to obtain the three-dimensional coordinate values of the measurement point, and measuring the distance to the measurement point by emitting (emitting) light waves, such as with a total station, and analyzing the light that returns to the measuring instrument.
[0004] However, in both methods, the measurement accuracy tends to decrease when the distance from the measuring device to the measurement target point is long. Here, when considering the case where the measurement target is a tall structure such as a steel tower, in order to shorten the distance to the measurement target point as much as possible, the measurement is performed as close as possible to the steel tower to be surveyed. However, if you approach close to the steel tower directly below, you will inevitably have to measure by looking up at the steel tower from the ground. When trying to measure a steel tower by looking up from below, in a steel tower composed of a combination of main pillar materials, horizontal members, diagonal members, cross members, cross members, auxiliary members, etc., the member to be measured is often in the shadow of other members, making it difficult to grasp the entire picture of the target member. Especially in a steel tower with a complex number of pillars and members, even if the measuring device is moved to another location, interference such as the creation of another blind spot cannot be avoided. Thus, even if you try to measure from the ground using a laser tracker, it is often impossible to irradiate the laser to the desired location of the target member from the ground, and complete measurement is often not possible.
[0005] To solve this problem, there is a method of measuring the size and shape of the part to be measured by mounting a camera on a UAV, such as a drone, taking photographs and generating point cloud data from the obtained photographic image data, but there is a significant measurement error when using only point cloud data created from photographic images. Another method is to measure the target location by irradiating a laser beam from a UAV equipped with a LiDAR. LiDAR is a technology that irradiates an object with laser beams and measures the shape and distance of the object from the wavelength and the time it takes for the beam to return, but the reality is that sufficient surveying accuracy cannot be obtained by using only that method. In other words, although the measurement using LiDAR is certainly more accurate than the method of generating point cloud data from photographic images, the measurement accuracy of LiDAR that can be mounted on a UAV is limited, so the current situation is that it is not possible to expect the millimeter-level accuracy required to create replacement parts. Therefore, as a method of solving these problems, a method of measuring by combining measurement data from a UAV and data measured from the ground using a laser tracker has been disclosed. [Prior art documents] [Patent documents]
[0006] [Patent Document 1] JP 2022-143471 A Summary of the Invention [Problem to be solved by the invention]
[0007] The surveying system disclosed in Patent Document 1 surveys a measurement point located on the top surface of a structure that cannot be directly irradiated with laser light by a laser scanner installed on the ground. Specifically, the surveying system superimposes second point cloud data generated from image data acquired by taking a picture from the air above with an unmanned aerial vehicle equipped with a camera on a first point cloud data acquired by laser scanning an area including the boundary between the top surface and the side surface of the structure from the side surface (i.e., the side where the laser scanner is installed), thereby surveying the top surface of the structure that cannot be irradiated with laser light from the ground. However, in order to superimpose point cloud data on point cloud data in this way, it is necessary to create each point cloud data. In particular, in order to create the second point cloud data that requires accuracy, it is necessary to perform laser scanning (i.e., scanning over a wide area) on the target object, which has a problem of long measurement time and poor work efficiency. In addition, the idea disclosed in Patent Document 1 is to perform laser scanning on an area as close as possible to a measurement point that cannot be seen from the ground. Even if one were to carry out a survey based on this idea, the boundaries between the top and side surfaces (i.e. corners and edges) and flat sides are shaped in a way that makes it difficult to obtain high accuracy using laser scanning, so in reality it is difficult to obtain the desired level of accuracy. Thus, the method disclosed in Patent Document 1 has the problem that it is only applicable to a limited number of structures.
[0008] In consideration of the above-mentioned circumstances, the present invention provides a three-dimensional surveying method that uses a simple configuration to obtain highly accurate measurement results in a relatively short time, even for architectural structures such as steel towers where the building materials are so intricate that the entire object to be measured cannot be grasped from the ground. [Means for solving the problem]
[0009] In order to achieve the above object, the three-dimensional surveying method of the present invention is a method for three-dimensionally surveying a component incorporated in a structure, comprising a first step of selecting a plurality of locations, including at least one location having a height coordinate value different from that of the component to be surveyed, as reference points from within the range of the structure in which the component to be surveyed is incorporated and its surrounding positions; a second step of acquiring photographic image data for an area including each of the reference points selected in the first step and an area including all or a part of the component to be surveyed, using a three-dimensional measuring machine equipped with a photographic image data acquisition means; and a second step of acquiring photographic image data for an area including each of the reference points selected in the first step as reference point coordinates converted into three-dimensional coordinate values, using a three-dimensional measuring machine for directly acquiring the three-dimensional coordinate values of desired measurement points. a third step of acquiring reference values for each of the plurality of reference points; a fourth step of acquiring imaged point cloud data in which the shapes of the structures and survey target components within the range of the acquired photographic image data are converted into 3D coordinate values by processing the photographic image data acquired in the second step; a fifth step of acquiring calibrated imaged point cloud data by selecting at least three of the plurality of reference points as calibration points and applying the reference point coordinate values acquired in the third step to the calibration point 3D coordinate values corresponding to each position of the calibration points in the imaged point cloud data acquired in the fourth step to perform calibration; and a sixth step of selecting any plurality of survey target points and calculating the distance between the survey target points from the calibrated imaged point cloud data.
[0010] The reference point includes a high-rise reference point set at a higher level than a preset safety altitude; The safety altitude may include a low-rise reference point set at a lower level than the safety altitude.
[0011] In addition, the reference point may be a target having a reflection point that reflects laser light or a prism having a reflection point that reflects light waves, and the 3D measuring device may be a 3D scanning device that obtains 3D coordinate values at the reflection point by irradiating the surveyed object with laser light or irradiating the surveyed object with light waves.
[0012] The target may also include a moving means for moving to each reference point while changing the altitude, and the target may include a lifting means using a mechanism attached to a structure in which the measurement target member is incorporated as the moving means for moving to each reference point. Furthermore, the photo image measuring device may be a UAV.
[0013] Furthermore, in order to achieve the above-mentioned object, the 3D surveying system for components of the present invention is a system for 3D surveying a component incorporated in a structure, and is characterized in that it comprises a photographic image data measuring machine for acquiring photographic image data for an area including the structure in which the survey target component is incorporated and each of a plurality of reference points previously set in its surroundings, and an area including all or part of the survey target component, a 3D measuring machine capable of directly acquiring the 3D coordinate values of each of the reference points, and a calculation device for acquiring imaging point cloud data in which the shapes of the structure and the survey target component within the range of the acquired photographic image data are converted into 3D coordinate values by data processing the photographic image data acquired by the photographic image data measuring machine, and for calculating the distance between any of a plurality of selected survey target points based on the calibrated imaging point cloud data acquired by applying the reference point 3D coordinate values of each of the reference points acquired by the 3D measuring machine to the calibration point 3D coordinate values corresponding to the respective positions of the calibration points in the imaging point cloud data, using at least three calibration points previously selected from the reference points. Effect of the Invention
[0014] According to the present invention, even when surveying tall structures such as steel towers, there is no need to actually climb the tower to the location where the components to be surveyed are located, and surveyors can easily conduct highly accurate surveys from the ground in a relatively short time. [Brief description of the drawings]
[0015] [Figure 1] Flowchart diagram showing the processing steps of the surveying method [Diagram 2] Schematic diagram showing the equipment configuration of the surveying system [Diagram 3] FIG. 1 is a diagram showing an example of captured point cloud data according to an embodiment; [Figure 4] Schematic diagram showing an example of selection of reference points for survey target components. [Diagram 5] Schematic diagram showing an example of a location where photographic image data is acquired for a survey target component. [Figure 6] FIG. 13 is a diagram showing an example of setting a reference point in the fourth embodiment; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] The three-dimensional surveying method of the present invention will be described with reference to the drawings. Fig. 1 is a block diagram of the surveying method of the present invention, and Fig. 2 is a schematic diagram showing the configuration of the entire system including instruments used in the surveying method of the present invention.
[0017] First, an outline of the three-dimensional surveying method of the present invention will be described. As shown in FIG. (First step): Select multiple reference points. (Second step): Photographic image data of the area and survey target components including each selected reference point is acquired. (Third step): The three-dimensional coordinate values of the selected reference points are obtained by a three-dimensional measuring machine. (Fourth step): The photographic image data acquired in the second step is converted into point cloud data by performing an operation on the photographic image data, thereby acquiring captured point cloud data. (Fifth step): The points (positions) corresponding to each reference point in the imaging point cloud data acquired in the fourth step are calibrated using the three-dimensional coordinate values acquired in the third step, and calibrated imaging point cloud data is calculated. (Sixth step): Surveying the survey target component is performed by selecting any two points within the range of the survey target component on the calibrated image point cloud data acquired in the fifth step and calculating the distance between the two points.
[0018] An overview of the system used in the surveying method of the present invention is shown in FIG. 2. For an architectural structure 1 in which a member S to be surveyed is incorporated, a number of arbitrary locations are selected as reference points 5 (5a, 5b, 5c, etc.). Next, photographs are taken by a photographic image measuring device 2 of the range including the reference points 5a, 5b, 5c, etc. and the member S to be surveyed to obtain photographic image data. In addition, measurements are performed using a three-dimensional measuring device 3 for each reference point to obtain the three-dimensional coordinate values of each reference point. The obtained photographic image data and the three-dimensional coordinate values of the reference points are sent to a processing device 4. The photographic image data is converted into 3D modeled point cloud data (imaging point cloud data) as shown in FIG. 3, for example, by image processing software (Structure from Motion (SfM) software) installed in the processing device 4. Next, the imaging point cloud data is calibrated using the three-dimensional coordinate values of each reference point acquired by the three-dimensional measuring device 3. By performing calibration for three or more reference points, the entire imaging point cloud data obtained from the photographic image data can be calibrated. For convenience of explanation, the data after the calibration is called calibrated imaging point cloud data. Then, by selecting any two points on the calibrated imaging point cloud data on the image processing software, the distance between the two points is calculated on the software. This makes it possible to accurately measure the size of the desired part of the target component, and by repeating the selection of any two points, it is also easy to calculate the exact shape and size of the entire target component. According to the surveying method of the present invention, the size and shape of the component can be measured within an error of mm, so that it is also possible to create a design drawing for creating a replacement component from the surveying results. Thus, according to the surveying method of the present invention, even if it is difficult for a worker to safely reach the location where the component is located because the component is located at a high place, for example, the worker can perform the survey from the ground without actually working at a high place, which is extremely safe, and at the same time, it reduces the cost and time required for the survey and leads to improved work efficiency.
[0019] The surveying method of the present invention is not particularly limited to the type of architectural structure or member to be surveyed, and can survey any object. If the advantage of being able to survey remotely from a distant location and therefore being able to perform high-precision surveying without working at height is maximized, high-rise buildings such as steel towers, bridges, buildings, and chimneys can be particularly preferably surveyed. In addition, even if a member is located in a position where it is difficult to irradiate the entire target member with a laser for surveying from the ground because a part of the member to be surveyed is in the shadow of another member, it is possible to accurately survey it. Therefore, a structure in which various members are arranged in a complicated manner, such as a steel tower, can be particularly preferably surveyed. The surveying method of the present invention will be described in detail below for each step.
[0020] The first step is to select a plurality of reference points for the survey target member S. The reference points are selected from the range of the structure in which the survey target member is incorporated and its surrounding positions. Here, the range of the structure in which the survey target member is incorporated and its surrounding positions refer to positions within the entire range of the architectural structure in which the member to be surveyed is incorporated and positions outside the architectural structure but located around the architectural structure. More specifically, the surroundings refer to positions that can be photographed in the same image as the target architectural structure in the acquisition of a photographic image performed in a later step. If such a range is shown by a steel tower, for example, it means that the reference points are selected at any positions of the steel tower support 11 from the top of the steel tower to the above-ground part of the leg and all other steel tower members, and further, if there is another structure near the steel tower, the reference point may be selected on a structure other than the target steel tower, provided that it is a position that can be photographed in the same image as the steel tower.
[0021] In this way, the multiple reference points selected from the range of the structure in which the survey target component is incorporated and its surrounding positions, more specifically, multiple locations that satisfy the following conditions are selected as reference points, making it possible to survey the size of the component with an accuracy of millimeter (mm) units. As a first condition, multiple reference points are selected, and at least one reference point is selected not only from within the range of the survey target component S but also from outside the survey target component S. At this time, at least one of the reference points selected from outside the target component has a height coordinate value different from that of the survey target component. In other words, this means that at least one reference point is selected as a reference point that is higher or lower than the survey target component. As a second condition, it is desirable that the reference points selected from outside the range of the target component include two points that are as far away from each other as possible. For example, when surveying a component incorporated in a steel tower, it is possible to include both a reference point near the top of the steel tower, which is the top of the steel tower, and a reference point selected from near the bottom, i.e., near the ground of the steel tower leg, if possible. In the surveying method of the present invention, it is preferable that the distance between the two reference points located at the furthest positions from each other is greater, since this improves the surveying accuracy.
[0022] As a third condition, it is desirable that the reference points include reference points selected from within the range of the survey target member, or from a location near the member that is as close as possible to the member even if it is outside the range of the member. Here, within the range of the target member means a position on the outer periphery (edge, border, corner, etc.) of the target member and a position inside it. This condition does not necessarily require that the reference point be set within the range of the target member, but it means that it is desirable to set at least one reference point at a location located as close as possible to the target member. Of course, one or more reference points may be set within the range of the target member. However, in reality, both ends of the survey target member S are often joints with other members. In such members, it may be difficult to set reference points at both ends. In that case, for example, a part that has the same shape as other parts, such as the middle part of the member, or a part of another member that is slightly away from the member (5g, 5f) as shown in Figure 4 can be selected as the reference point. Note that the reference point may be selected as a characteristic point, such as the center of a bolt 14 that appears on the surface of the building structure, or a target may be installed and its position used as the reference point. Taking the above points into consideration, the first step is to select multiple locations as reference points. Based on the reference points selected here, the range for actual data acquisition in the following steps will be determined.
[0023] In the second step, a photo image data measuring device 2 equipped with a photo image data acquiring means is used to acquire photo image data for each of the reference points selected in the first step, for the range including the reference point and the range including all or a part of the survey target component. The photo image data acquired here means a so-called photo, and may be taken in any image format as long as it can be processed by image processing software when read into a calculation processing device in a later step. The photographing is performed by photographing the range to be surveyed and the range including each reference point in the architectural structure in which the survey target component is incorporated. Here, the range to be surveyed specifically means the survey target component and its surroundings, or the part of the survey target component where the actual measurement value is to be obtained. Therefore, when the measurement value of the entire component is not required, it is sufficient to acquire photo image data only for the range of the required part of the component. In addition, the range including the reference point means the reference point and its surroundings.
[0024] The higher the resolution of the photographic image data acquired in the second step, the higher the accuracy of the point cloud data generated in the subsequent step will generally be. As shown in FIG. 5, multiple photographs are taken continuously while setting an overlapping area where a part of each member overlaps, such as P1, P2, P3, P4, etc. The number of photographs and the overlap rate for a single member can be the conditions generally set when generating point cloud data from SfM (Structure from Motion) software. It is desirable to continuously photograph the range connecting all the reference points, but in the surveying method of the present invention, as long as clear photographic images are obtained for the range including each reference point, the impact on accuracy is small even if the number of photographs is reduced for the intermediate parts between the reference points. Furthermore, the intermediate parts do not necessarily need to be continuous, and it is possible to omit photographing the intermediate parts and perform surveying by photographing only the range including each reference point. It is, of course, desirable to photograph each reference point and its surroundings as many times as possible with high resolution. In addition, it is desirable to take as many photographs as possible of the survey target components, especially the range for which survey values are to be obtained, at the highest possible resolution. For accurate surveying, it is desirable that the shape of the target components is clear on the point cloud data obtained after calculation, so it is desirable that the photographic images at least have a clear recognition of the shapes of the target components and the reference points on the photographic images at the previous stage. Although it is desirable to take photographs at the highest possible resolution, according to the surveying method of the present invention, even if the photographic images are taken at the standard resolution of the camera mounted on a general drone, that is, at a resolution of about 72 dpi, it is possible to achieve the millimeter-level accuracy that is the objective of the surveying method of the present invention.
[0025] In addition, in order to obtain 3D point cloud data that has been 3D modeled from photographic image data, it is necessary to take photographs of the object from as many directions as possible. To take such photographs, a suitable method is to mount a camera on a UAV such as a drone and take photographs while rotating the UAV around the object. In particular, when the object is located at a high place, it is preferable to take photographs using a UAV.
[0026] In the third step, a three-dimensional measuring machine 3 for directly acquiring the three-dimensional coordinate values of the measurement points is used to acquire the three-dimensional coordinate values of the positions of the reference points selected in the first step. For example, such a three-dimensional measuring machine is a laser tracker that irradiates a target location with laser light and measures the reflected light to obtain the three-dimensional coordinate values of the target location. The purpose of this third step is to acquire accurate three-dimensional coordinate values of the reference points used for calibration in the calibration of the point cloud data to be performed in the subsequent step. Therefore, it is sufficient to perform measurements only on the reference points. It is also possible to perform a scan by laser light scanning of the surroundings including the reference points and obtain the necessary three-dimensional coordinate values of the reference points from the data, but scanning the entire area of a certain range requires a considerable amount of time and is therefore not efficient. If a laser light is irradiated and measured only on one of the pre-selected reference points, the measurement can be completed in a very short time, so the method of the present invention enables surveying with excellent work efficiency.
[0027] Here, the order of performing the first to third steps is not necessarily restricted to the order shown in FIG. 1. The third step may be performed first, and the measured points may be selected as reference points, so as to select the reference points at the same time, or the first step of selecting the reference points may be performed for each reference point, while the second and third steps of data acquisition may be performed at the same time. That is, after acquiring photographic image data and three-dimensional coordinate values for one reference point, photographic image data and three-dimensional coordinate values may be acquired for other reference points at the same time, and this may be repeated to acquire photographic image data and three-dimensional coordinate values for all selected reference points. For example, when a laser tracker capable of acquiring highly accurate three-dimensional coordinate values without setting a target is used as a three-dimensional measuring instrument, any point on the architectural structure or the member to be surveyed may be set as the reference point. In this case, a method may be adopted in which a photograph is taken first, the resulting photograph is checked, and then characteristic points, easily visible points, points that are more clearly captured under favorable photographing conditions, etc. are selected as reference points, and the reference points are actually irradiated with a laser to acquire three-dimensional coordinate values. It is also possible to first irradiate the survey target with a laser and then take a photograph of the light reflected on the target as a reference point. In this case, the second and third steps are carried out simultaneously for each reference point, and by repeating this process, data is acquired for all reference points.
[0028] Next, each data acquired in the above steps is sent to the arithmetic processing device 4 for arithmetic processing. The data can be transferred from the photographic image data measuring device 2 and the 3D measuring device 3 to the arithmetic processing device 4 using a known method. For example, the data may be transferred via various storage media such as an SD card or smart media, or may be sent to a cloud server using a communication network. When a cloud server is used, the arithmetic processing to be performed in a later step may be performed on the cloud server, or the data may be sent from the cloud server to the arithmetic processing device 5 again via the communication network.
[0029] In the fourth step, imaging point cloud data is created from the photographic image data acquired in the second step and sent to the arithmetic processing device 5. This process can be performed using image processing software commonly known as SfM (Structure from Motion) software. According to this software, even if the photographic image data is multiple photographic data, a synthesis process of the joints is performed semi-automatically, and the photographic object is converted into 3D modeled data as point cloud data expressed as a set of points plotted with 3D coordinate values as shown in FIG. 3. For convenience of explanation, the point cloud data obtained from the photographic image data in this way is called imaging point cloud data. It is also possible to use the imaging point cloud data to select any two points on the image processing software and calculate the distance between the two points, but in that case, an error in the order of centimeters will occur. In particular, in the case of a survey aimed at creating a blueprint for a replacement part in order to replace the part, the allowable measurement error is in the order of millimeters, so it should be noted that a survey using this imaging point cloud data as it is will not meet the purpose at all.
[0030] The fifth step is a step of performing a process of calibrating the imaging point cloud data obtained in the fourth step. In this step, the imaging point cloud data obtained is calibrated using the reference point coordinate value, thereby obtaining a measurement accuracy with an error in the order of mm. Specifically, the point cloud data at the position corresponding to the reference point selected in the first step is calibrated using the reference point coordinate value obtained using the three-dimensional measuring device in the third step for the calibration point three-dimensional coordinate value corresponding to each position of the calibration point in the imaging point cloud data obtained in the fourth step. The more the number of reference points to be calibrated, the higher the calibration accuracy. In order to obtain accuracy in the order of mm, it is desirable to calibrate at least three or more reference points. Although there are some differences depending on the data acquisition conditions such as the resolution and shooting conditions of the photographic image data, the image quality of the obtained photographic image data, etc., in order to obtain accuracy in the order of mm more reliably, it is preferable to perform calibration using five or more reference points, and more preferable to perform calibration using seven or more reference points.
[0031] For the sake of convenience, the reference points selected in the first step that are to be calibrated are called calibration points. All of the reference points selected in the first step may be used as calibration points, but a certain number of reference points may be selected in advance, and after measurements in the second and third steps are performed, some of the reference points may be selected as calibration points when performing calibration in the fifth step. The calibration points may be selected in consideration of the positional relationship of the survey target members, such as the range of the building structure in which the positions of the members to be surveyed are located, which parts of the survey members are to be surveyed, the quality of the imaged point cloud data obtained in the fourth step, and the like. The selection may be made in advance before data acquisition, or may be made when performing calibration. The position of the calibration points is generally similar to the selection conditions for the reference points described above, but it is preferable to select the calibration points in consideration of the following points. 1) Select the two most distant control points possible as calibration points, regardless of the position of the survey members. 2) At least one point is selected from control points located within or around the area of the surveyed component. 3) When a plurality of reference points have the same direction axis coordinate value, at least one of the other reference points selects a position where the direction axis coordinate value is different.
[0032] Here, the condition 3) means that a lower-rise reference point (calibration point) is set on a vertical axis different from the vertical axis on which the higher-rise reference point (calibration point) is set. For example, when a steel tower is the object of survey, if multiple positions that differ only in height within the same pillar are selected as reference points (calibration points), it is preferable to set at least one of the other reference points (calibration points) on a different pillar. More specifically, when a three-dimensional space is expressed by an orthogonal coordinate system in which a plane (xy-plane) including the x-axis and the y-axis is the horizontal plane and the z-axis direction is positive in the vertical upward direction relative to the xy-plane, multiple reference points (calibration points) set on the same pillar differ only in the z-coordinate axis value, and the x-coordinate value and the y-coordinate value are almost the same, but by setting another reference point (calibration point) on another pillar, for example, it is possible to include a reference point (calibration point) with a different x-coordinate value or a different y-coordinate value. This makes it possible to further improve the accuracy of the calibration. For each calibration point selected in the above manner, SfM (Structure from Motion) software is used to calibrate the imaging point cloud data by applying the three-dimensional coordinate values of the reference point at the corresponding position among the reference point coordinate values obtained in the third step to the imaging point cloud data, thereby calibrating the entire imaging point cloud data to produce calibrated imaging point cloud data.
[0033] The sixth step is to obtain measurement values using the calibrated imaging point cloud data obtained in the fifth step. The measurement is carried out by specifying any two points on the calibrated imaging point cloud data in the software, and the distance between the two points is calculated. By repeating this process, it is possible to obtain accurate measurement values for the size of the entire object and each part of the object.
[0034] Next, each device used in the three-dimensional surveying method of the present invention will be described. The photographic image data measuring instrument 2 is not particularly limited as long as it can acquire photographic image data, i.e., take photographs, and a wide variety of general cameras can be used. It is preferable to use a digital camera, since photographic image data can be obtained in a data format that can be directly processed. It is desirable to install the photographic image data measuring instrument 2 at a position where the survey target member and the reference point can be photographed in detail, taking into consideration the positional relationship with the survey target member. The photographic image data does not have to be acquired only from a fixed position, and photographing may be performed while moving the photographic image data measuring instrument as necessary. When the survey target member is located at a low altitude, it may be photographed using the photographic image data measuring instrument 2 installed on the ground. When the target member is located at a high position, such as when it is built into the top of a steel tower, it is extremely desirable to use a UAV equipped with a camera as the photographic image data measuring instrument 2. A UAV (Unmanned Aerial Vehicle) is an aircraft (unmanned aerial vehicle) known as a drone, and can photograph desired locations while flying remotely or along a pre-programmed flight path. In this case, the GPS installed in the UAV automatically adds location information to the photo image data about the location where the photo was taken. In addition, if a UAV is used to take photos from the air, the UAV can take photos while rotating around the object to be measured, making it easy to obtain photo image data from multiple directions, which is necessary to obtain 3D point cloud data. Furthermore, not only is it easy to take photos of the object to be measured while avoiding blind spots such as positions behind other objects, but it is also easy to approach and take photos of objects in high positions, making it easy to obtain detailed photo image data with high resolution.
[0035] The three-dimensional measuring machine 3 is an instrument that can directly obtain the three-dimensional coordinate value of the measurement point by irradiating a laser or light wave to the location to be measured (measurement point). Specifically, LIDAR, laser scanner, total station, laser tracker, etc. can be used. These instruments irradiate a laser light or light wave to an object and receive the reflected light reflected by the object, thereby measuring the distance to the object based on the time from irradiation to reception and the phase of the reflected light, thereby obtaining the three-dimensional coordinate value of the measurement point. Many of these measuring machines require a target to be placed at the measurement point in order to obtain accurate reflected light. The method of the present invention can be used for both measurements with a target placed and measurements using a total station or laser tracker without placing a target, so that it is possible to appropriately select which one to use depending on the survey object and survey conditions.
[0036] When using targets, known targets can be used that match the 3D measuring device used. For example, in laser scanners, circular flat plates painted black and white are commonly used, and in laser trackers, reflectors are commonly used, which have a spherical structure with a mirror surface inside, so that the laser light is always reflected at the center regardless of the incident angle of the irradiated laser light, thereby measuring the sphere center coordinates. When surveying high-rise structures such as steel towers, if you try to shorten the distance from the 3D surveying device to the target as much as possible, you will inevitably have to install the measuring device in a location close to the high-rise structure. In this case, if you try to survey the area near the top of a high-rise structure, the laser light will be irradiated from directly below the target, making the irradiation angle obtuse, which makes it easier for accuracy to decrease due to a decrease in energy density. However, if you use a reflector, the light can always be reflected from the center regardless of the angle at which the laser light is received, so there is an advantage that accuracy is less likely to decrease even in such cases. In addition, it is possible to create and use calibration panels with crosses printed at a certain known interval. When installing these targets and conducting a survey, the target is placed at the desired position on the structure using a lifting mechanism. The lifting mechanism can be selected depending on the embodiment, and the specific contents will be described in detail in the description of the embodiments described later.
[0037] The data processor 4 may be a general computer, so long as it has sufficient specifications (CPU processor, memory, graphics board, storage capacity, etc.) to operate image processing software such as SfM software. Software used from the fourth step onwards may use software using SfM (Structure From Motion) or MVS (Multi-View Stereo) technology. Known examples of such software include Regard3D, Metashape, FieldReconst, and Pix4Dmapper. Also, a method is known in which SfM / MVS processing uses the open source OpenMVG / OpenMVS library and the generated 3D data is displayed using MeshLab.
[0038] As described above, according to the surveying method of the present invention, by performing calibration using three-dimensional coordinate values acquired by a three-dimensional measuring device for several calibration points, it is possible to perform surveying with high accuracy with an error of 1 mm or less. Since the surveying method of the present invention allows surveying from a position away from the target component, it is possible to safely perform surveying even for high-rise buildings. Furthermore, according to the surveying method of the present invention, it is sufficient to perform measurements using a three-dimensional measuring device for only several calibration points, so that time-consuming 3D scanning of the range is not required, and it is possible to significantly shorten the surveying time. Next, some specific examples of the surveying method of the present invention will be described. Explanations that overlap with the matters described above will be omitted, and only the characteristic parts of each embodiment will be described.
[0039] (First embodiment) For example, when surveying a survey target component incorporated in a low-rise building structure up to about 60 m high, the 3D measuring machine can be installed in a position close enough to the target component, so that a laser beam can be directly irradiated onto a characteristic point on the surface of the component or the surface of the building structure, and the point can be selected as a reference point without placing a target. This method allows the survey work to be carried out more efficiently because it does not require the installation of a target. Here, a position close enough means a distance within which measurement can be performed without a target, which is guaranteed by the performance of the 3D measuring machine used. For example, when using a laser tracker that can survey up to 60 m without a target as the 3D measuring machine, theoretically, it is sufficient to install the laser tracker within 60 m from the survey target component (or the reference point located farthest away). However, since the distance at which accurate 3D coordinate values can be obtained varies depending on the shape and reflectance of the component surface, it is desirable to install the laser tracker within 30 to 40 m, even when using a model that can survey up to 60 m. When such conditions are satisfied, the degree of freedom in determining where to set the reference point selected in the first step is higher than in the case of setting a target, so the first step does not necessarily need to be performed prior to the second and third steps. The second step of acquiring photographic image data and the fourth step of acquiring captured point cloud data may be performed first, and after confirming characteristic points or points with good data quality in the acquired captured point cloud data, these may be set as reference points, and the third step of acquiring three-dimensional coordinate values using a three-dimensional measuring machine (laser tracker) may be performed. Conversely, the third step of acquiring three-dimensional coordinate values using a three-dimensional measuring machine (laser tracker, etc.) may be performed first, and the second step of photographing the light points on the measurement object irradiated with laser light to acquire the three-dimensional coordinate values may be performed at the same time. This method is efficient in that it is easier to match the reference points on the captured point cloud data with the reference points on the captured point cloud data.
[0040] (Second embodiment) With current laser tracker technology, the maximum distance that can be measured without a target is about 60 m, but considering the measurement environment conditions, the actual limit is 30 to 40 m. This corresponds to the height of a 66 kV class steel tower, and when surveying a steel tower that is higher than this, it is necessary to install a target and perform the third step of surveying with a three-dimensional measuring machine. In this case, the target is installed on a high floor of the building structure using a lifting mechanism. In this embodiment, an industrial robot that can move on a wall can be used as the lifting mechanism. As such wall-moving robots, various types of industrial robots inspired by the movements of living things are known. For example, there are multi-legged robots that have suction cups at the tip of each leg and move on the wall using the suction power of these suction cups, and for steel towers whose main material is iron, there are robots that have magnets on the wall side (abdomen side) and move in a serpentine manner, and robots that have caterpillar-shaped magnets and move up and down like caterpillar armored vehicles. In the present invention, any type of robot can be used as long as a target (preferably a reflector) can be attached to the outside of the robot (in the case of the exemplified type, the back side). The surveying method of the present invention allows a high degree of freedom in determining where to set the reference point, so that a point that the robot can easily reach can be set as the reference point according to the characteristics of the robot to be used. Currently, the commonly used laser tracker can survey up to 160 m if a reflector is used. Therefore, according to this embodiment, even a large steel tower of 220 kV or more can be surveyed. In addition, in this embodiment, it is efficient to adopt a method in which a reflector is raised and lowered by an industrial robot while a location that is easy to survey is set as a reference point, and the second step of acquiring photographic image data for that location and the third step of acquiring three-dimensional coordinate values by a laser tracker are simultaneously performed.
[0041] (Third embodiment) In the second embodiment, large steel towers can also be surveyed, but the ease of the surveying work is somewhat inferior because an industrial robot is used. That is, industrial robots that can move on walls are expensive, the industrial robot must be brought to the site for surveying, and the vertical movement of the robot takes some time, so the surveying time is likely to be long. Therefore, in this embodiment, a lifting means is adopted that can raise and lower the reflector more easily. Specifically, the survey is performed using a target equipped with a lifting means that utilizes a mechanism installed in the architectural structure to be surveyed. For example, in the case of a steel tower, it is possible to use a rail (rail for mounting fall prevention hardware for lifting) 13 installed on one of the pillars 11 of each steel tower. This is a rail through which a worker working at height can pass the hook of a fall prevention harness, and is a rail that extends from near the ground to the top of the steel tower. There is a stopper near the top to prevent the hook from coming off. Usually, by attaching a harness to the safety device that is to be engaged with the rail 13, the safety device also rises and falls while connected to the rail as the worker rises and falls. As such a safety device, there is known one that can be raised and lowered freely by a plurality of wheels (guides) that are provided to sandwich the rail. In this embodiment, a motor can be attached to the safety device like an agricultural monorail to drive the wheels (guides) and make it possible to raise and lower the rail. By attaching a reflector to this safety device, the reflector can be raised and lowered along the rail. In this case, since the reflector that is usually used is lightweight, it is possible to stop the reflector at any position by stopping the drive of the motor at that position. Note that if the reflector is heavy or if it is desired to stop it more reliably, the stopping ability can be reinforced by stopping it using a mechanism similar to the fall prevention device of the safety device, or by using a suction cup or magnet used in the above-mentioned industrial robot for climbing up and down a wall.
[0042] In addition, as a simpler lifting mechanism using the rail 13 for mounting fall prevention fittings on the pylon, there is a method of lifting and lowering a reflector equipped with a hook to be connected to the rail using the buoyancy of a drone or balloon. A wire that reaches the ground is attached to the reflector, and the reflector can be fixed at the desired position by adjusting the length of the wire from the ground. After the measurement is completed up to the top, the wire can be rewound to lower it to the ground. In addition, since a stopper to prevent the hook from falling off is usually installed near the top of the rail, there is no need to worry about losing the reflector due to an operating error. Although this method has disadvantages such as being easily affected by wind, it has the advantage that it is relatively inexpensive and easy to survey if the weather conditions at the time of surveying are good.
[0043] When using a lifting mechanism using rails 13 of a steel tower as in the third embodiment, there is an advantage that the survey can be performed more easily, but in a normal steel tower, the rails are installed on only one of the four pillars. Therefore, when using this method, the reflector can be installed as a reference point only within the range of one pillar, that is, within the vertical range where only the z-axis coordinate value (i.e., height) is different in almost the same horizontal plane coordinate value (xy plane coordinate value). Depending on the position where the survey target member is installed, this may be sufficient to obtain a sufficient surveying accuracy, but in order to further improve the surveying accuracy, it is desirable to install a reflector on another pillar (at a position where the x-axis coordinate value or y-axis coordinate value is different). Therefore, in this embodiment, for one of the steel tower pillars equipped with a rail, the reflector is raised and lowered using the above-mentioned rail-based lifting means, and measurements are performed with reference points set at various height positions within the range from the top of the steel tower to near the ground, and for any of the other pillars (i.e., pillars without rails) other than the one with the rail, a reflector is installed within a preset safe height range, and measurements are performed using that as one of the reference points. Here, the safe height means a height that is set in advance in consideration of the various conditions of the site, within the range of a height at which a worker on the ground can manually install a reflector, that is, a height that can be reached, or a height at which a worker can attach a reflector with a low-rise ladder without causing a serious accident even if he falls. Although it varies depending on the conditions of the site, it is generally set to a height of 1.5 m or less. In Fig. 2, reflectors 5a, 5b, 5c, and 5d (reference number not shown for 5b) are reference points set at different heights using lifting means within the range of a support with a rail, and 5e is a reference point installed on a support without a rail within the range of the safety altitude. Although it depends on the position and conditions of the survey target member, i.e., whether the position conditions allow clear photographic image data to be obtained, by installing about 5 to 6 reference points set using lifting means and 1 to 2 reflectors set manually within the range of the safety altitude of other supports, it is possible to perform surveying with an error range of mm, which is the objective of the surveying method of the present invention.According to the third embodiment, the installation and measurement of a plurality of control points can be performed relatively easily and quickly, so that a survey excellent in terms of work efficiency and work cost is possible. Note that the other control points to be installed at positions having xy coordinate values different from the support post on which the rail is located do not necessarily have to be installed on the support post, and it goes without saying that it is sufficient to install them at positions with favorable installation conditions that are as far away as possible from the support post on which the rail is located.
[0044] (Fourth embodiment) When surveying a small-scale steel tower of about 66 kV class (30 m), a method of using a calibration panel as shown in FIG. 6 as a reference point can also be adopted. In this embodiment, the calibration of the imaged point cloud data, which is executed in the fifth step, is performed using the known opening (wideness) of the steel tower leg 12 and a calibration panel installed near the ground of the leg. For example, as shown in FIG. 6(a), a reflector can be installed near the ground of each of the support legs 12 of the steel tower to set it as a reference point (calibration point). In addition, since the wideness of the leg is determined as a specified value in the case of a steel tower, it is also possible to set a desired point of the steel tower leg as a reference value without installing such a target. In the case of a steel tower of 66 kv class, even if the survey target member is located at a high rise, the survey method of the present invention can be applied by simply setting a reference point near the ground in this way, so there is no need to set another reference point, for example, in the upper part of the steel tower. According to this embodiment, the reference point can be installed on the ground without requiring a special mechanism, so that the entire survey work can be performed simply and efficiently. Furthermore, it is also possible to use a calibration panel in which multiple targets are accurately arranged at a predetermined interval (distance) as the reference points. Specific examples of such calibration panels are shown in Figs. 6(b) and (c). Fig. 6(b) shows a panel in which multiple reflectors are installed at a fixed interval to serve as reference points, and Fig. 6(c) shows a panel in which crosses are marked at a fixed interval to serve as reference points. When using a calibration panel in which the exact distance between reference points is known in this way, the installation location can be anywhere as long as the panel can be photographed simultaneously with the structure to be surveyed in the acquisition of photographic image data in the second step. This makes it possible to perform survey work with a very high degree of freedom, without being influenced by the environmental conditions of the location of the survey object. In addition, when performing a survey using this embodiment, as in other embodiments, the survey accuracy is improved by making the interval between each reference point as wide as possible. Furthermore, according to this embodiment, even when a high-precision three-dimensional measuring device such as a laser tracker cannot be prepared, a survey using a total station can be expected to have sufficient survey accuracy in practice.
[0045] As described above, according to the surveying method of the present invention, the exact size and shape of the survey object can be remotely measured from a distant location, so that the surveying can be performed very safely without working at height. In addition, since laser scanning measurement, which requires time, is not required, the surveying method is excellent in terms of work efficiency and cost. Note that, although the above embodiment and the like have been described as being mainly used for surveying steel towers, the present invention can also be applied to other structures. [Explanation of symbols]
[0046] 1 Architectural structure 11 Posts 12 Pillars (legs) 13 Rail for mounting fall prevention brackets 2. Photographic image data measuring device 3. 3D measuring machine 4 Data Processing Device 5 Reference point (target) S Survey target material
Claims
1. A method for three-dimensionally surveying a member incorporated in a structure, comprising the steps of: A first step of selecting a plurality of locations as reference points from within the range of a structure in which the survey target components are incorporated and from positions around the range of the structure, the plurality of locations including at least one location having a height coordinate value different from that of the survey target components; a second step of acquiring photographic image data for an area including each of the reference points selected in the first step and an area including all or a part of the survey target member by using a photographic image data measuring device equipped with a photographic image data acquiring means; a third step of acquiring reference point coordinate values obtained by converting each of the reference points selected in the first step into three-dimensional coordinate values using a three-dimensional measuring machine for directly acquiring three-dimensional coordinate values of desired measurement points; a fourth step of processing the photographic image data acquired in the second step to obtain imaging point cloud data in which the shapes of the structures and survey target components within the range of the acquired photographic image data are converted into three-dimensional coordinate values; a fifth step of selecting at least three of the plurality of reference points as calibration points, and performing calibration by applying the reference point coordinate values obtained in the third step to the calibration point three-dimensional coordinate values corresponding to the respective positions of the calibration points in the imaging point cloud data obtained in the fourth step, thereby obtaining calibrated imaging point cloud data; a sixth step of selecting any of a plurality of survey points and calculating distances between the survey points from the calibrated imaged point cloud data; A method for three-dimensionally measuring a component comprising the steps of:
2. The three-dimensional surveying method for a member according to claim 1 , wherein the reference points include high-rise reference points set at a higher level than a preset safety altitude, and low-rise reference points set at a lower level than the safety altitude.
3. The reference point is a target having a reflection point that reflects a laser beam or a prism having a reflection point that reflects a light wave, 3. The method for three-dimensional surveying of a component as described in claim 1 or 2, wherein the three-dimensional measuring machine is a three-dimensional scanning device that obtains three-dimensional coordinate values at the reflection point by irradiating the surveyed object with laser light or by irradiating the surveyed object with light waves.
4. 4. The method for three-dimensionally measuring a member according to claim 3, wherein the target is provided with a moving means for moving to the position of each reference point while changing the altitude.
5. 4. The three-dimensional surveying method for a member according to claim 3, wherein the target is provided with a lifting means that utilizes a mechanism attached to a structure in which the member to be measured is incorporated as a moving means for moving the target to the position of each reference point.
6. The method for three-dimensionally measuring a member according to claim 3 , wherein the photo-image measuring device is a UAV.
7. 3. The three-dimensional surveying method according to claim 2, wherein the reference points further include a low-rise reference point that is set on a vertical axis different from the vertical axis on which the high-rise reference point is set.
8. A system for three-dimensionally measuring a member incorporated in a structure, comprising: a photographic image data measuring device for acquiring photographic image data for an area including a structure in which the survey target components are incorporated and a plurality of reference points preset in the vicinity of the structure, and an area including all or a part of the survey target components; a three-dimensional measuring machine capable of directly acquiring three-dimensional coordinate values of each of the reference points; The photographic image data acquired by the photographic image data measuring instrument is processed to acquire imaging point cloud data in which the shapes of the structures and survey target members within the range of the acquired photographic image data are converted into three-dimensional coordinate values, and Using at least three calibration points preselected from among the reference points, Based on calibrated imaging point cloud data acquired by performing calibration by applying the reference point three-dimensional coordinate values of each of the reference points acquired by the three-dimensional measuring machine to the calibration point three-dimensional coordinate values corresponding to the respective positions of the calibration points in the imaging point cloud data, A calculation device for calculating the distance between any of a plurality of selected survey points; This is a 3D surveying system for components.