Working hour calculation device, method, and program

The work time calculation device adjusts standard work times based on device, part, and worker data to optimize maintenance schedules, enhancing efficiency and satisfaction.

JP2025140735AActive Publication Date: 2025-09-29NEC FIELDING
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2024040297
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2024-03-14
Publication Date
2025-09-29
Estimated Expiration
2044-03-14

AI Technical Summary

Technical Problem

Existing methods for setting standard work times in maintenance tasks are inadequate as they do not account for variations due to factors like worker experience, device type, and fault level, leading to inefficiencies and customer dissatisfaction.

Method used

A work time calculation device and method that considers device data, replacement part data, fault level data, and worker data to determine optimal standard work times, adjusting for worker experience and task complexity.

Benefits of technology

Enables setting of optimal standard work times, improving productivity and customer satisfaction by ensuring tasks are completed efficiently.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2025140735000001_ABST
    Figure 2025140735000001_ABST
Patent Text Reader

Abstract

To provide a working hour calculation device capable of contributing to set an optimal standard working hour.SOLUTION: A working hour calculation device includes a working hour calculation unit which is configured to calculate a standard working hour related to a maintenance work, by referring to database, on the basis of device data for specifying a device as a maintenance object, replacement part data for specifying a replacement part, fault level data for specifying a fault level indicating high reproducibility of a fault, and worker data for specifying a worker.SELECTED DRAWING: Figure 9
Need to check novelty before this filing date? Find Prior Art

Description

[Technical Field]

[0001] The present invention relates to an operation time calculation device, method, and program. [Background technology]

[0002] In the maintenance work of various equipment, multiple tasks are typically assigned per day, and workers perform their work while traveling between multiple locations. Therefore, a target work time (hereinafter referred to as "standard work time") is set in advance for each task, and each worker's work schedule is set taking this standard work time into consideration. If the standard work time is set shorter than the appropriate value, the work cannot be completed according to the schedule, and the work cannot start at the time the customer requested, which may inconvenience the customer. This may lead to a decrease in customer satisfaction (CS). On the other hand, if the standard work time is set longer than the appropriate value, unnecessary time will be added to the schedule, resulting in a decrease in productivity. Therefore, the standard work time plays a very important role in performing maintenance work. For example, in Patent Document 1, the standard work time is calculated by using the actual time spent on the same work in the past as the time required for the work. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent Publication No. 2013-025771 Summary of the Invention [Problem to be solved by the invention]

[0004] The following analysis is provided by the present inventors.

[0005] However, even for the same task, the task time varies depending on factors other than the task content (for example, the worker, obstacles, etc.), so there is room for improvement in setting the optimal standard task time.

[0006] A main object of the present invention is to provide a task time calculation device, method, and program that can contribute to setting an optimal standard task time. [Means for solving the problem]

[0007] The work time calculation device according to the first aspect includes a work time calculation unit configured to calculate a standard work time for maintenance work by referring to a database based on device data identifying the device to be maintained, replacement part data identifying the replacement part, fault level data identifying a fault level indicating the reproducibility of the fault, and worker data identifying the worker.

[0008] The work time calculation method according to the second aspect includes a step in which a work time calculation device calculates a standard work time for maintenance work by referring to a database based on device data identifying the device to be maintained, replacement part data identifying the replacement part, fault level data identifying a fault level indicating the reproducibility of the fault, and worker data identifying the worker.

[0009] The program according to the third aspect causes the work time calculation device to execute a process of calculating a standard work time for maintenance work by referring to a database based on device data that identifies the device to be maintained, replacement part data that identifies the replacement part, fault level data that identifies the fault level indicating the reproducibility of the fault, and worker data that identifies the worker.

[0010] The program can be recorded on a computer-readable storage medium. The storage medium can be a non-transitory medium such as a semiconductor memory, a hard disk, a magnetic recording medium, or an optical recording medium. The present disclosure can also be embodied as a computer program product. The program is input to a computer device via an input device or a communication interface from the outside, stored in a storage device, and drives a processor according to predetermined steps or processes. The processing results, including intermediate states as needed, can be displayed at each stage on a display device, or the computer device can communicate with the outside via the communication interface. For example, a computer device for this purpose typically includes a processor, a storage device, an input device, a communication interface, and a display device as needed, all of which can be connected to each other via a bus. [Effects of the Invention]

[0011] The first to third aspects can contribute to setting optimal standard work times. [Brief explanation of the drawings]

[0012] [Figure 1] 1 is a block diagram schematically illustrating a first example of the configuration of an operation time calculation device according to the present disclosure. [Figure 2] 3 is a schematic diagram showing an example of the configuration of a standard work time database used in the work time calculation device according to the present disclosure. FIG. [Figure 3] 1 is a schematic diagram showing an example of the configuration of a worker database used in an operation time calculation device according to the present disclosure. FIG. [Figure 4] 10 is a flowchart schematically illustrating an example of the operation of the task time calculation device according to the present disclosure. [Figure 5] FIG. 4 is a block diagram schematically illustrating a second example of the configuration of an operation time calculation device according to the present disclosure. [Figure 6] FIG. 10 is a block diagram schematically illustrating a third example of the configuration of an operation time calculation device according to the present disclosure. [Figure 7]1 is a schematic diagram showing an example of the configuration of a task result database used in an task time calculation device according to the present disclosure. FIG. [Figure 8] FIG. 10 is a block diagram schematically illustrating a fourth example of the configuration of an operation time calculation device according to the present disclosure. [Figure 9] FIG. 10 is a block diagram schematically illustrating a fifth example of the configuration of an operation time calculation device according to the present disclosure. [Figure 10] FIG. 2 is a block diagram illustrating a configuration of hardware resources. DETAILED DESCRIPTION OF THE INVENTION

[0013] The following description of the embodiments will be made with reference to the drawings. Note that, where reference numerals are used in this application, they are intended solely to facilitate understanding and are not intended to limit the present invention to the illustrated embodiments. Furthermore, the following embodiments are merely exemplary and do not limit the present invention. Furthermore, connecting lines between blocks in the drawings and the like referred to in the following description include both bidirectional and unidirectional lines. Unidirectional arrows are used to schematically indicate the flow of main signals (data) and do not exclude bidirectionality. Furthermore, although not explicitly shown, input and output ports exist at the input and output ends of each connecting line in the circuit diagrams, block diagrams, internal configuration diagrams, connection diagrams, and the like shown in this disclosure. The same applies to input and output interfaces. A program is executed via a computer device, which includes, for example, a processor, a storage device, an input device, a communication interface, and, if necessary, a display device. The computer device is configured to communicate with internal or external devices (including computers) via the communication interface, whether wired or wireless.

[0014] [Form 1] An operation time calculation device according to a first embodiment will be described with reference to the drawings. FIG. 1 is a block diagram schematically illustrating a first example of the configuration of an operation time calculation device according to the present disclosure. FIG. 2 is a schematic diagram illustrating an example of the configuration of a standard operation time database used in the operation time calculation device according to the present disclosure. FIG. 3 is a schematic diagram illustrating an example of the configuration of a worker database used in the operation time calculation device according to the present disclosure.

[0015] The task time calculation device 10 is a device that calculates the time required for a task (see FIG. 1). A device having computer functions, such as a server or a personal computer, can be used as the task time calculation device 10. By executing a predetermined stored program, the task time calculation device 10 can virtually be configured to include a data acquisition unit 11, a task time calculation unit 12, a database unit 13, and a data output unit 14.

[0016] The data acquisition unit 11 is a functional unit that acquires data (see FIG. 1). Examples of the acquired data include device data, replacement part data, fault level data, and worker data. The device data is data that identifies the device (model) to be maintained. The replacement part data is data that is received from a customer when a fault occurs and identifies the replacement part that is predicted to be the cause of the fault based on the device to be maintained and the fault level. The fault level data is data that identifies the fault level, which indicates the reproducibility of the fault, such as whether the same fault has occurred in the past and how frequently it occurs. The higher the fault level, the lower the reproducibility of the fault (i.e., the higher the task difficulty). The fault level data is created based on a customer's report when a fault occurs. The worker data is data that identifies the worker who will perform the maintenance work, and may be any information that identifies the worker, such as the worker's name, employee number, email address, or mobile phone number. The data acquisition unit 11 may acquire various data by inputting various data through user operations, or by receiving various data from an external source. The data acquisition unit 11 can output the acquired various data to the work time calculation unit 12, the database unit 13, and the data output unit 14.

[0017] The work time calculation unit 12 is a functional unit that calculates a standard work time for maintenance work (see FIG. 1). The work time calculation unit 12 acquires equipment data, replacement part data, failure level data, and worker data from the data acquisition unit 11. The work time calculation unit 12 starts the calculation process of the standard work time by acquiring the equipment data, replacement part data, failure level data, and worker data. The work time calculation unit 12 extracts standard work times corresponding to the acquired equipment data, replacement part data, and failure level data from the standard work time database 13a (see FIG. 2) of the database unit 13. The work time calculation unit 12 extracts the number of work experiences corresponding to the acquired worker data from the worker database 13b (see FIG. 3) of the database unit 13. The work time calculation unit 12 calculates the standard work time based on the extracted standard work time and number of work experiences. As an example of calculating the standard work time, the work time calculation unit 12 determines whether the extracted number of times of work experience is equal to or greater than a predetermined first predetermined number N1 (e.g., 10 times). If the number of times of work experience is equal to or greater than the first predetermined number N1, the work time calculation unit 12 can calculate the standard work time so that the standard work time is shortened (e.g., by 10 minutes) on the assumption that the worker has more experience and the work time will be shorter. Furthermore, if the number of times of work experience is less than the first predetermined number N1, the work time calculation unit 12 determines whether the extracted number of times of work experience is equal to or greater than a predetermined second predetermined number N2 (a value smaller than N1; e.g., 3 times). If the number of times of work experience is equal to or greater than the second predetermined number N2, the work time calculation unit 12 can calculate the standard work time so that the standard work time is extended (e.g., by 20 minutes) on the assumption that the worker has less experience and the work time will be longer. If the worker data includes not only the extracted standard work time and number of work experiences but also the qualification information of the worker, the work time calculation unit 12 may calculate the standard work time based on the qualification information. For example, if the qualification information is available, the standard work time can be calculated so as to shorten the standard work time.

[0018] The database unit 13 is a functional unit that stores various databases (see FIG. 1). The database unit 13 stores a standard operation time database 13a (see FIG. 2) and a worker database 13b (see FIG. 3). As shown in FIG. 2, the standard operation time database 13a may be a database that associates, for example, equipment, replacement parts, failure levels, and standard operation times. The standard operation time database 13a allows for identifying equipment names, replacement part names, and failure levels, thereby extracting a standard time required for part replacement work (standard operation time). As shown in FIG. 3, the worker database 13b may be a database that associates, for example, worker names (e.g., names, employee numbers), contact information (e.g., email addresses, phone numbers), and the number of times the worker has performed work. While the worker database 13b lists the number of times the worker has performed work, it may also be more detailed, by associating the number of times the worker has performed work for each equipment with each worker. Updating the number of times the worker has performed work will be described in the second embodiment.

[0019] The data output unit 14 is a functional unit that outputs data (see FIG. 1). The data output unit 14 outputs standard work time data, which is the calculation result of the work time calculation unit 12. For example, the data output unit 14 acquires the standard work time calculated by the work time calculation unit 12 and outputs it to the outside (display, transmit, etc.).

[0020] Next, the operation of the work time calculation device according to the first embodiment will be described with reference to the drawings. Fig. 4 is a flow chart that schematically shows an example of the operation of the work time calculation device according to the present disclosure. Please refer to Figs. 1 to 3 for the configuration of the work time calculation device.

[0021] First, the data acquisition unit 11 acquires device data, replacement part data, fault level data, and worker data (step A1).

[0022] Next, the work time calculation unit 12 starts the calculation process of the standard work time by acquiring the equipment data, replacement part data, fault level data, and worker data from the data acquisition unit 11, and extracts the standard work time corresponding to the acquired equipment data, replacement part data, and fault level data from the standard work time database 13a (see Figure 2) of the database unit 13 (step A2).

[0023] Next, the task time calculation unit 12 extracts the number of task experiences corresponding to the acquired worker data from the worker database 13b (see FIG. 3) of the database unit 13 (step A3).

[0024] Next, the task time calculation unit 12 determines whether the extracted number of task experiences is equal to or greater than a first predetermined number N1 (for example, 10 times) (step A4).

[0025] If the number of times the worker has performed the task is equal to or greater than the first predetermined number N1 (YES in step A4), the task time calculation unit 12 calculates the standard task time to shorten the reference task time (for example, by 10 minutes) assuming that the worker has more experience and the task time will be shorter (step A5), and then proceeds to step A9.

[0026] If the number of times the work has been performed is less than the first predetermined number N1 (NO in step A4), the work time calculation unit 12 determines whether the extracted number of times the work has been performed is equal to or greater than a preset second predetermined number N2 (a value smaller than N1; for example, 3 times) (step A6).

[0027] If the number of times the task has been performed is equal to or greater than the second predetermined number N2 (YES in step A6), the task time calculation unit 12 calculates the acquired reference task time as the standard task time (step A7), and then proceeds to step A9.

[0028] If the number of times the worker has performed the task is less than the second predetermined number N2 (NO in step A6), the task time calculation unit 12 calculates the standard task time so as to extend the reference task time (for example, by 20 minutes) assuming that the worker has little experience and the task time will be long (step A8), and then proceeds to step A9.

[0029] After step A5, step A7, or step A8, the data output unit 14 outputs the standard work time data that is the calculation result of the work time calculation unit 12 (step A9), and then the process ends.

[0030] According to the first aspect, the standard work time is calculated based on the data of the device to be worked on, the replacement parts required for the maintenance work, the failure level, and the worker, which contributes to setting an optimal standard work time. As a result, it is possible to prevent a decrease in customer satisfaction and productivity, and to perform work efficiently.

[0031] [Form 2] The following describes an operation time calculation device according to embodiment 2 with reference to the drawings. Fig. 5 is a block diagram schematically illustrating a second example of the configuration of an operation time calculation device according to the present disclosure.

[0032] The second embodiment is a modification of the first embodiment, and includes an experienced work count update unit 15. In the second embodiment, the data acquisition unit 11 acquires task completion data (e.g., data including the worker and the task completion) related to task completion, and the experienced work count update unit 15 updates (adds one count to) the experienced work count of the worker in the worker database 13b corresponding to the worker in the task completion data. The task completion data can be acquired by a user performing an input operation on the task time calculation device 10, or can be received and acquired from a worker terminal used by the worker. The experienced work count is updated each time a task is completed, and the experienced work count update unit 15 may request task completion data from the worker terminal (not shown) of the corresponding worker (or may request an update of the experienced work count from the user of the task time calculation device 10) after a predetermined time has elapsed since the task time calculation unit 12 calculated the standard task time (or after the data output unit 14 output the standard task time). The other configurations and operations are the same as those of the first embodiment.

[0033] According to the second aspect, as with the first aspect, it is possible to contribute to setting an optimal standard working time, and also to automatically update the number of work experiences of workers, which affects the setting of the optimal standard working time.

[0034] [Form 3] An operation time calculation device according to the third embodiment will be described with reference to the drawings. Fig. 6 is a block diagram showing a schematic diagram of a third example of the configuration of an operation time calculation device according to the present disclosure. Fig. 7 is a schematic diagram showing an example of the configuration of an operation result database used in the operation time calculation device according to the present disclosure.

[0035] The third embodiment is a modification of the first embodiment, and includes an operation time comparison unit 16 (see FIG. 6). In the third embodiment, the data acquisition unit 11 acquires operation result data including the device, replacement part, failure level, actual operation time, and worker name. The user can acquire the operation result data by inputting information into the operation time calculation device 10, or the data can be received and acquired from a worker terminal used by the worker. The acquired operation result data is stored in the operation result database 13c of the database unit 13 (see FIG. 7). The operation time comparison unit 16 extracts and compares the actual operation time in the operation result database 13c corresponding to the device, replacement part, failure level, and worker name in the operation result database 13c with the latest standard operation time output and stored by the operation time calculation unit 12. The operation time comparison unit 16 calculates the proportion of the number of operations in which the actual operation time exceeded (or fell short of) the standard operation time out of the total number of operations for each device in a predetermined period (e.g., one month), and determines whether the calculated proportion exceeds a predetermined proportion. If the calculated ratio exceeds a predetermined ratio (if there is variation depending on the worker's number of experiences), the work time comparison unit 16 can output information regarding a review of the standard work time (review of the shortened or extended time) via the data output unit 14. For example, if there are five cases where the actual work time exceeds 30 minutes, exceeding the standard work time of 60 minutes by 90 minutes, a request can be made to the department that manages the standard work time to review the standard work time. This allows for setting a highly accurate standard work time that takes actual work time into consideration. Information regarding the difference in time and the number of times the time has exceeded the standard work time, which serves as a guide for the review request, can be stored in the work time comparison unit 16 or in the database unit 13. Other configurations and operations are the same as those of the first embodiment. Furthermore, the third embodiment may be applied to the second embodiment.

[0036] According to the third embodiment, similar to the first embodiment, it is possible to contribute to setting an optimal standard work time, and also to set a highly accurate standard work time that takes into account actual work time.

[0037] [Form 4] An operation time calculation device according to form 4 will be described with reference to the drawings. Fig. 8 is a block diagram schematically showing a fourth example of the configuration of an operation time calculation device according to the present disclosure.

[0038] The fourth embodiment is a modification of the first embodiment, and includes an additional alarm unit 17 (see FIG. 8). The alarm unit 17 has a timer function and issues an alarm a predetermined time before the end of the standard work time calculated by the work time calculation unit 12 (for example, 10 minutes before the end of the standard work time). The alarm is sent to a worker terminal 20 (for example, an information communication terminal such as a smartphone or smartwatch) used by the worker. If the work has been completed before the predetermined time (for example, if the work time calculation device 10 has acquired the work completion data of FIG. 5 or the work result data of FIG. 6), the worker can disable the alarm by operating the worker terminal 20 (or automatically disable the alarm when the work result data has been acquired). The other configurations and operations are the same as those of the first embodiment. The fourth embodiment may also be applied to the second and third embodiments.

[0039] According to the fourth embodiment, similar to the first embodiment, it is possible to contribute to setting an optimal standard work time, and since the alarm issuing unit 17 issues an alarm to the worker terminal 20 at a predetermined time before the end of the standard work time, it is possible to make the worker aware of the work time again if the worker has not been able to work as planned. Also, if the work has not been completed at a predetermined time before the end of the standard work time, it is possible to prompt the remote supporter to provide support.

[0040] [Form 5] An operation time calculation device according to form 5 will be described with reference to the drawings. Fig. 9 is a block diagram schematically showing a fifth example of the configuration of an operation time calculation device according to the present disclosure.

[0041] The operation time calculation device 10 is a device that calculates operation time. The operation time calculation device 10 includes an operation time calculation unit 12. The operation time calculation unit 12 is configured to calculate a standard operation time for maintenance operation by referring to the database 13d based on device data that identifies the device to be maintained, replacement part data that identifies the replacement part, failure level data that identifies a failure level indicating the reproducibility of the failure, and worker data that identifies the worker.

[0042] According to the fifth aspect, the standard work time is calculated based on the data of the device to be worked on, the replacement parts required for the maintenance work, the failure level, and the worker, which can contribute to setting the optimal standard work time.

[0043] The task time calculation device according to the first to fifth aspects can be configured using so-called hardware resources (information processing devices, computers), and can use a device having the configuration shown in Fig. 10. For example, the hardware resource 100 includes a processor 101, a memory 102, a network interface 103, and the like, which are interconnected by an internal bus 104.

[0044] 10 is not intended to limit the hardware configuration of the hardware resource 100. The hardware resource 100 may include hardware (e.g., an input / output interface) that is not shown. Furthermore, the number of units such as the processor 101 included in the device is not intended to be limited to the example shown in FIG. 10, and for example, multiple processors 101 may be included in the hardware resource 100. The processor 101 may be, for example, a central processing unit (CPU), a microprocessor unit (MPU), a graphics processing unit (GPU), or the like.

[0045] The memory 102 may be, for example, a random access memory (RAM), a read only memory (ROM), a hard disk drive (HDD), or a solid state drive (SSD).

[0046] The network interface 103 may be, for example, a LAN (Local Area Network) card, a network adapter, a network interface card, or the like.

[0047] The functions of the hardware resource 100 are realized by the processing modules described above. The processing modules are realized, for example, by the processor 101 executing a program stored in the memory 102. The programs can be updated by downloading them over a network or by using a storage medium that stores the programs. Furthermore, the processing modules may be realized by semiconductor chips. In other words, it is sufficient that the functions performed by the processing modules be realized by software being executed on some kind of hardware.

[0048] Some or all of the above aspects may be described as, but are not limited to, the following supplementary notes.

[0049] [Appendix 1] A work time calculation device comprising a work time calculation unit configured to calculate a standard work time for maintenance work by referring to a database based on device data identifying a device to be maintained, replacement part data identifying replacement parts, fault level data identifying a fault level indicating the reproducibility of the fault, and worker data identifying the worker. [Appendix 2] The database comprises: a standard work time database in which the device, the replacement part, the failure level, and a standard work time are associated with each other; a worker database in which the workers are associated with the number of times they have worked; Equipped with The operation time calculation unit extracting the standard work time corresponding to the device data, the replacement part data, and the failure level data from the standard work time database; extracting the number of work experiences corresponding to the worker data from the worker database; Calculating the standard work time based on the extracted reference work time and the number of times of work experience. It is configured as follows: 2. The operation time calculation device according to claim 1. [Appendix 3] When calculating the standard work time, the work time calculation unit: determining whether the extracted number of times of work experience is equal to or greater than a first predetermined number of times; If the number of times of work experience is equal to or greater than the first predetermined number of times, the standard work time is calculated so as to shorten the extracted reference work time; If the number of times of work experience is less than the first predetermined number of times, it is determined whether the extracted number of times of work experience is equal to or greater than a second predetermined number of times that is less than the first predetermined number of times; If the number of times of work experience is equal to or greater than the second predetermined number of times, the extracted reference work time is calculated as the standard work time, If the number of times of work experience is less than the second predetermined number of times, the standard work time is calculated so as to extend the extracted reference work time. It is configured as follows: 3. The operation time calculation device according to claim 2. [Appendix 4] the work time calculation unit is configured to, when calculating the standard work time, calculate the standard work time so as to shorten the extracted reference work time if the worker data includes qualification information held by the worker. 4. The operation time calculation device according to claim 3. [Appendix 5] a data acquisition unit that acquires the device data, the replacement part data, the failure level data, and the worker data; the operation time calculation unit is configured to calculate the standard operation time by referring to the database based on the device data, the replacement part data, the fault level data, and the worker data acquired by the data acquisition unit. 5. An operation time calculation device according to any one of appendices 1 to 4. [Appendix 6] a data output unit that outputs data related to the standard work time calculated by the work time calculation unit, 6. An operation time calculation device according to any one of appendices 1 to 5. [Appendix 7] a work experience count updating unit configured to update the work experience count of the worker in the worker database corresponding to the worker name in the work completion data by acquiring work completion data related to work completion including the worker name, 5. An operation time calculation device according to any one of Supplementary Notes 2 to 4. [Appendix 8] the work experience count updating unit is configured to request the work completion data from the worker terminal used by the corresponding worker after a predetermined time has elapsed since the standard work time was calculated. 8. The operation time calculation device according to claim 7. [Appendix 9] a work time comparison unit configured to compare the standard work time and actual work time related to the maintenance work, the database includes a work result database that associates the device, the replacement part, the failure level, the actual work time, and the worker name; The work time comparison unit acquiring work result data including the device, the replacement part, the failure level, the actual work time, and the worker name, and storing the work result data in the work result database; extracting and comparing the actual work time from the work result database corresponding to the device, the replacement part, the failure level, and the worker name from the work result database with the latest standard work time output and stored by the work time calculation unit; Calculating the percentage of the number of tasks for which the actual work time exceeded or fell short of the standard work time out of the total number of tasks for each device in a predetermined period; determining whether the calculated ratio exceeds or falls below a predetermined ratio; If the calculated ratio exceeds or falls below the predetermined ratio, output information regarding a review of the standard work time. It is configured as follows: 5. An operation time calculation device according to any one of Supplementary Notes 2 to 4. [Appendix 10] an alarm issuing unit that issues an alarm to a worker terminal used by the worker at a point in time before a predetermined time from the end of the standard work time; 10. An operation time calculation device according to any one of appendices 1 to 9. [Appendix 11] A work time calculation method including a step in which a work time calculation device refers to a database and calculates a standard work time for maintenance work based on device data that identifies a device to be maintained, replacement part data that identifies a replacement part, fault level data that identifies a fault level indicating a degree of reproducibility of the fault, and worker data that identifies the worker. [Appendix 12] A program that causes a work time calculation device to execute a process of calculating a standard work time for maintenance work by referring to a database based on device data that identifies a device to be maintained, replacement part data that identifies replacement parts, failure level data that identifies a failure level indicating the degree of reproducibility of the failure, and worker data that identifies the worker.

[0050] Note that Supplements 11 and 12 relating to the method and program can be expanded as Supplements 2 to 10.

[0051] The disclosures of the above-cited patent documents are incorporated herein by reference and may be used as the basis or part of the present invention, as necessary. Modifications and adjustments of the embodiments are possible within the scope of the entire disclosure of the present invention (including the claims and drawings), and further based on the basic technical concept thereof. Furthermore, various combinations and selections (or non-selections, as necessary) of the various disclosed elements (including each element of each claim, each element of each embodiment or embodiment, each element of each drawing, etc.) are possible within the scope of the entire disclosure of the present invention. In other words, the present invention naturally includes various modifications and alterations that would be possible by a person skilled in the art in accordance with the entire disclosure, including the claims and drawings, and the technical concept thereof. Furthermore, with regard to the numerical values ​​and numerical ranges described in this application, any intermediate values, lower values, and smaller ranges are deemed to be included, even if not explicitly stated. Furthermore, the disclosures of the above-cited documents, when used in part or in whole in combination with the disclosures herein as part of the disclosure of the present invention, in accordance with the spirit of the present invention, are also deemed to be included in (belong to) the disclosures of this application. [Explanation of symbols]

[0052] 10. Work time calculation device 11 Data Acquisition Section 12 Work time calculation section 13 Database Department 13a Standard work time database 13b Worker Database 13c Work Results Database 13d database 14 Data output section 15 Work experience count update section 16 Work time comparison section 17 Alarm transmitter 20 Worker terminal 100 Hardware Resources 101 processors 102 memory 103 Network Interface 104 Internal Bus

Claims

1. A work time calculation device comprising a work time calculation unit configured to calculate a standard work time for maintenance work by referring to a database based on device data identifying a device to be maintained, replacement part data identifying replacement parts, fault level data identifying a fault level indicating the reproducibility of the fault, and worker data identifying the worker.

2. The database comprises: a standard work time database in which the device, the replacement part, the failure level, and a standard work time are associated with each other; a worker database in which the workers are associated with the number of times they have worked; Equipped with The operation time calculation unit extracting the standard work time corresponding to the device data, the replacement part data, and the failure level data from the standard work time database; extracting the number of work experiences corresponding to the worker data from the worker database; Calculating the standard work time based on the extracted reference work time and the number of times of work experience. It is configured as follows: The operation time calculation device according to claim 1.

3. When calculating the standard work time, the work time calculation unit: determining whether the extracted number of times of work experience is equal to or greater than a first predetermined number of times; If the number of times of work experience is equal to or greater than the first predetermined number of times, the standard work time is calculated so as to shorten the extracted reference work time; If the number of times the work has been performed is less than the first predetermined number of times, it is determined whether the extracted number of times the work has been performed is equal to or greater than a second predetermined number of times that is less than the first predetermined number of times; If the number of times of work experience is equal to or greater than the second predetermined number of times, the extracted reference work time is calculated as the standard work time; If the number of times of work experience is less than the second predetermined number of times, the standard work time is calculated so as to extend the extracted reference work time. It is configured as follows: The operation time calculation device according to claim 2.

4. a data acquisition unit that acquires the device data, the replacement part data, the failure level data, and the worker data; the operation time calculation unit is configured to calculate the standard operation time by referring to the database based on the device data, the replacement part data, the fault level data, and the worker data acquired by the data acquisition unit. The operation time calculation device according to claim 1.

5. a data output unit that outputs data related to the standard work time calculated by the work time calculation unit, The operation time calculation device according to claim 1.

6. a work experience count updating unit configured to update the work experience count of the worker in the worker database corresponding to the worker name in the work completion data by acquiring work completion data related to work completion including the worker name, The operation time calculation device according to claim 2.

7. a work time comparison unit configured to compare the standard work time and actual work time related to the maintenance work, the database includes a work result database that associates the device, the replacement part, the failure level, the actual work time, and the name of the worker; The work time comparison unit acquiring work result data including the device, the replacement part, the failure level, the actual work time, and the worker name, and storing the work result data in the work result database; extracting and comparing the actual work time from the work result database corresponding to the device, the replacement part, the failure level, and the worker name from the work result database with the latest standard work time output and stored by the work time calculation unit; Calculating the percentage of the number of tasks for which the actual work time exceeded or fell short of the standard work time out of the total number of tasks for each device in a predetermined period; determining whether the calculated ratio exceeds or falls below a predetermined ratio; If the calculated ratio exceeds or falls below the predetermined ratio, output information regarding a review of the standard work time. It is configured as follows:

3. The operation time calculation device according to claim 2.

8. an alarm issuing unit that issues an alarm to a worker terminal used by the worker at a point in time before a predetermined time from the end of the standard work time; The operation time calculation device according to claim 1.

9. A work time calculation method including a step in which a work time calculation device refers to a database and calculates a standard work time for maintenance work based on device data that identifies a device to be maintained, replacement part data that identifies a replacement part, fault level data that identifies a fault level indicating a degree of reproducibility of the fault, and worker data that identifies the worker.

10. A program that causes a work time calculation device to execute a process of calculating a standard work time for maintenance work by referring to a database based on device data that identifies a device to be maintained, replacement part data that identifies replacement parts, failure level data that identifies a failure level indicating the degree of reproducibility of the failure, and worker data that identifies the worker.

Citation Information

Patent Citations

  • Work management system

    JP2002328716A

  • Skill evaluation program, skill evaluation method, and skill evaluation device

    JP2008070643A

  • Standard working time estimation device and program

    JP2015148961A

  • Operation management program, device, method, and system

    JP2018055608A

  • Work time analysis system, work time analysis program, and work time analysis method

    WO2017191743A1