Project management device, project management method, and project management program

The project management device and method enhance profit management by accurately predicting end-of-period costs and revenues using cost forecast classifications, addressing inefficiencies in existing systems.

JP7569462B2Active Publication Date: 2024-10-17OBIC CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2024008921
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-10-17
Estimated Expiration
2040-07-31

AI Technical Summary

Technical Problem

Existing project management systems fail to accurately predict the expected cost and revenue amounts at the end of the period when using the percentage-of-completion method, necessitating inefficient manual calculations and resource management.

Method used

A project management device and method that includes a control section to manage budget amounts and cost items, with features for inputting execution budgets, order information, and calculating expected costs and revenues based on cost forecast classifications, using point-in-time and elapsed cost forecasts to predict future expenditures and revenues.

Benefits of technology

Enables early-stage prediction of expected costs and revenues, improving profit management by optimizing resource allocation and reducing manual calculation efforts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007569462000001
    Figure 0007569462000001
  • Figure 0007569462000002
    Figure 0007569462000002
  • Figure 0007569462000003
    Figure 0007569462000003
Patent Text Reader

Abstract

To enable the achievement of profit improvement by predicting a term-end time cost schedule amount and a term-end time profit schedule amount at an early stage and taking a measure to management resources in the case of adopting a progressive standard.SOLUTION: According to this embodiment, a project management device includes execution budget input means for inputting execution budget information including a budget amount, a plurality of cost items, an internal budget amount of each cost item about a target project, order information input means for inputting order information including an order amount and a purchase schedule date of each cost item about the target project, and a cost schedule amount calculation part 102d for calculating a term-end time cost schedule amount of each cost item on the basis of a cost prediction classification regulated in each cost item.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a project management device, a project management method, and a project management program. [Background technology]

[0002] On March 30, 2018, the Accounting Standards Board of Japan published the New Revenue Recognition Standard, a comprehensive accounting standard for revenue recognition in Japan, which will be applied in principle from April 2021. For example, Patent Document 1 is an example of a system that complies with the New Revenue Recognition Standard. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-87031 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, Patent Document 1 does not state anything about calculating the estimated end-of-period cost amount and the estimated end-of-period revenue amount at an early stage when the progress-of-completion method is adopted.

[0005] The present invention has been made in consideration of the above problems, and has an object to provide a project management device, a project management method, and a project management program that, when a progress-of-progress method is adopted, are capable of predicting planned end-of-period costs and planned end-of-period revenues at an early stage and improving profits by taking measures with management resources. [Means for solving the problem]

[0006] In order to solve the above-mentioned problems and achieve the object, the present invention provides a project management device including a control unit, the control unit including: an execution budget input unit for inputting execution budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project; The system is characterized by comprising an order information input means for inputting order information including the order amount and planned purchase date of each cost item for the target project, and a cost forecast amount calculation means for calculating the end-of-period planned cost amount of each cost item based on the cost forecast classification defined for each cost item.

[0007] In addition, according to one aspect of the present invention, the control unit may further include a planned revenue calculation means for calculating a planned revenue amount at the end of the period of the target project in proportion to the costs based on the planned cost amount at the end of the period of each of the cost items.

[0008] According to another aspect of the present invention, the cost forecast classification of material costs and subcontract costs may use a current cost forecast, and costs may be incurred in the planned month of purchase.

[0009] According to one aspect of the present invention, regarding labor costs and expenses, past costs may be forecasted, and future costs may be calculated on a monthly basis based on the cost incurred amount at the time of each month and the working budget amount.

[0010] According to another aspect of the present invention, the project may be related to the construction industry, the IT industry, or the machinery industry.

[0011] In order to solve the above-mentioned problems and achieve the object, the present invention provides a project management method to be executed by an information processing device having a control unit, the method being executed by the control unit, The method includes an execution budget input process for inputting execution budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project, an order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project, and a planned cost amount calculation process for calculating a planned cost amount at the end of the period for each cost item based on a cost forecast classification defined for each cost item.

[0012] In addition, in order to solve the above-mentioned problems and achieve the object, the present invention is a project management program to be executed by an information processing device having a control unit and a memory unit, and is characterized in that the control unit executes an execution budget input process for inputting execution budget information for a target project, including a budget amount, a plurality of cost items, and an internal budget amount for each cost item, an order information registration process for registering order information for the target project, including an order amount and a planned purchase date for each cost item, and a planned cost amount calculation process for calculating the planned cost amount at the end of the period for each cost item based on a cost forecast classification specified for each of the cost items. Effect of the Invention

[0013] According to the present invention, when the progress of completion method is adopted, it is possible to predict the planned cost amount and the planned revenue amount at the end of the period at an early stage and improve profits by taking measures with management resources. [Brief description of the drawings]

[0014] [Figure 1] FIG. 1 is a block diagram showing an example of a configuration of a project management device according to the present embodiment. [Diagram 2] FIG. 2 is a diagram showing a flow for explaining an example of the overall processing of the project management device in this embodiment. [Diagram 3] FIG. 3 is a diagram showing cost forecast classification for each cost category. [Figure 4]FIG. 4 is a diagram showing an example of the configuration of the project cost item division master, the cost classification master, the product number master, and the project type master. [Diagram 5] FIG. 5 is a diagram showing an example of setting the project cost subject division master, the cost classification master, and the project type master. [Figure 6] FIG. 6 is a diagram showing an example of a display of the working budget registration screen. [Figure 7] FIG. 7 is a diagram showing an example of the structure of contract information. [Figure 8] FIG. 8 is a diagram illustrating an example of a configuration of the execution information. [Figure 9] FIG. 9 is a diagram showing a display example of the order registration screen. [Figure 10] FIG. 10 is a diagram showing an example of the configuration of order information. [Figure 11] FIG. 11 is a diagram showing a display example of the landing prediction input screen. [Figure 12] FIG. 12 is a diagram showing an example of the configuration of the landing prediction registration information. [Figure 13] FIG. 13 is a diagram for explaining a method for calculating a monthly estimated cost amount based on a cost forecast classification. [Figure 14] FIG. 14 is a diagram for explaining a method of calculating a projected revenue amount based on the cost-proportional method. [Figure 15] FIG. 15 is a diagram showing an example of output of income and expenditure forecast data. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail with reference to the drawings. However, the present invention is not limited to the embodiment.

[0016] [1. Overview] On March 30, 2018, the Accounting Standards Board of Japan published new revenue recognition standards, comprehensive accounting standards for revenue recognition in Japan, which will come into effect in April 2021.

[0017] In industries such as construction, IT, and machinery, the new revenue recognition standards will, in principle, change the calculation method from the completed contract method to the percentage of completion method.

[0018] Specifically, "if the criteria are met that result in control of a good or service being transferred to a customer over time, revenue is recognized over time as the performance obligation to transfer the good or service to the customer is satisfied (quoted from Accounting Standard, paragraphs 38 and 41-45; Implementation Guidance, paragraphs 9-13 and 15-22)."

[0019] In the past, the completed construction method was often used, and sales could be forecasted by tallying up data from on-site to see whether work was complete at the end of the period. However, going forward, the percentage of completion method will be adopted as the rule, and this means that a huge amount of work will be required to calculate the estimated cost and estimated revenue at the end of each period for each construction period, calling for measures to improve work efficiency.

[0020] In this embodiment, when predicting the end-of-period profit under the percentage of completion method, a profit forecast is calculated from the construction period of each project and the characteristics of each cost classification.

[0021] The purpose of this embodiment is to predict the estimated end-of-period costs and estimated end-of-period revenues early when the progress-by-completion method is adopted, and to improve profits by taking measures with management resources.

[0022] In this embodiment, the calculation method is classified according to the characteristics of the cost classification, and the end-of-term cost estimate is calculated. For example, in the case of facility construction, the cost of materials such as large equipment accounts for a large proportion of the cost, so it is necessary to calculate accurate information on material costs based on delivery date information.

[0023] Specifically, in this embodiment, when planning the execution budget, costs are classified into external expenditure costs (point-in-time cost forecasts) such as material costs and subcontract costs, whose occurrence time can be predicted, and costs (expected cost forecasts) such as labor costs and expenses that accumulate over time, and future costs are calculated based on the construction period according to their characteristics. Subcontract costs may be classified as costs that accumulate over time depending on the progress of work, such as performance appraisal, so they can be set for each cost category.

[0024] [2. Configuration] An example of the configuration of a project management apparatus 100 according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing an example of the configuration of the project management apparatus 100.

[0025] The project management device 100 is a commercially available desktop personal computer. Note that the project management device 100 is not limited to a stationary information processing device such as a desktop personal computer, and may be a portable information processing device such as a commercially available notebook personal computer, a PDA (Personal Digital Assistant), a smartphone, or a tablet personal computer.

[0026] The project management device 100 includes a control unit 102, a communication interface unit 104, a storage unit 106, and an input / output interface unit 108. The units included in the project management device 100 are connected to each other so as to be able to communicate with each other via any communication path.

[0027] The communication interface unit 104 communicatively connects the project management apparatus 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via the communication line. Here, the network 300 has a function of connecting the project management apparatus 100 and the server 200 to each other so that they can communicate with each other, and is, for example, the Internet or a LAN (Local Area Network).

[0028] An input device 112 and an output device 114 are connected to the input / output interface unit 108. The output device 114 may be a monitor (including a touch panel), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that cooperates with a mouse to realize a pointing device function. In the following, the output device 114 may be referred to as the monitor 114 or the printer 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112. Moreover, "output" refers to outputting by the output device 114, and includes, for example, display output to the monitor 114, print output by the printer 114, and transmission of data to the outside.

[0029] The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs for cooperating with an OS (Operating System) to give instructions to a CPU (Central Processing Unit) to perform various processes. For example, memory devices such as RAM (Random Access Memory) and ROM (Read Only Memory), fixed disk devices such as hard disks, flexible disks, and optical disks can be used as the storage unit 106. The storage unit 106 also includes a project cost subject classification master 106a, a cost classification master 106b, a product number master 106c, a project type master 106d, and a data file 106e. FIG. 4 is a diagram showing configuration examples of the project cost subject classification master 106a, the cost classification master 106b, the product number master 106c, and the project type master 106d. FIG. 5 is a diagram showing setting examples of the project cost subject classification master 106a, the cost classification master 106b, and the project type master 106d.

[0030] The project cost item classification master 106a is a master that classifies the cost classifications into smaller categories. As shown in Fig. 4, the project cost item classification master 106a can be configured with tables for registering data on the project cost item classification, project cost item classification name, cost classification code, and cost classification name in association with each other. As shown in Fig. 5, the cost item classifications are, for example, main material costs, auxiliary material costs, wages and salaries, miscellaneous wages, and subcontract costs. The cost forecast classification of the cost classification master 106b is specified based on the cost classification code of the project cost item classification master 106a.

[0031] The cost category master 106b is a master that specifies the cost forecast category of cost elements (e.g., materials, outsourcing, labor, and expenses). The cost category master 106b can be configured with tables and the like for registering data on the cost category code, cost category name, cost category type, and cost forecast category in association with each other, as shown in Fig. 4. The cost categories are, for example, material costs, outsourcing costs, labor costs, expenses, and machine costs, as shown in Fig. 5.

[0032] The product number master 106c can be configured with a table for registering data such as product number code, product number name, project type code, and project cost item classification in association with each other. A specified product number is linked to a project cost item classification and a project type.

[0033] The project type master 106d is a master that sets the type of cost, such as budget type and execution budget. The project type master 106d can be configured with a table or the like for registering data on project type codes and project type names in association with each other, as shown in Fig. 4. Project types, as shown in Fig. 5, are, for example, paving work, general building construction, electrical work, piping work, paving work, etc.

[0034] The data file 106e is a table for storing various data such as contract information, working budget information, order information, and arrival forecast registration information.

[0035] Contract information consists of a project order header and project order details (see Figure 7). The project order header may include the project number, order number, customer code, invoice net sales amount, invoice sales consumption tax amount, invoice cost amount, and invoice gross profit amount. The project order details may include the order number, order line number, product code, product name, credit account category, consumption tax rate category, order quantity, unit sales price, unit sales price, net sales amount, sales consumption tax amount, unit cost price, cost amount, and gross profit amount.

[0036] The execution budget information consists of a project budget header and project budget details (see Figure 8). The project budget header may include the project number, order number, order line number, number of budget changes, accounting year and month, registration date, project budget unit category, and voucher budget amount. The project budget details may include the project number, order number, order line number, project budget line number, number of budget changes, project type code, and project budget amount.

[0037] The order information consists of a project order header and project order details (see Figure 10). The project order header may include the order number, order date, accounting year and month, supplier, invoice purchase amount, project number, order number, and order line number. The project order details may include the order number, order line number, part number code, part number name, order quantity, order price, order amount, and scheduled purchase date.

[0038] The estimated final cost registration information consists of a project estimated cost header and project estimated cost details (see Figure 12). The project estimated cost header may include the accounting year and month, project number, order number, order line number, and contract amount. The project estimated cost details may include the accounting year and month, project number, order number, order line number, project planned cost line number, project type code, project cost item category, budget amount, incurred cost amount, cost incurred this month amount, future planned cost amount, final estimated cost amount (cumulative incurred costs + future estimated costs), and budget-to-actual variance amount.

[0039] The control unit 102 is a CPU or the like that performs overall control of the project management apparatus 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, required data, and the like, and executes various information processing based on these stored programs. In terms of function, the control unit 102 includes a master maintenance unit 102a, an execution budget registration unit 102b, an order registration unit 102c, a planned cost amount calculation unit 102d, a planned revenue amount calculation unit 102e, a screen display control unit 102f, and a monthly estimated landing amount registration unit 102g.

[0040] The master maintenance section 102a is for editing, such as adding, deleting, and changing data in the project cost item classification master 106a, the cost classification master 106b, the product number master 106c, and the project type master 106d, in response to, for example, an operator's operation on a master maintenance screen (not shown) displayed on the monitor 114.

[0041] The execution budget registration unit 102b inputs execution budget information including the budget amount, multiple cost items, and the internal budget amount of each cost item for the target project in response to, for example, an operator's operation on the execution budget registration screen (see FIG. 6) displayed on the monitor 114, and registers it in the data file 106e. The execution budget registration unit 102b also inputs contract information for the target project and registers it in the data file 106e. The project may be related to the construction industry, the IT industry, or the machinery industry.

[0042] The order registration unit 102c, for example, in response to an operator's operation on the order registration screen (see Figure 9) displayed on the monitor 114, inputs order information for the target project, including the order amount and planned purchase date for each cost item, and registers it in the data file 106e.

[0043] The monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to, for example, an operator's operation on the estimated landing amount registration screen (see Figure 11) displayed on the monitor 114, and registers it in the data file 106e.

[0044] The estimated cost calculation unit 102d calculates the estimated cost amount at the end of the term for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use the current cost forecast, and the cost may be generated in the planned purchase month. For labor costs and expenses, the historical cost may be forecast, and the future cost amount may be calculated by dividing it by the monthly cost amount and the actual budget amount.

[0045] The estimated revenue calculation unit 102e calculates the estimated revenue at the end of the target project in proportion to the cost based on the estimated cost at the end of the target project for each cost item. The estimated revenue calculation unit 102e may also output income and expenditure forecast data for the target project based on the estimated cost at the end of the target project and the estimated revenue at the end of the target project calculated for each cost item (see FIG. 15).

[0046] The screen display control unit 102f controls the display and input of various screens (for example, a master maintenance screen, an execution budget registration screen, an order registration screen, a forecast arrival registration screen, etc.) displayed on the monitor 114.

[0047] [3. Specific Examples] A specific example of the processing of project management apparatus 100 in this embodiment will be described with reference to Figures 2 to 15. First, an overview of the overall processing of project management apparatus 100 in this embodiment will be described with reference to Figure 2. Figure 2 is a diagram showing a flow for explaining an example of the overall processing of project management apparatus 100 in this embodiment.

[0048] 2, the master maintenance unit 102a executes a master setting process (step S1). Specifically, in the master setting process, the master maintenance unit 102a sets data for the project cost item division master 106a, the cost classification master 106b, the product number master 106c, and the project type master 106d in response to, for example, an operator's operation on a master maintenance screen (not shown) displayed on the monitor 114.

[0049] The execution budget registration unit 102b executes the execution budget registration process (step S2). Specifically, in the execution budget registration process, the execution budget registration unit 102b inputs execution budget information including the budget amount, multiple cost items, and the internal budget amount of each cost item for the target project in response to, for example, an operator's operation on the execution budget registration screen (see FIG. 6) displayed on the monitor 114, and registers it in the data file 106e.

[0050] The order registration unit 102c executes the order registration process (step S3). Specifically, in the order registration process, the order registration unit 102c inputs order information including the order amount and the planned purchase date of each cost item for the target project in response to, for example, an operator's operation on the order registration screen (see FIG. 9) displayed on the monitor 114, and registers the information in the data file 106e.

[0051] The monthly estimated landing amount registration unit 102g executes the monthly estimated landing amount registration process (step S4). Specifically, in the monthly estimated landing amount registration process, the monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to the operation of the operator on the estimated landing amount registration screen (see FIG. 11) displayed on the monitor 114, for example, and registers it in the data file 106e.

[0052] The estimated cost calculation unit 102d and the estimated revenue calculation unit 102e execute end-of-term forecast processing (step S5). Specifically, in the end-of-term forecast processing, the estimated cost calculation unit 102d calculates the estimated end-of-term cost amount for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use a current cost forecast, and costs may be incurred in the planned month of purchase. In addition, for labor costs and expenses, the historical cost forecast may be used, and future costs may be calculated on a monthly basis based on the cost amount incurred at the monthly point in time and the working budget amount.

[0053] In the end-of-term forecast process, the estimated revenue calculation unit 102e calculates the estimated end-of-term revenue for the target project in proportion to the cost based on the estimated end-of-term cost. In the end-of-term forecast process, the estimated revenue calculation unit 102e may output income and expenditure forecast data for the target project based on the calculated estimated end-of-term cost amount and estimated end-of-term revenue amount for each cost item (see FIG. 15).

[0054] Next, a specific example of the processing of the project management device 100 in this embodiment will be described with reference to FIGS.

[0055] (S1: Master setting process) The master setting process will be described in detail with reference to Fig. 3 to Fig. 5. Fig. 3 is a diagram showing cost forecast classification for each cost classification. Fig. 4 is a diagram showing configuration examples of the project cost subject classification master 106a, the cost classification master 106b, the product number master 106c, and the project type master 106d. Fig. 5 is a diagram showing setting examples of the project cost subject classification master 106a, the cost classification master 106b, and the project type master 106d.

[0056] The master maintenance unit 102a sets data in the project cost item classification master 106a, the cost classification master 106b, the product number master 106c, and the project type master 106d, for example, in response to an operator's operation on a master maintenance screen (not shown) displayed on the monitor 114.

[0057] As shown in Figure 3, the cost forecast classification for "material costs" is "current cost forecast," the cost forecast classification for "subcontract costs" is "current cost forecast," the cost forecast classification for "labor costs" is "past cost forecast," and the cost forecast classification for "expenses" is "past cost forecast." For items with current cost forecasts such as material costs and subcontract costs, it is determined whether costs have been incurred at the end of the period based on the delivery date information for order registration.

[0058] In the example of the project cost item category master 106a shown in FIG. 4, the PJ cost item category is "G10", the PJ cost item category name is "major material cost", the cost classification code is "1000", and the cost classification name is "material cost".

[0059] In the example of the cost category master 106b shown in FIG. 4, the cost category code is "1000", the cost category name is "material cost", the cost category type is "direct cost (material)", and the cost forecast category is "current cost forecast".

[0060] In the example of item number master 106c shown in FIG. 4, the item number code is "C001001," the item name is "painting-materials," the project type code is "A01," the project type code is "02," and the project cost item category is "G10."

[0061] In the example of the project type master 106d shown in FIG. 4, the project type code is "A01" and the project type name is "foundation work".

[0062] (S2: Execution budget registration process) The working budget registration process will be described in detail with reference to Fig. 6 to Fig. 8. Fig. 6 is a diagram showing an example of a display of an working budget registration screen. Fig. 7 is a diagram showing an example of the structure of contract information. Fig. 8 is a diagram showing an example of the structure of execution information. The following description will be given on the assumption that contract information has been registered in advance in data file 106e.

[0063] The working budget registration unit 102b inputs working budget information for the target project in response to, for example, an operator's operation on an working budget registration screen displayed on the monitor 114, and registers it in the data file 106e.

[0064] On the execution budget registration screen shown in Fig. 6, the project type, project cost item, etc. are specified. The budget registration screen shown in Fig. 6 has a header area that displays the contract amount, project number, accounting year and month, order number, number of budget changes, and registration date, and a details area that displays items such as the budget (project type, type name, budget amount, project cost item, detailed budget amount).

[0065] When a project number is entered in the header area, the contract amount, project number, accounting year and month, order number, etc. are read from the contract information using the project number as a key and displayed. When budget items (project type, type name, budget amount, project cost item, detailed budget amount, etc.) are entered in the details area and a register button (not shown) is pressed, the budget execution information according to the entered contents is registered in the data file 106e.

[0066] In the example shown in Figure 6, the project number is "PJ0001", the contract amount is "15,000,000", the fiscal year is "2020 / 11", the order number is "JY0001-01", and the registration date is "2020 / 11". As for the budget, the budget amount for project "02: Complete Construction" is "5,000,000", and the budget amount for "A01: Electrical Work" is "6,000,000", totaling "11,000,000". The budget breakdown is as follows: for project type "02: Complete Construction", the main material cost is "3,000,000", and the outsourcing cost is "2,000,000". For project type "A1: Electrical Work", the main material cost is "2,000,000", the outsourcing cost is "1,000,000", and the labor cost is "3,000,000".

[0067] (S2: Order registration process) The order registration process will be described in detail with reference to Fig. 9 and Fig. 10. Fig. 9 is a diagram showing a display example of an order registration screen. Fig. 10 is a diagram showing a configuration example of order information.

[0068] The order registration unit 102c inputs order information for the target project in response to, for example, an operator's operation on an order registration screen displayed on the monitor 114, and registers the information in the data file 106e.

[0069] On the order registration screen, a product number is specified when registering an order. The example of the order registration screen shown in Fig. 10 has a header area that displays the order number, project number, order date, order number, supplier, accounting year and month, registration date, etc., and a details area for inputting budget details (product number, product number name, order amount, planned purchase date, cost classification), and by pressing a registration button (not shown), the order information according to the input contents is registered in the data file 106e.

[0070] In the example shown in Figure 9, the header area contains the purchase order number "HA0010," project number "PJ0001," order date "2020 / 12 / 10," order number "JY0001-01," supplier "Chiba Engineering," accounting year and month "2020 / 11," and registration date "2020 / 11."

[0071] The details area has the following: line 1: product number "C001001", product number name "Electrical work materials", order amount "2,000,000", planned purchase date "2020 / 12 / 31", cost classification "Materials cost". line 2: product number "C001002", product number name "Electrical work outsourced", order amount "1,000,000", planned purchase date "2020 / 12 / 20", cost classification "Outsourcing cost".

[0072] (S4: Monthly estimated landing amount registration process) The monthly estimated cost of arrival registration process will be described in detail with reference to Fig. 11 and Fig. 12. Fig. 11 is a diagram showing a display example of an estimated cost of arrival registration screen. Fig. 12 is a diagram showing a configuration example of estimated cost of arrival registration information. In the estimated cost of arrival registration, the final estimated cost of the construction work is registered.

[0073] The monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to, for example, an operator's operation on the estimated landing amount registration screen (see Figure 11) displayed on the monitor 114, and registers it in the data file 106e.

[0074] On the estimated final cost registration screen shown in Fig. 11, costs expected to occur in the future are registered for each project type and project cost item. The estimated final cost registration screen shown in Fig. 11 has a header area in which the project number, accounting year and month, and order number are displayed, and a details area for inputting construction information (project type, project cost item, budget amount, ordered cost, accumulated cost to be incurred, future expected cost, and final estimated final cost). By pressing a register button (not shown), estimated final cost registration information according to the input contents is registered in the data file 106e.

[0075] The final estimated cost is calculated by adding the accumulated incurred cost and the future estimated cost. This is the denominator when calculating the progress rate of a construction progress-based project.

[0076] In the example of the estimated cost input screen shown in Figure 11, the header area displays the project number "PJ0001", the accounting year and month "2020 / 12", and the order number "JY0001". In the details area, the first line of the construction information displays the project type "Construction as a whole", the project cost item "Major material cost", the budget amount "3,000,000", the ordered cost "1,000,000", the accumulated cost incurred "0", the future estimated cost "1,500,000", and the final estimated cost "1,500,000".

[0077] (S4: End-of-period arrival forecast processing) The end-of-term arrival forecast process will be described in detail with reference to Figs. 13 to 15. Fig. 13 is a diagram for explaining a method for calculating a monthly estimated cost amount based on a cost forecast classification. Fig. 14 is a diagram for explaining a method for calculating an estimated revenue amount based on the cost proportion method. Fig. 15 is a diagram showing an example of output of income and expenditure forecast data.

[0078] The estimated cost calculation unit 102d calculates the estimated cost amount at the end of the period for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use the current cost forecast, and the cost may be incurred in the planned month of purchase. For labor costs and expenses, the historical cost may be forecast, and the future cost amount may be calculated by dividing it by the monthly cost amount and the working budget amount.

[0079] The estimated revenue calculation unit 102e also calculates the estimated end-of-term revenue of the target project in proportion to the cost based on the contract amount, the accumulated incurred costs, and the estimated cost amount. The estimated revenue calculation unit 102e outputs the construction income and expenditure data (see FIG. 15) based on the calculated estimated end-of-term cost amount and estimated end-of-term revenue amount.

[0080] In FIG. 13, (1) a planned cost amount is calculated for each month based on a cost forecast classification (current cost forecast or historical cost forecast) corresponding to the cost classification type registered in the cost classification master 106b.

[0081] (a) For material costs and subcontract costs, current cost estimates are used. In the case of point-in-time cost forecasting, costs are incurred in the planned purchase month. For order information, the delivery month is the subject of cost calculation, and the cost amount for future planned order amounts is the amount incurred in the final month of the construction period. Planned order amount = (cumulative incurred costs + future expected costs) - amount already ordered.

[0082] (b) For labor costs and expenses, use the estimated historical cost (outsourcing costs subject to piecework appraisal). In the case of a past cost forecast, the future cost to be incurred is calculated on a monthly basis based on the cost to be incurred at the monthly point in time and the actual budget amount.

[0083] Figure 13 shows an example of the remaining amount divided by month when the construction period is 10 months, the labor cost budget is 3 million, 3 months have passed, and the cost incurred is 900,000. 3 million - 900,000 is expected to incur 2.1 million in the future, with 300,000 to be incurred per month for the remaining 7 months. The cost amount at the end of the period, 2021 / 3, will be 1.8 million.

[0084] In the example shown in Figure 13, the costs incurred for "2020 / 10", "2020 / 11", and "2020 / 12" are "300,000" each, totaling "900,000". The labor cost budget is "3 million" - the incurred costs are "900,000", and the future costs are expected to be "2.1 million", with 300,000 to be incurred per month for the remaining 7 months. The costs incurred for "2021 / 1", "2021 / 2", "2020 / 12", and "2020 / 12" are each set at "300,000".

[0085] In Figure 14, revenue is forecasted, and the sales progress rate is calculated for each construction project based on the cost ratio, and the estimated sales amount is calculated. The calculation items for the cost ratio method are the contract amount, the accumulated amount incurred, and the estimated cost amount.

[0086] An example of calculating the sales amount for each construction project (when the contract amount is 5 million yen) is shown below. As of December, the sales amount for March 2021 is predicted. Sales amount = contract amount x (cumulative amount incurred / estimated cost amount).

[0087] In the example shown in FIG. 14, for the year / month "2020 / 10", the sales amount is "500,000", the sales progress rate is "10%," the accumulated amount incurred is "300,000", and the planned cost amount is "3 million", for the year / month "2020 / 11", the sales amount is "1 million", the sales progress rate is "20%," the accumulated amount incurred is "600,000", and the planned cost amount is "3 million", for the year / month "2020 / 12", the sales amount is "1.5 million", the sales progress rate is "30%," the accumulated amount incurred is "900,000", and the planned cost amount is "3 million". As of December, the sales amounts "2 million", "2.5 million", and "3 million" are calculated based on the progress rates of the year / month "2021 / 1", "2021 / 2", and "2021 / 3" as "40%, "50%, and 60%".

[0088] Figure 15 shows an example of income / expense forecast data output. In this example, for the accounting year and month "December 2020", output year and month "2020 / 12~2021 / 03", project "PJ0001", project name "Facility Construction Complete", contract number "JYU0001", and contract amount "15,00,000", data on the (planned) sales amount, sales progress rate, cumulative incurred costs, and final estimated cost for the current accounting year and month and future months "2021 / 1", "2021 / 2", and "2021 / 3" is displayed. The (planned) sales amount is "3,125,000" for the current accounting year and month, "6,000,000" for 2021 / 1, "7,625,000" for 2021 / 2, and "8,000,000" for 2021 / 3.

[0089] By drilling down, data on accumulated incurred costs for each cost category by project type is displayed. By drilling down further, data on voucher type, voucher number, incurred amount, and planned purchase month is displayed. In this way, outputting the planned order amount for each project type can encourage planning of the planned cost month for each cost category.

[0090] In the example of the project type "Electrical work", for the cost classification "Major material costs", the amount incurred is "2,000,000", the planned purchase month is "2021 / 1", and the cumulative cost incurred amount is "0" for the current accounting month, "2,000,000" for 2021 / 1, "2,000,000" for 2021 / 2, and "2,000,000" for 2021 / 3, with costs incurred in the planned purchase month of "2021 / 1" (in the case of the example in Figure 9, costs are incurred in the planned purchase month based on the current cost forecast).

[0091] In addition, for the cost classification "subcontract expenses", the amount incurred is "1,000,000", the planned purchase month is "2020 / 12", and the cumulative cost incurred amount is "1,000,000" for the current accounting month, "1,000,000" for 2021 / 1, "1,000,000" for 2021 / 2, and "1,000,000" for 2021 / 3, meaning that costs were incurred in the planned purchase month of "2020 / 12" (in the case of the example in Figure 9, purchases were completed in December).

[0092] In addition, for the cost classification "labor costs," the accumulated costs incurred are "900,000" for the current accounting year and month, "1,200,000" for January 2021, "1,500,000" for February 2021, and "1,800,000" for March 2021 (divided into monthly increments of 300,000 based on the estimated past costs).

[0093] As described above, according to this embodiment, the system includes an execution budget registration unit 102b for inputting execution budget information including the budget amount, multiple cost items, and internal budget amount of each cost item for the target project, an order registration unit 102c for inputting order information including the order amount and planned purchase date of each cost item for the target project, and a planned cost calculation unit 102d for calculating the planned cost amount at the end of the term for each cost item based on the cost forecast classification specified for each cost item.The system also includes a planned revenue calculation unit 102e for calculating the planned revenue amount at the end of the term for the target project in proportion to the cost based on the planned cost amount at the end of the term for each cost item.

[0094] As a result, when the percentage of completion method is adopted, it becomes possible to predict the estimated cost amount and estimated revenue amount at the end of the period at an early stage and improve profits by taking measures for management resources.

[0095] [4. Other embodiments] The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.

[0096] For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using known methods.

[0097] In addition, the processing procedures, control procedures, specific names, information including parameters such as registered data and search conditions for each process, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.

[0098] Furthermore, with regard to the project management apparatus 100, each of the components shown in the figures is merely a functional concept, and does not necessarily have to be physically configured as shown in the figures.

[0099] For example, the processing functions of the project management device 100, particularly the processing functions performed by the control unit 102, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded on a non-transient computer-readable recording medium including programmed instructions for causing the information processing device to execute the processes described in this embodiment, and is mechanically read by the project management device 100 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive). This computer program is executed by being loaded into a RAM, and cooperates with the CPU to form the control unit.

[0100] In addition, this computer program may be stored in an application program server connected to the project management apparatus 100 via any network, and it is also possible to download all or part of it as necessary.

[0101] In addition, the program for executing the process described in this embodiment may be stored in a non-transient computer-readable recording medium, or may be configured as a program product. Here, the "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.

[0102] Moreover, a "program" is a data processing method written in any language or description method, and may be in any form, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a configuration that is distributed as a plurality of modules or libraries, and a program that achieves its function by cooperating with a separate program, such as an OS. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in this embodiment, as well as the installation procedure after reading, may use well-known configurations and procedures.

[0103] The various databases etc. stored in the memory unit 106 are storage means such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files etc. used for various processes and providing websites.

[0104] The project management device 100 may be configured as an information processing device such as a known personal computer or a workstation, or may be configured as the information processing device to which any peripheral device is connected. The project management device 100 may be realized by installing software (including programs, data, etc.) that causes the device to realize the processes described in this embodiment.

[0105] Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the drawings, and all or part of them can be functionally or physically distributed and integrated in any unit according to various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively. [Explanation of symbols]

[0106] 100 Project Management Equipment 102 Control section 102a Master Maintenance Department 102b Working Budget Registration Department 102c Order Registration Department 102d Cost Estimate Calculation Department 102e Revenue Calculation Section 102f Screen display control unit 102g Monthly Landing Estimate Registration Section 104 Communication interface section 106 Storage section 106a Project Cost Item Classification Master 106b Cost classification master 106c Part Number Master 106d Project type master 106e Data File 108 Input / Output Interface Section 112 Input Devices 114 Output Device 200 Servers 300 Network

Claims

1. A project management device including a control unit, The control unit is an actual budget input means for inputting actual budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project; An order information input means for inputting order information including an order amount and a planned purchase date for each cost item for a target project; a cost forecast amount calculation means for calculating a final end cost forecast amount of each cost item based on a cost forecast classification defined for each cost item; Equipped with (1) when the cost forecast classification specified is a historical cost forecast, the device calculates the estimated cost at the end of the period by adding the amount calculated by dividing the future cost amount by the execution budget amount by the cumulative cost amount as of the current fiscal year and month, for the number of months from after the current fiscal year and month to the end of the period, in order to calculate the estimated cost amount at the end of the period; and (2) when the cost forecast classification specified is a current cost forecast, the device calculates the estimated cost amount at the end of the period by adding the amount of cost incurred from after the current fiscal year and month to the cumulative cost amount up to the current fiscal year and month, including the planned purchase month.

2. The control unit further includes an acquisition means for acquiring a cost classification from a cost item master based on a cost item included in the execution budget information, and acquiring a cost forecast classification from a cost classification master based on the acquired cost classification, The cost forecast classification defined is acquired by the acquisition means; 2. The project management device according to claim 1, wherein:

3. A project management method for causing an information processing device having a control unit to execute the project management method, Executed by the control unit, an actual budget input process for inputting actual budget information including a budget amount, a number of cost items, and an internal budget amount for each cost item for a target project; An order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project; a cost forecast amount calculation step of calculating a cost forecast amount at the end of a period for each cost item based on a cost forecast classification specified for each cost item; Including, A project management method characterized in that (1) when the specified cost forecast classification is a historical cost forecast, the planned cost at the end of the period is calculated by adding the amount calculated by dividing the future costs to the actual budget amount by the number of months from after the current fiscal year to the end of the period to the accumulated costs incurred up to the current fiscal year, and (2) when the specified cost forecast classification is a point-in-time cost forecast, the planned cost at the end of the period is calculated by adding the amount incurred from after the current fiscal year to the end of the period, including the planned purchase month, to the accumulated costs incurred up to the current fiscal year.

4. A project management program for execution by an information processing device having a control unit and a storage unit, In the control unit, an actual budget input process for inputting actual budget information including a budget amount, a number of cost items, and an internal budget amount for each cost item for a target project; An order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project; a cost forecast amount calculation step of calculating a cost forecast amount at the end of a period for each cost item based on a cost forecast classification specified for each cost item; This is a program for executing A project management program characterized in that (1) when the specified cost forecast classification is a historical cost forecast, the program adds the amount calculated by dividing future costs by the execution budget amount by the number of months from after the current fiscal year to the end of the fiscal year to calculate the planned cost amount at the end of the fiscal year, in order to the accumulated cost amount as of the current fiscal year and month, for the number of months from after the current fiscal year and month to the end of the fiscal year, in order to calculate the planned cost amount at the end of the fiscal year, and (2) when the specified cost forecast classification is a current cost forecast, the program adds the amount of costs incurred from after the current fiscal year and month to the end of the fiscal year, including the planned purchase month, in order to calculate the planned cost amount at the end of the fiscal year.

Citation Information

Patent Citations

  • Cost management system

    JP2003296557A

  • Construction cost management processing program

    JP2004303039A

  • Progress rate calculating apparatus, progress rate calculating method, and progress rate calculating program

    JP2020087031A