A miniaturized hydroelectric power generation system using pipes and turbines within buildings addresses the resource and location constraints of traditional hydroelectric power, enabling efficient electricity generation and water reuse.

JP7576865B2Active Publication Date: 2024-11-01原 ミッシェル
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
JP2023046296
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-03-23
Publication Date
2024-11-01
Estimated Expiration
2042-07-26

AI Technical Summary

Technical Problem

Hydroelectric power generation requires abundant water resources and large-scale storage, limiting its installation to locations away from urban and industrial areas.

Method used

A miniaturized hydroelectric power generation system utilizing a series of pipes and turbines, including Francis and Pelton turbines, installed within buildings to harness falling water energy, with a chamber creating a vacuum region for efficient water supply and reuse.

Benefits of technology

Enables hydroelectric power generation in urban and industrial areas by efficiently converting falling water energy into electricity, with improved power generation efficiency and water reuse, despite limited resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007576865000001
    Figure 0007576865000001
  • Figure 0007576865000002
    Figure 0007576865000002
Patent Text Reader

Abstract

To provide a hydroelectric system which achieves downsizing to enable installation at an urban area or an industrial district.SOLUTION: A hydroelectric system includes: a first pipe including a first water supply port, and a first drain outlet positioned at a height lower than the first water supply port; a first Francis turbine which generates electric power with water discharged from the first drain outlet; a second pipe including a second water supply port to which water discharged from the first Francis turbine is supplied, and a second drain outlet positioned at a height lower than the second water supply port, the second pipe having a pipe diameter larger than that of the first pipe; and a Pelton turbine which generates electric power with water discharged from the second drain outlet.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a hydroelectric power generation system. [Background technology]

[0002] One of the power generation methods that utilize natural energy is hydroelectric power generation (for example, Patent Document 1). Hydroelectric power generation is a power generation method that converts the potential energy of water into electrical energy, and pumped-storage power generation, in which water for generating electricity is pumped up to a high altitude, is one type of hydroelectric power generation. Electrical energy obtained from hydroelectric power generation has attracted attention as a renewable energy that emits almost no carbon dioxide. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2004-251259 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, hydroelectric power plants require abundant water resources, so they must be installed in locations geographically far from urban areas and industrial areas that require a lot of electricity, and installation locations are limited to mountainous areas with abundant water resources. Moreover, hydroelectric power plants are large-scale because they need to store the large amount of water required to generate electricity.

[0005] The present invention has been made in consideration of the above-mentioned current situation, and has an object to provide a compact hydroelectric power generation system that can be installed in urban areas and industrial zones. [Means for solving the problem]

[0006] The present application includes a number of means for solving at least part of the above problems, examples of which are as follows.

[0007] In order to solve the above problems, a hydroelectric power generation system according to one embodiment of the present invention includes a first pipe having a first water inlet and a first drain outlet at a height lower than the first water inlet, a first Francis turbine that generates power using water discharged from the first drain outlet, a second pipe having a second water inlet to which the water discharged from the first Francis turbine is supplied and a second drain outlet at a height lower than the second water inlet and having a larger pipe diameter than the first pipe, and a Pelton turbine that generates power using water discharged from the second drain outlet.

[0008] The Pelton turbine may further include a plurality of branch pipes that branch the water discharged from the second drain outlet, and the Pelton turbine may include a plurality of coaxial impellers that receive the water discharged from each of the plurality of branch pipes.

[0009] Each of the plurality of branch pipes may have a smaller pipe diameter than that before branching.

[0010] The system may further include a pool for storing water discharged from the Pelton turbine, a chamber connected to the first water inlet and located higher than the first water inlet, a pumping pipe connecting the pool and the chamber, and a pump for pumping water from the pool to the chamber via the pumping pipe.

[0011] The interior of the chamber may consist of water and a vacuum region extending above the water.

[0012] The first water supply port is located below sea level, and seawater can be supplied as the water from the first water supply port.

[0013] The Pelton turbine further includes a second Francis turbine that generates power using the water discharged from the second drain outlet, a third water inlet to which the water discharged from the second Francis turbine is supplied, and a third drain outlet at a height lower than the third water inlet and having a larger pipe diameter than the second piping, and the Pelton turbine is capable of generating power using the water discharged from the third drain outlet.

[0014] The chamber may be installed on a first floor, the first Francis turbine may be installed on a second floor below the first floor, and the first piping may extend from the first floor to the second floor. Effect of the Invention

[0015] According to the present invention, it is possible to provide a compact hydroelectric power generation system that can be installed in urban areas or industrial zones. [Brief description of the drawings]

[0016] [Figure 1] FIG. 1 is a configuration diagram of a hydroelectric power generation system according to this embodiment. [Diagram 2] FIG. 2 is a configuration diagram of a hydroelectric power generation system according to a modified example. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0017] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In all drawings for describing an embodiment, the same components are generally given the same reference numerals, and repeated description thereof will be omitted. In the following embodiments, the components (including element steps, etc.) are not necessarily essential, unless otherwise specified or considered to be obviously essential in principle. In addition, when "consisting of A," "consisting of A," "having A," or "including A" is used, it is understood that other elements are not excluded, except when it is specifically specified that only the element is included. Similarly, in the following embodiments, when referring to the shape, positional relationship, etc. of components, etc., it is understood that the shape, positional relationship, etc. of components, etc. are included, except when it is specifically specified or considered to be obviously not essential in principle.

[0018] 1 is a configuration diagram of a hydroelectric power generation system according to this embodiment. The hydroelectric power generation system 1 is a power generation system constructed in, for example, a building 30 in an urban area. The building 30 is, for example, a building having floors 20-23.

[0019] As an example, the hydroelectric power generation system 1 includes a chamber 2, pipes 3 to 7, a pumping pipe 8, and a pool 15.

[0020] Chamber 2 is a tank for storing water W for power generation, and is installed on the top floor 20. In this example, the height of chamber 2 is set sufficiently high so that the water pressure of water W on floor 20 is greater than atmospheric pressure. As a result, a vacuum region V spreads above water W inside chamber 2.

[0021] The piping 3 extends substantially vertically downward from the floor 20 to the floor 21 below, and includes a water supply port 3a and a drain port 3b at a lower height. The chamber 2 is located higher than the water supply port 3a, and is connected to the water supply port 3a in the vicinity of the floor 20. As a result, the water W in the chamber 2 falls from the water supply port 3a to the drain port 3b in the piping 3 due to its own weight.

[0022] The drain outlet 3b is connected to the Francis turbine 11 in the vicinity of the floor 21. The Francis turbine 11 is a power generating turbine installed on the floor 21, and generates power using the water W drained from the drain outlet 3b.

[0023] The pipe 4 has a larger diameter than the pipe 3, extends substantially vertically downward from the floor 21 to the floor 22 below, and has a water inlet 4a and a drain outlet 4b at a lower height. The water inlet 4a is connected to the Francis turbine 11 near the floor 21. Water W used for power generation by the Francis turbine 11 falls in the pipe 4 from the water inlet 4a to the drain outlet 4b due to its own weight.

[0024] The drain outlet 4b is connected to the Francis turbine 12 in the vicinity of the floor 22. The Francis turbine 12 is a power generating turbine installed on the floor 22, and generates power using the water W drained from the drain outlet 4b.

[0025] The piping 5 has a larger diameter than the piping 4, extends substantially vertically downward from the floor 22 to the floor 23 below, and has a water inlet 5a and a drain outlet 5b at a lower height. The water inlet 5a is connected to the Francis turbine 12 near the floor 22. Water W used for power generation by the Francis turbine 12 falls in the piping 5 from the water inlet 5a to the drain outlet 5b due to its own weight.

[0026] The drain outlet 5b is connected to the Francis turbine 13 in the vicinity of the floor 23. The Francis turbine 13 is a power generating turbine installed on the floor 23, and generates power using the water W drained from the drain outlet 5b.

[0027] The pipe 6 has a larger diameter than the pipe 5, extends substantially vertically downward from the floor 23, and has a water supply port 6a and a drain port 6b located at a lower height.

[0028] The water supply port 6a is connected to the Francis turbine 13 near the floor 23. Water W used for power generation in the Francis turbine 13 falls through the piping 6 from the water supply port 6a toward the water discharge port 6b due to its own weight.

[0029] The pipe 7 is connected to the drain outlet 6b and includes a branch pipe 7a that branches the water W drained from the drain outlet 6b into a plurality of pipes.

[0030] A Pelton turbine 14 is provided below the branch pipe 7a. The Pelton turbine 14 is a turbine that generates power using the water W discharged from the branch pipe 7a. In this example, the Pelton turbine 14 includes a plurality of impellers 14a, a shaft 14c, and a generator 14d.

[0031] Each impeller 14a is provided coaxially with a shaft 14c, and rotates the shaft 14c by receiving water W. The rotational motion of the shaft 14c causes a generator 14d to generate electricity.

[0032] In this example, an impeller 14a is provided for each branch pipe 7a. This allows the impeller 14a to efficiently receive the water W drained from the branch pipe 7a, thereby improving the power generation efficiency of the Pelton turbine 14.

[0033] In addition, the water pressure in each branch pipe 7a may be increased by making the pipe diameter of the branch pipe 7a smaller after branching than before branching. This increases the flow rate of the water W discharged from each branch pipe 7a, and the water W can be obtained with a flow rate sufficient to drive the Pelton turbine 14.

[0034] The pool 15 is a tank for storing the water W discharged from the Pelton turbine 14, and is provided, for example, on the first floor or basement of the building 30.

[0035] A pump 16 for pumping up water W from pool 15 is provided above pool 15. The water W pumped up by pump 16 returns to chamber 2 through pumping piping 8 and is used for power generation again. Note that, as the power to drive pump 16, for example, other commercial electricity or pre-stored electricity may be used in addition to or instead of the power generated by each of the Francis turbines 11-13 and the Pelton turbine 14.

[0036] Thus, the hydroelectric power generation system 1 has pipes 3 to 5, and of these pipes 3 to 5, the pipe located upstream with respect to the flow of water W corresponds to the first pipe of the present invention, and the pipe located downstream corresponds to the second pipe. For example, pipe 3 corresponds to the first pipe, and either pipe 4 or 5 located further downstream corresponds to the second pipe. Furthermore, the third pipe of the present invention is, of pipes 5 and 6, the pipe located downstream of the second pipe of the present invention. For example, when pipe 4 is the second pipe, either pipe 5 or 6 becomes the third pipe.

[0037] In addition, the number of pipes and Francis turbines is not particularly limited. In this example, three Francis turbines 11-13 are provided in three stages of pipes 3-5, but any number of Francis turbines may be provided in any number of stages of pipes. Furthermore, in this example, the number of branch pipes 7 is four, but the number of branch pipes 7 may be any number equal to or greater than two.

[0038] According to the hydroelectric power generation system 1 described above, each of the Francis turbines 11 to 13 and the Pelton turbine 14 converts the falling energy of the water W into electrical energy, thereby enabling hydroelectric power generation.

[0039] In addition, in this hydroelectric power generation system 1, the pipes 3-7 provide flow paths for water supplied to the Francis turbines 11-13 and the Pelton turbine 14. Therefore, by housing the pipes 3-7, the Francis turbines 11-13, and the Pelton turbine 14 in a structure such as a building, it is possible to construct a compact hydroelectric power generation system 1 that can be installed in urban areas or industrial zones.

[0040] Furthermore, by reusing the floors of the existing building 30 as the floors 21-23 on which the Francis turbines 11-13 are installed and extending the pipes 3-5 from the upper floors to the lower floors, the hydroelectric power generation system 1 can be constructed while making effective use of the existing building 30.

[0041] Furthermore, in this embodiment, since the pipe diameter of the pipe 4 is made larger than the pipe diameter of the pipe 3, the pressure that the water W discharged from the Francis turbine 11 receives in the pipe 4 drops rapidly. Therefore, the water W is easily discharged from the Francis turbine 11, and the power generation efficiency of the Francis turbine 11 is improved. Furthermore, since the flow velocity of the water W falling through the pipe 4 increases, the power generation efficiency of the Francis turbine 12 in the subsequent stage is improved. For the same reason, since the pipe diameter of the pipe 5 is made larger than the pipe diameter of the pipe 4, the power generation efficiency of each of the Francis turbines 12 and 13 is improved. Furthermore, since the pipe diameter of the pipe 6 is made larger than the pipe diameter of the pipe 5, the power generation efficiency of the Francis turbine 13 is improved.

[0042] Moreover, the water W used for power generation by each of the Francis turbines 11-13 and the Pelton turbine 14 can be stored in the pool 15 and pumped up to the chamber 2 by the pump 16, so that the water W can be used again for power generation. Therefore, the hydroelectric power generation system 1 can generate power even in urban areas where water resources are scarce.

[0043] In addition, because a vacuum region V is formed in the chamber 2, atmospheric pressure does not act on the surface of the water W in the chamber 2. Therefore, the amount of water W supplied from the chamber 2 to the pipe 3 is less susceptible to the effects of atmospheric pressure, and fluctuations in the amount of power generation caused by changes in atmospheric pressure due to changes in weather can be suppressed.

[0044] When constructing the hydroelectric power generation system 1 in a cold region, it is preferable to use a heat insulating material for the outer wall of the building 30. Also, heat insulating material may be wrapped around each of the pipes 3 to 7. This makes it possible to prevent the water W from freezing, which would cause each of the Francis turbines 11 to 13 and the Pelton turbine 14 to be unable to generate power.

[0045] <Modification> FIG. 2 is a configuration diagram of a hydroelectric power generation system 1 according to a modified example. In this modified example, the chamber 2 and the pumping pipe 8 in FIG. 1 are omitted. The entire hydroelectric power generation system 1 is submerged in the sea, and the water inlet 3a of the pipe 3 is set lower than the sea level S. This allows seawater to be taken in from the water inlet 3a as the water W for power generation. Then, each of the Francis turbines 11 to 13 and the Pelton turbine 14 generates power using seawater, making it possible to make effective use of seawater. The seawater used for power generation is stored in a pool 15 and then discharged into the sea from a drainage port 16a of a pump 16. [Explanation of symbols]

[0046] 1...Hydroelectric power generation system, 2...Chamber, 3-7...Pipes, 3a, 4a, 5a, 6a...Water inlet, 3b, 4b, 5b, 6b...Drain, 7a...Branch pipe, 8...Pumping pipe, 11-13...Francis turbine, 14...Pelton turbine, 14a...Impeller, 14c...Shaft, 14d...Generator, 15...Pool, 16...Pump, 16a...Drain, 20-23...Floor, 30...Building

Claims

1. a first pipe having a first water inlet and a first drain outlet at a lower height than the first water inlet; a first Francis turbine that generates power using the water discharged from the first outlet; a second pipe having a diameter larger than that of the first pipe, the second pipe including a second water inlet to which water discharged from the first Francis turbine is supplied and a second water outlet located at a height lower than that of the second water inlet; a Pelton turbine that generates electricity using the water discharged from the second outlet; a pool for storing water discharged from the Pelton turbine; a chamber connected to the first water inlet and located higher than the first water inlet; A water pumping pipe connecting the pool and the chamber; a pump for pumping the water from the pool through the water pumping pipe to the chamber; The interior of the chamber is composed of water and a vacuum region extending above the water. Hydroelectric power system.

2. 2. The hydroelectric power generation system according to claim 1, The water discharged from the second drain outlet is further branched into a plurality of branch pipes, The Pelton turbine has a plurality of coaxial impellers that receive water discharged from each of the plurality of branch pipes. Hydroelectric power system.

3. 3. The hydroelectric power generation system according to claim 2, Each of the plurality of branch pipes has a smaller pipe diameter than that before branching. Hydroelectric power system.

4. 2. The hydroelectric power generation system according to claim 1, a second Francis turbine that generates power using the water discharged from the second outlet; and a third water inlet to which water discharged from the second Francis turbine is supplied, and a third drain outlet located at a height lower than the third water inlet, and a third pipe having a diameter larger than that of the second pipe; The Pelton turbine generates electricity using the water discharged from the third outlet. Hydroelectric power system.

5. 2. The hydroelectric power generation system according to claim 1, the chamber is disposed above a first floor; the first Francis turbine is installed on a second floor below the first floor; The first pipe extends from the first bed to the second bed. Hydroelectric power system.

Citation Information

Patent Citations

  • High-efficiency environment-friendly hydroelectric power generation system

    CN203452970U

  • Wall-mounted power generation device

    CN211500864U

  • Vertical shaft type pelton turbine

    JP1994307322A

  • Underground hydraulic power generating method utilizing sea water or river water and generating mechanism therefor

    JP2000009015A

  • Multiple-turbine with gear shift means

    JP2000179443A