Business support device, business support method, and business support program

The business support device accurately calculates progress rates and percentage-of-completion sales by aggregating actual and estimated costs, addressing underestimation issues in existing systems and enhancing cost recognition and sales recording accuracy.

JP7591100B2Active Publication Date: 2024-11-27OBIC CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023107510
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-06-29
Publication Date
2024-11-27
Estimated Expiration
2042-07-28

AI Technical Summary

Technical Problem

Existing cost accounting systems struggle to accurately calculate progress rates and percentage-of-completion sales amounts due to unrecorded purchases and outstanding invoices, leading to underestimation of costs and inaccurate sales recording.

Method used

A business support device and method that includes an estimated cost accounting input screen to provisionally record costs, aggregating actual and estimated costs based on work order data, sales standards, and budget amounts to calculate a cumulative cost amount, which is then divided by the expected final destination amount to determine the progress rate.

Benefits of technology

Enables accurate calculation of progress rates and percentage-of-completion sales amounts by incorporating both actual and estimated costs, ensuring precise cost recognition and sales recording.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007591100000001
    Figure 0007591100000001
  • Figure 0007591100000002
    Figure 0007591100000002
  • Figure 0007591100000003
    Figure 0007591100000003
Patent Text Reader

Abstract

To provide a business support device enabling accurate accounting of a progress reference sales amount, etc., by calculating an accurate progress rate of work.SOLUTION: A deemed cost accounting input screen display control part displays, on a display part, a deemed cost accounting input screen for tentatively accounting a deemed cost for an unaccounted cost of prescribed work. A tabulation part tabulates an actual cost and the deemed cost input via the deemed cost accounting input screen. A calculation part calculates a progress rate, the value obtained by dividing the cumulative cost amount by an estimated final sales landing amount, based on the cost accounted by an accounting part, a sales reference attached to order data of the work, a cumulative cost amount input based on a budget amount and an order amount, and the estimated final sales landing amount. A data generation part generates progress rate data representing the calculated progress rate. A business support device can thus calculate the accurate progress rate of the work, and account an accurate progress reference sales amount, etc.SELECTED DRAWING: Figure 15
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a business support device, a business support method, and a business support program. [Background technology]

[0002] Nowadays, when recording sales in construction transactions using the percentage of completion method or cost recovery method, it is necessary to grasp accurate costs that correspond to the actual situation at the time of recording sales. For this reason, the cost recording device disclosed in Patent Document 1 (JP Patent Publication No. 2019-079233) sets a provisional cost at the time of sales, including the cost incurred at the time of sales, the unreached cost at the time of sales, and the estimated cost at the time of sales, calculates the cost incurred in the sales month, the accumulated unreached cost in the sales month, and the accumulated estimated cost in the sales month, and creates journal entry data for the provisional cost in the sales month, including the accumulated unreached cost in the sales month and the accumulated estimated cost in the sales month.

[0003] In addition, at the beginning of the month, reversal data is created to cancel the journal data created in the previous month for the accumulated unreached costs and accumulated estimated costs, and in each month after the month of sales, the costs incurred in that month, the accumulated unreached costs in that month, and the accumulated estimated costs in that month are calculated, and journal data for monthly provisional costs including the accumulated unreached costs in that month and the accumulated estimated costs in that month are created. This makes it possible to cancel the journal entries recorded as provisional costs at the beginning of the following month, and record the amount obtained by evaluating the final estimated costs as provisional costs each month after sales. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2019-079233 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, when determining costs by recording purchases such as outsourcing costs and material costs, if invoices are not received from suppliers by the end of the month and purchase recording is not possible, the amount of costs incurred cannot be determined, the progress rate calculation results are underestimated, and the progress basis sales amount, etc., may be recorded as less than the actual amount.

[0006] The present invention has been made in consideration of the above-mentioned problems, and aims to provide a business support device, a business support method, and a business support program that are capable of calculating an accurate progress rate and recording an accurate progress-based sales amount, etc. [Means for solving the problem]

[0007] In order to solve the above problems and achieve the object, the business support device according to the present invention includes an assumed cost apportionment input screen display control unit that displays an assumed cost apportionment input screen on a display unit for provisionally apportioning assumed costs for unapportioned costs of a predetermined task; During the period when sales are recognized Entered via the actual cost and assumed cost entry screen During the period when sales are recognized A calculation section that calculates the deemed cost and a calculation section that calculates the estimated cost. During the sales recognition period Input based on cost, sales criteria attached to the work order data, budget amount and order amount During the sales recognition period Based on the accumulated cost amount and the final estimated amount, the accumulated cost amount, which is the sum of the actual cost and the deemed cost, is divided by the final estimated amount. By doing so, the progress rate of work during the sales recognition period and a data generating unit that generates progress rate data indicating the calculated progress rate.

[0008] In order to solve the above-mentioned problems and achieve the object, the business support method according to the present invention includes an assumed cost apportionment input screen display control step in which an assumed cost apportionment input screen display control unit displays an assumed cost apportionment input screen on a display unit for provisionally apportioning assumed costs for unapportioned costs of a predetermined task; During the period when sales are recognized Entered via the actual cost and assumed cost entry screen During the sales recognition period A calculation step for calculating the estimated cost and a calculation unit for calculating the estimated cost calculated in the calculation step. During the period when sales are recognizedInput based on cost, sales criteria attached to the work order data, budget amount and order amount During the period when sales are recognized Based on the accumulated cost amount and the final estimated amount, the accumulated cost amount, which is the sum of the actual cost and the deemed cost, is divided by the final estimated amount. By doing so, the progress rate of work during the sales recognition period and a data generating step in which the data generating unit generates progress rate data indicating the calculated progress rate.

[0009] In order to solve the above-mentioned problems and achieve the object, a business support program according to the present invention includes a computer, which includes an assumed cost calculation input screen display control unit that displays an assumed cost calculation input screen on a display unit for provisionally calculating assumed costs for uncalculated costs of a specific task; During the sales recognition period Entered via the actual cost and assumed cost entry screen During the sales recognition period A calculation section that calculates the deemed cost and a calculation section that calculates the estimated cost. During the sales recognition period Input based on cost, sales criteria attached to the work order data, budget amount and order amount During the period when sales are recognized Based on the accumulated cost amount and the final estimated amount, the accumulated cost amount, which is the sum of the actual cost and the deemed cost, is divided by the final estimated amount. By doing so, the progress rate of work during the sales recognition period and a data generating unit that generates progress rate data indicating the calculated progress rate. Effect of the Invention

[0010] The present invention can calculate an accurate progress rate, which makes it possible to record an accurate progress-based sales amount, etc. [Brief description of the drawings]

[0011] [Figure 1] FIG. 1 is a block diagram illustrating a hardware configuration of a task support device according to an embodiment. [Diagram 2] FIG. 2 is a schematic diagram showing a flow from construction information input processing to budget input processing in the business support device according to the embodiment. [Diagram 3] FIG. 3 is a diagram showing an example of basic construction information. [Figure 4] FIG. 4 is a diagram illustrating an example of the order data. [Diagram 5] FIG. 5 is a diagram illustrating an example of budget detail data. [Figure 6] FIG. 6 is a schematic diagram showing a flow from an order input process to an assumed cost input process in the business support device according to the embodiment. [Figure 7] FIG. 7 is a diagram showing an example of the order input screen. [Figure 8] FIG. 8 is a diagram showing an example of the order details screen. [Figure 9] FIG. 9 is a diagram illustrating an example of the order data. [Figure 10] FIG. 10 is a diagram illustrating an example of purchase data. [Figure 11] FIG. 11 is a diagram showing an example of the deemed cost input screen. [Figure 12] FIG. 12 is a diagram showing another example of the deemed cost input screen. [Figure 13] FIG. 13 is a diagram showing an example of the project basic information master screen. [Figure 14] FIG. 14 is a diagram illustrating an example of deemed cost apportionment data. [Figure 15] FIG. 15 is a schematic diagram showing a flow from the cost calculation process to the progress-of-sales calculation process in the task support device according to the embodiment. [Figure 16] FIG. 16 is a diagram showing an example of landing prediction data. [Figure 17] FIG. 17 is a diagram illustrating an example of the progress rate data. [Figure 18] FIG. 18 is a diagram showing an example of progress-based sales data. [Figure 19] FIG. 19 is a schematic diagram for explaining the action and effect of the task support device according to the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0012] Hereinafter, a task support device according to an embodiment of the present invention will be described in detail with reference to the drawings, although the present invention is not limited to such an embodiment.

[0013] (Hardware configuration) Fig. 1 is a block diagram showing a hardware configuration of a task support device 1 according to an embodiment. The task support device 1 shown in Fig. 1 includes a storage unit 2, a control unit 3, a communication interface unit 4, and an input / output interface unit 5. An input device 6 and an output device 7 are connected to the input / output interface unit 5. The output device 7 may be a display unit such as a monitor device (including a home television). The input device 6 may be a keyboard device, a mouse device, a microphone device, or a monitor device that cooperates with a mouse device to realize a pointing device function.

[0014] The communication interface unit 4 is connected to a wide area network such as the Internet or a private network such as a LAN (Local Area Network).

[0015] The storage unit 2 may be, for example, a storage device such as a ROM (Read Only Memory), a RAM (Random Access Memory), an HDD (Hard Disk Drive), or an SSD (Solid State Drive). The storage unit 2 is provided with a project basic information management master 11, which is a storage area in which the deemed cost order period apportionment classification (see FIG. 13) described later and the like are stored. The storage unit 2 also stores a business support program that enables business support operations, as well as various data generated based on input operations from a business operator and various data generated by the execution of the business support program. That is, although details will be described later, the storage unit 2 stores construction basic data, order data, budget details data, order data, purchase data, deemed cost data, cost details data, expected completion data, progress rate data, and progress-based sales data and the like.

[0016] (Functional configuration of business support device) Next, the control unit 3 executes the business support program stored in the memory unit 2, thereby functioning as a display control unit 21 (an example of an assumed cost accounting input screen display control unit), a data generation unit 22, a memory control unit 23, a calculation unit 24, and a aggregation unit 25.

[0017] The display control unit 21 displays an assumed cost calculation input screen for provisionally calculating assumed costs for uncalculated costs of construction work, which is an example of a predetermined task, via the output device 7, which is an example of a display unit. The tallying unit 25 tally up the actual costs and the assumed costs input via the assumed cost calculation input screen.

[0018] The calculation unit 24 calculates a progress rate, which is a value obtained by dividing the accumulated cost amount by the estimated final cost amount, based on the costs, which are the actual cost and deemed cost, collected by the collection unit 25, the accumulated cost amount and the estimated final cost amount, which are input based on the sales standard, budget amount, and order amount attached to the order data for the construction work. The data generation unit 22 generates progress rate data indicating the progress rate calculated by the calculation unit 24. The memory control unit 23 controls the storage of the generated progress rate data in the memory unit 2.

[0019] The calculation unit 24 also calculates a progress-based sales amount, which is an amount obtained by multiplying the order amount of the construction work included in the order data by the progress rate and subtracting the progress-based sales amount recorded before the previous month, which is an example of the previous recording period. The data generation unit 22 generates progress-based sales data indicating the calculated progress-based sales amount, and the memory control unit 23 stores this in the memory unit 2.

[0020] In addition, when the planned purchase date is after the recording period and the sales criteria attached to the order data is for work based on the progress of work or the cost recovery basis, the display control unit 21 displays the estimated cost recording amount, which is the order amount prorated over a specified period, as an initial value on the estimated cost recording input screen.

[0021] (Business support operation) Next, a description will be given of the business support operation in the business support device 1 of the embodiment. The business support device 1 of the embodiment executes a series of processes based on a business support project stored in the storage unit 2, including a construction information input process, a contract information input process, and a budget input process shown in steps S1 to S3 in Fig. 2, an order input process and an assumed cost input process shown in steps S4 and S5 in Fig. 6, a cost calculation process, a final price forecast input process, a progress rate input process, and a progress-based sales calculation process shown in steps S6 to S9 in Fig. 15.

[0022] First, in step S1 shown in Fig. 2, the business operator performs an input process for basic construction information. When the business operator specifies input of basic construction information, the display control unit 21 displays a basic construction information input screen (not shown) via the output device 7. The business operator inputs basic construction information into this basic construction information input screen. Fig. 3 is a diagram showing an example of basic construction information generated by the data generation unit 22 based on input from the business operator. As shown in Fig. 3, various pieces of information such as the project number (PJ number: construction number), construction project name, direct / intermediate division, and construction site are input as basic construction information.

[0023] Next, in step S2, the business operator inputs contract information for the received construction work. When the business operator specifies input of contract information, the display control unit 21 displays a contract information input screen (not shown) via the output device 7. The business operator inputs contract information into this contract information input screen. FIG. 4 is a diagram showing an example of order data, which is contract information generated by the data generation unit 22 based on the input from the business operator. As shown in FIG. 4, the order data includes order header data shown in FIG. 4(a) and order detail data shown in FIG. 4(b).

[0024] The order header data includes the project number, order number, and project name, as shown in Fig. 4(a). The order detail data includes the project number, order number, order line number, expected sales date, order amount, and sales criteria information, as shown in Fig. 4(b). As the sales criteria information, for example, sales criteria such as "progress criteria" or "cost recovery criteria" are set.

[0025] The percentage of completion method is a sales standard in which revenue is recorded according to the progress of construction. The cost recovery method is a sales standard in which revenue is recognized and recorded based on the amount of expenses incurred in fulfilling a performance obligation that are expected to be recovered. Figure 4(b) shows an example in which the "percentage of completion method" has been set for construction with project number "PJ001," and the "cost recovery method" has been set for construction with project number "PJ003."

[0026] Next, in step S3 of Fig. 2, the business operator inputs the budget. When the business operator specifies budget input, the display control unit 21 displays a budget input screen (not shown) via the output device 7. The business operator inputs budget information into this budget input screen.

[0027] FIG. 5 is a diagram showing an example of detailed budget data generated by the data generating unit 22 based on a budget input from a business operator. As shown in FIG. 5, the detailed budget data includes a PJ number, an order number, an order line number, a PJ cost item, and a budget amount. The PJ cost item is material cost or subcontracting cost. The example in FIG. 5 is an example in which a budget amount of "650,000 yen" is input as the budget amount of material cost for a construction project having a project number of "PJ001", an order number of "JU001", and an order line number of "001", a budget amount of "1,450,000 yen" is input as the budget amount of subcontracting cost for a construction project having a project number of "PJ001", an order number of "JU001", and an order line number of "001", and a budget amount of "2,000,000 yen" is input as the budget amount of subcontracting cost for a construction project having a project number of "PJ003", an order number of "JU004", and an order line number of "001".

[0028] Next, in step S4 of Fig. 6, the business operator inputs an order. When the business operator specifies order input, the display control unit 21 displays an order input screen as exemplified in Fig. 7 via the output device 7. The business operator inputs the order date, supplier, project number, order number, and order line number to this order input screen. The business operator also displays the order details screen shown in Fig. 8 and inputs the name of the purchased product to be ordered, project number, order number, order line number, order quantity, order price, and planned purchase date. The calculation unit 24 calculates the order amount by multiplying the input order quantity by the order price. The display control unit 21 displays the calculated order amount on the order details screen.

[0029] Furthermore, when the Confirm button on the order details screen is operated, the display control unit 21 displays the information input via the order details screen as details on the order input screen shown in Fig. 7. That is, on the order input screen shown in Fig. 7, the information input sequentially via the order details screen is displayed as a list as details of the order information.

[0030] The data generating unit 22 generates the order data shown in Fig. 9 based on the order information input via the order input screen and the order details screen. This order data includes the order header data shown in Fig. 9(a) and the order details data shown in Fig. 9(b).

[0031] The order header data includes the order number, order date, supplier code, supplier name, project number, order number, order line number, and order amount, as shown in Fig. 9(a). The order detail data includes the order number, order line number, purchased product name, project number, order number, order line number, project cost item, order quantity, order unit price, order amount, and planned purchase date, as shown in Fig. 9(b).

[0032] In addition, when an invoice arrives from a supplier, the business operator performs purchase input. Based on this purchase input, the data generation unit 22 generates purchase data shown in Fig. 10. This purchase data includes purchase header data shown in Fig. 10(a) and purchase detail data shown in Fig. 10(b).

[0033] As shown in Fig. 10(a), the purchase header data includes purchase number, purchase order number, purchase date, supplier code, supplier name, project number, order number, order line number, and purchase amount. As shown in Fig. 10(b), the purchase detail data includes purchase number, purchase line number, order number, order line number, purchase product name, project number, order number, order line number, project cost item, purchase quantity, purchase price, and purchase amount.

[0034] This purchasing data is different from the deemed cost, which is provisionally recorded and then deducted the following month or later, and is the so-called "actual cost," which is recorded when the invoice is received from the supplier.

[0035] Next, the business operator performs the deemed cost recording input in step S5 of Fig. 6. That is, when the business operator specifies the deemed cost recording input, the display control unit 21 displays the deemed cost recording input screen shown in Fig. 11. The business operator inputs the deemed cost recording date, project number, order number, and order line number to this deemed cost recording input screen, and specifies the order data for which deemed cost recording is to be performed.

[0036] The display control unit 21 refers to the order detail data shown in Fig. 9(b) based on the input project number etc., and displays a list of deemed cost apportionment data including the order number, line number, supplier name, product name, project cost item, scheduled purchase date, order quantity, order unit price, and order amount, as shown in Fig. 11. The calculation unit 24 also calculates the remaining order amount, which indicates the amount that has been ordered but not yet purchased, by subtracting the purchased amount from the order amount of each estimated cost apportionment data displayed in the list.

[0037] When the purchase is not completed, the display control unit 21 displays the amount (order amount - purchased amount) calculated by the calculation unit 24 in the deemed cost apportionment data, and when the purchase is completed, the display control unit 21 displays the remaining order amount of "0 yen" in the deemed cost apportionment data. Furthermore, the display control unit 21 displays an input field for the deemed cost apportionment amount of the deemed cost to be apportioned in the deemed cost apportionment data.

[0038] The display control unit 21 displays the deemed cost apportionment input screen in a state where only the input field for the deemed cost apportionment amount is available for input among the items of the deemed cost apportionment data such as the supplier name, order quantity, order unit price, and order amount. In other words, the business operator cannot input anything on the deemed cost apportionment input screen other than the input fields for the deemed cost apportionment date, project number, order number, order line number, and deemed cost apportionment amount. If the business operator wishes to re-input the order quantity or the like, he or she must re-input the information via the order input screen shown in Figs. 7 and 8.

[0039] The business operator inputs a desired deemed cost amount corresponding to the order balance in the deemed cost amount input field on this deemed cost input screen. The example of deemed cost accounting data shown in the first and second lines of Fig. 11 is an example in which an deemed cost amount of "200,000 yen" is input for an order balance of "200,000 yen", and an deemed cost amount of "210,000 yen" is input for an order balance of "210,000 yen". Also, the example of deemed cost accounting data shown in the third line of Fig. 11 is an example in which an deemed cost amount of "400,000 yen" is input for an order balance of "400,000 yen".

[0040] The calculation unit 24 adds up the thus input deemed cost appropriation amounts to calculate the total deemed cost appropriation amount. The display control unit 21 displays the calculated total deemed cost appropriation amount on the deemed cost appropriation input screen as shown in FIG.

[0041] Here, when the planned purchase date is in a period after the recording period and the sales standard attached to the order data (order detail data) shown in Fig. 4(b) is construction based on the progress of completion standard or cost recovery standard, the display control unit 21 displays the deemed cost recording amount obtained by dividing the order amount by a predetermined period as an initial value on the deemed cost recording input screen. On the deemed cost recording input screen shown in Fig. 12, the deemed cost recording amount of "500,000 yen" indicates the deemed cost recording amount obtained by dividing the order amount by a predetermined period.

[0042] That is, as shown in Fig. 13, the desired period for apportioning the order amount is preset as the deemed cost generation period apportionment category in the project basic information master 11 in the storage unit 2. The example in Fig. 13 is an example in which "1 month allocation" is set as the deemed cost generation period apportionment category. As an example, it is preferable to set this deemed cost generation period apportionment category in accordance with the period for which progress-of-performance sales are recorded. Of course, it is also possible to set it in accordance with a desired period.

[0043] In the case of the details of the order number "HC003" illustrated in FIG. 12, the order date is "July 10, 2022" as shown in FIG. 9(a). In addition, in the case of the details of the order number "HC003" illustrated in FIG. 12, the order amount is "2 million yen" as shown in FIG. 9(b). In addition, the deemed cost occurrence period apportionment category is set to "1 month" as described above. Therefore, the calculation unit 24 calculates the deemed cost amount by calculating "2 million yen x (1 month / 4 months) = 500,000 yen". The display control unit 21 displays the calculated deemed cost amount of "500,000 yen" as an initial value on the deemed cost apportionment input screen as shown in FIG. 12.

[0044] In this way, the deemed cost amount according to the construction period is automatically displayed as the initial value on the deemed cost input screen, which promotes the review of the deemed cost amount and supports appropriate cost recording. In addition, the input operation can be simplified, reducing the workload of the operator.

[0045] When the deemed cost apportionment amount is input in this manner, the data generation unit 22 generates deemed cost apportionment data as exemplified in Fig. 14 based on the input contents on the deemed cost apportionment input screen. This deemed cost apportionment data includes deemed cost apportionment header data as exemplified in Fig. 14(a) and deemed cost apportionment detail data as exemplified in Fig. 14(b). The deemed cost apportionment header data as exemplified in Fig. 14(a) includes deemed cost apportionment number, deemed cost apportionment date, project number, order number, order line number, and deemed cost apportionment amount.

[0046] The deemed cost accounting detail data shown in Fig. 14(b) includes the deemed cost accounting number, line number, purchase order number, project cost item, deemed cost accounting amount, deemed cost reversal amount, and reversal completion category. Note that at the time the deemed cost accounting amount is entered, the deemed cost has not been reversed, so the deemed cost reversal amount is "0 yen" and the reversal completion category is "not completed."

[0047] Next, in step S6 of Fig. 15, the tallying unit 25 shown in Fig. 1 tally up the purchase cost (actual cost: 240,000 yen in the example of Fig. 10) explained using Fig. 10 and the deemed cost input by the business operator via the deemed cost input screen shown in Fig. 11. The data generating unit 22 generates cost detail data exemplified in Fig. 16(a) based on the totaled actual cost and deemed cost. This cost detail data includes the project number, order number, order line number, occurrence category, project cost item, cost amount, and occurrence date.

[0048] Of the cost detail data shown in Figure 16(a), the detail "240,000 yen" on the first line is the actual cost based on purchase input, and the details "410,000 yen," "400,000 yen," and "500,000 yen" on the second to fourth lines are the estimated cost amounts based on estimated cost input.

[0049] Next, in step S7 of Fig. 15, the business operator inputs the expected final cost based on the cost detail data shown in Fig. 16(a), the order detail data shown in Fig. 16(b), and the budget detail data shown in Fig. 16(c). Specifically, the business operator inputs the project number, order number, order line number, project cost item, budget amount, order amount, accumulated cost amount, final expected final cost amount, and future planned cost as the expected final cost.

[0050] The data generating unit 22 generates the estimated cost data shown in Fig. 16(d) based on the estimated cost input entered by the business operator. In this example, the estimated final cost for material costs for PJ number "PJ001" is "650,000 yen", and the estimated final cost for outsourcing costs for PJ number "PJ001" is "1,450,000 yen". In addition, the estimated final cost for material costs for PJ number "PJ003" is "2,000,000 yen".

[0051] When the estimated end result is input in this manner, the calculation unit 24 calculates the progress rate of the construction work by calculating "accumulated cost amount / estimated final end result amount" in step S8 of Fig. 15. In the example shown in Fig. 16(d), for a construction work with a PJ number of "PJ001", the accumulated cost amount of material costs is "650,000 yen" and the accumulated cost amount of subcontract costs is "400,000 yen". For a construction work with a PJ number of "PJ001", the estimated final end result amount of material costs is "650,000 yen" and the estimated final end result amount of subcontract costs is "1,450,000 yen".

[0052] Therefore, the calculation unit 24 calculates the progress rate of "50%" by performing the calculation "(650,000 yen+400,000 yen) / (650,000 yen+1,450,000 yen)".

[0053] 16(d), in the case of a construction project with a PJ number of "PJ003", the cumulative cost amount of the outsourcing expenses is "500,000 yen" and the final estimated cost amount is "2,000,000 yen". Therefore, the calculation unit 24 calculates the progress rate of "25%" by calculating "500,000 yen / 2,000,000 yen".

[0054] Based on such a calculation result, the data generating unit 22 generates progress rate data including the PJ number, the order number, the order line number, and the progress rate, as exemplified in FIG.

[0055] Next, in step S9 of Fig. 15, the calculation unit 24 calculates the progress-of-progress-basis sales amount for the construction project by calculating "(order amount x progress rate) - progress-of-progress-basis sales amount recorded in the previous month or earlier". In the start month, the "progress-of-progress-basis sales amount recorded in the previous month or earlier" is "0 yen", so the calculation unit 24 calculates "3 million yen x 50% = 1.5 million yen" for the construction project with PJ number "PJ001".

[0056] Furthermore, the calculation unit 24 performs the calculation of "2,100,000 yen x 25% = 525,000 yen" for the construction work with PJ number "PJ003". However, since the construction work with PJ number "PJ003" is a construction work based on the cost recovery standard as shown in Fig. 4(b), the incurred cost amount of "500,000 yen" is set as the upper limit and recorded.

[0057] Based on such a calculation result, the data generating unit 22 generates progress-based sales data including the project number, the order number, the order line number, and the progress-based sales amount, as shown in FIG.

[0058] 19 is a schematic diagram comparing the conventional business support device 1 with the embodiment. In the conventional business support device 1, the deemed cost could not be recorded and the progress rate was calculated only based on the actual cost, so the progress-based sales amount was also inaccurate.

[0059] In contrast, the business support device 1 according to the embodiment can calculate the progress rate based on the cost amount obtained by adding the deemed cost to the actual cost, and therefore can calculate an accurate progress rate and therefore an accurate progress-based sales amount. This makes it possible to record an accurate progress-based sales amount, etc.

[0060] (Effects of the embodiment) As is clear from the above description, the task support device 1 according to the embodiment can achieve the following effects.

[0061] 1. Accurate cost amounts can be recognized for calculating the percentage of completion (Percentage of completion method). By accruing costs in the month in which sales are recorded on an assumed basis, the actual costs can be recognized. This makes it possible to improve the appropriateness of the percentage of completion of the work and the sales amount based on the percentage of completion method, and to make them more precise.

[0062] 2. By inputting the cost amount based on the actual situation, it can be reflected in the sales amount (cost recovery basis). By generating costs in the month in which sales are recorded on an assumed basis, it is possible to input costs that are based on the actual situation, and sales based on the cost recovery basis can be accurately recorded.

[0063] [Contribution to the United Nations-led Sustainable Development Goals (SDGs)] This embodiment can contribute to improving business efficiency and promoting appropriate management decisions by companies, and can therefore contribute to Goals 8 and 9 of the SDGs.

[0064] Furthermore, this embodiment can contribute to reducing waste and promoting paperless and electronic systems, thereby contributing to the achievement of Goals 12, 13, and 15 of the SDGs.

[0065] Furthermore, this embodiment can contribute to strengthening control and governance, making it possible to contribute to Goal 16 of the SDGs.

[0066] [Other embodiments] The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.

[0067] For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using known methods.

[0068] In addition, the processing procedures, control procedures, specific names, information including parameters such as registered data and search conditions for each process, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.

[0069] Moreover, with regard to the task support device 1, each of the components shown in the figures is a functional concept, and does not necessarily have to be physically configured as shown in the figures.

[0070] For example, the processing functions of the business support device 1, particularly the control unit 3 and each processing function performed by the control unit 3, may be realized in whole or in part by a CPU (Central Processing Unit) and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded in a non-transient computer-readable recording medium including programmed instructions for causing the information processing device to execute the processes described in this embodiment, and is mechanically read by the business support device 1 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD. This computer program is executed by being loaded into a RAM, and constitutes the control unit 3 in cooperation with the CPU.

[0071] In addition, the business support program of this business support device 1 may be stored in another server device connected to the business support device 1 via any network, and it is also possible to download all or part of it as needed.

[0072] The business support program for executing the process described in the present embodiment may be stored in a non-transient computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical Disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.

[0073] Moreover, a "program" is a data processing method written in any language or description method, and may be in any form, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration as multiple modules or libraries, and a program that achieves its function by working with a separate program, such as an OS. Note that well-known configurations and procedures can be used for the specific configuration and reading procedure for reading a recording medium in the business support device 1 shown in the embodiment, as well as the installation procedure after reading.

[0074] The memory unit 2 is a storage means such as a memory device such as RAM or ROM, a fixed disk device such as a hard disk, a flexible disk, or an optical disk, and stores various programs, tables, databases, and web page files used for various processes and providing websites.

[0075] The business support device 1 may be configured as an information processing device such as a known personal computer device or a workstation, or may be configured as an information processing device to which any peripheral device is connected. The information processing device may be realized by implementing software (including programs or data, etc.) that realizes the processing described in this embodiment.

[0076] Furthermore, the specific form of distribution and integration of the devices is not limited to those shown in the drawings, and all or part of them can be functionally or physically distributed and integrated in any unit according to various additions or function additions. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively. [Industrial Applicability]

[0077] The present invention is suitable for application to industries that perform assumed cost management, such as the construction industry. [Explanation of symbols]

[0078] 1 Business support equipment 2 Storage section 3. Control Unit 4. Communication Interface Section 5 Input / Output Interface Section 6 Input Devices 7 Output Devices 11 Project Basic Information Management Master 21 Display control unit 22 Data Generation Section 23 Memory control unit 24 Calculation section 25 Counting Department

Claims

1. an assumed cost apportionment input screen display control unit that displays an assumed cost apportionment input screen on a display unit for provisionally apportioning assumed costs for unapportioned costs of a specific task; a counting unit that counts actual costs during a sales recording period and deemed costs during a sales recording period input via the deemed cost recording input screen; a calculation unit that calculates a progress rate of the work during the sales recording period by dividing the accumulated cost amount, which is an amount obtained by adding up the actual cost and the deemed cost, by the final estimated amount, based on the cost during the sales recording period compiled by the compilation unit, and the accumulated cost amount and the final estimated amount during the sales recording period that are input based on the sales standard, budget amount, and order amount attached to the order data for the work; a data generating unit that generates progress rate data indicating the calculated progress rate; A business support device having the above configuration.

2. the calculation unit calculates a progress-based sales amount, which is an amount obtained by multiplying the order amount of the work included in the order data by the progress rate and subtracting the progress-based sales amount recorded in a previous recording period or earlier; the data generation unit generates progress-based sales data indicating the calculated progress-based sales amount; 2. The business support device according to claim 1,

3. the deemed cost apportionment input screen display control unit displays, as an initial value on the deemed cost apportionment input screen, an deemed cost apportionment amount calculated by dividing the order amount by a predetermined period when the planned purchase date is in a period after the apportionment period and the sales standard attached to the order data is work based on the progress of completion standard or the cost recovery standard; 3. The business support device according to claim 1 or 2,

4. an deemed cost apportionment input screen display control step in which an deemed cost apportionment input screen display control unit displays an deemed cost apportionment input screen on a display unit for provisionally apportioning deemed costs for unapportioned costs of a predetermined operation; a counting step in which a counting unit counts the actual cost during the sales recognition period and the deemed cost during the sales recognition period input via the deemed cost entry input screen; a calculation step in which a calculation unit calculates a progress rate of the work during the sales recording period by dividing the accumulated cost amount, which is an amount obtained by adding up the actual cost and the deemed cost, by the final estimated amount, based on the cost during the sales recording period collected in the collection step, the accumulated cost amount during the sales recording period and the final estimated amount, which are input based on the sales standard, budget amount and order amount attached to the order data for the work; a data generating step in which a data generating unit generates progress rate data indicating the calculated progress rate; A business support method having the above-mentioned features.

5. Computer, an assumed cost apportionment input screen display control unit that displays an assumed cost apportionment input screen on a display unit for provisionally apportioning assumed costs for unapportioned costs of a specific task; a counting unit that counts actual costs during a sales recording period and deemed costs during a sales recording period input via the deemed cost recording input screen; a calculation unit that calculates a progress rate of the work during the sales recording period by dividing the accumulated cost amount, which is an amount obtained by adding up the actual cost and the deemed cost, by the final estimated amount, based on the cost during the sales recording period compiled by the compilation unit, and the accumulated cost amount and the final estimated amount during the sales recording period that are input based on the sales standard, budget amount, and order amount attached to the order data for the work; functioning as a data generating unit that generates progress rate data indicating the calculated progress rate; A business support program that features:

Citation Information

Patent Citations

  • Estimation method and system for settlement of accounts using computer and computer readable recording medium recording settlement-of-accounts estimation program

    JP1999259562A

  • Cost accounting device, cost accounting method, and cost accounting program

    JP2019079233A

  • Progress rate calculating apparatus, progress rate calculating method, and progress rate calculating program

    JP2020087031A

  • Sales support device

    JP2021068036A

  • Device, method, and program for calculating estimated progress rate

    JP2021093070A