Equipment reservation device

The facility reservation device optimizes construction equipment reservations by prioritizing based on usage mode and construction progress, addressing inefficiencies in existing systems by aligning reservations with construction needs.

JP7731208B2Active Publication Date: 2025-08-29TAKENAKA CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2021022862
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-02-16
Publication Date
2025-08-29
Estimated Expiration
2041-02-16

AI Technical Summary

Technical Problem

Existing reservation systems for construction equipment at construction sites fail to prioritize reservations based on the mode of use, leading to inefficiencies and inconveniences due to overlapping requests from multiple subcontractors, as they do not account for the progress of construction work.

Method used

A facility reservation device that includes a reception unit to receive reservation request information with usage mode details and a reservation unit to generate reservations based on predetermined priorities, adjusting schedules according to construction work progress.

Benefits of technology

Reservations are confirmed according to the mode of use, optimizing equipment usage based on construction priorities, reducing administrative effort, and ensuring efficient allocation of resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007731208000001
    Figure 0007731208000001
  • Figure 0007731208000002
    Figure 0007731208000002
  • Figure 0007731208000003
    Figure 0007731208000003
Patent Text Reader

Abstract

To provide a facility reservation device which determines reservations in accordance with a usage mode of a facility when a plurality of users make applications to reserve the facility.SOLUTION: In a facility reservation system 10, a server 30 being one type of facility reservation devices includes: an accepting unit 300 which accepts reservation request information including a reservation request for a facility to be used and usage mode information about a usage mode of the facility from each of terminals of a plurality of users; and a reservation unit 306 which generates reservation information representing reservations for the facility on the basis of the usage mode information of the reservation request information of the plurality of users accepted by the accepting unit 300 and priorities preliminarily set with respect to the usage mode of the facility.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical Field]

[0001] The present invention relates to a facility reservation device. [Background technology]

[0002] Conventionally, there is known a system that allows a computer to make a reservation request for lifting equipment such as cranes, lifts, and elevators to be installed at a construction site (for example, Patent Document 1). When a reservation request for lifting equipment is made from a terminal, the server of the system disclosed in Patent Document 1 transmits screen configuration data for a reservation request screen. The server then obtains the information entered on the reservation request screen from the terminal and checks this information by comparing it with usage restrictions. If the server determines that the reservation request can be accepted, it notifies the terminal of this fact and stores the information in a memory unit (for example, Abstract of Patent Document 1).

[0003] There is also known a technology for streamlining the process by combining material management and transportation work required to lift interior materials and the like in a timely manner (for example, Patent Document 2). In the technology of Patent Document 2, a material management device at the construction office inputs delivery reservation data in accordance with a material transportation plan and material delivery reservation form that correspond to the construction process, determines the lifting weight that can be handled in a day, and sends this to an operation management device at the construction site, which stores information on delivered materials and loading information and controls automatic guided vehicles on specified floors to transport and unload cargo (for example, abstract of Patent Document 2). [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Japanese Patent Application Laid-Open No. 2001-220893 [Patent Document 2] Japanese Patent Application Publication No. 7-207946 Summary of the Invention [Problem to be solved by the invention]

[0005] At a construction site, there are multiple subcontractors involved in the construction. When materials need to be transported to the upper floors of a building under construction, these subcontractors reserve a shared temporary elevator. After the reservation for the temporary elevator is confirmed, the subcontractors use the temporary elevator at the confirmed time on the confirmed date.

[0006] For example, when reserving this temporary elevator, users belonging to each cooperating company input the required information into the reservation screen of the reservation system. When such an equipment reservation system is adopted, the dates and times of temporary elevator reservation requests from multiple cooperating companies often overlap. Therefore, when the reservation dates and times overlap, the management user belonging to the management company that manages the construction site adjusts the multiple reservation requests to finalize the temporary elevator reservation schedule.

[0007] When a management user belonging to a management company adjusts multiple reservation requests, there is a problem of which reservation request should be prioritized. At a construction site, the progress of construction work changes daily, so it is preferable to determine which subcontractor's usage mode should be prioritized according to the progress level.

[0008] In this regard, the technology disclosed in Patent Document 1 discloses that a lifting equipment is reserved according to the items entered on a reservation application screen, but does not disclose that the reservation of the equipment to be used is adjusted according to the progress of the construction work.Furthermore, the technology disclosed in Patent Document 2 also discloses that the lifting weight that can be handled in a day is determined according to delivery reservation data and that an automated guided vehicle on a specified floor is controlled according to that lifting weight, but does not disclose that the reservation of the equipment to be used is adjusted according to the progress of the construction work.

[0009] Therefore, the techniques of Patent Documents 1 and 2 have a problem in that when a plurality of users apply to reserve a facility, the reservation cannot be confirmed in accordance with the mode of use of the facility.

[0010] In consideration of the above, an object of the present invention is to, when a plurality of users apply for reservation of a facility, confirm the reservation in accordance with the mode of use of the facility. [Means for solving the problem]

[0011] A first aspect of the present invention is a facility reservation device including: a reception unit that receives reservation request information from each of a plurality of user terminals, the reservation request information including a reservation request for a facility to be used and usage mode information regarding a usage mode of the facility; and a reservation unit that generates reservation information representing a reservation of the facility based on the usage mode information in the reservation request information of the plurality of users received by the reception unit and a predetermined priority regarding the usage mode of the facility. Thus, when a plurality of users apply for a facility reservation, the facility reservation can be confirmed in accordance with the progress of construction work.

[0012] The facility according to a second aspect of the present invention is a facility that is shared by a plurality of users at a construction site.

[0013] Furthermore, when the usage mode information received by the reception unit includes floor information regarding the floor on which the luggage is to be lifted, lifting count information regarding the number of lifts, and loading time information regarding the time required to load and unload the luggage, the reservation unit of the equipment reservation device of the third aspect of the present invention calculates a lifting time representing the time required to lift the luggage based on the floor information, the lifting count information, and the loading time information, determines a reservation time for the equipment according to the lifting time, and generates the reservation information including the reservation time.

[0014] In addition, the reservation request information of the fourth aspect of the facility reservation device according to the present invention includes multiple desired reservation times indicating desired time periods for facility reservations, and when one user's first desired reservation time overlaps with the other user's first desired reservation time and the priority of the other user's usage mode information is higher than that of the one user, the reservation unit generates the reservation information giving priority to the other user's desired reservation time, and also generates the reservation information corresponding to the one user's second or subsequent desired reservation times. [Effects of the Invention]

[0015] According to the present invention, when a plurality of users apply for reservation of a facility, the reservation can be confirmed according to the mode of use of the facility. [Brief explanation of the drawings]

[0016] [Figure 1] 1 is a block diagram showing an example of the configuration of a facility reservation system 10 according to an embodiment. [Figure 2] FIG. 10 is a diagram showing an example of a reservation screen displayed by the server 30. [Figure 3] FIG. 10 is a diagram showing an example of a setting screen displayed by the server 30. [Figure 4] FIG. 10 is a diagram for explaining the priority order according to the use mode information included in the reservation request information. [Figure 5] FIG. 10 is a diagram for explaining reservation allocation. [Figure 6] FIG. 10 is a diagram for explaining generation of reservation information according to work performed by an administrative user. [Figure 7] 1 is a diagram illustrating an example of the configuration of a computer of a server 30 in a facility reservation system 10 according to an embodiment. [Figure 8] FIG. 2 is a diagram showing an example of a sequence executed by each device in the facility reservation system 10. DETAILED DESCRIPTION OF THE INVENTION

[0017] Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

[0018] [Outline of the embodiment] In reservation systems that process reservations for equipment shared by multiple users, reservations are often confirmed on a first-come, first-served basis. On the other hand, at construction sites, if reservations for equipment are confirmed on a first-come, first-served basis, it can cause inconvenience during construction, so it is preferable to confirm reservations for equipment based on, for example, the manner in which the equipment is used, rather than on a first-come, first-served basis.

[0019] For example, at a construction site, a certain subcontractor company, X, wants to use the equipment to carry out work type A. In this case, another subcontractor company, Y, wants to use the equipment to carry out work type B, so it applies for and confirms a reservation for the equipment earlier than subcontractor company X. However, in terms of the construction site schedule, work type A needs to be given priority over work type B, so it may be preferable for subcontractor company X to confirm the equipment reservation.

[0020] Therefore, the equipment reservation system of this embodiment confirms reservations for equipment to be used based on a predetermined priority order for the usage modes of equipment used by cooperating companies. For example, if a cooperating company X's equipment is used for construction work type A and another cooperating company Y's equipment is used for construction work type B, and if it is necessary to prioritize construction work type A over construction work type B depending on the progress of the construction work, the priority order for the equipment usage mode for construction work type A is set higher. This gives priority to the reservation request for equipment from cooperating company X rather than on a first-come, first-served basis, and allows equipment reservations to be confirmed depending on the progress of the construction work.

[0021] Since the progress of construction work at a construction site changes daily, the usage pattern of prioritized equipment also changes daily. Therefore, the equipment reservation system of this embodiment allows the administrative user to change the priority order. This makes it possible to confirm equipment reservations according to the progress of construction work, which changes daily. This will be explained in detail below.

[0022] <Reservation system configuration> FIG. 1 is a block diagram showing an example of the configuration of a facility reservation system 10 according to this embodiment. Functionally, as shown in FIG. 1, the facility reservation system 10 can be represented as a configuration including multiple user terminals 20-1, 20-2, and 20-3, and a server 30, which is an example of a facility reservation device. Note that, hereinafter, unless a specific user terminal is being referred to, it will be simply referred to as a "user terminal 20." Also, while the example of FIG. 1 shows three user terminals 20-1, 20-2, and 20-3, the facility reservation system 10 may include more or fewer user terminals. Note that, in this embodiment, a case will be described where the facility to be used is a temporary elevator.

[0023] (user terminal) The user terminal 20 is, for example, a smartphone or tablet terminal, and is operated by a user of a cooperating company reserving a temporary elevator. The user terminal 20 is equipped with a touch panel (not shown), which is an example of an operation unit and a display unit. The user inputs operation information to the user terminal 20 via the touch panel (not shown). The user also checks the information displayed on the touch panel (not shown).

[0024] (server) The server 30 performs a reservation process for the temporary elevator in accordance with the information transmitted from the user terminal 20. Functionally, the server 30 includes a reception unit 300, a data storage unit 302, a setting information storage unit 304, and a reservation unit 306, as shown in FIG.

[0025] The reception unit 300 receives reservation request information from each of the multiple user terminals 20, which includes a reservation request for a temporary elevator at a construction site and usage mode information regarding the usage mode of the temporary elevator. The reservation request information also includes a desired reservation time indicating a desired time period for reserving the temporary elevator. For example, the desired reservation time for the temporary elevator may be information such as first preference: X month, X day, X o'clock to X o'clock, and second preference: Y month, Y day, Y o'clock to Y o'clock.

[0026] Fig. 2 shows an example of a reservation screen that is displayed when the user terminal 20 accesses the server 30. The server 30 outputs, for example, a reservation screen such as that shown in Fig. 2. As a result, the reservation screen such as that shown in Fig. 2 is displayed on the display unit (not shown) of the user terminal 20 that has accessed the server 30.

[0027] A user operating the user terminal 20 inputs predetermined information into a reservation screen as shown in Fig. 2. As a result, reservation request information is transmitted from the user terminal 20 to the server 30. Among the reservation request information input into the reservation screen, for example, reservation type 100, work type 102, object to be lifted 103, lifting floor 104, and desired lifting date 105 are examples of usage mode information relating to the usage mode of the equipment. Then, the reception unit 300 stores the reservation request information transmitted from the user terminal 20 in the data storage unit 302, which will be described later.

[0028] Various types of data are stored in the data storage unit 302. For example, the data storage unit 302 stores a plurality of pieces of reservation request information accepted by the accepting unit 300.

[0029] The reception unit 300 also receives information input by a management user who manages a construction site.

[0030] Fig. 3 shows an example of a setting screen displayed by the server 30 on its own display unit (not shown). The administrative user inputs predetermined information into the setting screen as shown in Fig. 3. The administrative user, for example, checks the setting screen as shown in Fig. 3 and sets the priority order of the priority items in the reservation request information.

[0031] The receiving unit 300 receives setting information relating to the priority order of priority items in reservation request information input by the administrative user, and stores the setting information in the setting information storage unit 304 .

[0032] For example, the administrative user decides which of "delivery-in / delivery-out," "delivery-in only," and "delivery-out only" will be given priority for the priority item "reservation type." For example, the administrative user decides that the first priority is "delivery-in / delivery-out," the second priority is "delivery-in only," and the third priority is "delivery-out only," and enters this information in input field P1. In this case, reservation request information with a "reservation type" of "delivery-in / delivery-out" takes priority over reservation request information with a "reservation type" of "delivery-in only" and "delivery-out only."

[0033] Similarly, the administrative user also determines the priorities of the priority items "type of work," "lifted object," and "lifting floor," and inputs the information in input fields P2, P3, and P4.

[0034] For example, consider the case where the first priority for the priority item "reservation type" is determined as "delivery in / out," the second priority as "delivery in only," and the third priority as "delivery out only," the first priority for the priority item "type of work" is determined as "interior work," the second priority as "metal work," and the third priority as "structural work," the first priority for the priority item "lifting objects" is determined as "manufactured items," the second priority as "temporary materials," and the third priority as "tools," and the first priority for the priority item "lifting floor" is determined as "10th floor," the second priority as "7th floor," and the third priority as "14th floor."

[0035] Fig. 4 is a diagram for explaining the priority order according to the usage mode information included in the reservation request information. As shown in Fig. 4, in the above case, for example, reservation request information with the items "reservation type: delivery / removal," "type of work: interior construction," "item to be lifted: manufactured item," and "lifting floor: 10F" will have the highest priority and will be the first priority reservation.

[0036] Next, reservation request information with the following items is given priority: "Reservation type: Delivery / Carry-out," "Work type: Interior work," "Lifted items: Fabricated items," and "Lifting floor: 7F," and becomes a second-priority reservation. Next, reservation request information with the following items is given priority: "Reservation type: Delivery / Carry-out," "Work type: Interior work," "Lifted items: Fabricated items," and "Lifting floor: 14F," and becomes a third-priority reservation. Next, reservation request information with the following items is given priority: "Reservation type: Delivery / Carry-out," "Work type: Interior work," "Lifted items: Temporary materials," and "Lifting floor: 10F," and becomes a fourth-priority reservation. Next, reservation request information with the following items is given priority: "Reservation type: Delivery / Carry-out," "Work type: Interior work," "Lifted items: Temporary materials," and "Lifting floor: 7F," and becomes a fifth-priority reservation. Next, the reservation request information with the items "Reservation type: Delivery / Removal", "Type of work: Interior construction", "Lifted material: Temporary materials", and "Lifting floor: 14F" is given priority and becomes the 6th priority reservation.

[0037] In this way, the reservation unit 306 of the server 30 generates reservation information representing a reservation of the facility based on the priority set in advance regarding the usage mode of the temporary elevator. Fig. 5 shows an example of the generation of reservation information.

[0038] For example, as shown in Fig. 5, the reservation unit 306 generates reservation information for reserving equipment of X Construction, which has made a first priority reservation, from 8:00 to 10:00 on Monday, November 30th, which is X Construction's desired date and time. Also, as shown in Fig. 5, reservation information is generated for reserving equipment of Y Construction, which has made a second priority reservation, from 9:00 to 11:00 on Tuesday, December 1st, which is Y Construction's desired date and time. Next, as shown in Fig. 5, reservation information is generated for reserving equipment of Z Industry, which has made a third priority reservation, from 14:00 to 16:00 on Monday, November 30th, which is Z Industry's desired date and time. Similarly, reservation information is generated for reserving equipment of A Construction, which has made a third priority reservation, from 14:00 to 16:00 on Wednesday, December 2nd, which is A Construction's desired date and time.

[0039] If multiple users have overlapping desired reservation times for the temporary elevator, the reservation unit 306 gives priority to reservations for usage modes with higher priorities.

[0040] For example, consider a case where one user's first desired reservation time overlaps with another user's first desired reservation time. In this case, if the priority of the other user's usage mode is higher than the priority of the one user's usage mode, the reservation unit 306 generates reservation information by prioritizing the other user's desired reservation time. In this case, the reservation unit 306 generates reservation information corresponding to the one user's second or subsequent desired reservation times.

[0041] If the priority of the usage mode of the other user is the same as the priority of the usage mode of one user, the reservation unit 306 adjusts the reservations by, for example, giving priority to the reservation request information of a user who has requested a reservation for an earlier time than the first desired reservation time of the user. Also, if the first to third desired reservation times all overlap, the reservations are adjusted by giving priority to the reservation request information of the user who requested the reservation earlier.

[0042] This makes it possible to automatically generate reservation information according to the usage pattern of the temporary elevator included in the reservation request information.

[0043] The final reservation information may be confirmed by work by the administrative user. Fig. 6 shows a diagram for explaining the generation of reservation information in accordance with work by the administrative user. As shown in Fig. 6, each reservation request information included in reservation list L, which represents the reservation request information of multiple cooperating companies, is allocated to a schedule, and reservation information is generated. The administrative user who adjusts the reservation can manually make fine adjustments within the desired time frame based on the results automatically allocated to the schedule, or can simply confirm the reservation.

[0044] For example, when the administrative user inputs the four priority items 31 shown in Figure 6 and presses the allocation button, the allocation process is performed as shown on the right side of Figure 6. For example, a reservation 32 with X Construction Company, which is the first priority reservation, is allocated to the schedule from the reservation list L. At this time, second and third choice reservations 33 with X Construction Company are also displayed with dotted lines.

[0045] 6, when confirming the allocation of the reservation 35 for XX Industry, the Confirm button 34 is pressed to confirm the allocation. Note that a reservation 36 for another company, which has a lower priority than the reservation 35 for XX Industry, is displayed with a dotted line and is not confirmed. In this case, the second-choice reservation 37 for this other company is highlighted, and when the administrative user confirms it, the second-choice reservation 37 for this other company is confirmed.

[0046] The administrative user then repeats the above steps until the schedule is filled or until there is no more reservation request information included in the reservation list L.

[0047] As shown in Fig. 6, after a reservation has been allocated with multiple priority items specified, it is possible to remove one priority item and allocate the reservation again. For example, the administrative user deletes the third priority item "lifting load" from the priority items 31 in Fig. 6 and sets priority item 38 again. Then, by performing allocation processing using priority item 38, the reservation is allocated again.

[0048] In addition, when allocating reservations to a schedule, the reservation time may be automatically calculated. In this case, the temporary elevator usage information must include lifting floor information regarding the floor where the luggage will be lifted, lifting count information regarding the number of lifts, and loading time information regarding the time required to load and unload the luggage.

[0049] The reservation unit 306 calculates the lifting time Ta, which indicates the time required to lift a load, based on the cycle time Ti, the number of lifts N, and the loading time X derived from the lifting floor information, according to the following formula:

[0050] Ta = (Ti + 2X) × N T=Ta+M

[0051] The cycle time Ti derived from the lifting floor information is the time it takes for the temporary elevator to load the cargo, close the doors of the temporary elevator, move to the target floor, and open the doors of the temporary elevator, and is set in advance according to the target floor for lifting the cargo. The cycle time Ti varies depending on the departure and arrival floors, so it is set in advance for each combination of the floor from which the temporary elevator departs and the floor at which the temporary elevator arrives.

[0052] In the above formula, M is the adjustment time [min], and as shown in the above formula, the sum of the lifting time Ta and the adjustment time M is calculated as the reservation time T. Note that the adjustment time M is set, for example, according to the lifting time Ta as follows:

[0053] 0 <Ta≦60 [min]:M=5[min] 60 <Ta≦120[min]:M=10[min] 120 <Ta [min]:M=15[min]

[0054] For this reason, the reservation unit 306 determines the reservation time T of the temporary elevator according to the lifting time Ta, and generates reservation information including the reservation time T. Then, the reservation unit 306 generates reservation information for the reservation time T, starting from the start time of the user's desired reservation time.

[0055] When finalizing the reservation information, the reservation information may be generated by allocating the desired reservation times transmitted from multiple user terminals 20 to a schedule, or by allocating a reservation time automatically calculated as described above to a schedule. Furthermore, if it is difficult to allocate the desired reservation times transmitted from multiple user terminals 20 to a schedule, it is possible that the user has set a longer desired reservation time. In such a case, the reservation information may be generated by allocating the automatically calculated reservation time T to a schedule.

[0056] In this way, the facility reservation system 10 of this embodiment accepts reservation request information including usage mode information regarding the usage mode of the temporary elevator from each of multiple user terminals 20, and generates reservation information for the temporary elevator based on the usage mode information in the reservation request information of the multiple users and the predetermined priority regarding the usage mode of the temporary elevator. As a result, when multiple users apply for reservations for the facility, the reservations can be confirmed according to the usage mode of the facility. Furthermore, when multiple users apply for reservations for the temporary elevator, the reservations can be appropriately confirmed according to the progress of the construction work.

[0057] The server 30 of the facility reservation system 10 can be realized, for example, by a computer 60 as shown in Fig. 7. The computer 60 that realizes the server 30 includes a CPU 61, a memory 62 as a temporary storage area, and a non-volatile storage unit 63. The computer 60 also includes an input / output interface (I / F) 64 to which input / output devices (not shown) are connected, and a read / write (R / W) unit 65 that controls reading and writing of data from and to a recording medium 69. The computer also includes a network I / F 66 that is connected to a network such as the Internet. The CPU 61, memory 62, storage unit 63, input / output I / F 64, R / W unit 65, and network I / F 66 are connected to one another via a bus 67.

[0058] The storage unit 63 can be realized by a hard disk drive (HDD), a solid state drive (SSD), a flash memory, etc. The storage unit 63 as a storage medium stores a program for causing the computer to function. The CPU 61 reads the program from the storage unit 63, loads it into the memory 62, and sequentially executes the processes contained in the program.

[0059] <Facility reservation system operation> Next, we will explain the operation of the facility reservation system 10. Each device in the facility reservation system 10 executes a sequence as shown in FIG.

[0060] In step S100, the user terminal 20 transmits reservation request information to the server 30. For example, a user operating the user terminal 20 accesses the server 30 by operating the user terminal 20 and views a facility reservation screen (not shown). The user then inputs predetermined information into the reservation screen as shown in FIG. 2 above to generate reservation request information including a reservation request for a temporary elevator, temporary elevator usage mode information, and desired reservation time for the temporary elevator, and transmits the reservation request information to the server 30.

[0061] In step S102, the reception unit 300 of the server 30 receives the reservation request information transmitted in step S100 from the user terminal 20. The reception unit 300 then stores the received reservation request information in the data storage unit 302.

[0062] The administrative user sets in advance setting information relating to the priority order of priority items in the reservation request information by inputting predetermined information into the setting screen as shown in Fig. 3. The reception unit 300, which receives the input of setting information from the administrative user, stores the setting information in the setting information storage unit 304.

[0063] When the deadline for accepting reservation request information arrives, the reservation unit 306 of the server 30 reads out the setting information from the setting information storage unit 304 in step S104.

[0064] In step S106, the reservation unit 306 generates reservation information for the temporary elevator based on the priority of the usage mode of the temporary elevator represented by the setting information read out in step S104 and the plurality of pieces of reservation request information stored in the data storage unit 302. For example, the reservation unit 306 generates the reservation information for the temporary elevator by allocating the reservations of each user to a schedule.

[0065] In step S108, the reservation unit 306 of the server 30 notifies the user terminal 20 that the facility reservation has been confirmed.

[0066] In step S110, the user terminal 20 receives the notification sent in step S108. The user of the user terminal 20 checks the received notification and confirms whether the reservation in accordance with the reservation request information sent by the user terminal 20 has been confirmed.

[0067] As described above, the server of the facility reservation system of this embodiment accepts reservation request information from each of multiple user terminals, including a reservation request for the facility to be used and usage mode information regarding the usage mode of the facility.The server then generates reservation information representing a facility reservation based on the usage mode information in the reservation request information from the multiple users and a predetermined priority regarding the usage mode of the facility.As a result, when multiple users request a facility reservation, the reservation can be confirmed according to the usage mode of the facility.

[0068] In addition, the equipment reservation system server can reduce the administrative user's effort in adjusting and confirming reservations by presenting equipment reservation allocation proposals based on the priority of equipment use, which changes as the construction work progresses.

[0069] In addition, by including the type of loading and unloading in the priority items, unnecessary loading and unloading vehicles are prevented from staying, which prevents space from being wasted on the construction site and shortens the time the space is occupied.

[0070] Furthermore, by including the type of construction work in the priority items, reservations can be adjusted taking into consideration the type of construction work, reducing the administrative user's time and effort in adjusting and confirming reservations.

[0071] Furthermore, by including the type of lifting object in the priority items, it is possible to prioritize reservations for temporary elevators for lifting temporary materials or high-rise vehicles, etc., depending on the progress of the construction work. It is also possible to prioritize reservations for temporary elevators for discharging garbage, depending on the accumulation status of garbage, etc., and the planned removal schedule.

[0072] Furthermore, by including the floor to be used in the priority items, reservations can be adjusted taking into consideration the floor to be used.

[0073] Furthermore, reservations can be confirmed based on the reservation time T automatically calculated according to the number of lifts N, etc., which can prevent users from requesting longer reservation times. This allows for efficient operation of the equipment to be used.

[0074] Furthermore, by including a plurality of desired reservation times in the reservation request information, the conditions for the reservation allocation process are relaxed, making it possible to generate reservation information that meets the desires of many users.

[0075] The present invention is not limited to the above-described embodiment, and various modifications and applications are possible without departing from the spirit and scope of the present invention.

[0076] For example, in the above embodiment, the facility is described as a temporary elevator, but the facility is not limited to this and may be any facility that is shared by multiple users. For example, the shared facility may be an aerial work platform, which is an example of lifting equipment used at a construction site.

[0077] Furthermore, although the above describes a form in which the program according to the present invention is pre-stored (installed) in a storage unit, the program according to the present invention can also be provided in a form in which it is recorded on a recording medium such as a CD-ROM, DVD-ROM, or microSD card. [Explanation of symbols]

[0078] 10 Facility reservation system 20 User terminal 30 servers 300 Reception 302 Data storage unit 304 Setting information storage unit 306 Reservation Department

Claims

1. a reception unit that receives reservation request information from each of the terminals of the plurality of users, the reservation request information including a reservation request for lifting equipment to be used in common by the plurality of users at a construction site and usage mode information regarding a usage mode of the lifting equipment; a reservation unit that generates reservation information representing a reservation for the lifting equipment based on the usage mode information among the reservation request information of the plurality of users accepted by the acceptance unit and a predetermined priority regarding the usage mode of the lifting equipment; Including, The usage mode information includes: Reservation type information indicating whether the lifting equipment is used for loading / unloading a lifting object, loading only a lifting object, or unloading only a lifting object; Construction type information indicating the type of construction related to the lifting load; Lifted object information indicating the type of lifted object; and lifting floor information indicating a floor to which the lifted object is to be carried in or out, A management user different from the plurality of users sets a priority order of priority items regarding priority item names indicating which items among the reservation type information, the construction type information, the lifting object information, and the lifting floor information are to be prioritized; The administrative user sets a priority order for priority values ​​indicating which of the reservation type information values, i.e., carry-in / out, carry-in only, and carry-out only, is to be prioritized; which of the construction type information values, i.e., the construction type, is to be prioritized; which of the lifting object types, is to be prioritized, is to be prioritized; and which of the lifting floor information values, is to be prioritized; The reservation unit Based on each piece of information included in the usage mode information of a plurality of users, the priority item order, and the priority value order, refer to the value of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information in the order represented by the priority item order; generating reservation information representing a reservation for the lifting equipment by comparing the values ​​of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information of a plurality of users and adjusting which of the reservation request information of the plurality of users is to be given priority in accordance with the priority indicated by the priority value order; Equipment reservation device.

2. When the usage mode information received by the reception unit includes lifting count information regarding the number of liftings and loading time information regarding the time required to load and unload the lifted object, the reservation unit calculates a lifting time representing the time required to lift the object based on the lifting floor information, the lifting count information, and the loading time information, determines a reservation time for the lifting equipment according to the lifting time, and generates the reservation information including the reservation time. The facility reservation device according to claim 1.

3. The reservation request information includes a plurality of desired reservation times that indicate desired time periods for facility reservations, When the first desired reservation time of one user overlaps with the first desired reservation time of the other user, the reservation unit: In the order represented by the priority items, the value of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information of one user are referenced, and the value of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information of the other user are referenced, the values ​​of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information of one user are compared with the values ​​of the reservation type information, the value of the construction type information, the value of the lifting object information, and the value of the lifting floor information of the other user, and whether the reservation request information of one user or the reservation request information of the other user is to be given priority is adjusted according to the priority indicated by the priority value order. If the reservation request information of the other user is to be given priority, the reservation information corresponding to the first desired reservation time of the other user is generated, and the reservation information corresponding to the second or subsequent desired reservation times of the one user is generated; 3. The facility reservation device according to claim 1 or 2.

Citation Information

Patent Citations

  • Automatic carrying method of building materials and device thereof

    JP1995207946A

  • Facility lending device

    JP1998283402A

  • Lifting reservation system for construction materials

    JP2001220893A

  • Elevator system

    JP2020066513A